Professional Documents
Culture Documents
2 Months Lookahead Plan & Major Material Requirments
2 Months Lookahead Plan & Major Material Requirments
160,422,911.67
___________________
Marshall Dmello
Sr. Manager (Accounts)
SPCPL E & C
Shapoorji Pallonji & Co. Pvt. Ltd.
JOYVILLE RESIDENTIAL PROJECT
BOLINJ, VIRAR
146,121,590.80
___________________
Marshall Dmello
Sr. Manager (Accounts)
SPCPL E & C
Shapoorji Pallonji & Co. Pvt. Ltd.
JOYVILLE RESIDENTIAL PROJECT
BOLINJ, VIRAR
___________________
Marshall Dmello
Sr. Manager (Accounts)
SPCPL E & C
Shapoorji Pallonji & Co. Pvt. Ltd.
JOYVILLE RESIDENTIAL PROJECT
BOLINJ, VIRAR
___________________
Marshall Dmello
Sr. Manager (Accounts)
SPCPL E & C
Shapoorji Pallonji & Co. Pvt. Ltd.
JOYVILLE RESIDENTIAL PROJECT
BOLINJ, VIRAR
___________________
Marshall Dmello
Sr. Manager (Accounts)
SPCPL E & C
Pvt. Ltd.
ROJECT
9 - APRIL 2018
Amount Amount Amount
Upto previous Present Total
- 0.00 0.00
54,694.00 0.00 54,694.00
82,041.00 0.00 82,041.00
77,820,882.12 2,014,014.96 79,834,897.08
___________________
Marshall Dmello
Sr. Manager (Accounts)
SPCPL E & C
Joyville Monthly Plan For August 2018 Joyville Towerwise Plan Vs Achieved for August 2018
4 Anti - termite Treatment Works Sq.m. 65 2124 138060 138060 2124 138060 100% Completion in August 18 2124 138060 0 0 0 0
5 Grade slab -M15 cum 3450 296 1021856 690000 296.19 1021855.5 100% Completion in August 18 200 690000 0 0 0 0
GF TO FF: 20% completed in April 18 ; 80% in GF TO FF:20% completed in April 18 ; 80% in
May 18 FF SLAB; May 18 FF SLAB;
FF TO SF: 20% Columns from FF TO SF in May FF TO SF: 100% Columns from FF TO SF & 80% SF
18; 80% Columns from FF TO SF in June 18 & Slab
100% SF Slab in June 18 ;
SF TO TF: 0% in June 18 Columns from SF TO TF;
SF TO TF: 100% in JuLY 18 Columns from SF 100% Columns + sLAB- July 2018
0% Columns (Grade Slab to P1 Slab)- to TF. + 3rd Floor Slab in August 2018
June; 3rd to 4th : 25% Columns in July +75% Columns
Reinforcement of Column & 3rd to 4th : 100% Columns in July 18 + 100% + 100% 4TH Slab in August
6 MT 41000 165 6,767,498.02 5924295 30.56592724 1253203.0169 10 410000 50.19 2057790 4TH Slab August 18 50.19 2057790 2 Slabs 84.305 3456505 84.305 3456505
Slabs 40% COLUMNS IN August 18;
4th to 5th : 100% Columns + Slab - August 18
17% slab in August 2018
5TH TO 6th : 100% Column + Slab- August 18
6th to 7th : 100% Column + Slab- August 18
8 SlabCasting (M30) Cum 3800 166 630800 0 166 630800 1st PourConcrete 0 0 0 0 0 0 0 0
Labour Cost Block Work 0 - 0 Only one Floor Considered. And not even 174 41760 Only one Floor Considered. And not even Stilt 0 0
12 Sqm 240 174.00 41760 0 Stilt Level Level
(150MM)at Floor Level
Depreciation(PMV+ MATERIAL+
17 Mivan + Tower Crane to be 268,558.52 192,808.52 0
added)
Tower crane 1
(7286000)+Tower crane 2
23 TOTAL DC Cost 36,452,983.95 24,109,773.50 726,080.00 (7286000)+ Concrete pump 1
Lac+ 5.06 lac mivan formwork
(90mt)
7286000 1,539.78
109290 10,265.19
218580 1,026.50
0.6926952141 1500
3.26
264000
23.376
2.66
1000 0.3929263566
1000
0.64
177.25
62.6
684.5
Budget for the quarter (In Rs.)
