Professional Documents
Culture Documents
Hazop Amp Hazid Report CNG Gas Plant Tambak Lorok Rev B
Hazop Amp Hazid Report CNG Gas Plant Tambak Lorok Rev B
DOCUMENT STATUS
Approved
:
Approved
: as Noted
Not Approved
TABLE OF CONTENTS
1 INTRODUCTION 7
1.1 BACKGROUND 7
1.2 STUDY OBJECTIVES 7
1.3 SCOPE OF HAZOP/HAZID STUDY 8
1.4 REPORT LAYOUT 8
2 PROJECT DESCRIPTION 9
2.1 OVERVIEW 9
2.1.1 Inlet scrubber (V-100) 9
2.1.2 Station Inlet metering (M-100 A/B) 9
2.1.3 Dryer Unit (D-100 A/B) 10
2.1.4 Compressor (K-101 / … / K-109) 10
2.1.5 CNG Cooler ( E-100) 11
2.1.6 CNG storage cylinders (V-200 1/../ 82) 11
2.1.7 Double pipe Exchanger 12
2.1.8 CNG Heat Exchanger (E-200) 12
2.1.9 Pressure reducing system (PV-0501 A/B) 12
2.1.10 Storage and Decanting process 12
2.1.11 Station Outlet Metering (M-200 A/B) 13
2.1.12 Waste Heat recovery Unit (E-300) 13
2.1.13 Fuel Gas 13
2.1.14 Instrument air 13
2.1.15 Cooling water (E-400) 14
2.1.16 Fire water system 14
2.1.17 Water treatment system (W-001) 14
2.1.18 Insulation 14
2.1.19 Vent System 14
3 STUDY METHODOLOGY 16
3.1 HAZOP 16
3.1.1 Overview 16
3.1.2 Worksheet Definition 16
3.2 HAZID 16
3.2.1 Overview 16
3.2.2 Worksheet Definitions 17
4.1 INTRODUCTION 18
4.2 THE HAZOP/HAZID TEAM 18
4.3 GUIDE WORDS 18
4.4 DRAWINGS REVIEWED 19
4.5 SELECTED NODES 20
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
PT. Enviromate Technology International
PT Pertadaya Gas HAZOP/HAZID of CNG PLANT TAMBAK LOROK
5 HAZOP/HAZID RESULTS 21
5.1 ACTIONS/RECOMMENDATIONS 21
5.2 MAJOR HAZARD SCENARIO 23
6 HAZOP/HAZID FOLLOW-UP 25
7 REFERENCES 26
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
EXECUTIVE SUMMARY
The PT Perta Daya Gas has awarded to PT. Enviromate Technology International (PT. ETI) to
conduct and construction of Compressed Natural Gas (CNG) facility. The plant will be located at
Tambak Lorok, Central Java, Indonesia. The CNG facility is consisting of following equipment:
Gas-Liquid separation system, Gas Drying & H2S adsorption system, Gas Compression system,
CNG Cylinders storage package, Heat Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instrument Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in Plaza
Citivew Kemang, Jakarta, utilizing 2 days for review, over the period 17th, and 21st June 2013.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak
Lorok, some of the valve arrangement need to be lock open to ensure that it doesn’t block due to
human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting
for all the instrumentation system (e.g. PIC, PSHH, PSV)
It’s been reviewed that gas from suction compressor can be directed to downstream of E-200 to
metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was
recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas
blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and
also to nsure vent stack at sump tank is located high enough to prevent exposure to
personnel/operator at Incoming Scrubber System.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
4
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B
to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in
overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is
adequate to handle fire on the CNG plant in addition with existing fire water requirement in
Tambak Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Based on the discussion raised up, it’s required to develop operating manual for delivery gas
including showing correlation between pressure and flow at storage period and operation of
redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at
cooling tower periodically.
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is
recommended to review the location of the lightning stack to be away from the venting stack to
reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the
personnel who operate the plant in daily basis. It was recommended to have noise study and provide
warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the
philosophy of the fire and gas detection system of the plant in formal documentation and provide
clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire
detection philosophy was not provided in the building, specifically in the electrical room such as
control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early
warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including
fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g.
FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review
especially in relation position of the processing facility to location where stand by personnel
available such as control room. Therefore, review of this scenario is recommended to justify design
and location of the control room building. It is include also the fire and explosion impact to
surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not
provided with glass windows to avoid explosion effect from the plant, hence that CCTV is
recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and
radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review
emergency evacuation plan including emergency route, muster point location, safety equipment lay
out and emergency lighting.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
5
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
Good communication among parties involved (Tambak Lorok and Gundih) also important to make
sure operability and deliverability of the process plant, especially to handle emergency situation.
Therefore a procedure defining internal and external communication need to be established among
parties to make sure the plant is operated safely.
• Process Hazard :
1. High Pressure Gas containment in the CNG Storage Tanks
2. Gas Compression System
3. Hot water circulation system
4. Cold Venting
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
6
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
1 INTRODUCTION
1.1 BACKGROUND
PT. Perta Daya Gas is planning to develop CNG Plant Project. The plant will be located at Tambak
Lorok, Central Java province, Indonesia.
PT. Perta Daya Gas therefore commissioned an independent Chairman and Scribe for a series of
safety studies to review and identify hazards and operability issues related to operation of
Compressed Natural Gas Plant Project.
This report details the Hazard and Operability (HAZOP) and Hazard Identification (HAZID) review
and includes a summary of the recommendations identified during the review, as well as the
HAZOP/HAZID review worksheets.
• Identify safety related hazards and operability problems related to the process that could directly
threaten the safety of production personnel or cause operational problems;
• Determine the seriousness of the consequences for the identified problems;
• Identify engineering and procedural safeguards already incorporated into the design that will
reduce the likelihood or the severity of consequences related to the identified problem;
• Evaluate the adequacy of existing engineering and procedural safeguards; and
• Recommend additional safeguards or operational procedures where necessary.
• Assess changes and consider new requirements that have emerged since the last PHA;
• Identification of new hazard causes or initiating factors associated with the modifications with a
potential to result in major accident events (MAEs), which may give rise to serious and
immediate risk to health and safety of personnel;
• Assessment of the consequences of these new MAEs;
• Determination of risk based on the likelihood and the severity of the consequences for each
identified MAEs;
• Identification of existing safeguards that may include engineering or operational controls and
measures included in the design for prevention and/or mitigation of the MAEs;
• Evaluation of the residual risk taking into account the existing control and mitigation measures;
and
• Recommendation of additional safeguards or procedures, where necessary to demonstrate as
Low as Reasonable Practicable (ALARP).
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
7
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
2. Utilities
· Venting system
· Engine Generator
• Section 1 gives an introduction, defining the objectives and scope of the study;
• Section 2 describes the process;
• Section 3 describes the HAZOP/HAZID methodology;
• Section 4 describes the HAZOP/HAZID workshops;
• Section 5 lists the references given in the report;
• Appendix A presents the summary HAZOP & HAZID recommendations;
• Appendix B presents the HAZOP review worksheets;
• Appendix C presents the HAZID review worksheets; and
• Appendix D presents the Drawings used, outlining the nodes.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
8
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
2 PROJECT DESCRIPTION
2.1 OVERVIEW
The CNG facility is consisting of following equipment: Gas-Liquid separation system, Gas Drying
& H2S adsorption system, Gas Compression system, CNG Cylinders storage package, Heat
Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instru-ment Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 to 5 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
The gas scrubber (V-100) will be installed on incoming gas to remove any hydrocarbon liquid from
upstream facility. The liquid level on the gas scrubber will be controlled by control valve LV-0101
to avoid liquid carried over to the CNG Plant. High liquid level on the scrubber will initiate the
valve to open, then if liquid level has reached normal condition valve will be closed, so the valve
will be as on/off mode.
The gas scrubber is provided with PSV-0101A/B with set pressure of 34 barg for overpressure
protection, One PSV will be on operation and another one as spare.
Inlet line will be provided with SDV-0101 in order to isolate the plant in emergency condition. The
initiators of SDV-0101 closing refer to Cause & effect diagram.
The metering will measure natural gas inlet to CNG plant. Total gas inlet is 19.88 MMSCFD. Gas
inlet would be 19.88 MMSCFD and flows to inlet compressor and 1.1 MMSCFD flows to auxiliary
fuel gas. Metering type is 2x100% custody orifice meter. Metering will be operated in continous
operation. Flow and accumulation flow should be monitored by flow computer. Gas inlet to
metering tends to consist of high moisture. Orifice should be designed for wet gas condition.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
9
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
The outlet gas from gas scrubber (V-100) will be dried through Gas Drying Unit (D-100A/B). Unit
consist of two Gas Dryer + H2S absorber, i.e D-100A/B and D-200A/B. These will be operated on
parallel configuration. Maximum capacity of drying Unit is 10 MMSCFD. The range of inlet
pressure is 20.6-25 barg. One bed will be on drying mode and the other one is on regenerating
mode. Gas dryer will remove water and H2S content on the feed gas to produce moisture dew point
to -40oC and maximum 3 ppm H2S. Dew point meter and H2S meter should be installed within
Dryer package unit. Adsorption time is 4-8 hours and the regeneration time is 4-8 hours (heating,
cooling and standby).
Gas dryer pre filter (F-100) will be provided at upstream of desiccant gas dryer (D-100A/B) to
ensure that gas goes to molecular sieve is clean and no hydrocarbon liquid carried over. One filter
will be operated and bypass line opened during filter maintenance, pressure differential indicator
will be provided across the filter such that operator will able to determine the switching operation.
Gas dryer after filter (F-110) will be provided on the downstream of desiccant gas dryer (D-100A/B)
to ensure that are there is no solid particle carried over on the gas before entering the CNG
compressor. One filter will be operated and bypass line opened during filter maintenance, pressure
differential indicator will be provided across the filter such that operator will able to determine the
switching operation.
Blower, electric heater, air cooler and liquid knocked out drum will be provided on the regeneration
line. A portion of dried gas will be utilized as regeneration gas. The regeneration gas will be heated
by an electric heater then after removing the water on the desiccants, the regent gas will be cooling
downed via the air cooler then liquid will be removed on the liquid knocked out drum. After
removing liquid on the knocked out drum, regent gas will be re-injected on the main gas line.
The valve sequences on the dryer unit will be controlled by a microprocessor on the dryer unit
package. Running and fault status on the dryer package will be transferred to Plant Control System
(PCS) for monitoring only.
