Organization Profile

About PriMove
PriMove Infrastructure Development consultants Pvt. Ltd. is a consulting company
working in the field of development planning, rural and urban infrastructure development
and capacity building. The promoters have been working in water sector since 1991.
PriMove‟s motif is engineering growth for facilitating sustainable development. Our vision
is to be First choice of clients, partners and professionals in the Infrastructure sector.
End to end services for water projects is our specialization. Based at Pune in
Maharashtra state of India, the organization has been promoted and managed by
professionals to provide support services to the Government, Multilateral and bilateral
agencies, NGOs, Corporate, Urban Local Bodies (Municipal Governments) and Rural Local
Bodies. It has provided services in Maharashtra, other states of India and also
internationally. PriMove has also worked in African countries. We have provide services
for water sector projects to cities with current population ranging from 3.5 million to
small rural habitations with population of few thousands. We have also provided services
to the regional water supply schemes covering multiple rural and urban habitations.
PriMove provides services in the field of Water Supply, Sewage, Storm Water
Management, Environmental Sanitation, Master plan, Water Resource Development &
Management and Rural Development.
PriMove provide technical services for preparation of Detailed Project Reports and Project
Management services for both rural and urban infrastructure development projects.
PriMove services also include appraisals, project design, development of capacity
building and project implementation strategies, delivery of capacity building components
through training of trainers, development of tools, process design; management and
monitoring systems, project evaluations and development of knowledge products.
Environmentally responsible and socio economically viable project design and
implementation management is the core strength of PriMove team. We have robust and
intensive experience of operationalizing demand led water & sanitation projects in rural
areas based on firm foundation of participatory approach involving multiple stakeholders
ranging from local women groups in the villages to the highest level decision makers at
program and policy level.

We have been closely working with Irrigation, Water Supply, Sanitation, Rural
development department of various governments at policy, program and project level.
We also partner with agencies like UNICEF, the World Bank, GIZ, Plan India for
implementing various water sector projects.
PriMove has a multidisciplinary team of professionals who on one hand has strong
technical capabilities, robust cutting edge level experience and on the other have
insights into program and policy development. The group members are from various
disciplines like civil engineering, electro mechanical engineering, environmental
engineering and hydrogeology, project management, development planning, sanitation,
water quality, geology, agriculture economics, information technology, sociology,
geographical information system, institution development and capacity building. The
team members have worked at various levels in their sectors and have contributed from
policy level to the project implementation level. We also have a well-trained support staff
for field investigations and piloting of tools.
In last two years water infra projects worth around 400 million USD designed by PriMove
have been approved and are under implementation. Primove team has developed a
protocol for Water use efficiency in urban & rural water supply schemes of various sizes
& also specializes in providing assistance in converting intermittent water supply to
continuous (24X7).
Sectors

Water

Availability of dependable and affordable water is non-


negotiable condition for any infrastructure development.
Wise water solutions are needed in the current context of
competition for access to water. We specialize in
developing water solution to various types of
infrastructure.

Rural Water Supply

Demand responsive rural water supply ensuring


water source and system sustainability,
appropriate water quality with access to all rural
households is a mission for all the governing
agencies. We design and support
implementation of such rural water supply
solutions owned by the user communities.

We engineer sustainable rural water supply


solutions through multidisciplinary teams
comprising of engineers, sociologists, institution
development and capacity building specialists as
per the situation requirements.

Urban water Supply

In urban areas the service standards for water


supply are high and is a crucial factor affecting
the urban development. Consistency, quality and
quantity are equally important in urban water
supply. Environmentally responsible planning for
appropriate water management is desired by all
the stakeholders. We specialize in designing such
urban water systems.

We undertake the situation assessment, demand


articulation, option evaluation, strategy
development, technical designs, estimation,
project management and risk analysis for the
urban water supply schemes.
The developing world continues to be in the
intermittent drinking water supply systems
which are vulnerable for contamination of water
during distribution. We have competent team for
modelling the distribution networks and
developing continuous 24X7 water supply
systems.

