MATERIAL ISSUANCE VOUCHER

Work order: Account: Date: 9th Aug 2018

S. Description Stock Code Quantity Unit Equipment Tag Remarks


no Requested Issued
1 Mechanical Seal –Pump CCR65A-250R1 Pump CCR65A-250R1 M2 L3(TPL 1 1 Nos Pump No- Seal found to
M2 L3(TPL IC- 5000360800030) IC- 5000360800030) be
damaged.(pump
not taken for
operation)
2 Complete Mechanical Seal(box no- (box no-20/Pumpccr 200 -400 1 1 Nos Pump No- Seal found to
20/Pumpccr 200 -400 R1 M2 L4/Tag: P- R1 M2 L4/Tag: P- MTL 003A/B & be
MTL 003A/B & P- SOL -003A/B) P- SOL -003A/B)
damaged.(pump
not taken for
operation)