The dry gas from dryer with operating pressure of 20.6-25 barg at 26.7-51.7 oCwill be transferred to
the storage cylinder at pressure of 250 barg through CNG compressors (K-
101/102/103/104/105/106/107/108/109/110). There are 10 (ten) compressor trains with 9 (nine)
compressors will be operated in parallel and 1 (one) compressor on standby mode.
Each compressor will be operated with outlet capacity of 2.3 MMSCFD at inlet pressure of 24 barg.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
10
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
The compressor is reciprocating type in three stages compression, air coolers will be provided on
each discharge stage to enhance the efficiency of compressor.
The maximum discharge pressure and temperature from CNG compressor are 250 barg and 48OC
respectively. The compressor will be supplied by vendor as a skid including electrical and
instrumentation inside. Control system of CNG compressor is provided with PLC by vendor, the
operating parameter will be transferred to Plant Control System (PCS) for monitoring purpose.
Shutdown system of the compressors will be managed by PLC, trigger of shutdown such as lube oil
pressure low, suction pressure low, discharge pressure high, discharge temperature high and High
vibration will be further developed by vendor.
Compressors are driven by Gas Engine drive with fuel gas that supplied from upstream of dryer
skid.
Compressed gas from CNG compressor with temperature of 48oC will be cooled down to 35oC
before entering to CNG cylinders. Cooling water system is closed loop cooling system which
involving CNG cooler (E-100), Cooling water circulation pump (P-200A/B) and Cooling Tower (E-
400). The compressed natural gas need to be cooled down to 35oC for optimizing the requirement of
cylinder storage capacity. The temperature of cooling water inlet to CNG cooler (E-100) is 30oC and
temperature cooling water outlet at 39oC. To avoid prolonged overpressure due to tube rupture,
CNG Compressor would be shut downed by PSHH-0503 then CNG gas would be release to cooling
water return line to Cooling tower (E-400).
Cooling water to CNG Cooler will be discontinued to produce CNG stream with temperature 48oC
and it will be commingled with CNG stream from compartment (Temperature 35 oC).
If pressure decreases and disturbing performance of CNG compressor then CNG stream could be
flowed through E-100 bypass line. Restriction orifice installed in this bypass line to giving sufficient
backpressure for CNG compressor.
CNG from E-200 will be stored at CNG storage cylinders. The CNG storage cylinders are consisting
of 95 compartment (base on 20 hours storage time at 18.7 MMSCFD CNG inlet). Each
compartment is consisting of 8 tube cylinders. One cylinder has capacity of 2.38 m3. Three CNG
compartment will be arranged in 1 (one) bank. Each bank will be provided 1 unit manual valve for
incoming and outgoing CNG. Pressure relief device (PSV) protect respectives cylinders. Discharge
PSV will be released to atmosphere and no additional pipe is required for PSV discharge line.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
11
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
If temperature at downstream PV-0501 close with -25o C, Hot water supply could be discontinued
this condition occur when pressure in compartments was dropped.
The CNG Heat exchanger is required during decanting stage, this is to reheat CNG on the
downstream of pressure reducing valve. The temperature decrease due to large pressure drop in
PV0501A/B, this is called Joule Thompson effect. Temperature on the downstream can be lower
than the dew point of CNG such that condensation may occurs.
The CNG heat exchanger (E-200) maximum duty is 4100 kW (basis 4 hours decanting time) then
duty will decrease gradually as the upstream pressure is reduced during decanting process. The
initial stage of decanting, the temperature of CNG will be increased from -38oC to about 30oC. The
heating media for this heat exchanger is hot water system with temperature of 90oC. Hot water
circulation flowrate is 140 m3/hr and the flowrate to E-200 will be controlled by (TV0502).
Temperature control Valve (TV-0502) will manipulate hot water flowrate to E-200 to maintain CNG
export to the pipeline at temperature of 30oC. Temperature control is using cascade with TIC-0502.
The pressure of CNG outlet to PLN will be maintained at 28 barg and temperature of 30oC. PIC-
0501A/B are used for controlling CNG outlet pressure. Pressure reducing system will be provided
by two control valves ( PV0501A/B) with one operating and one standby.
The storage and decanting process will be performed by opening and closing delivery valve (KV-
0501A/B) downstream of CNG storage cylinders. Storage CNG will be carried out fixed maximum
20 hours per day and decanting will be performed 4 to 5 hours per day. During decanting period the
CNG Cooler (E-100) will be bypassed to reduced joule thomphson effect on the downstream of PV-
0501A/B.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
12
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
Duration of decanting can be resetted from the control room, but changing setting time shall refer to
operating pressure on the CNG storage cylinders. Over pressure on the CNG cylinders will initiate
high pressure on the discharge compressor then process shutdown can be triggered.
The metering system with 2x100% with crossover will measure natural gas outlet from CNG plant.
Total gas outlet is 113 MMSCFD for 4 hours. Metering is used as custody meter. Flow and
accumulation flow should be monitored in main PLC. For Gas composition analysis, one sampling
connection is installed at the upstream of Outlet Metering (M200A/B).
Gas Flow would be measured for 4 hours per day during decanting time. Totalizer would count total
value base on measured gasflow.
The exhaust gas from gas engines ducting will be utilized as source of energy to increase the
temperature of hot water from 63oC to 90oC. Exhaust gas from each turbine will be commingled on
header before entering WHRU, and water will be heating up on the WHRU boiler.
Hot water from WHRU will be stored on the hot water storage Tank at temperature of 90oC.
During storage phase (20 hours), WHRU would heat water in Hot water tank (T-200) for
approximately 10 hours from 30o to 90o C. The water circulating pump (P-500 A/B) with capacity of
45m3/hr is used to circulate water from T-200 through WHRU heater (E-300) and back to T-200.
During decanting phase (4 hours), Hot water pump (P-300 A/B) with capacity of 140 m3/h will
circulate hot water from T-200 to E-200 and back to T-200. Temperature of hot water in the Hot
water tank (T-200) is controlled by manipulating damper position on each exhaust gas Turbine of
CNG compressors.
Fuel gas is supplied for two (2) units gas engine generators (1 operation & 1 stand by) thru Fuel gas
strainer and for ten (10) units gas engine compressors (9 operation and 1 unit standby). The fuel gas
strainer is designed based on capacity of less than 1.5 MMSCFD.
Fuel Gas metering (FQI-0901) is provided to measure auxilary fuel gas consumption in CNG
facility.
The instrument air will be provided on CNG plant to enhace the overall reliability of the Plant.
Instrument air requirement is calculated based on the number of control valves and on-off control
valves plus a design margin of 20%. Three (3) Air compressors will be provided with two operating
as lead and lag basis and one compressor as a standby.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
13
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
Instrument air system will be provided with a drying unit such that the dew point of instrument air is
less than -40oC.
Water as cooling media will be utilized for CNG Cooler (E-100) before storage stage, The CNG
from gas compressor with temperature of 48oC will be cooled down to 35oC using cooled water.
Cooling water is supplied to the heat exchangers through the Cooling Tower Pump (P-200 A/B) at
flowrate of 35m3/hr. After taking heat of CNG, cooling water leaves heat exchanger at temperature
of 30oC is re-circulated to the Cooling Tower ( E-400) for cooling down and reused. Make-up water
will be provided to compensate water losses on the Cooling Tower (E-400).
Fire water will be taken from existing fire water system in front of CNG plant.
Fire hydrants and monitors will be located based on equipment layout during detail engineering.
Auxiliary water for CNG plant will be taken from well in plant. Well water will be treated by
Reverse osmisis (RO) technology prior to be used as make up water. Total consumption for make
up water is 3.2 m3/h. The feedwater to the RO unit will be design accordingly based on input from
vendor.
2.1.18 Insulation
Personnel Protection Insulation (PP) shall be specified on all lines with normal operating
temperatures above 70°C. This will be applied only to sections of pipe that personnel could come
into contact with during normal operation.
Heat Conservation Insulation (HC) shall be specified for heated systems above 65°C (e.g. hot water
from WHRU).
Noise Abatement Insulation (NI) shall be specified on compressor suction and discharge lines,
subject to vendor confirmation.
Relief Gas from Pressure safety valves and Blow down system would be collected to vent header
then to vent stack. Automatic drain would be provided to controlling liquid level at bottom vent
stack.
Flame arrester would be installed at upstream of vent stack to avoid flame due to lightning or other
fire source.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
14
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
Relief gas from CNG cylinders would be free vent to atmosphere instead of to vent header line as
per client and manufacture requirement.
The vent stack with providing water seal at the bottom of the vent stack to prevent air ingress.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
15
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
3 STUDY METHODOLOGY
3.1 HAZOP
3.1.1 Overview
The study was carried out using the traditional HAZOP Guide Word method, where the system is
broken down into manageable sections and a set of standard Guide Words applied. The
methodology requires exhaustive consideration of each process activity to determine if there are any
potential problems in relation to safety or operations that may arise due to deviations in the process.
The Causes and Consequences of each deviation are identified. The HAZOP team evaluates the
severity of the problem and adequacy of existing safeguards, and where necessary, recommends
additional safeguards as Actions. The hazard and operability problems highlighted in the course of
the review were captured in the HAZOP Review worksheets (Appendix A).
All concerns raised are documented in the HAZOP Review Worksheets, which include the column
headers as described in Table 3.2a.
Guide word/Deviation A set of standard guide words used to analyse and determine
potential problems that arise
Possible Consequences Description of the consequences of the possible impact of the cause
3.2 HAZID
3.2.1 Overview
HAZID review is used as a means to identifying potential hazards, determining the associated
consequences and evaluating means of preventing the hazard or controlling the consequences. They
should not be confused with a HAZOP review which looks at specific areas of the process to
identify potential design/operating problems and determine ways of improving the process design to
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
16
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
prevent such incidents from occurring. A HAZID review is based on a combination of identification,
analysis and brainstorming activities. The technique exhaustively considers each review area, by
reference to an agreed set of guidewords. During the review, each facility was considered in turn
with the facility broken down according to specific areas or enclosed buildings, e.g., Main Deck.
All findings during the HAZID sessions are recorded by the scribe using HAZID worksheets. These
worksheets contain the column headings given in Table 3.3b.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
17
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
4.1 INTRODUCTION
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in
Plaza Citiview Kemang, Jakarta, utilizing 2 days for review, over the period 17th and 21st
June 2013.
The HAZOP/HAZID team comprises a multidisciplinary team of personnel involved with the design
and operation of the facilities, led by a safety consultant from PT PROSIM The names and
attendance records of the HAZOP/HAZID team members for each of the systems are tabulated in
Table 4.2a.
