GEEKNSON

GEEK FURNITURE

STANDARD PROJECT TEMPLATE

Project number: ……………………………………………………………………………………………………

Production Manager: ………………………………………………………………………………………………

Project Manager: …………………………………………………………………………………………………

Workshop manager: ………………………………………………………………………………………………

Customer name: …………………………………………………………………………………………………...

Customer contact info.: ……………………………………………………………………………………………

SPECIFICATIONS
Playing Surface: ……………………………………………………………………………………….

Type of Wood: Oak Mahogany Teak Elm

Table: Length: ……………………………………………………………………

Width: ……………………………………………………………………..

Thickness: ……………………………………………………………….

Height: ………………………………………………………………….

Chair: Frame Height:

Frame Width: …………………………………………………………….

Seat Length: …………………………………………………………….

Seat Width: …………………………………………………………….

Cushions: Yes No Color:

Armrests: Yes No

Optional Extras: ………………………………………………………………………………………………

Other Personalisations: ……………………………………………………………………………………….


PROJECT BREAKDOWN

GAMING
TABLE

TABLE CHAIRS FINISHING

OPTIONAL
TOP FRAME
EXTRAS

LEGS SEAT SANDING

LEGS STAINING

ARMREST
RISKS

COMMON
RISK MITIGATION RESPOSIBLITY
Customer enquiry not being Ensure phones and website is Sales and Marketing
received or answered monitored constantly Department
Inadequate information from Follow prompts from this Project manager
consultation template
Unavailability of required Ensure alternative materials have Project manager and
material been researched Procurement department
Supplier delay Order as early as possible Procurement department
Equipment breakdown Have cushion days Workshop manager
Accidents in the workshop Ensure proper safety regulations Workshop manager
are followed
Product not to specification Proper communication with Project manager and
customer Workshop manager
Delivery delay Proper scheduling must be Project manager
followed

PROJECT SPECIFIC

RISK MITIGATION RESPONSIBILITY


TIME LINE

First contact KEY

Critical path

Consulatation

Design

Deposit MILESTONES
payment
ACTIVITY DAY DATE (Insert exact dates)

First Contact Designate as first day


Material Consultation Max of 14 days
ordering
Designing Max of 7 days after consultation

Deposit Payment 1 day after design completion


Construction
Material ordering 2 days after design completion
• Tables
• Chairs Construction commencement Max 10 days after ordering
• Finishing
Construction completion Max 30 days

Finishing 3 days after fully constructed


Testing Testing and packing Max of 2 days

Delivery and installation Max of 1 day

Packing

Delivery

Installation
• Checking
WEEKS
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
First
contact
Consultati
on
Design
Deposit
Payment
Material
Arrival
Constructi
on
Finishing
Testing
Packing
Delivery
Installation
COMMUNICATION
Communication is the key to project success and customer satisfaction

AUDIENCE MEANS REASON RESPONIBILITY


Customer Email or Phone  Response to enquiry
 Consultation  Project manager
 Quotation communication  Sales and marketing
 Delivery department
 Satisfaction
Production manager Meetings and reports  Progress of project Project Manager
 Problems encountered
Workshop Manager Meetings and Reports  Design and Client  Project manager
specifications  Procurement department
 Arrival of Material
 Progress of construction
 Solution to problems
encountered
Material suppliers Email or phone  Materials required  Procurement department
 Delivery  Project manager
 Cost
Chairman Meetings, Reports and  Progress of projects  Project manager
Phone  Problems encountered  Production manger
 Finance

OTHER INFORMATION
Delivery Location: ………………………………………………………………………………

Customer Comments…………………………………………………………………………….

……………………………………………………………………………

……………………………………………………………………………..

Signatures

Project Manager…………………………………………...

Production manager………………………………………….

Workshop Manager…………………………………………...

Chairman……………………………………………………….