Quality Plan
Quality Plan
1 Upper Half Mean length (mm) < 28.0 < 28.0 < 29.0 < 29.0
2 Fineness (Micrograms/Inch) 3.5 - 5.5 3.5 - 5.5 3.5 - 5.5 3.5 - 5.5
REMARKS Need written confirmation from corporate R/M to use the lots below these specifications
PREPARED BY
HOD (Q.A.) Tech. Head Unit Head
SEL MANUFACTURING COMPANY LIMITED. MEHATWARA, M.P
QUALITY ASSURANCE DEPARTMENT
PROCESS QUALITY PLAN
INSPECTION CHECK Process Parameter Equipment Sample Size No. Of Tests Frequency
STAGE POINT Stage
RECEIVING 1 CARTONS DIMENSION MEASURING TAPE 5 CARTONS/CONSIGNMENT 1 Test EVERY CONSIGNMENT
WEIGHT Weighing balance 5 CARTONS/CONSIGNMENT 1 Test
BURSTING STRENGTH Bursting Strength Tester 5 CARTONS/CONSIGNMENT 2 tests per carton
2 SEPERATORS DIMENSION MEASURING TAPE 5 CARTONS/CONSIGNMENT 1 Test EVERY CONSIGNMENT
WEIGHT Weighing balance 5 CARTONS/CONSIGNMENT 1 Test
BURSTING STRENGTH Bursting Strength Tester 5 Seperator/CONSIGNMENT 1 tests per sepeartor
CRITICAL 3 CONES DIMENSION VERNIER CALIPER 10 CONES PER CONSIGNMENT 1 Test EVERY CONSIGNMENT
WEIGHT Weighing balance 10 CONES PER CONSIGNMENT 1 Test
COLLAPSING STRENGTH COLLAPSING STRENGTH TESTER 10 CONES PER CONSIGNMENT 1 Test
REJECTION CHECKING VISUAL ONE BUNDLE PER CONSIGNMENT 1 Test
ITEMS 4 WAX DIMENSION VERNIER CALIPER 10 WAX PER CONSIGNMENT 1 Test EVERY CONSIGNMENT
WEIGHT Weighing balance 10 CONES PER CONSIGNMENT 1 Test
CONSUMPTION IN GMS/KG Weighing balance 10 WAX PER CONSIGNMENT 1 Test
Yarn Friction Uster Zweigle friction tester 100 mtr / test 1 test per cone , 5 cones
5 POLYTHENE BAGS DIMENSION MEASURING TAPE 10 BAGS PER CONSIGNMENT 1 Test EVERY CONSIGNMENT
WEIGHT Weighing balance 50 BAGS PER CONSIGNMENT
1 COTTON LENGTH (mm) HVI - 1000 Approx.100g 4 test/Bale*10%Bales/Lot Every lot
RECEIVING FINENESS(Mic) DO DO 2 Test/Bale*10%Bales/Lot Every lot
RAW - STRENGTH g/tex DO DO 4 test/Bale*10%Bales/Lot Every lot
COTTON UNIFORMITY % DO DO 4 test/Bale*10%Bales/Lot Every lot
ELONGATION % DO DO 4 test/Bale*10%Bales/Lot Every lot
Colour Grade (Rd and +b value) DO DO 4 test/Bale*10%Bales/Lot Every lot
Moisture% DO DO 2 Test/Bale*10%Bales/Lot Every lot
TRASH % Trash Seperator Approx.100g 1Test / Lot Every lot
NEPS/GMS AFIS PRO-2 Approx.100g 3Tests / Sample As Reqd.
1 B/R(cotton) Cleaning Efficiency Trash Seperator Approx.100g 1 Test ALL B/R ONCE IN MONTH
NEPS/GM AFIS PRO-2 Approx.100g 5Tests / Sample ALL B/R ONCE IN MONTH
INPROCESS WASTE % Weighing Balance One hour Waste % 1Test / m/c ALL B/R ONCE IN MONTH
2 CARDING COUNT(g/m), Sliver Wrap Block/Balance 6 Yd 8Tests / m/c All Cards/ DAY
UNEVENNESS%, Sliver UT - 5 25m/Min, 2.5 min study 1Test / m/c As Reqd.
