Professional Documents
Culture Documents
Ms For Indoor Ligthing Installation
Ms For Indoor Ligthing Installation
Date: 04.04.2013
HOSPITAL BARU PEREMPUAN DAN KANAK-KANAK,
KG. KIULAP Page 1 of 6
(FASA 1 )
M & E CONTRACTOR
METHOD STATEMENT
FOR
TABLE OF CONTENTS
1) Purpose
2) Scope of Works
3) Storage
4) Pre-installation
5) Installation
AUTO ENGINEERING SDN BHD P299/ELE/01
Date: 04.04.2013
1) PURPOSE
2) SCOPE OF WORKS
The procedure will define the method to be used to ensure that the Indoor
Light Fittings are installed correctly and acceptable to the Client requirements
and specifications.
3) STORAGE
* Indoor lights and lamps are stored and kept on proper place.
* Make sure every type of fitting and lamp shall be stacked on one locations.
4) PRE - INSTALLATION
After finishing the pre-final coat of painting we will start fixing the surface
conduit and accessories for light fittings installation, fire alarm, and
PA System devices. Of course, the fittings which are coming in the false ceiling
should be fixed in the proper way with more supports if required.
AUTO ENGINEERING SDN BHD P299/ELE/01
Date: 04.04.2013
* Make sure that the ceiling and painting work are completed before installing
the fittings.
* All light fittings that requires ceiling opening we mark the location, opening
done by the Main Contractor
5) INSTALLATIONS
* Fix light fittings support. Recessed light fitting and shall be supported
independently from ceiling. Down lights have mounting arrangements to
fix to the ceiling.
* Terminate power cable to the fittings. Ensure that terminate properly. Light
fittings body shall be earthed.
* Fix lamp on the fixture. Make sure install correct colour of the lamps.
AUTO ENGINEERING SDN BHD P299/ELE/01
Date: 04.04.2013
Fix the diffuser and reflectors properly. Ensure that they are fixed properly.
Surface mounted fitting shall be installed after the final finishing work is
completed related light fitting installation are installed using wall plugs and
proper screws,
Ensure that all related finishing work completed prior to installing wall
lights / flood lights.
Fix fittings on the brackets, connect power cables ensure that termination is done
properly and also fitting properly earthed.
Documents / Checklist
Rating for the switches shall be 10A. Single and Multi gauges are as per the
construction drawings. Switches are generally installed 1200mm above the
finished floor
Approved type switches and sockets are installed at site. The light fittings are
controlled by local light switches
Install sockets and outlet boxes at required position, lay pvc conduits from
receptacle point to distribution units, conduit can be embedded into
the structural wall. Install pvc conduit to the boxes.
Ensure all switches / sockets are installed as per the requirements and as per
Construction Drawings.