June June
Name Co. Role 2013 2013
17 21
Margaretha T PT PROSIM Chairman Ö Ö
Yulia Tirtasiwi PT PROSIM Scribe Ö Ö
Sugiyanto PT ETI Process Engineer Ö Ö
Bernardo PT ETI Ö Ö
Rudolf S PT ETI Ö Ö
Suarno PT ETI Ö Ö
Cut Julia PT IKL Project Manager Ö Ö
Warno Abdullah PT IKL Engineering Manager Ö Ö
Suseno PT IKL Process Engineer Ö Ö
Irvan N PT IKL Ö Ö
Haidar PT IKL Ö Ö
Gigin Ginanjar PT IKL Ö Ö
Isa PT IKL Process Engineer Ö Ö
The full set of Guide Words used in the HAZOP/HAZID Review is listed in Table 4.3a & b. It
should be noted that if not found to be applicable or not to produce any problem of concern that had
not already been raised, the Guide Word was not recorded in the Worksheets for that node.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
18
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
8 Less Pressure
9 More Pressure
10 Less Temperature
11 More Temperature
12 Contaminants
13 Composition
14 Corrosion / Erosion
15 Instrumentation
16 Relief
17 Personnel Safety
18 External Factors
19 Operations
20 Maintenance
21 Drawing
A basic Piping and Instrumentation (P&ID) for the process acted as a basis for discussion during the
review, along with the operating procedures. The drawings used are attached in Appendix B.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
19
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
The process was initially broken down according to the step and then by each action comprising the
step. Each action was considered separately with the full list of Guide Words applied. Thus each
action becomes a “node”, so, for instance, each feed line into a reactor was considered as a separate
node. The nodes used are presented in Table 4.5a & b while the associated worksheets are given in
Appendix A (HAZOP) and Appendix B (HAZID).
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
20
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
5 HAZOP/HAZID RESULTS
5.1 ACTIONS/RECOMMENDATIONS
A total of 40 HAZOP recommendations and 18 HAZID recommendations were generated during the
review. The recommendations would reduce potential safety or operability problems associated with
the process or improve the clarity of the process drawings (P&ID’s). A complete list of the
recommendations made by the team during the review itself is tabulated in Appendix A. A unique
number is assigned to each recommendation and the node identification number is included so that it
may easily be traced back to the review worksheets (Appendix B & C). Brief summary of
highlighted recommendations are presented below.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak
Lorok, some of the valve arrangement need to be lock open to ensure that it doesn’t block due to
human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting
for all the instrumentation system (e.g. PIC, PSHH, PSV)
It’s been reviewed that gas from suction compressor can be directed to downstream of E-200 to
metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was
recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas
blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and
also to nsure vent stack at sump tank is located high enough to prevent exposure to
personnel/operator at Incoming Scrubber System.
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B
to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in
overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is
adequate to handle fire on the CNG plant in addition with existing fire water requirement in Tambak
Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Based on the discussion raised up, it’s required to develop operating manual for delivery gas
including showing correlation between pressure and flow at storage period and operation of
redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at
cooling tower periodically.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
21
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is
recommended to review the location of the lightning stack to be away from the venting stack to
reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the
personnel who operate the plant in daily basis. It was recommended to have noise study and provide
warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the
philosophy of the fire and gas detection system of the plant in formal documentation and provide
clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire
detection philosophy was not provided in the building, specifically in the electrical room such as
control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early
warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including
fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g.
FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review
especially in relation position of the processing facility to location where stand by personnel
available such as control room. Therefore, review of this scenario is recommended to justify design
and location of the control room building. It is include also the fire and explosion impact to
surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not
provided with glass windows to avoid explosion effect from the plant, hence that CCTV is
recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and
radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review
emergency evacuation plan including emergency route, muster point location, safety equipment lay
out and emergency lighting.
Good communication among parties involved (Tambak Lorok and Gundih) also important to make
sure operability and deliverability of the process plant, especially to handle emergency situation.
Therefore a procedure defining internal and external communication need to be established among
parties to make sure the plant is operated safely.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
22
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
• Process Hazard :
1. High Pressure Gas containment in the CNG Storage Tanks
2. Gas Compression System
3. Hot water circulation system
4. Cold Venting
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
23
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
24
PT. Enviromate Technology International PT. PROSIM
PT. Pertadaya Gas
6 HAZOP/HAZID FOLLOW-UP
The project, design and operation team should conduct a HAZOP/HAZID follow up session to
response the HAZOP/HAZID recommendations. The response and action plan shall be back up with
the relevant data and justification whether the recommendation is agreed or rejected. At the end, the
team shall formulate action plans, steward all action items and ensure that the relevant changes are
made to the design to address hazard and operability concerns identified as part of this
HAZOP/HAZID.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB JULY 2013
25
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
7 REFERENCES
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BA26 JULY 2013
PT. Enviromate Technology International HAZOP/HAZID of CNG PLANT TAMBAK LOROK
Appendix A
3 Switch operation between Potential human error to operate manual valve and Provide operating manual for operating redundant CNG-HP-13
compressors safety devices equipments, including compressors
4 One of running compressor fails Less of CNG production Review sizing of manual valve incoming CNG CNG-HP-14
to operate compartment to be available at market or provide
spare manual valve in the case of maintenance
required
4 Fouling/Plugging at E-100 or Inefficiency in cooling resulting in high temperature Provide portable temperature detector to check skin CNG-HP-15
loss of cooling water leading to less CNG production temperature of CNG compartment
4 Loss of containment/piping leak Tube leak at E-100 Provide SOP to control PH at cooling tower CNG-HP-16
due to corrosion periodically
5 SDV0601 fails close or manual Potential overpressurization of CNG HE E-200 Show setting point of PV 0501A/B CNG-HP-17
valve in the metering station leading to hydrocarbon release and potential fire
inadvertenly closed
5 Gas from suction compressor Double counting of sales gas from Santos meter with Install additional check valve at line PG-2"-3C-027 CNG-HP-18
going to downstream of E-200 to M-100
metering M-200
5 Manual valve upstream BDV- Overpresurization of upstream equipment leading to Provide Lock Open (LO) manual valve at upstream CNG-HP-19
0505 inadvertenly close in the fire/fatality BDV-0505
event of ESD and BDV-0505
required to open
6 Hot Water Pump P-300A/B stop Loss of hot water supply leading to inefficient heat Provide low temperature switch at line PG-12"-3C- CNG-HP-20
due to failure OR Strainer at transfer and lower gas sales temperature 021 to close KV-0503 A to prevent low temperature
upstream P-300A/B blockage in the gas sales
6 Hot Water Pump P-300A/B stop High temperature in the circulation water around the Provide low temperature alarm at line PG-12"-3C- CNG-HP-21
due to failure OR Strainer at waste heat recovery unit 021 to alert operator
upstream P-300A/B blockage
6 Three way valve TV-0502 to E- Loss of hot water supply leading to inefficient heat Provide Temperature Control Valve at bypass line CNG-HP-22
200 is inadvertenly close transfer and lower gas sales temperature of E-200
7 Any manual valve at upstream E- Potential overpressure of downstream pump Vendor to provide minimum flow recycle line at P- CNG-HP-23
300 inadvertenly close or check 500A/B
7 One or more gas engine driver Less of flue gas to E-300 resulting in lower Review requirement set point of TIA-0704 CNG-HP-25
shutdown temperature generated for water circulation
7 Start up Low gas temperature from exhaust gas compressor to Provide drain line at lowest point gas ducting E-300 CNG-HP-26
WHRU resulting condensation at gas ducting E-300
7 Condense water from flue gas at Corrosion at E-300 leading to equipment damage Review requirement TIA-0705 CNG-HP-27
E-300
12 Manual valve upstream of Potential overpressurization of upstream piping Confirm availability of high pressure trip at CNG-HP-34
Instrument Air Receiver V-300 internal of Air Compressor C300A/B/C package to
inadvertently closed shut down compressor in the case of block of
discharge
12 Manual valve downstream Loss of instrument air supply potentially leading to Lock Open (LO) for manual valve downstream CNG-HP-35
Instrument Air Receiver V-310 PSD Instrument Air Receiver V-310
inadvertently closed
13 Operation Review existing Tambak Lorok’s fire water capacity CNG-HP-36
to be adequate for fire water handling in CNG
Plant
13 Operation Consider to provide additional flowmeter to CNG-HP-37
measure fire water consumption for Tambak Lorok
14 Any manual valve down stream Overheating at GE-100A leading to equipment Confirm availability of TSHH to trip Gas CNG-HP-38
GE-100A to cooling system damage Generator GE-100A in case of high temperature has
inadvertenly close been included in the generator package.
14 Any manual valve down stream Overheating at GE-100A leading to equipment Lock Open (LO) for manual valve downstream GE- CNG-HP-39
GE-100A to cooling system damage 100A
inadvertenly close
15 Lighting struck during Fire at vent stack Consider to install CO2 snuffing system at VS-100 CNG-HP-40
PSV/BDV release to extinguish fire at vent stack completed with
fusible plug
4.8.3 Hazardous waste Personnel injury during PPE - hand gloves, - Alocate waste disposal resulting CNG-HD- 5 S (1) 3 S (H3) Operation /
disposal handling waste disposal face shield from operation/construction C(-) C(-) Maintenance
activity in safe area (third party)
4.9.6 Hot Surfaces at Potential injury due to personal protection PPE Provide warning sign around CNG-HD- 6 S (2) 2 S (M4) Design
exhaust gas, WHRU exposure to heat insulation provided hot surface equipment and C(-) C(-)
and heat exchanger (E- pipings
200)
4.10.1 Leak from Process Release of hydrocarbon Unit SD by low Gas detection system Define philosophy of fire and CNG-HD- 7 S (4) 2 S (H8) Design
Equipment resulting in potential pressure trip at process area gas detection system and C(4) C(H8)
fire/explosion leading to develop fire and gas detection
injury/fatality area at process plant
Loss of Containment Release of hydrocarbon NA Fire hydrant provided Regularly to check temperature CNG-HD- 8 S (4) 2 S (H8) Operation /
resulting in potential with source from in the MCC cabinet and DCS C(4) C(H8) Maintenance
fire/explosion leading to existing IP panel to monitor short circuit
injury/fatality and provide portable fire
extinguisher
4.11.1 Battery Fire/explosion in the Battery room is Heat & Smoke Regularly to check temperature CNG-HD- 9 S (4) 2 S (H8) Operation /
event of hydrocarbon located in non detector, Portable Fire in the MCC cabinet and DCS C(4) C(H8) Maintenance
release. hazardous area Extinguisher provided panel to monitor short circuit
at control room & and provide portable fire
MCC room extinguisher
4.11.2 Vent Fire/explosion in the - Lightning protection Define safe location and CNG-HD- 10 S (4) 2 S (H8) Design
event of hydrocarbon provided at CNG minimum height required for C(4) C(H8)
release in process area if compartment area vent stack and vent location to
stroke by lightning be suitable with wind directions
so that dispersed gas will not be
exposed to process plan
4.12.1 Fire on Plant area Personnel trap/ unable ERP - Provide emergency evacuation CNG-HD- 11 S (4) 3 S (H8) Design
to evacuate leading to risk analysis to determine safe C(4) C(H8)
injury/fatality evacuation route and location of
muster area
4.16.1 Inability to initiate Inability to control fire Local ESD push - Define safety layout at CNG CNG-HD- 17 S (4) 2 S (H8) Design
ESD leading to potential button at control plant to show ESD push button, C(4) C(H8)
major accident leading to room fire hydrant, etc
personnel injury/fatality
and asset loss
4.18.3 Blowdown of water Potential contamination Discharge water is Define Sampling point Define Sampling point to CNG-HD- 18
from cooling tower, from process fluid connected to existing to monitor discharge monitor discharge water
discharge RO canal (IP) water
Appendix B
Ri
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Rec. No.