WASTE % Weighing Balance One hour Waste % 1Test / m/c As Reqd.
TRASH % - FEED Trash Seperator Approx.100g 1Test / m/c ONCE IN MONTH LINE WISE
TRASH % - SLIVER Trash Seperator Approx.100g 1Test / m/c ONCE IN MONTH LINE WISE
NEPS/GM AFIS PRO-2 Approx.100g 3Tests / Sample All Cards/ 15DAYS
3 B.D.F. COUNT(g/m), Sliver Wrap Block/Balance 5 Yd/Sample 4Tests / m/c/Side ALL BDF /Days
UNEVENNESS% UT - 5 25m/Min, 2.5 min study 1Test / m/c/Side ALL BDF / 15 Days
5 COMBER COUNT(g/m), Sliver Wrap Block/Balance 5 Yd/Sample 4Tests / m/c All COMBER/ IN A WEEK
NOIL % Weighing Balance Approx.25 Meter 1Test / m/c All COMBER/ 15 Days
UNEVENNESS% UT - 5 25m/Min, 2.5 min study 1Test / m/c All COMBER/ 15 Days
NEPS/GM AFIS PRO-2 Approx.100g 3Tests / Sample All COMBER/ 15 Days
6 F.D.F. COUNT(g/m), Sliver Wrap Block/Balance 5 Yd/Sample 4 Tests / m/c side EVERY BATCH
SLIVER TEST Wrap Block/Balance 5 Yd/Sample 10 Tests each for (n-1),n and (n+1) dblg. All FDF/ MONTH
UNEVENNESS%, Sliver UT - 5 25m/Min, 2.5 min study 1Test / m/c All FDF/ Day
NEPS/GM AFIS PRO-2 Approx.100g 3Tests / Sample All FDF/ MONTH
7 S/F. Hank of Roving Wrap Block/Balance 15 Yd 4B*2T=10Tests All m/cs per Day
UNEVENNESS%(Roving) UT - 5 25m/Min, 2.5 min study 4B*1T=4Tests All S/F/ week
Stretch % Wrap Block/Balance 15 Yds 4B*1T=4Tests (top and bottom) As Reqd.
BREAKS/100SPINDLE/HR ---- FULL DOFF --- As Reqd.
8 R/F. COUNT (Ne) (Yarn) Wrap Reel/Statex CSP system 120 Yd/ Bobbin 10 Bobbins/m/c All R/F In Two Days
CSP/ LEA STRENGTH Wrap Reel/Statex CSP system 120 Yd/ Bobbin 10 Bobbins/m/c One R/F per count, all counts daily.
Rkm & ELONGATION % Single yarn strenth tester 50 cm/Test 10T/B*10B*1m/c/ count All counts daily.
U% IPI / HAIRINESS # UT - 5 800m/Test, 0.5 MIN STUDY 1Test/B* (14 -16)B All R/F In Two Days
TPI STATEX TWIST TESTER 20 inch / test 1 t/B, 10 Bobbins/m/c One R/F per count, all counts daily.
