P06363 Coaching For Perf FNL
P06363 Coaching For Perf FNL
P06363 Coaching For Perf FNL
WELLSITE Name..................................
PERFORMANCE
Coach................................
...........................................
Restricted
C ontents
Foreword ...................................................................... 3
Introduction.................................................................... 3
HSE............................................................................... 4
People........................................................................... 5
Performance................................................................... 6
Technology..................................................................... 7
QA/QC........................................................................ 8
Technical Assurance........................................................ 9
Contacts ..................................................................... 11
Notes.......................................................................... 13
Restricted
F orewor d
The Wells Learning & Development (L&D) strategy provides industry leading technical training
through the Wells Distance Learning Package and Round 1 & 2 examinations, but post Round
2 we have until now lacked advanced learning events to further develop the performance
leadership skills of our site supervisors.
This booklet is part of a training programme designed to enhance the capabilities of site
supervisory staff and thus enable improved operational and safety performance at our well sites
in pursuit of Top Quartile and Goal Zero.
Peter Sharpe
Executive Vice President, Wells
Projects & Technology.
I ntro d uction
Welcome to the Well site Coaching for TQ Performance booklet.
There are seven tables in this guide. Each table represents a theme that aligns with the functional
improvement plan. The tables contain selected TQ objectives for each respective theme and the
relevant actions supporting each TQ objective.
As a participant of the Coaching for Wells TQ Performance programme, you are expected to
use this guide to enable TQ performance at your well site. This will be achieved by completing
all of the actions listed in this booklet and ensuring quality closeout. If there are actions that are
not clear or you find difficult to progress, a Principle Site Supervisor (PSS), in your region, will
provide coaching to help you throughout the programme. You are expected to complete this
programme within one-year time.
When you have completed an action, you are required to close out with a completion date
and ensure sign-off by your line supervisor (LS) or PSS. It is advised that evidence text is included
in the notes pages to enable assessment of the quality of close out. The PSS will also monitor
progress and performance at your location and will give you feedback and identify any
performance gaps.
Restricted 3
HSE
Close Initial by
Actions
out date LS/PSS
Objective: Prevent fatalities in Wells Operations.
1. Actively seek out routine tasks which require adherence to Life Saving Rules and
update JSAs to reflect the Life Saving Rules.
2. Assess the effectiveness of Life Saving Rules – for example using well site quiz
(Check LSR website for ideas).
3. Address in implementation, any gaps highlighted through review and quiz
results.
4. Monitor and report non-compliance incidents to establish key learning.
Following investigation, ensure accountability follow up.
Objective: TQ HSE behaviour and performance among all company site
representatives.
1. Personally reflect on why safety is important for you, consider your past
experiences. Document it and practice explaining it to others.
2. Use HSE behaviour framework for self assessment and include for review in
performance appraisal (available on Global HSE functional website).
3. Participate in incident investigation training.
4. Identify your top 3 behaviour and performance gaps and build an action plan
to address the gaps.
5. Close out action plan and report compliance level.
Objective: 100% compliance to DROPS standard – 0 dropped objects incidents.
1. Roll out DROPS standards on site and communicate clearly to all personnel.
2. Assign DROPS Lead on your site and agree your DROPS campaign including
regular review meetings.
3. Conduct DROPS gap analysis/audit and communicate findings and learning.
4. Close out audit action list and report compliance level.
Objective: TQ contractor HSE behaviour and performance.
1. Assess the contractors’ on-site HSE management systems (toolbox talks, PtW,
JSA, HSE critical equipment preventive maintenance, etc) using Worksite
Hazard Minimum framework and using ‘non-related’ parties where possible
(available on Global HSE functional website).
2. Identify top 3 behaviour and performance gaps and build an action plan with
the contractor to address the gaps.
3. Close out action plan and report compliance level.
Objective: Creating a TQ HSE environment at your well site.
1. Create the expectation (preferably on induction) with personnel arriving on site.
Introduce TQ HSE behaviour and performance to all new personnel.
2. Conduct daily HSE well site walks, talk to personnel on site about the risks they
are working with and their mitigations and view critical equipment. Record
positive and negative findings from these discussions and observations.
3. Participate in Safety meetings and share observations with all personnel.
4. Cascade learning from relevant HIPOs and close out relevant actions.
5. Communicate and enforce zero tolerance to rule breaking.
Restricted 5
P erformance
Close Initial by
Actions
out date LS/PSS
Objective: Creating a performance focused environment.
1. Prepare a personal story illustrating why performance improvement is important
to you. Present at weekly meetings.
2. Highlight and congratulate individual and team success – ‘meet or beat’ the
activity plan.
3. Hold simple worksite After Action Reviews and encourage others to adopt –
What did we plan, what did we achieve, what did we learn!
4. Record performance improvement interventions in trip report and share with
SWE.
Objective: Flawless execution of the optimised well programme.
1. Establish a material and services ‘load-out-list’ ensuring all equipment and
services are ordered, received and back loaded in a timely manner.
2. Prepare and communicate a 24hr well site activity plan.
3. Set mini targets and display current best performance within the plan.
4. Select critical well site activities on all shifts and personally witness them.
Objective: Achieve TQ well delivery using the Global Well Delivery Process.