Words L
Parameter: Flow
1.1.1 No No Flow SDV 0101 at upstream V-100 close Potential overpresurization Pressure regulator (PV) at S (4) 1 S (M4) Ensure existing pipeline design CNG-HP-1
due to failure of upstream plant (Gundih upstream facility to adjust C(4) C(M4) pressure is higher than maximum
Facility ) resulting in discharge pressure discharge pressure from Gundih
hydrocarbon release facility
leading to fire or fatality
Loss of Production
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Rec. No.
Words L
1.1.3 No No Flow PV 0105 stuck close or manual valve Potential PIH-0103 set at 31 barg as S (4) 1 S (M4) Provide setting pressure PIC-0105 CNG-HP-4
around the PV 0105 inadvertently overpressurization of V-100 high pressure alarm to C(4) C(M4) to show at PID TS78-P
close resulting in hydrocarbon alert operator
release leading to fire or
fatality
PIHH-0103 set at 33 barG
to close SDV-0101
PSV 0101A/B set at 34 Note : maximum upstream pressure
barG is sized for fire case from Gundih is not more than 34 barG
1.1.4 No No Flow Any of manual valves at Station Inlet Potential overpresurization PIH-0103 set at 30 barg as S (4) 1 S (M4)
Metering M100A/B inadvertently of upstream M-100A/B high pressure alarm to C(4) C(M4)
close resulting to fire or fatality alert operator
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Rec. No.
Words L
1.6.1 Less Less Level Control loop malfunction causing LV- Gas blowby to Sump Tank LIL-0102 alarm to alert S (4) 1 S (M4) Provide SOP to accommodate gas CNG-HP-5
0101 to open fully V-400 leading to potential Operator C(4) C(M4) release from vent of sump tank due
vessel damage (design to gas blow by from V-100
pressure 3.5 barG), fire and
explosion
LILL-0102 to initiate Ensure equipment purchase CNG-HP-6
shutdown of SDV-0102 suitable as per hazardous area
classification
Sump Tank open to Ensure vent stack at sump tank is CNG-HP-7
atmosphere located high enough to prevent
exposure to personnel/operator
1.6.2 Less Less Level Manual valve at bypass line LV-0101 Gas blowby to Sump Tank LIL-0102 alarm to alert S (4) 1 S (M4)
or manual drain valves V-400 leading to potential Operator C(4) C(M4)
inadvertently open, leak at liquid vessel damage (design
lines pressure 3.5 barG), fire and
explosion
LILL-0102 to initiate
shutdown of SDV-0102
Sump Tank open to
atmosphere
1.7.1 More More Level Control loop malfunction causing LV- High level at V-100 leading LIH-0102 as high level S (-) 1 S (-)
0101 to stuck close to liquid carry over to alarm to alert Operator to E (2) E (L2)
metering skid M-100 and open by pass line C(2) C(L2)
downstream equipment
LIHH-0102 to initiate
shutdown of SDV-0101
1.7.2 More More Level Any of manual valve High level at V-100 leading LIH-0102 as high level S (-) 1 S (-)
upstream/downstream LV-0101 to liquid carry over to alarm to alert Operator to C(2) C(L2)
inadvertently close metering skid M-100 and open by pass line
downstream equipment
LIHH-0102 to initiate
shutdown of SDV-0101
1.7.3 More More Level SDV-0102 fails closed High level at V-100 leading LIH-0102 as high level
to liquid carry over to alarm to alert Operator to
metering skid M-100 and open by pass line
downstream equipment
LIHH-0102 to initiate
shutdown of SDV-0101
1.7.4 More More Level Slugging High level at V-100 leading LIH-0102 as high level S (-) 1 S (-)
to liquid carry over to alarm to alert Operator to C(2) C(L2)
metering skid M-100 and open by pass line
downstream equipment
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Rec. No.
Words L
LIHH-0102 to initiate
shutdown of SDV-0101
as
1.8.1 Less Less Pressure Loss of containment/piping leak Release of hydrocarbon PIL-0102 as low pressure S (4) 1 S (M4)
due to corrosion leading to environmental alarm at incoming V-100 C(4) C(M4)
pollution and potential fire to alert operator
PILL-0102 at incoming V-
100 will initiate closure of
SDV 0101
Fire and Gas Detector at V-
100
1.8.2 Less Less Pressure Refer to Misdirected Flow 1.5.1
1.9.1 More More Pressure Refer to No Flow 1.1.1, 1.1.2, 1.1.3,
1.1.4 ; Less Level 1.6.1, 1.6.2
PV-0105 stuck open Potential overpressure at PIH-S01 set at 30 bar as S (-) 1 S (-)
Metering M100A/B and high pressure alarm to E (2) E (L2)
downstream equipment alert operator C(2) C(L2)
Parameter: Instrumentation
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Rec. No.
Words L
1.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
1.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
1.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
1.18.1 Other External Factors Fire at plant Overpresurization of Fire and Gas Detector at V- S (-) 1 S (-)
Than piping leading to 100 C(2) C(L2)
equipment damage
Parameter: Operation & Maintenance
1.19.1 Other Operations No additional significant issues of
Than concerns identified
1.20.1 Other Maintenance Single isolation valve for Potential exposure of high NA Note: Certification/testing of PSV is
Than Maintenance of PSV-0101A/B pressure to personnel conducted during online operation
during maintenance of PSV- without dismantle of PSV itself.
0101A/B Dismantle of PSV can only be
conducted if there is a risk assessment
for single valve at upstream of the PSV
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
Parameter: Flow
2.1.1 No No Flow Any of manual valve at Gas Dryer Potential PIH 0102 alarm set at 30 S (4) 1 S (M4)
package is inadvertenly close overpressurization of barG to alert Operator C(4) C(M4)
upstream equipment of D-
100 leading to rupture and
potential fire event
PIHH 0102 set at 33 barG to
initiate closure of SDV 0101
2.2.1 Less Less Flow F-100 Blockage Potential PIH 0102 alarm set at 30 S (4) 1 S (M4)
overpressurization of barG to alert Operator C(4) C(M4)
upstream equipment of D-
100 leading to rupture and
potential fire event
PIHH 0102 set at 33 barG to
initiate closure of SDV 0101
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
Potential wet gas to Gas AIH (dew point alarm) at
Compression system downstream of Dryer unit
resulting in equipment
damage
2.2.2 Less Less Flow D-100A/B Blockage (caking) Potential PSH 0301A set at 32 bar at S (4) 1 S (M4)
overpressurization of Gas Dryer D-100A/B to C(4) C(M4)
upstream equipment of D- close SDV-0101
100 leading to rupture and
potential fire event
2.3.1 More More Flow BDV-0301 open due to failure Depressurization of the BDV position indication S (-) 1 S (-)
system, loss of gas to flare and alarm C(3) C(M3)
and loss of production
2.5.2 Part of Misdirected Flow Manual valve at 1/2-in drain line Gas blowby to Sump Tank SOP/Maintenance of liquid S (4) 1 S (M4)
inadvertently open/leak or liquid leading to gas cloud and trap C(4) C(M4)
trap at F-100 and F-110 stuck open potential fire and explosion
2.5.3 Part of Misdirected Flow Manual bypass line of F-100 is Potential condense liquid SOP
inadvertenly open carry over to D-100
resulting in equipment
damage
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
2.5.4 Part of Misdirected Flow Manual bypass line of F-110 is Potential condense liquid SOP
inadvertenly open carry over to compressor
unit resulting in
equipment damage
2.5.5 Part of Misdirected Flow Manual valve to regeneration unit is Ineffective regeneration PSV 0301B set at 34 barG is
inadvertenly open process in Gas Dryer D- sized for block discharge
100A/B
2.5.6 Part of Misdirected Flow Manual by pass valve at Potential wet gas to Gas SOP S (-) 2 S (-) LC by pass manual valve 10" at CNG-HP-9
downstream line PG-10-30-053 from Compression system C(3) C(M6) downstream line PG-10-30-053
metering M100A/B to Compressor resulting in equipment and update PID
unit unit is inadvertenly open damage
Parameter: Level
2.6.1 Less Less Level Refer to Misdirected Flow 2.5.2
2.7.1 More More Level Liquid trap of F-100 stuck close High level at F-100 leading SOP to open by pass
to liquid carry over to Gas manual valve 1/2"
Dryer D-100A/B
Parameter: Pressure
2.8.1 Less Less Pressure Loss of containment/leak on D-100 Release of hydrocarbon Fire and gas detection S (4) 1 S (M4)
due to corrosion leading to environmental system C(4) C(M4)
damage and potential fire
Parameter: Temperature
2.10.1 Less Less Temperature No additional significant issues of
concerns identified
2.11.1 More More temperature No additional significant issues of
concerns identified
Parameter: Contamination
2.12.1 As Well Contamination No additional significant issues of
As concerns identified
Parameter: Composition
2.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
2.14.1 Other Corrosion / Sour Gas (H2S) and water content in Internal corrosion of piping Wall thickness of piping S (3) 1 S (M3)
Than Erosion the production gas and vessel leading to and equipment already C(4) C(M4)
release of hydrocarbon gas considered sour gas
and potential fire condition
Parameter: Instrumentation
2.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
2.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
2.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
2.18.1 Other External Factors Fire Overpresurization of drier F & G S (-) 2 S (-)
Than leading to equipment C(2) C(M4)
damage
Parameter: Operation & Maintenance
2.19.1 Other Operations No additional significant issues of
Than concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
Parameter: Flow
2R.1.1 No No Flow Manual valve to regeneration system No regeneration process F-101 to collect any S (-) 1 S (-)
inadvertenly close causing wet gas going to condense liquid C(3) C(M3)
compressor
AIH (dew point alarm) at
downstream of Dryer unit
2R.1.2 No No Flow Blower E-101 at regeneration unit No regeneration process F-102 to collect any S (-) 1 S (-) Ensure interlock system install to prevent CNG-HP-11
damage/ not in operation causing wet gas going to condense liquid C(3) C(M3) overtemperature/overpressure in the case P-101
compressor shutdown, Electric Heater should also
shutdown
(Check with vendor)
Potential AIH (dew point alarm) at
overtemperature/overpres downstream of Dryer unit
sure at gas regeneration
system
Back up dryer available
2R.1.3 No No Flow F-102 blockage Pump cavitation Regular Filter mainentance S (-) 1 S (-)
C(3) C(M3)
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
2R.2.1 Less Less Flow F-102 partially blocked Pump cavitation Regular Filter maintenance S (-) 1 S (-)
C(3) C(M3)
2R.5. Part of Misdirected Flow Liquid trap at F-102 or at separator Gas blowby to Sump Tank Sump Tank connected to S (4) 1 S (M4)
after cooler stuck open leading to gas cloud and Atmospheric C(4) C(M4)
potential fire and explosion
Parameter: Pressure
2R.8.1 Less Less Pressure Loss of containment/leak on Release of hydrocarbon F & G system S (4) 1 S (M4)
regeneration system due to corrosion leading to environmental C(4) C(M4)
damage and potential fire
No. Guide Deviation Causes / Concerns Consequences Safeguards Initiating Co Pr Ri Comments / Recommendations Action Party Rec. No.