9 WINDING/ TFO C.M.T FAULT (S,L,T) Classimat Quantum Minimum 100 Km 1 Test All counts/ week
U% IPI / HAIRINESS # UT - 5 800m/Test, 0.5 MIN STUDY 2T/Cone*5 Cone All counts/ Day
SEL MANUFACTURING COMPANY LIMITED. MEHATWARA, M.P
QUALITY ASSURANCE DEPARTMENT
PROCESS QUALITY PLAN
COUNT (Ne) (Yarn) Wrap Reel/Statex CSP system 120 Yd/ Cone 2T/Cone*5Cone/Count All counts/ Day
CSP/ LEA STRENGTH Wrap Reel/Statex CSP system 120 Yd/ Bobbin 2T/Cone*10Cone/Count All counts/ Day
Rkm & ELONGATION % Single yarn strenth tester 50 cm/Test 10T/B*10B*1m/c/ count ALL COUNTS/ DAY
REWINDING STUDY Winding machine Minimum 100 Km 2 FULL CONES / COUNT DAILY ONE COUNT
SPLICE STRENGTH AND APPEARANCE CHECKIN Splice strength tester one test per drum, all drums DAILY ONE M/C
CONE DIA CHECKING Vernier Caliper 10 cones / count DAILY ONE COUNT
YARN FRICTION Uster Zweigle friction tester 100 mtr / test 1 test per cone , 5 cones As required
WEIGHT OF CONE Weighing Balance 20 Cones/Machine 1 Test/Cone all winding m/cs / shift
FINAL 1 PACKING CARTON CHECKING VISUAL 2 CARTONS/ COUNT 1 Test Min one Count/ Day
MOISTURE CONTENT % Moisture Meter 10 Cones/Count 1Tests/Cone All Count/ Day
WEIGHT OF CONE Weighing Balance 2 CARTONS/ COUNT 1 Test/Cone Min one Count/ Day
FDF U % Combed MAX 2.1 2.1 2.0 2.0 AFTER 2 CONSECUTIVE TESTS
U% Carded MAX 2.6 2.6 N.A. N.A. 2.8 4.0
Sliver wt / 5 yards Std +/- 0.002 +/- 0.002 +/- 0.002 +/- 0.002 +/- 0.002 +/- 0.002 IMMEDIATE
Sliver test (A%) +/- 0.5 +/- 0.5 +/- 0.5 +/- 0.5 +/- 0.5 +/- 0.5
SPEED FRAME U % Combed MAX 3.5 3.5 3.5 3.5 3.5 3.5 AFTER 4 CONSECUTIVE TESTS
U % Carded MAX 5.0 5.0 5.0 5.0 5.0 5.0
Sliver Hank / 15 yards Std +/- 0.02 +/- 0.02 +/- 0.02 +/- 0.02 +/- 0.02 +/- 0.02 IMMEDIATE
STRECH % MAX 1.0 0.8 1.0 1.0 1.0 1.0 AFTER 2 CONSECUTIVE TESTS
BREAKS/100 SPINDLES/HR MAX 2.0 2.0 2.0 2.0 2.0 2.0 AFTER 2 CONSECUTIVE TESTS
RING FRAME/OE COUNT Std +/- 1% +/- 1% +/- 1% +/- 1% +/- 1% +/- 1% AFTER 3 CONSECUTIVE TESTS
COUNT C.V. % MAX 1.5 1.5 1.5 1.5 1.5 1.5 -------
TWIST Std +/- 5% +/- 5% +/- 5% +/- 5% +/- 5% +/- 5% IMMEDIATE
UT-5 CV%m,IMPS,RKM As per SEL Standards As per SEL standards
FINAL WINDING/TFO UT-5 CV%m,IMPS,RKM As per SEL Standards As per SEL/ Customer Standards
PACKING CONE WEIGHT CHECKING Std +/- 50 GMS +/- 50 GMS +/- 50 GMS +/- 50 GMS +/- 50 GMS +/- 50 GMS IMMEDIATE
CONE CHECKING(VISUAL) MAX +/- 10% +/- 10% +/- 10% +/- 10% +/- 10% +/- 10% AFTER 2 CONSECUTIVE TESTS
MOISTURE CONTENT MAX 8.2 8.2 8.2 8.2 8.2 8.2 AFTER 2 CONSECUTIVE TESTS
CUTIVE TESTS
CUTIVE TESTS
CUTIVE TESTS
IATE
CUTIVE TESTS
CUTIVE TESTS
CUTIVE TESTS
CUTIVE TESTS
IATE
IATE
CUTIVE TESTS
IATE
CUTIVE TESTS
CUTIVE TESTS
CUTIVE TESTS
IATE
CUTIVE TESTS
IATE
CUTIVE TESTS
CUTIVE TESTS
CUTIVE TESTS
IATE
rds
mer Standards
IATE
CUTIVE TESTS
CUTIVE TESTS
OVED BY
HEAD
Ha-Meem Spinning mills limited
QUALITY PLAN
Date : 01.01.17
COTTON :
Raw cotton HVI test HVI-1000 100 g 1 Sample / Bale, Whenever new lot comes
All bales
Raw cotton AFIS test AFIS PRO-2 0.50 gm 3 Samples / bale Whenever new lot comes