S. No. Description
Jul-17 Aug-17 Aug-17-Actual Sep-17 Sep-17-Actual
Budget for the quarter (In Rs.) Budget for the quarter (In
483.24 144.56 135.71 149.80 241.81 193.46 173.07 487.81 550.58 220.03 144.91 69.73
0.00 200.00 200.00
642.49 144.56 135.71 149.80 241.81 193.46 173.07 487.81 550.58 220.03 144.91 69.73
81.26 153.56 94.54 154.02 114.37 48.81
54.45 88.25 78.53 66.01 30.54 20.92
89.95
345.81 78.67 59.64 78.67 86.41 78.67 89.95 236.00 236.00 21.68 104.53 17.59
89.12 24.00 21.00 24.56 33.64 29.25 26.96 77.81 81.60 28.69 26.81 14.06
918.18 247.22 216.35 253.02 361.86 301.38 289.98 801.62 868.19 295.59 276.25 144.88
9.18 2.47 2.16 2.53 3.62 3.01 2.90 8.02 8.68 2.96 2.76 1.45
Q2-P Oct-P Oct-A Nov -P Dec-P Q3-P Jan-P Feb-P
840 1
840
get for the quarter (In Rs.)
April -18 May-18 ( As
June-18 ( As June -18 July -18 (As July -18 RA
Mar-18 Total - Q4 - SubmittedQ ( As per April -18 per May -18 per
FEB -18 actual Mar-18 Monthly per Monthly bill Not yet
Submitted 2017 4 2017 Monthly Submitted Monthly Submitted Planning) Submitted Planning) Submitted
Palnning) Planning)
85.0056 71.37 59.16 361.13 289.08 113.52 23.81 150.42 368.33 150.35 106.08 228.15
85.01 71.37 59.16 591.05 289.08 113.52 23.81 150.42 368.33 150.35 106.08 228.15
59.16 49.96 54.80 56.76 20.14 97.63 346.77 82.86 101.91 154.30
25.84 21.41 4.36 50.03 3.67 52.79 21.56 67.49 4.17 73.85
63.01 34.03 29.63 73.30 197.17 21.89 119.00 21.89 117.16 23.69 141.70 24.91
15.17 24.17 9.10 66.92 51.09 13.88 14.64 17.66 49.76 17.84 25.40 25.94
163.19 249.00 97.89 689.47 537.34 149.29 157.45 189.97 535.25 191.88 273.18 279.00
1.63 2.49 0.98 6.89 5.37 1.49 1.57 1.90 5.35 1.92 2.73 2.79
Mar-P Q4-P
10.76
9038.4 1782000
August -18
(As per Remarks
Monthly
Planning)
362.00
28.43
333.57
6.65
6.00
0.65
0.18
29.16
40.09
431.25
4.31
Sep-18 Cash Flow
Planned cash flow
Sr.No. Activity Unit Rate
Qty.