Words L
2R.8.3 Less Less Pressure Regeneration pump loss of power gas cannot circulate to AIH (dew point alarm) at S (-) 1 S (-)
due to mechanical problem regeneration system downstream of Dryer unit C(3) C(M3)
resulting in wet gas to
compressor
2R.9.1 More More Pressure See Now Flow 2R.1.3
Parameter: Temperature
2R.10.1 Less Less Temperature Electric heater stop due to In efficient heat absorbtion Maintenance S (-) 1 S (-)
mechanical failure to D-100 C(3) C(M3)
Parameter: Instrumentation
2R.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
2R.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
2R.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
2R.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
2R.19.1 Other Operations No additional significant issues of
Than concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
3.1.1 No No Flow SDV W151 fails close Potential PSH-0301A at Gas Dryer D-
overpressurization of 100A/B to close SDV-0101
upstream equipment and
piping leading to loss of
integrity and fire event
PSV 0301A/B at dryer unit
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
PILL 501 at SS-101 to
shutdown SDV-151
3.2.1 Less Less Flow Blockage of filter FF-201 Potential PSH-0301A at Gas Dryer D-
overpressurization of 100A/B to close SDV-0101
upstream equipment and
piping leading to loss of
integrity and fire event
PDI - S01 provided around
FF 201
PSV 0301A/B at dryer unit
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
4.1.1 No No Flow Manual valves at inlet CNG Less of CNG production Local pressure indicator
Compartement inadvertenly close provided each
compartment
4.2.1 Less Less Flow See no flow partially
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
4.2.2 Less Less Flow One of running compressor fails to Less of CNG production Indicator of online Review sizing of manual valve CNG-HP-14
operate compressor in control incoming CNG compartment to
room be available at market or provide
spare manual valve in the case of
maintenance required
Standby compressor
available
Indication of pressure
and flow of storage
period by graph to
shown loss of production
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
Maximum discharge
pressure of Compressor
255 barG is less than
MAWP Tube storage
design 373 barG
Parameter: Temperature
4.10.1 Less Less Temperature No additional significant issues of
concerns identified
4.11.1 More More Fouling/Plugging at E-100 or loss of Inefficiency in cooling TIH-0503/TIH 0508/TIH Provide portable temperature CNG-HP-15
Temperature cooling water resulting in high 0509 alarm will alert detector to check skin
temperature leading to less operator temperature of CNG
CNG production compartment
Parameter: Contamination
4.12.1 As Well Contamination Tube leak at E-100 Gas contamination to Gas detector at cooling Provide SOP to control PH at CNG-HP-16
As cooling water system tower fan cooling tower periodically
leading to gas release at
cooling tower
Explosion-proof motor of
cooling tower
Gas trapped at shell side TIH-0503/TIH 0508/TIH
resulting in eficient heat 0509 alarm will alert
transfer operator
Parameter: Composition
4.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
4.14.1 Other Corrosion / See contamination
Than Erosion
Parameter: Instrumentation
4.15.1 Other Instrumentation Instrument air failure Unable to supply gas to Nitrogen back up is
Than customer provided to open KV-
0501 to deliver gas from
CNG compartement to
tambak lorok
Parameter: Relief
4.16.1 Other Relief No additional significant issues of
Than concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
Parameter: Safety
4.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
4.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
4.19.1 Other Operations No additional significant issues of
Than concerns identified
4.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
4.21.1 Other Drawing No additional significant issues of
Than concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
5.1.1 No No Flow Any of manual valves on the Compressor shut off PIH 0502 set at 250psig to
decanting line to E-200 inadvertenly pressure is 255 barg vs alert operator
close or PV0501A/B stuck close design pressure of
equipment is 263 barg - no
adverse consequence
identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
PIHH 0502 set at 255 psig to
shutdown compressor
5.3.1 More More Flow PV0501A/B stuck open Potential PIH 0509 set at 31 psig to
overpressurization of CNG alert operator
HE E-200 and downstream
piping
PSHH 0509 set at 33 barG to
close KV 0501A
5.4.2 Reverse Reverse Flow Gas from suction compressor going Double counting of sales Install additional check valve at CNG-HP-18
to downstream of E-200 to metering gas from Gundih meter line PG-2"-3C-027
M-200 with M-100
5.5.1 Part of Misdirected Flow BDV-0505 fails open Loss of gas to vent BDV position indicator and
alarm in control room
5.5.2 Part of Misdirected Flow XV-0506 fails open Loss of gas back to system Valve position indicator and
instead to customer alarm in control room
Parameter: Level
5.6.1 Less Less Level No additional significant issues of
concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
5.7.1 More More Level No additional significant issues of
concerns identified
Parameter: Pressure
5.8.1 Less Less Pressure Loss of containment/leak on Release of hydrocarbon F&G
Decanting Line leading to environmental
damage and potential fire
Parameter: Temperature
5.10.1 Less Less Temperature No additional significant issues of
concerns identified
5.11.1 More More temperature No additional significant issues of
concerns identified
Parameter: Contamination
5.12.1 As Well Contamination Tube leak at E-200 Gas contamination to hot Atmospheric venting at Hot
As water system leading to gas Water Tank T-200
release at WHRU
Parameter: Composition
5.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
5.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
5.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
5.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
5.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
No. Guide Deviation Causes / Concerns Consequences Safeguards Comments / Recommendations Action Party Rec. No.
Words
5.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
5.19.1 Other Operations No additional significant issues of
Than concerns identified
5.20. Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
5.21.1 Other Drawing No additional significant issues of
Than concerns identified
Design To heat compressed gas from storage facility to be ready for sales gas
Intent
Design E-500 DP : 2 barG Temperature: 120 deg C T-200 : 290 m3
Conditions: T-200 DP : 0.17 barG P-300 : 140 m3/hr
E-500 : 127 kW
Opt. Source Pressure : atm; Discharge Pump : 3.35 barG CNG Heat Exchanger : Inlet /Outlet Shell side : OT : 90 deg C / 65 deg C Power : 36.8 kW
Conditions
Drawing PID - Waste Heat Recovery Unit Drawing No. TS78-P-PID-007 Rev: B
PID - CNG Heat Exchanger TS78-P-PID-005 sheet 2 of 2 B
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
6.1.1 No No Flow Hot Water Pump P-300A/B stop Loss of hot water supply TT-0512 as low temperature S (-) 1 S (-) Provide low temperature switch at line CNG-HP-20
due to failure OR Strainer at leading to inefficient heat alarm to alert operator C(2) C(L2) PG-12"-3C-021 to close KV-0503 A to
upstream P-300A/B blockage transfer and lower gas prevent low temperature in the gas
sales temperature sales
High temperature in the TIC 0703 set at 85 deg C to Provide low temperature alarm at line CNG-HP-21
circulation water around control exhaust gas supply PG-12"-3C-021 to alert operator
the waste heat recovery from compressor
unit
TAH 0703 set at 85 deg C
alarm to alert operator
TAH 0706 set at 85 deg C
alarm to alert operator
Low discharge pressure for SOP to operate standby
hot water circulation pump P-300B
leading to inefficient heat
transfer
6.1.2 No No Flow Manual valve on the downstream Loss of hot water supply TT-0512 as low temperature S (-) 1 S (-)
P300A/B inadvertently closed leading to inefficient heat alarm to alert operator C(2) C(L2)
transfer and lower gas
sales temperature
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
High temperature in the TIC 0703 set at 85 deg C to
circulation water around control exhaust gas supply
the waste heat recovery from compressor
unit
TAH 0703 set at 85 deg C
alarm to alert operator
TAH 0706 set at 95 deg C
alarm to alert operator
Potential PSHH 0703A set at 4.5 barG
overpressurization of to close P-300A/B
upstream piping
6.2.1 Less Less Flow Three way valve TV-0502 to E-200 is Loss of hot water supply TT-0512 as low temperature S (-) 1 S (-) Provide Temperature Control Valve at CNG-HP-22
inadvertenly close leading to inefficient heat alarm to alert operator C(2) C(L2) bypass line of E-200
transfer and lower gas
sales temperature
High temperature in the TIC 0703 set at 85 deg C to
circulation water around control exhaust gas supply
the waste heat recovery from compressor
unit
TAH 0703 set at 85 deg C
alarm to alert operator
Three way valve TV-0502 to by pass Not adverse consequence
line E-200 is inadvertenly close
6.3.1 More More Flow Hot Water Pump P-300A andB Excess hot water supply to TIC-0502 as high S (-) 1 S (-)
running simultaneously E-200 resulting in potential temperature alarm to alert C(2) C(L2)
overheating operator
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Pressure
6.8.1 Less Less Pressure refer to No Flow 6.1.1
6.9.1 More More Pressure Refer to No Flow
Parameter: Temperature
6.10.1 Less Less Temperature Leak at hot water system at Loss of hot water supply TT-0512 as low temperature S (-) 1 S (-)
discharge P-300A/B leading to inefficient heat alarm to alert operator C(2) C(L2)
transfer and lower gas
sales temperature
High temperature in the TIC 0703 set at 85 deg C to
circulation water around control exhaust gas supply
the waste heat recovery from compressor
unit
TAH 0703 set at 85 deg C
alarm to alert operator
TAH 0706 set at 85 deg C
alarm to alert operator
6.10.2 Less Less Temperature Fouling/Plugging at E-200 Inefficiency in heating TT-0512 as low temperature S (-) 1 S (-)
resulting in lower gas alarm to alert operator C(2) C(L2)
temperature
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Operation & Maintenance
6.19.1 Other Operations No additional significant issues of
Than concerns identified
6.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
6.21.1 Other Drawing No additional significant issues of
Than concerns identified
Design To recover heat from exhaust gas of compressor and heating water for heating media E-100 and E-200
Intent
