Item Description RM
1.1 General
Carry Forward
BQ1/1
CADANGAN MEMPERTINGKATKAN INFRASTRUKTUR JALANRAYA, PARIT DAN SIARAKI DI JALAN RADIN,
JALAN RADIN ANUM 1, JALAN MERAH CAGAR DAN KAWASAN SEKITARNYA DI TAMAN SRI PETALING,
KUALA LUMPUR.
Item Description RM
Carry Forward
BQ1/2
CADANGAN MEMPERTINGKATKAN INFRASTRUKTUR JALANRAYA, PARIT DAN SIARAKI DI JALAN RADIN,
JALAN RADIN ANUM 1, JALAN MERAH CAGAR DAN KAWASAN SEKITARNYA DI TAMAN SRI PETALING,
KUALA LUMPUR.
Item Description RM
1.7 Insurance
The Contractor must within seven (7) days from the date of
notification that his tender has been accepted in writing by the
Superintending Officer before the contract documents are signed
submit insurance policies indemnifying the Datuk Bandar
The contractor shall take out the following insurance policies and
include the cost of the premiums in his Preliminaries:-
ii) All Risk (including Public Liability the amount of which shall be
unlimited for the period and RM200,000.00 for any one accident)
The Insurance Policies shall also cover the Datuk Bandar, his
employees and agents’ accident while on the project site. The
policies shall be in the joint names of Datuk Bandar Kuala Lumpur,
the contractor and all other contractors connected with the project
Carry Forward
BQ1/3
CADANGAN MEMPERTINGKATKAN INFRASTRUKTUR JALANRAYA, PARIT DAN SIARAKI DI JALAN RADIN,
JALAN RADIN ANUM 1, JALAN MERAH CAGAR DAN KAWASAN SEKITARNYA DI TAMAN SRI PETALING,
KUALA LUMPUR.
Item Description RM
The contractor shall ensure that the existing road are clears of any
construction debris, earth, etc at all times.
1.10 Communication
The contractor is required to provide suitable and competent
manpower and labours and can communicate very well labours
and can communicate very well. Any foreign workers engaged must
have valid working permit. Suitable site supervisors to be present at
various construction sites within any cactment areas and must
have suitable gadget equipment to facilitate communication. In order
for the workscarried out smoothly the Contractor has to be provide
provide telephone hotline and email to receive instruction at any time.
The Contractor required to supply S.O's representatives with 1 (one)
set of computerized equipment with quad core application and
4G connection.
Carry Forward
BQ1/4
CADANGAN MEMPERTINGKATKAN INFRASTRUKTUR JALANRAYA, PARIT DAN SIARAKI DI JALAN RADIN,
JALAN RADIN ANUM 1, JALAN MERAH CAGAR DAN KAWASAN SEKITARNYA DI TAMAN SRI PETALING,
KUALA LUMPUR.
Item Description RM
a) signboard
i) AWAS KERJA-KERJA DBKL DI HADAPAN
(dwg No : JKA/SP/0003/03-94-no syit 25) - 2 nos
ii) Tanda AWAS
(dwg No : JKA/SP/0003/03-94-no syit 27) - 2 nos
iii) Tanda LENCONGAN
(dwg No : JKA/SP/0003/03-94-no syit 27) - 2 nos
b) signage
i) CLEARENCE MARKER
(dwg No : JKA/SP/0003/03-94-no syit 25) - 2 nos
c) blinkers - 20 nos
d) cones
(dwg No : JKA/SP/0003/03-94-no syit 25) - 20 nos
Carry Forward
BQ1/5
CADANGAN MEMPERTINGKATKAN INFRASTRUKTUR JALANRAYA, PARIT DAN SIARAKI DI JALAN RADIN,
JALAN RADIN ANUM 1, JALAN MERAH CAGAR DAN KAWASAN SEKITARNYA DI TAMAN SRI PETALING,
KUALA LUMPUR.
Item Description RM
BQ1/6
CADANGAN MEMPERTINGKATKAN INFRASTRUKTUR JALANRAYA, PARIT DAN SIARAKI DI JALAN RADIN,
JALAN RADIN ANUM 1, JALAN MERAH CAGAR DAN KAWASAN SEKITARNYA DI TAMAN SRI PETALING,
KUALA LUMPUR.
Item Description RM
BQ1/7