Professional Documents
Culture Documents
Work Progress Measurement System: XXX-XXX-XXX 0
Work Progress Measurement System: XXX-XXX-XXX 0
REV
CONTRACTOR COMPANY
REV DATE PURPOSE
PREP’D CHK’D APP’D APP’D
1 22-MAY-18 ISSUED FOR PROPOSAL LIS
RECORD OF REVISION
The revisions listed below have been incorporated in this copy of the document.
TABLE OF CONTENTS
1. SCOPE ............................................................................................................................ 4
1. SCOPE
This Procedure shall cover the basis and method of progress measurement for PT. Pupuk
Kujang (COMPANY) for CO2 Plant Project, which is prepared by PT. Encona Inti Industri
(CONTRACTOR). This procedure describes the basis and method to be used for calculating
the progress of Engineering (Incl. Project Management), Procurement, Construction,
Commissioning and Overall progress of the Project.
1. DEFINITION OF PROGRESS
1.1. General Definition of Progress
Progress is generally defined as:
2. Breakdown
Master Document List Deliverables are further classified in disciplines (see
Appendix 2).
Work steps for deliverables as mentioned in Appendix 3.
(c) Work steps i.e., Issued For Review (IFR)/Issued For Approval (IFA), Issued For
Construction (IFC) and Approved For Construction (AFC). (see Appendix 3)
2. Breakdown
Procurement progress is classified in disciplines (refer to Appendix 4)
Work steps for procurement activities as mentioned in Appendix 5.
Procurement progress shall be rolled up as follow;
(a) Work discipline, i.e., mechanical, civil, electrical, etc (see Appendix 4).
Work steps, i.e., Issue Purchase Order (PO), Vendor Engineering Document
Approved, etc. (see Appendix 5)
2. Breakdown
Commissioning progress is broken down in to unit wise (refer to Appendix 9).
Commissioning progress shall be rolled up as follow;
(a) Unit wise, i.e., Unit XX-De-Humidifying System, Unit ZZ-Refrigerant System, etc
Doc. No:
CO2 PLANT PROJECT
XX-XXX-XXX
Rev. 0 Page : 7 of 21
WORK PROGRESS MEASUREMENT SYSTEM
Date : 22-May-2018
3. APPENDIXES
APPENDIX 3 WORK STEPS AND WEIGHT FACTORS FOR PMT AND ENGINEERING
DELIVERABLES
APPENDIX 1
OVERALL TO ENGINEERING, PROCUREMENT AND CONSTRUCTION
APPENDIX 2
WEIGHT FACTORS FOR EACH WORK DISCIPLINE FOR ENGINEERING
APPENDIX 3
WORK STEPS AND WEIGHT FACTORS FOR ENGINEERING DELIVERABLES
CATEGORY WEIGHT FACTOR AGGREGATE
1. Engineering
IFR/IFA
Issued For Review 35.00% 35.00%
Issued For Approval 35.00% 70.00%
IFC
Issued For Construction 10.00% 90.00%
AFC
Approved For Construction 10.00% 100.00%
Doc. No:
CO2 PLANT PROJECT
XX-XXX-XXX
Rev. 0 Page : 10 of 21
WORK PROGRESS MEASUREMENT SYSTEM
Date : 22-May-2018
APPENDIX 4
WEIGHT FACTORS FOR EACH CATEGORY AND DISCIPLINE WORKS FOR
PROCUREMENT
WEIGHT