Design Pressure: WHRU : 18 Barg Temperature: WHRU : 545 deg C P-500 : 48 m3/hr
Conditions:
Opt. Shell / Coil : 0.03 barG / 3 barG Shell / Coil OT : 490 deg C / 63 to 90 deg C Power : 1283 kW
Conditions
Drawing PID - Waste Heat Recovery Unit Drawing No. TS78-P-PID-007 Rev: B
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
7.1.1 No No Flow Water Circulation Pump P-500A/B Loss of water circulation TIC-0703 to close S (-) 1 S (-)
stop due to failure OR Strainer at leading to overheating of dampener from C(2) C(L2)
upstream P-500A/B blockage hot water circulation to T- compressor flue gas
200
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
routed to open drain
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
7.1.2 No No Flow Any manual valve at upstream E-300 Loss of water circulation TIC-0703 to close S (-) 1 S (-)
inadvertenly close or check valve leading to overheating of dampener from C(2) C(L2)
blockage hot water circulation to T- compressor flue gas
200
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
7.2.1 Less Less Flow Any manual valve on the water Loss of water circulation TIC-0703 to close S (-) 1 S (-)
circulation line at WHRU system leading to overheating of dampener from C(2) C(L2)
partially closed hot water circulation to T- compressor flue gas
200
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
7.3.1 More More Flow Water Circulation Pump P-500A/B Excess water circulation to Pump running status
running simultaneously E-300/T-200 - no safety indication at control room
consequence
7.4.1 Reverse Reverse Flow No additional significant issues of
concerns identified
7.5.1 Part of Misdirected Flow 3/4" manual valve to open drain Loss of water circulation TIC-0703 to close S (-) 1 S (-)
inadvertenly open leading to overheating of dampener from C(2) C(L2)
hot water circulation to T- compressor flue gas
200
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
7.5.2 Part of Misdirected Flow Manual valve to venting open Loss of water circulation TIC-0703 to close S (-) 1 S (-)
leading to overheating of dampener from C(2) C(L2)
hot water circulation to T- compressor flue gas
200
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
Parameter: Level
7.6.1 Less Less Level No additional significant issues of
concerns identified
7.7.1 More More Level No additional significant issues of
concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Pressure
7.8.1 Less Less Pressure Refer to No Flow 6.1.1
7.9.1 More More Pressure Refer to No Flow
Parameter: Temperature
7.10.1 Less Less Temperature Refer to No Flow
One or more gas engine driver Less of flue gas to E-300 TIA 0704 to alert operator S (-) 1 S (-) Review requirement set point of CNG-HP-25
shutdown resulting in lower C(2) C(L2) TIA-0704
temperature generated for
water circulation
Start up Low gas temperature from Provide drain line at lowest point CNG-HP-26
exhaust gas compressor to gas ducting E-300
WHRU resulting
condensation at gas
ducting E-300
7.11.1 More More Refer to No Flow, Less Flow,
Temperature Misdirected Flow
Parameter: Contamination
7.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
7.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
7.14.1 Other Corrosion / Condense water from flue gas at E- Corrosion at E-300 leading Check with vendor the S (-) 2 S (-) Review requirement TIA-0705 CNG-HP-27
Than Erosion 300 to equipment damage requirement of TIA-0705 C(2) C(M6)
as low temperature alarm
Parameter: Instrumentation
7.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
7.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
7.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
7.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
7.19.1 Other Operations No additional significant issues of
Than concerns identified
7.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
7.21.1 Other Drawing
Than
7.21.2 Other Drawing
Than
7.21.3 Other Drawing Revise drawing TS78-P-PID-007 to CNG-HP-28
Than show setting point of all
instrumentation alarm and trip
Design to treat sea water and provide potable water for cooling media
Intent
Design Pressure : 7 barG Temperature: 65 deg C Flow : 3.2 m3/hr
Conditions:
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
8.1.1 No No Flow Manual valve at inlet Feed Pump No make up water supply SOP to monitor Water S (-) 2 S (-)
P701 inadvertenly close for cooler/heater leading Treatment Plant (WTP) C(1) C(L2)
to low performance of heat
transfer
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
8.1.4 No No Flow High Pressure Pump P702 failure No make up water supply Pump maintenance S (-) 2 S (-)
for cooler/heater leading C(1) C(L2)
to low performance of heat
transfer
8.1.5 No No Flow Manual valve downstream P702 No make up water supply SOP to monitor Water
inadvertenly close for cooler/heater leading Treatment Plant (WTP)
to low performance of heat
transfer
Manual valve downstream PU-201 No make up water supply SOP to monitor Water S (-) 2 S (-)
inadvertenly close for cooler/heater leading Treatment Plant (WTP) C(1) C(L2)
to low performance of heat
transfer
8.2.2 Less Less Flow Filter FX-01/02 blockage Potential overpressure of PDI 1201 to monitor S (-) 2 S (-)
upstream equipment differential pressure C(1) C(L2)
8.2.3 Less Less Flow RO-A blockage Potential overpressure of PSH 1211 to stop P702 and S (-) 2 S (-)
upstream equipment P701 C(1) C(L2)
8.3.1 More More Flow Control valve upstream FM 1205 Potential overflow to TK01 LS01 to stop FEED pump S (-) 1 S (-)
stuck open P701 C(1) C(L1)
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Temperature
8.10.1 Less Less Temperature No additional significant issues of
concerns identified
Parameter: Contamination
8.12.1 As Well Contamination No additional significant issues of
As concerns identified
Parameter: Composition
8.13.1 Other Composition Manual valve from chemical source Low make up water SOP
Than inadvertenly close quality leading to scale
Parameter: Instrumentation
8.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
8.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
8.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: Drawing
8.21.1 Other Drawing
Than
Opt. Pressure : ATM Temperature : 30 - 45 deg C Power P-100 : 0.85 kW; P-200A/B :
Conditions 5.88 kW
Drawing PID - Cooling System Drawing No. TS78-P-PID-011 Rev: B
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
9.1.1 No No Flow Manual valve at inlet T-100 is Low level at T-100 leading LSL 1101 to shutdown S (-) 2 S (-)
inadvertenly close to loss of pump suction and Pump P-600 C(2) C(M4)
potential pump damage
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Pump maintenance
9.1.4 No No Flow Manual valve or strainer at inlet Loss of make up water for Temperature alarm at E-100 S (-) 1 S (-)
Basin cooling water is inadvertently cooling media leading to C(2) C(L2)
close ineffective heat transfer
Potential overflow at T-600 Floating valve at T-600 to Review design of floating valve T- CNG-HP-30
start/stop pump P-100 600 to be radar type
9.1.5 No No Flow Cooling water pump P-200A/B Loss of make up water for Pump running status S (-) 1 S (-)
broken or not in operation cooling media leading to indication at control room C(2) C(L2)
ineffective heat transfer
9.1.6 No No Flow Manual valve at upstream P-200A/B Loss of pump suction and Strainer Maintenance S (-) 2 S (-) Provide lock open (LO) for manual CNG-HP-31
inadvertenly close or strainer potential pump damage periodically C(2) C(M4) valve upstream P-200
blocked
Loss of make up water for
cooling media leading to
ineffective heat transfer
9.1.7 No No Flow Manual valve at downstream P- Potential PSH 1108A to stop P- S (-) 1 S (-)
200A/B inadvertently close overpressurization of 200A/B C(2) C(L2)
piping at pump discharge
9.3.1 More More Flow Cooling Tower Pump P-200 A and B More of water cooling Pump running status
running simultenaously media - no adverse indication at control room
consequence
9.4.1 Reverse Reverse Flow No additional significant issues of
concerns identified
9.5.1 Part of Misdirected Flow 3" manual valve at T-100/E-400 to Low level at T-100 leading LSL 1101 to shutdown
open drain inadvertenly open to loss of pump suction and Pump P-600
potential pump damage
9.5.1 Part of Misdirected Flow 2" manual valve at E-400 to open Low level at E-400 leading Floating valve will flow
drain inadvertenly open to loss of pump suction and water from T-600
potential pump damage
Parameter: Level
9.6.1 Less Less Level see no flow 9.1.1, 9.1.2,9.1.3,9.5.1 Loss of water for cooling
media resulting insufficent
heat absorbed during heat
transfer leading to CN gas
offspec
9.6.2 Less Less Level Make up water pump P-100 fails to Low level at T-100 leading LSL 1101 to shutdown S (-) 2 S (-)
stop to loss of pump suction and Pump P-100 C(2) C(M4)
potential pump damage
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
High level at Cooling Float valve will stop
Tower basin T-600 incoming flow to cooling
tower
9.7.1 More More Level Float valve at Cooling Tower basin E- Potential overflow to open SOP S (-) 1 S (-)
400 failure drain C(2) C(L2)
Parameter: Pressure
9.8.1 Less Less Pressure Leak in water supply line to E-100 Loss of water for cooling S (-) 2 S (-)
media resulting insufficent C(2) C(M4)
heat absorbed during heat
transfer leading to CN gas
offspec
9.9.1 More More Pressure see no flow 9.1.1, 9.1.2,9.1.3
Parameter: Temperature
9.10.1 Less Less Temperature No additional significant issues of
concerns identified
9.11.1 More More Motor at E-400 fails to run high temperature of water TT-0503 at E-100 as high S (-) 1 S (-)
Temperature supply to E-100 leading to temperature alarm to alert C(2) C(L2)
less production operator
Parameter: Contamination
9.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
9.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
9.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
9.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
9.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
9.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
9.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
9.19.1 Other Operations No additional significant issues of
Than concerns identified
9.20.1 Other Maintenance No additional significant issues of
Than concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Drawing
9.21.1 Other Drawing
Than
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
10.1.1 No No Flow 4" manual valve at inlet V-400 High level at source vessel Safeguards at source vessel S (-) 1 S (-)
inadvertenly closed C(1) C(L1)
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Double-valve provided at