The efficiencies in the water supply system are


low in most of the developing world. 40 to 50 %
of the system water input is Non-Revenue Water
(NRW). Most of it is also physical leakage. We
specialise in the systematic program
implementation for efficiency improvements in
water supply systems, which lead them towards
sustainability.

Rainwater Harvesting:

In urban areas water supplied by urban local


bodies is becoming very costly and limited in
quantity.
It‟s become a necessity to increase the ground
water level to avoid insufficiency of Water.
There is a need to conserve and collect the rain
water from roofs as well as open spaces and
effectively put in to daily uses such as washing
vehicles, gardening & flushing toilets etc.
We provide Turnkey solutions in designing and
building these Rain Water Harvesting systems of
various scales, such as Single household to
Multiple buildings & Townships. This is also been
very well implanted in Commercial & Industrial
setups.
Storm Water Management

In the urban areas efficient storm water


management is vital for ensuring proper
functioning and designed life of roads and other
infrastructure. It also contributes to
environmentally sensitive planning and quality of
life in the city areas. The storm water
management for the cities cannot be effectively
addressed with piece meal approach. Integrated
planning of storm water management based on
the principles of urban watershed management
helps in ensuring quality and life of
infrastructure and overall quality of life. It also
enhances the capability of a city to reduce the
flood disaster risks caused due to high intensity
rains.
It requires experienced team of hydrologists,
engineers and environmentalists. We specialize
in preparing the storm water management
master plans, detailed engineering reports and
implementation management.

Water Resources Development and Management

Optimal utilization of available natural resources


using eco-logic along with robust technical
inputs on engineering, hydrology, geology and
environment are key ingredients of sustainable
water resource development and management.
We specialize in developing such water
resources for various purposes like irrigation,
industry, townships and small marginalize
communities. We design, manage
implementation of specific projects and also
develop programs and policies at regional and
national level.
Sewage & Sanitation

Appropriate management of sewage and sanitation is of


critical importance for sustained quality of life and
environmental health. Effective sanitation and sewage
management can have positive impact on the economic
productivity of the communities. It also forms a part of
diligent water resource management as the bad
management of sanitation constrains the water availability

Sewage

In the urban areas the population density is high


and in many cases land availability is
constrained. In many urban centres the
centralized sewerage systems exist in parts,
which affect the quality of environment and
people‟s life. It also generates the waste water
affecting the quality of life of many settlements
downstream.

We design master plans for sewage and waste


water management of cities. Water reuse
strategies and technologies are part of the
overall master planning. We prepare the detailed
project reports of sewerage systems and also
specific interventions like sewage treatment
plants and water reuse plans. We also develop
the projects to use sewage for the energy
production.
Rural Sanitation

The sanitation in rural areas has many


challenges. They range from identification of
socio culturally acceptable solutions to
promoting appropriate technology. Implication
of poor sanitation on the health and the
economic productivity of rural population are
cause of concern for many developing
countries.

We facilitate development of socio culturally


acceptable rural sanitation solutions in terms
of technology and behaviour change. We also
undertake capacity building and training for
promoting rural sanitation and environmental
health.

Roads

Connectivity by all-weather good quality roads is


precondition for any development. The road
infrastructure decides the value of any
development may it be a life style project in the
countryside, the rural households or urban
neighbourhoods. We design roads in any types of
terrains, in urban and rural settings. We prepare
master plans and detailed engineering reports for
the road projects.
Industrial & Residential Townships

In country like India the policy environment is


supporting the development of independent
townships and residential areas. These townships
and special economic zones are emerging as
building blocks of economic development.

We provide technically sound and sustainable


infrastructure solutions for such development units.
It can be a flood management solution, integrated
water- waste water solutions, roads, water
resource development, geological stability analysis
and roads. We also prepare infrastructure master
plans for such units.