1. Give input to the detailed well design – optimise the well programme.
2. Make sure the DWOP takes place prior to well programme approval and has
full rig team and service contractor involvement.
3. Close out actions identified in DWOP for rig and service contractors team.
Objective: Ensure subsequent execution activities benefit from learnings and
good ideas to prevent recurring problems.
1. Capture, record and report all positive and negative performance gains against
the activity plan.
2. Establish actions to ensure positives are repeated and negatives are eliminated.
3. Communicate actions to the team, assigning responsibility were appropriate.
Objective: Improve Drilling Efficiency ($/ft).
1. Establish 5 Drilling Efficiency Optimisation Activities for your rig based on
“DEO recommendations” (Refer Shell Wiki).
2. Monitor, report and display actual (bit on bottom) ROP vs planned by formation.
Restricted 7
QA/QC
Close Initial by
Actions
out date LS/PSS
Objective: Achieve 0% NPT due to Quality related issues.
1. Ensure that all Non-Productive Times (NPT) are recorded and reported correctly
on a daily basis.
2. Review RCFA (root cause failure analysis) Awareness Bulletins: http://sww.shell.
com/ep/epw/wells/RCFA-PWR/home.html
3. Communicate relevant alerts to well site team and ensure controls are in place.
4. Report QA/QC related NPT events that exceeds 6 hours to Trouble Action Team
(TaT) team via Wells QA/QC Manager: melvyn.wright@shell.com
Objective: Improve service contractor QA/QC performance.
1. Identify key quality control factors prior to activity execution. Consider the
following if applicable:
a. Vendor Quality Management System – Evidence.
b. Verify critical equipment inspection validation performed at vendors site
prior to delivery – Wells QA/QC Team.
c. Verify certificate of conformity or other applicable information for verification
on equipment receipt.
d. Verify process control plan as appropriate and FAT (factory acceptance test)
have been followed and verified.
e. Verify service hand training history in QA/QC.
f. Verify that service contractor is on approved vendors list.
g. Ensure that the service provider feedback information documentation is fully
completed and submitted.
2. Assign single point responsibility for each of the control factors identified.
3. After each operation use the AAR process to assess job quality vs activity
execution plan.
Objective: Flawless receipt and preparation of equipment and tubular goods
at rig site.
1. Ensure requirements for load transportation, safekeeping and heavy lift are
understood and complied with for the receipt and shipping of all goods.
2. Verification of rig ready status:
a. Ensure correct quantity and description of goods (size, weight, grade).
b. Visual inspection for damage by qualified individual or service hand
(threads, seal surfaces, X-over subs) – inform appropriate personnel for
action if damage encountered.
c. Ensure equipment functionality checks are made and acceptable prior to
running in hole.
d. For critical wells and top 70 projects, it is advised that the liner hanger
technical support team is contacted prior to running.
Objective: Encourage positive QA/QC practises and eliminate waste (non-
scheduled events).
1. Report areas of excellence and areas to improve in QA/QC – Utilise the
practices worth replicating (PWR) web based application.
2. http://sww-pwr.shell.com/pwr/index.jsp
3. Forward by email, areas of improvement of QA/QC practices to the Wells
QA/QC Manager.
Restricted 9
C ontracting & P rocurement ( C & P )
Close Initial by
Actions
out date LS/PSS
Objective: Achieving TQ contractor performance.
1. Know the key performance indicators for each contract.
2. Create and maintain a contractor well site performance improvement
action plan.
3. Report all significant contract performance non-compliance to the contract
holder.
4. Establish and maintain an accurate record of key internal and contractor focal
points (e.g. contract holder, CP contract engineer, cost controller, contractor
account manager etc.).
Objective: Establish and maintain excellent contractor relations.
1. Manage external requests for action for contractors from non well site sources.
2. Hold monthly well site contractor engagement and discuss performance status,
contractual issues and improvement opportunities.
3. Raise contract disputes to contract holder, agree action and close-out within
an agreed timeframe.
4. Ensure your roles and responsibilities are defined and there is a clear
understanding between yourself and contractor supervisor with respect
to crew engagement.
Objective: Ensure accurate and consistent cost reporting.
1. Personally check and approve all daily drilling reports ensuring appropriate
contract rate allocation.
2. Ensure contract rates are up to date in daily drilling cost tracking tool.
3. Ensure contract rate summary sheets are available on site and referenced prior
to signing service tickets.
Objective: Achieving TQ Sub-Contractor Management.
1. Conduct a quarterly check on lead contractor’s process for managing
subcontractor performance.
2. Report findings to contract holder.
Restricted 11
ECCN: Not subject to EAR – No disclosure of technology.
Restricted - This document is classified as Restricted. Access is allowed to Shell personnel, designated Associate
Companies and Contractors working on Shell projects who have signed a confidentiality agreement with a Shell
Group Company. ‘Shell Personnel’ includes all staff with a personal contract with a Shell Group Company. Issuance
of this document is restricted to staff employed by a Shell Group Company. Neither the whole nor any part of this
document may be disclosed to Non-Shell Personnel without the prior written consent of the copyright owners.