1 Backfilling cum 500 1200
2 Tower 6 & 7 BWK @ plinth cum 6150 10
3 Rubble Soling Cum. 745 66
4 Anti - termite Treatment Works Sq.m. 65 287
5 Grade slab -M15 cum 3450 22
6 Reinforcement of Column & Slabs MT 41000 222
7 Concrete Works M 40 Grade- Columns + Slab cum 4125 1290
8 SlabCasting (M30) Cum 3800 567
9 Concrete Works M35 Grade: Columns + Slab Cum 4100 436
10 Labour cost for Tower 6&7 Sq Ft 150 60201
11 Labour Cost of Block Work (100MM) at Floor Level Sqm 2400 89
12 Labour Cost Block Work (150MM)at Floor Level Sqm 240 174
13 Labour Cost Block Work (200MM)at Floor Level Sqm 1200 11
14 Waterproofing Sqm 933 19
15 MEP Works- Electrical 0
Total D.C work Value
IDC & others
DC + IDC
DC + IDC @ 10.25% markup
P.R
Qty
5 M.T
upto 8th floor t6 & T7 raised, T1 podium P2 slab raised, Next P.R to be raised
0 8,007 PO available
659 990 PO available
0 to be checked
2574 sqm sufficent
2082 CFT sufficent
Approved, STO done except CT props
652 Liters Upto P2 level
326 Liters Upto P2 level
4092 kg Upto P2 level
600 Nos Upto P2 level
500 nos Upto P2 level
2550 RMT Upto P2 level
1200 Liters Upto 10th floor level in T6 & T7, next P.R will be raised
17650 kg upto 15th floor
8000 Liters
12 Liters
38 kg
Joyville Monthly Plan For Sept 201
Sr.No
Activity Unit
.
1 Backfilling cum
2 Tower 6 & 7 BWK @ plinth cum
3 Rubble Soling Cum.
14 Waterproofing Sqm
15 MEP Works- Electrical
16 Formwork Depreciation
Depreciation(PMV+ MATERIAL+
17 Mivan + Tower Crane to be
added)
18 Procurement Items
19 Cement Procurement
22 Variation items
23 TOTAL DC Cost
26 MARKUP 10.25%
Expected Billing without taxes F =
27 D+E
Monthly Plan For Sept 2018
65 287 18636
3450 22 74184
41000 222 9,112,487.80
4125 1290 5321250
5,487,000.00
268,558.52
1,600,000.00
2,331,000.00
2,300,000.00
516,000.00
100,000.00
38,824,123.90
2,916,000.00
41,740,123.90
4278363
46,018,486.60
Tower 1
1200 600000
10 61500
65.941 49126.045
286.7 18635.5
21.5025 74183.625
87.7608 3598192.8
374 1542750
567 2154600
0 0
26,680.50 1099522.37682
Tower 1
Remarks Qty.
Ramp 0
Ramp 0
P1 Slab + Beam = 41.5 MT; Columns
= 72.368 mt-10MT ( Taken in August
18);
50.19
Ramp : P0-P1 = 9.65 MT
0
For Grade Slab Level: 70% TAKEN
EARLIER ;0% Completion in April 18 ;
0% completion in May 18 ; 7.5% in
June 18; 17.5 % in July 18 (5% ; 19,503.58
August 2018 Completed
-
-
-
Joyville Towerwise Sept 2
Tower 6
Amount Remarks
0
0
0
0
GF TO FF: 20% completed in April 18 ; 80% in
May 18 FF SLAB;
0
FOR GF TO FF :15% TAKEN FOR FF; 0% FOR FF
IN MAR18 ; 40% for For April 2018; 25% For
May 18 FOR ; 15% for June 18 (5% HOLD);
FOR FF TO SF : 70% FOR July 18
2925536.4 FOR SF TO TF: 95% FOR August 18
0 Of one Flat
ville Towerwise Sept 2018 Plan
Tower 6
0
14,627.68 2194152.3
684.5
Tower 7
0 0
0 0
0
0
0 0
0 0
3 Slabs 84.305 3456505
1 Slab 436 1798500
0 0
436 1787600
1.5 Slab 33446.384 5016957.6
89 213600
174 41760
11 13200
19.295 18,008.67
3.26
23.376
2.66
0.7
475
0.64
Tower 7
Remarks
GF TO FF:20% completed in April 18 ; 80% in
May 18 FF SLAB;
205 840500
29265.586 4389837.9
0 0
0 0
0 0
0 0
489,000.00
726,080.00
1,000,000.00
Salary + Dept. Labour+ Land
Rent (1.25 lac)+Security
(14000*6) +100000-
Kitchen+Dinning PCC+Rubble
+Road Entrance PCC+
rUBBLE+ Aluminium Shed for
Fab +
Tower crane 1
(7286000)+Tower crane 2
(7286000)+ Concrete pump 1
Lac+ 5.06 lac mivan formwork
(90mt)