drain line of the individual
equipments
10.4.1 Reverse Reverse Flow No additional significant issues of
concerns identified
10.5.1 Part of Misdirected Flow No additional significant issues of
concerns identified
Parameter: Level
10.6.1 Less Less Level Sump Pump P-400 fails to stop due Loss of liquid level leading Pump will be stopped S (-) 1 S (-)
to LT-1001 failure to function to Sump Pump P-400 during no signal (FC) C(1) C(L1)
damage due to cavitation
10.7.1 More More Level Pump stopped due to no power Overfilling of Sump Tank LAH 1001 as high level S (-) 1 S (-)
supply or pump damage V-400 and liquid release alarm to alert operator C(1) C(L1)
from vent to environment
Parameter: Pressure
10.8.1 Less Less Pressure No additional significant issues of
concerns identified
10.9.1 More More Pressure Refer to More flow
10.9.2 More More Pressure Blockage of flame arrestor at vent Potential Bug screen provided
line overpressurization of V-
400
Parameter: Temperature
10.10.1 Less Less Temperature No additional significant issues of
concerns identified
10.11.1 More More No additional significant issues of
Temperature concerns identified
Parameter: Contamination
10.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
10.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
10.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
10.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Relief
10.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
10.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
10.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
10.19.1 Other Operations No additional significant issues of
Than concerns identified
10.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
10.21.1 Other Drawing
Than
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
11.1.1 No No Flow 3" Manual valves at Loss of fuel gas supply PT-0902 as low pressure S (-) 1 S (-) Provide lock open (LO) for 3" CNG-HP-33
incoming/outgoing line Fuel Gas leading to compressor alarm to alert operator C(4) C(M4) manual valves at upstream and
filter is inadvertently closed shutdown downstream Fuel Gas Filter
11.1.2 No No Flow PCV-0901A/B stuck closed Loss of fuel gas supply PT-0902 as low pressure S (-) 1 S (-)
leading to compressor alarm to alert operator C(4) C(M4)
shutdown
Standby PCV available
11.2.1 Less Less Flow Pump N4 stop due to failure Less of fuel gas supply PDI 0901A/B to monitor S (-) 1 S (-)
leading to compressor differential pressure C(2) C(L2)
shutdown
Back up fuel gas filter
available
PT-0902 as low pressure
alarm to alert operator
11.3.1 More More Flow PCV-0901A/B stuck open Potential PT-0902 as high pressure S (-) 1 S (-)
overpressurization of alarm to alert operator C(1) C(L1)
downstream equipment
11.4.1 Reverse Reverse Flow No additional significant issues of
concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
11.5.1 Less Misdirected Flow No additional significant issues of
concerns identified
Parameter: Level
11.6.1 Less Less Level No additional significant issues of
concerns identified
11.7.1 More More Level No additional significant issues of
concerns identified
Parameter: Pressure
11.8.1 Less Less Pressure Refer to No Flow and Less Flow
11.9.1 More More Pressure Refer to More Flow
Parameter: Temperature
11.10.1 Less Less Temperature No additional significant issues of
concerns identified
11.11.1 More More No additional significant issues of
Temperature concerns identified
Parameter: Contamination
11.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
11.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
11.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
11.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
11.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
11.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
11.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
11.19.1 Other Operations No additional significant issues of
Than concerns identified
11.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
11.21.1 Other Drawing
Than
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
12.1.1 No No Flow Manual valve upstream of Loss of instrument air Instrument air supply from S (-) 1 S (-)
Instrument Air Receiver V-300 supply potentially leading Instrument Air Receiver V- C(2) C(L2)
inadvertently closed to PSD 300 is provided for 5
minutes in operation
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Potential PSV 0801 set at 12 barG
overpressurization of release air to atmosphere
upstream piping
12.1.3 No No Flow Any manual valve upstream of Air Loss of instrument air Instrument air supply from
Dryer D300A/B inadvertently supply potentially leading Instrument Air Receiver V-
closed to PSD 300 is provided for 5
minutes in operation
12.1.7 No Flow Manual valve downstream Loss of instrument air Instrument air supply from S (-) 1 S (-) Lock Open (LO) for manual valve CNG-HP-35
Instrument Air Receiver V-310 supply potentially leading Instrument Air Receiver V- C(2) C(L2) downstream Instrument Air Receiver
inadvertently closed to PSD 310 is provided for 5 V-310
minutes in operation
Potential
overpressurization of
upstream piping
12.2.1 Less Less Flow Air Dryer Prefilter F300A/B Less of instrument air PDI 0801 to monitor S (-) 1 S (-)
blockage supply potentially leading differential pressure C(2) C(L2)
to PSD
Wet instrument air quality Dew Point Meter D0801
resulting in
instrumentation damage
leading to potential
shutdown
Spare Air Dryer Prefilter
available
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
12.2.2 Less Less Flow Air Dryer D-200A/B blockage Less of instrument air PDI 0802A/B to monitor S (-) 1 S (-)
supply potentially leading differential pressure C(2) C(L2)
to PSD
Wet instrument air Dew Point Meter DE 0801
resulting in
instrumentation damage
leading to potential
shutdown
Spare Air Dryer available
12.2.3 Less Less Flow Air Dryer After Filter F301A/B Less of instrument air PDI 0802 to monitor S (-) 1 S (-)
blockage supply potentially leading differential pressure C(2) C(L2)
to PSD
Wet instrument air quality Dew Point Meter D0801
resulting in
instrumentation damage
leading to potential
shutdown
Spare Air Dryer After filter
available
12.3.1 More More Flow All Air Compressor running
simultaneously - no adverse
consequence
12.4.1 Reverse Reverse Flow No additional significant issues of
concerns identified
12.5.1 Part of Misdirected Flow 3/4" manual drain valve at V-300 High pressure air blowby Sump Tank V-400 is open to S (-) 1 S (-)
inadvertently close to sump tank V-400 atmosphere C(2) C(L2)
Parameter: Temperature
12.10.1 Less Less Temperature No additional significant issues of
concerns identified
12.11.1 More More No additional significant issues of
Temperature concerns identified
Parameter: Contamination
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
12.12.1 As Well Contamination No additional significant issues of
As concerns identified
Parameter: Composition
12.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
12.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
12.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
12.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
12.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
12.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
12.19.1 Other Operations No additional significant issues of
Than concerns identified
12.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
12.21.1 Other Drawing No additional significant issues of
Than concerns identified
12.21.2 Other Drawing No additional significant issues of
Than concerns identified
Design to provide cooling system and extinguish fire from the process plant and building
Intent
Design Pressure : ATM Temperature: 45 deg C
Conditions:
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
13.1.1 No No Flow Any of manual valve at fire water Lack of fire water supply SOP S (3) 1 S (M3)
ring inadvertently close/stuck close resulting in inadequate C(3) C(M3)
water to extinguishing fire
13.1.2 No No Flow Existing fire water pump inoperation Fail to supply fire water in S (3) 1 S (M3)
case of fire leading to fire C(3) C(M3)
escalation
13.2.1 Less Less Flow Any of manual valve at fire water Lack of fire water supply SOP S (3) 1 S (M3)
ring partially close resulting in inadequate C(3) C(M3)
water to extinguishing fire
Parameter: Level
13.6.1 Less Less Level No additional significant issues of
concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
13.7.1 More More Level No additional significant issues of
concerns identified
Parameter: Pressure
13.8.1 Less Less Pressure see less flow
13.9.1 More More Pressure No additional significant issues of
concerns identified
Parameter: Temperature
13.10.1 Less Less Temperature No additional significant issues of
concerns identified
13.11.1 More More No additional significant issues of
Temperature concerns identified
Parameter: Contamination
13.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
13.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
13.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
13.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
13.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
13.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
13.18.1 Other External Factors No additional significant issues of
Than concerns identified
Parameter: Operation & Maintenance
13.19.1 Other Operations Review existing Tambak Lorok’s fire CNG-HP-36
Than water capacity to be adequate for fire
water handling in CNG Plant
13.19.2 Other Operations Consider to provide additional flowmeter CNG-HP-37
Than to measure fire water consumption for
Tambak Lorok
13.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
13.21.1 Other Drawing
Than
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
14.1.1 No No Flow Power Generator unable to operate No power generated Standby Generator S (-) 1 S (-)
due to damage leading to plant shutdown provided C(3) C(M3)
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
14.7.1 More More Level No additional significant issues of
concerns identified
Parameter: Pressure
14.8.1 Less Less Pressure see less flow
14.9.1 More More Pressure see more flow
Parameter: Temperature
14.10.1 Less Less Temperature No additional significant issues of
concerns identified
14.11.1 More More Any manual valve down stream GE- Overheating at GE-100A S (-) 1 S (-) Confirm availability of TSHH to CNG-HP-38
Temperature 100A to cooling system inadvertenly leading to equipment C(3) C(M3) trip Gas Generator GE-100A in
close damage, plant shutdown case of high temperature has been
included
Lock Open in (LO)
the generator package.