BLOW ROOM:
Blow Room machine setting check Visual Inspection n/a n/a Once per shif
Contamination Collection & Ejection Check Visual Inspection Twice per shif
CARDING :
B/R Nep Generation% test AFIS PRO-2 0.5 gms X 1 3 readings / card Once in a lot change
Fiber Groth test AFIS PRO-2 0.5 gms X 1 3 readings / card Once in a lot change
Wrapping Wrap block/ Balance 6 yd./sample 5 samples/card All card per day
Afer Maint wrapping check Wrap block/ Balance 6 yd./sample 5 samples/card As per maint schedule
Afer maint. Uster check UT-5 25 mtrs/min x 5 min 1 test / mc As per maint schedule
Carding Sliver U% UT-5 25 mtrs/min x 5 min 1 test / mc Daily-3 carding from 3 line
Drawing
Growth Test (Raw Cotton to Simplex). AFIS PRO-2 0.5 gms X 1 3 readings / DF Once in a lot change
Autoleveller Adjust. Wrap block/ Balance 6 yd./sample 5 samples/Doubling Once in a lot change
B/D Wrapping. Wrap block/ Balance 6 yd./sample 5 samples/DF Once in a lot change
F/D Wrapping. Wrap block/ Balance 6 yd./sample 5 samples/DF Once per 02 hrs.
Afer maint. Uster check UT-5 25 mtrs/min x 5 min 1 test / mc As per maint schedule
F/D Online CV% check. Monitor check All m/c per shif
SIMPLEX
Afer maint wrapping check Warp block/Balance 15 yds/Bobbin 6 Bobbins /mc As per maint schedule
Afer maint. Uster check UT-5 50 mtrs/min x 2.5 min 1 test /Roving, 5 Roving As per maint schedule
Simplex U% UT-5 50 mtrs/min x 2.5 min 1 test /Roving, 5 Roving Daily-3 m/c from 3 process
Ring frame
R/T Change Schedule & R/T Stock Register Each R/T Change
Roving check at R/F creel & BTS Visual Inspection Once per shif
Zinser slub yarn monitor setting check Visual Inspection Once per shif
Siro machine roving guide check Visual Inspection Once per shif
Ring Audit (Before -Afer maint) Visual Inspection As per maint schedule
Yarn Apparence board Prepare Black board winder once in a lot all count
R/F New count UT-5 test UT-5 400m/min x 1 min 6 cops/count Once for new count
Ring count & CSP Check. Wrap reel/Balance 1lea/copX6cops/mc All RF Everyday all ringframe
Ring cops Uster Check. 400m/min x 1 min 6 cops/count one m/c per Count
UT-5
Afer maint Count-CSP check Wrap reel/Balance 1lea/copX6cops/mc 6cops/RF As per maint schedule
1 Test/count,
Cone yarn Uster check UT-5 400 m/min, 1 5 cones/count All counts/day
min
Rewinding study Splice board 1 Test/count 2 full cones/Count As per required or Lot change
Length checking for Denim yarn 1 Test/count 2 full cones/Count For each new lot
One Lycra, One Denim , 24 drum
Splice Apperance check Splice board 3 Splice/drum kint& 24 drum PC,CVC /day
Splice & parent
Splice Strength check Splice Stremgth Tester yarn/spl 3 sample/spls 20 drum per day
EYC setting and clearer data checking. Clearer Monitor All m/cs check per day
Hard waste and machine pressure check Register Once per shif
Blend Ratio Check Acid, Beaker, Pipet Ratio change or once in a week
Packing
Afer Heat Count & CSP check Wrap reel, CSP Tester 1 Test/count 5 cones/count All counts/day
