Works Schedule - in the form of a Gantt or Bar Chart

Sep
No. Activity Dur.
Week I Week II Week III Week IV

1 Preparation Works 2 days

2 Walling Works 5 days

3 Walling Treatment Works 5 days

4 Electrical Works 3 days

5 Mechanical Works 3 days

6 IT Works 3 days

7 Built-In Custom Furniture 14 days