for manual valve CNG-HP-39
downstream GE-100A
Parameter: Contamination
14.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
14.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
14.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
14.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
14.16.1 Other Relief No additional significant issues of
Than concerns identified
Parameter: Safety
14.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Flow
15.1.1 No No Flow No additional significant issues of
concerns identified
15.2.1 Less Less Flow No additional significant issues of
concerns identified
15.3.1 More More Flow PSV or BDV passing Loss of gas to atmosphere Flame arrestor installed S (4) 1 S (M4)
resulting gas cloud around C(4) C(M4)
process area and potential
fire if ignited
15.4.1 Reverse Reverse Flow Air ingress to venting system Potential fire/explosion Water seal at bottom of vent S (4) 1 S (M4)
inside piping stack to prevent air ingress C(4) C(M4)
to venting system
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
Parameter: Level
15.6.1 Less Less Level No additional significant issues of
concerns identified
15.7.1 More More Level Liquid carry over from PSV/BDV release of hydrocarbon Vent stack is equipped by S (-) 1 S (-)
liquid to environment dead leg to collect liquid C(2) C(L2)
and drain to Sump Tank V-
400
Parameter: Pressure
15.8.1 Less Less Pressure No additional significant issues of
concerns identified
15.9.1 More More Pressure No additional significant issues of
concerns identified
Parameter: Temperature
15.10.1 Less Less Temperature No additional significant issues of
concerns identified
15.11.1 More More No additional significant issues of
Temperature concerns identified
Parameter: Contamination
15.12.1 As Well As Contamination No additional significant issues of
concerns identified
Parameter: Composition
15.13.1 Other Composition No additional significant issues of
Than concerns identified
Parameter: Corrosion / Erosion
15.14.1 Other Corrosion / No additional significant issues of
Than Erosion concerns identified
Parameter: Instrumentation
15.15.1 Other Instrumentation No additional significant issues of
Than concerns identified
Parameter: Relief
15.16.1 Other Relief No additional significant issues of
Than
Parameter: Safety concerns identified
15.17.1 Other Occupational No additional significant issues of
Than Safety concerns identified
Parameter: External Factor
15.18.1 Other External Factors Lighting struck during PSV/BDV Fire at vent stack S (4) 1 S (M4) Consider to install CO2 snuffing CNG-HP-40
Than release C(3) C(M3) system at VS-100 to extinguish
fire at vent stack completed with
fusible plug
Parameter: Operation & Maintenance
15.19.1 Other Operations No additional significant issues of
Than concerns identified
15.20.1 Other Maintenance No additional significant issues of
Than concerns identified
Parameter: Drawing
No. Guide Deviation Causes / Concerns Consequences Safeguards Iniating L S L R Comments / Recommendations Action Party Rec. No.
Words
15.21.1 Other Drawing
Than
15.21.2 Other Drawing
Than
Appendix C
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
4.1.1 Natural Events Earthquake Potential of loss of - Plant, equipment,
plant integrity building and
leading to damage foundation design
and hydrocarbon anticipated to
release accommodate
earthquake factor
(0.15G), referring to
UBC-1997 and soil
investigation result
4.1.2 Natural Events Rob in process area Potential damage to Plant is designed NA
process equipment above Rob
posistion (80 cm
above average
ground level vs
70 cm average
rob) and in high
position
4.1.3 Natural Events Lightning Possible damage to - Grounding provided Update EQL drawing to CNG-HD- 1 S (4) 4 S (H16)
the equipment and for each equipment show Lightning C(3) C(H12)
potential fire protection at CNG
compartment area
(lightning stack) in
process/utility area
Lightning protection at
CNG compartment
area (lightning stack)
in process/utility area
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
4.1.4 Natural Events Settlement Possible damage to - Pile foundation (block
the equipment and design) provided to
potential fire withstand settlement
4.1.5 Natural Events Land slide No major concern -
4.2.1 External Events External corrosion Damage to the Painting & Periodic maintenance S (-) 2 S (-)
equipment, loss of coating for piping and inspection for all C(3) C(H9)
production and equipment surface vessels and
pipings
-
4.3.1 Transportation Light vehicles impact Potential impact to - vehicle park area away Operation cars shall be CNG-HD- 2 S (4) 2 S (H8)
e.g. Car piping/equipment from process area equipped with flame C(4) C(H8)
leading to arrestor and diesel engine
hydrocarbon
release, fire,
personnel
injury/fatality and
asset damage
4.3.2 Transportation Heavy equipment to Potential impact to Concrete road Pipe bridge provided S (4) 2 S (H8)
gas plant e.g. mobile piping/equipment to connect each C(4) C(H8)
crane leading to equipment across road
hydrocarbon
release, fire,
personnel
injury/fatality and
asset damage
4.4.1 Lifting Lifting equipment Potential damage to SOP for lifting - S (-) 2 S (-)
(mobile crane, forklift) pipeline and activity including C(2) C(M4)
failure equipment certified
personnel to
conduct the
lifting
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
SOP for control - S (4) 2 S (H8)
personnel C(4) C(H8)
incoming to the
plant
4.6.2 Security Vandalism No additional - -
significant issues of
concerns identified
4.6.3 Security Wild animals (tiger, No additional - -
crocodile and snake) significant issues of
concerns identified
4.7.1 Noise High noise level from Potential personnel - Provide SOP to wear ear CNG-HD- 3 S (1) 3 S (H3)
compressor and gas ear injury plug around noise area C(-) C(-)
engine area
4.8.1 Health Hazards Toxic Material during Personnel injury MSDS provided Ensure portable eye wash CNG-HD- 4 S (1) 3 S (H3)
handling chemical: for in the storage station provided during C(-) C(-)
cooling water, facility chemical handling (e.g : at
corrosion inhibitor e.g. control room, loading area
oxygen scavanger and water treatment area)
4.8.2 Health Hazards Handling molecular Personnel exposure PPE - hand JSA S (1) 3 S (H3)
sieve at dryer system to H2S resulting in gloves, face C(-) C(-)
personnel injury shield
4.8.3 Health Hazards Personnel hygiene and Health impact to Toilet and pantry Medical emergency S (1) 4 S (M4)
living activity operator are provided in provided (clinic) for C(-) C(-)
control room operation personnel
building
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
4.8.3 Health Hazards Hazardous waste Personnel injury PPE - hand - Alocate waste disposal CNG-HD- 5 S (1) 3 S (H3)
disposal during handling gloves, face resulting from C(-) C(-)
waste disposal shield operation/construction
activity in safe area (third
party)
4.9.1 Maintenance/ Working at high Fall and slip Maintenance Permit to works system S (4) 2 S (H8)
construction location such as resulting in access provided C(-) C(-)
lightning pole, WHRU injury/fatality at WHRU
4.9.2 Maintenance/ Hot/cold Work Fire and potential SOP for hot/cold permit to works system S (4) 2 S (H8)
construction fatality work activity C(4) C(H8)
during
construction,
including
competent
personnel
4.9.3 Maintenance/ Confined Space Entry Potential fatality SOP for confined permit to works system S (4) 2 S (H8)
construction due to asphyxiation space entry C(-) C(-)
during
maintenance and
construction,
including
4.9.5 Maintenance/ Electrical Hazards Potential Proper insulation ELCB (Earth Leakage S (4) 2 S (H8)
construction electrocution for Circuit Breaker) C(-) C(-)
resulting in cabling/wiring provided for electrical
injury/fatality equipment/devices e.g.
welding machine
4.9.6 Maintenance/ Hot Surfaces at Potential injury due personal PPE Provide warning sign CNG-HD- 6 S (2) 2 S (M4)
construction exhaust gas, WHRU to exposure to heat protection around hot surface C(-) C(-)
and heat exchanger (E- insulation equipment and pipings
200) provided
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
4.10.1 Loss of Leak from Process Release of Unit SD by low Gas detection system Define philosophy of fire CNG-HD- 7 S (4) 2 S (H8)
Containment Equipment hydrocarbon pressure trip at process area and gas detection system C(4) C(H8)
resulting in and develop fire and gas
potential detection area at process
fire/explosion plant
leading to
injury/fatality
- Fire hydrant provided Regularly to check CNG-HD- 8
with source from temperature in the MCC
existing IP cabinet and DCS panel to
monitor short circuit and
provide portable fire
extinguisher
4.11.2 Ignition Sources Vent Fire/explosion in - Lightning protection Define safe location and CNG-HD- 10 S (4) 2 S (H8)
the event of provided at CNG minimum height required C(4) C(H8)
hydrocarbon compartment area for vent stack and vent
release in process location to be suitable
area if stroke by with wind directions so
lightning that dispersed gas will not
be exposed to process
plan
S (4) 2 S (H8)
C(4) C(H8)
4.11.3 Ignition Sources Static electricity from Fire/explosion in - vehicle park area away S (4) 2 S (H8)
external vehicle the event of from process area C(4) C(H8)
hydrocarbon
release.
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
4.12.1 Escape/ Refuge Fire on Plant area Personnel trap/ ERP - Provide emergency CNG-HD- 11 S (4) 3 S (H8)
unable to evacuate evacuation risk analysis to C(4) C(H8)
leading to determine safe evacuation
injury/fatality route and location of
muster area
- - S (4) 5 S (H8)
C(4) C(H8)
4.13.1 Emergency Personnel trap in Personnel Emergency - S (4) 6 S (H8)
Lighting wrong way injury/fatality lighting for C(4) C(H8)
evacuation is
provided in
control room and
evacuation route
4.14.1 Manned Building Control room Fire or explosion - Heat and Smoke Review scenario of fire CNG-HD- 13 S (4) 2 S (H8)
from process area detector and explosion from gas C(4) C(H8)
impact to control plant to the area of
room leading to standby personnel such as
potential personnel control room and provide
injury/fatality mitigation plan (design
and location of the
building) to anticipate
fire/explosion
- - S (4) 4 S (H8)
C(4) C(H8)
Inability to monitor - - Consider to provide CNG-HD- 15 S (4) 5 S (H8)
process area CCTV in the control room C(4) C(H8)
for monitoring purpose
No. Category/ Hazard Description Consequences Prevention Control Recommendation/ Rec Number Action Party Co. Pr Ri
Guideword Comment
4.15.1 Communication Inability to contact Inability to Each operator F&G alarm system Define internal and CNG-HD- 16 S (4) 2 S (H8)
control room within coordinate response provided with external communication C(4) C(H8)
emergency leading to potential hand held radio system (PABX) for
major accident connecting operator in the
leading to control room to outside
personnel parties
injury/fatality and
asset loss
4.16.1 Shutdown Inability to initiate Inability to control Local ESD push - Define safety layout at CNG-HD- 17 S (4) 2 S (H8)
ESD fire leading to button at control CNG plant to show ESD C(4) C(H8)
potential major room push button, fire hydrant,
accident leading to etc
personnel
injury/fatality and
asset loss
4.16.2 Shutdown Loss of power Plant shutdown ESD is fail safe UPS is provided S (-) 2 S (-)
resulting loss of action C(4) C(H8)
production
Uncontrolled - Alternative power S (-) 3 S (-)
process upset source from PLN for C(4) C(H8)
emergency equipment
4.17.1 Other Plant layout - - S (-) - S (-)
C(-) C(-)
Appendix D
Drawings Reviewed
NODE 1
NODE 2
NODE 2
NODE 2R
NODE 3
NODE 4
NODE 6
NODE 5
NODE 5
NODE 7
NODE 6
NODE 12
NODE 12
NODE 11
NODE 10
NODE 9
NODE 8
NODE 13
NODE 14
NODE 15