Präsentation P4 Installation (Compatibility Mode)
Präsentation P4 Installation (Compatibility Mode)
accessories
High Voltage Accessories
Installation Quality circle
Installation
Mounting Environment
procedures
Tool selection
and calibration
Installer certification
Easier to remember
and reproduce
Reduction of installation
time
Short
Avoidance of cable
insulation damages
during cable
preparation Fork
Relaxation of insulation
mechanical stress
Reduction of failures
due to displacement of
joint body!
Precise cut
distances
Reduction of failures
due to bad cable Pull off insulation with
preparation device to expose
conductor
Brugg Cables Academy
Efficiency improvements in joint
installations
piece of glass Cable peeling & Insulation grinding.
can also be
used for
peeling of SC
SC PEELING & STRIPPING TOOL
Provides precise peeling
Polishing of
XLPE by corund
cloth.
Motorized GRINDING MACHINE reduces
Time and effort
Brugg Cables Academy
Brugg best practices for peeling and
grinding
Max. concentration of electric
fields at the edge where SC ends
Stress cones
High contact resistance between Middle Electrode
cable SC layer and deflector avoids
optimal field control particularly in
high transient overvoltage!
Deflector Deflectors
Brugg Cables Academy
11
Brugg best practices – Clean insulations
• Avoid
contamination
while preparing
other cables
• Cable preparation
completed.
Avoids adhesion of SC
particles into joint body
Reduces mechanical
stress of joint body
Reduction of failures
Bolted connectors
• Well established
method
• Easy to install, no
special equipment
• Reduced
installation time
Head of each bolt will break away
after a specific applied torque. Fill all
gaps with compound to avoid sharp
edges
Brugg Cables Academy
Efficiency improvements in joint
installations
Screen connection without plumbing and soldering
Connection of Coaxial cable
(bonding cable) soldered
Soldering requires special
skills – Danger of cable core
overheating Bonding Outer
cable conductors
Cooling times required Power
Cable
Soldered
Press ring
Gland Adapter Intermediate
ring ring
Cu braids fixed with
bandits
ca.3200
No heating required
Flexible installation
(pump from top or bottom)
4795
2351
1200
200
Vacuum pump –
to pump gases
and vapors out of
insulator.
Pump for filling
Filling of Silicon oil inside the insulator of silicon oil
inside insulator
Brugg Cables Academy
Efficiency improvements in termination
installations
GIS Insulators acc. IEC
62271-209
Reduction of installation
time and costs
Reduction of stock of
special parts Fasten termination with GIS cable box
Eng. S. Abu Muhammad
Brugg Cables.