DISCIPLINE PACKAGE FACTOR
3. Rotary 23.06%
R-XXXX CO2 Compressor 86.13%
R-XXXX LCO2 Transfer Pump 7.07%
R-XXXX Cooling Water Circulation Pump 6.80%
Sub Total 100.00%
4. Package 22.47%
R-XXXX De-Humidifying Package 25.66%
Refrigerant Package 74.34%
Sub Total 100.00%
5. Piping 9.08%
R-XXXX Carbon Steel (CS) And LTCS Pipes 22.11%
R-XXXX Stainless Steel (SS) Pipes 34.67%
R-XXXX Cast Carbon Steel And LTCS Gate, 5.78%
Globe Valves, Check Valves
R-XXXX Carbon Steel And LTCS Fittings 5.15%
Stainless Steel (SS) Fitting 3.55%
R-XXXX Cast Stainless Steel (SS) And LTCS 1.66%
Gate, Globe Valves, Check Valves
R-XXXX Flanges And Orifice Flanges 5.51%
R-XXXX Bolts And Nuts 6.59%
R-XXXX Gaskets 14.98%
Sub Total 100.00%
6. Instrument 9.78%
R-XXXX PLC 31.92%
R-XXXX Level Transmitter 0.96%
R-XXXX Level Gauge 0.51%
R-XXXX Pressure Differential Indicator 1.20%
R-XXXX Pressure Transmitter 2.18%
R-XXXX Temperature Transmitter 1.37%
R-XXXX Temperature Indicator 0.55%
R-XXXX Process Analyser 1.46%
R-XXXX Control Valves & Pressure Regulator 6.42%
Valves
R-XXXX Shut Down Valve (SDV) 36.82%
R-XXXX Pressure Safety Valve (PSV) 7.58%
R-XXXX Control Panels 3.26%
R-XXXX Junction Box 2.74%
R-XXXX Bulk Materials and Miscellaneous 6.84%
Sub Total 100.00%
Doc. No:
CO2 PLANT PROJECT
XX-XXX-XXX
Rev. 0 Page : 12 of 21
WORK PROGRESS MEASUREMENT SYSTEM
Date : 22-May-2018
7. Electrical 5.01%
R-XXXX Electrical Bulk Materials 32.01%
R-XXXX SWGR & MCC 8.95%
R-XXXX Transformer 10.52%
R-XXXX Miscellaneous Panel 32.92%
R-XXXX AC and DC UPS 11.08%
R-XXXX Lighting Fixture 3.61%
R-XXXX Communication and CCTV System 0.93%
Sub Total 100.00%
APPENDIX 5
WORK STEPS AND WEIGHT FACTORS FOR PROCUREMENT
APPENDIX 7
A. WEIGHT FACTORS FOR EACH WORK CATEGORY OF MOBILIZATION
PERSONNEL & EQUIPMENT
2. STEEL STRUCTURE
Pipe rack & Access Way/ 82.00%
Misc. Structure/Tower
Shelter 18.00%
100.00%
3. DRAINAGE SYSTEM
Underground Pipe Sewer 59.00%
Open Ditch (U & V-Ditch) 22.00%
Pit & Pond 19.00%
100.00%
4. BUILDING, ROAD AND
OTHERS WORK
Road & Pavement 28.00%
Fence & gate 25.00%
Deep Well 6.00%
Building 41.00%
100.00%
APPENDIX 8
CONSTRUCTION WORK STEP
2. STEEL STRUCTURE
Work Category Work Step Weight Factor Unit Of
Measure
Piperack Pedestal Preparation 5.00% m3
Erection 85.00% kg
Plumpness 5.00% kg
Tightening 5.00% kg
5. PIPING WORK
6. INSTRUMENT WORK
Work Category Work Step Weight Factor Unit Of
Measure
Control Board Install Panel/Console Installation 30.00% ea
Inter Wiring 50.00% m
Doc. No:
CO2 PLANT PROJECT
XX-XXX-XXX
Rev. 0 Page : 18 of 21
WORK PROGRESS MEASUREMENT SYSTEM
Date : 22-May-2018
7.ELECTRICAL WORK
8.MECHANICALWORK
Boxing Up 5.00%
ea
APPENDIX 9
WEIGHT FACTORS FOR EACH WORK CATEGORY FOR PRE-PRE-
COMMISSIONING
APPENDIX 11
WEIGHT FACTOR FOR EACH UNIT FOR COMMISIONING