Ultra Violet light cone Check Register All cones per shif
Overall
BLOW ROOM:
Blow Room machine setting
Visual Inspection N/A N/A Once per shift
check
PSF tuft size check Visual Inspection Twice per shift
Contamination Collection & Format & Update in
Twice per shift
Ejection Check Excel sheet
Laydown plan wise Bale
Visual Inspection Daily
placing check
QA Pass of Laydown given Visual Inspection
Vision shield performance
Visual Inspection 0nce in a week
checking
CARDING :
B/R Nep Generation% test AFIS PRO-2 0.5 gms X 1 3 readings / card Once in a lot change
Fiber Groth test AFIS PRO-2 0.5 gms X 1 3 readings / card Once in a lot change
Wrapping Wrap block/ Balance 6 yd./sample 5 samples/card All card per day
After Maint wrapping check Wrap block/ Balance 6 yd./sample 5 samples/card As per maint schedule
After maint. Uster check UT-5 25 mtrs/min x 5 min 1 test / mc As per maint schedule
Carding Sliver U% test UT-5 25 mtrs/min x 5 min 1 test / mc Daily-3 carding from 3 line
Drawing
Growth Test (Raw Cotton to
AFIS PRO-2 0.5 gms X 1 3 readings / DF Once in a lot change
Simplex).
Autoleveller Adjust. Wrap block/ Balance 6 yd./sample 5 samples/Doubling Once in a lot change
B/D Wrapping. Wrap block/ Balance 6 yd./sample 5 samples/DF Once in a lot change
F/D Wrapping. Wrap block/ Balance 6 yd./sample 5 samples/DF Once per 02 hrs.
After maint wrapping check Warp block/Balance 15 yds/Bobbin 6 Bobbins /mc As per maint schedule
After maint. Uster check UT-5 50 mtrs/min x 2.5 min 1 test /Roving, 5 Roving As per maint schedule
Simplex U% test UT-5 50 mtrs/min x 2.5 min 1 test /Roving, 5 Roving Daily-3 m/c from 3 process
Ring frame
R/F New count UT-5 test UT-5 400m/min x 1 mi 6 cops/count Once for new count
Ring count & CSP Check. Wrap reel/Balance 1lea/copX6cops/mc All RF Everyday all ringframe
Ring cops Uster Check. UT-5 400m/min x 1 mi 6 cops/count one m/c per Count
After maint Count-CSP check Wrap reel/Balance 1lea/copX6cops/mc 6cops/RF As per maint schedule
After maint. Uster check UT-5 400m/min x 1 mi 6 cops/count As per maint schedule
Winding 1 Test/count,
Cone yarn Uster check UT-5 5 cones/count All counts/day
400 m/min, 1
min As per required or Lot
Rewinding study Splice board 1 Test/count 2 full cones/Count
change
Length checking for Denim yarn 1 Test/count 2 full cones/Count For
Oneeach new
Lycra, lotDenim ,
One
24 drum kint& 24 drum
Splice Apperance check Splice board 3 Splice/drum
PC,CVC /day
Splice Stremgth Splice & parent
Splice Strength check 3 sample/spls 20 drum per day
Tester yarn/spl
EYC setting and clearer data
Clearer Monitor All m/cs check per day
checking.
Cone trolly check Visual Inspection Twice per shift
Hard waste and machine
Register Once per shift
pressure check
Cops rejection check Register Once/shift
After Heat Count & CSP check Wrap reel, CSP Tester 1 Test/count 5 cones/count All counts/day
Ultra Violet light cone Check Register All cones per shift
Overall