Natural Resources Management

Integrated management of natural resources like


water, soil, agriculture, forests, bio mass has a
potential to contribute to the sustainable livelihoods
of millions of rural families. The approaches like
„watershed based land use planning and
management of natural resources‟ can substantially
contribute towards decentralized development in
many parts of the world. The natural resource
management is not just linked to technical expertise
in various subjects but it also requires ability to
design capacity building strategies and appropriate
institutional arrangements to ensure sustainability.
We specialize in designing of natural resource
management projects and programs and support the
implementation. We design the NRM solutions for
different development units starting from a small
village to a regional level and national level.

Renewable Energy

Decentralized energy solutions based on renewable


sources through climate friendly technologies
contribute to reduction of green House Gas and
bridging demand – supply gap. Considerable amount
of bio waste is generated from agriculture, dairy,
sewage systems etc.
We design projects and prepare detailed project
report to use bio gas to produce electrical power.
Agriculture

In countries like India still more than 70 % people


depend on agriculture for their livelihoods and
subsistence. Similar scenario exists in many
developing countries. In current context of food
insecurity this sector becomes more important. We
provide services to plan the agriculture projects
which include technology transfer, farming system
development, farmer‟s capacity building and linkage
development. We undertake feasibility studies,
business planning, detailed engineering reports, and
resource mobilization and implementation
management for agribusiness projects.

Services

Feasibility studies and Project Development

PriMove provides services for situation assessment, challenge definition, strategy


development and action planning for various infrastructure development projects. We
undertake techno- economic and social feasibility studies and design the projects.

 Techno-economic feasibility of SVO/ Renewable based village electrification in a


cluster of 10/12 villages in Kolwan Valley in District Pune- GTZ
 Feasibility study for supporting Indian Investment abroad in Strategic Agricultural
Activities, CRISIL, EXIM Bank
 Water Audit, Energy Audit Hydraulic modeling in the Reform Work under Sujal
Nirmal Abhiyan for Vadagaon Municipal Council, Kolhapur Dist., Maharashtra,
India.
 Water Audit, Energy Audit Hydraulic modeling in the Reform Work under Sujal
Nirmal Abhiyan for Indapur Municipal Council Pune Dist. Maharashtra, India
 Preparation of DPR for Liquid and Solid waste Management in 39 Villages and
Prefeasibility Report for 135 villages in Panchganga River basin causing
pollution.
 Feasibility studies of water requirement of Kuravade site for a private developer
in Pune
 Provided technical service for preparation of Pre-feasibility Report of Commercial
Agriculture Project in Angola. (Africa )

Master Planning

PriMove provides services for developing master plans for basic infrastructure in urban
and rural areas. The range of service varies from basin wise master plan for Water, to
infrastructure master plans for private industrial and residential townships. Our ability
and experience of working at both national policy level and grass root levels gives us a
unique perspective to provide complete solution to our clients.
Indicative list of projects
 Preparing for a Master Plan for Integrated Development and Management of
Resources of Terna, Lendi and Manar sub-basins of river Godavari in Maharashtra
– India
 Providing flood management consultancy for proposed special Township and SEZ
project for Lodha Developers at - Dombivali and Pune - India
 Providing storm water and flood management consultancy for proposed special
Township project at Ghesar, Mumbai for Lodha Group – India
 Consultancy services for Infrastructure Development of Engineering SEZ project
in KhandalaTaluka, DisrictSatara, Maharashtra – India
 Providing RCC design of well and pump house including evaluation of options for
various construction methods to overcome current problems at site for Khed SEZ
2 MLD scheme for Kalyani Global ltd, Pune – India
 Feasibility Study and report for water master plan for Capricon Developers at
Mulshi, Pune –India
 Environmental Development Plan for village Ghulewadi & Uchgaon for
Maharashtra Pollution Control Board.
 Preparation of Environmental Development Plan for a clusterof villages
BaramatiTaluka – Malegaon BK, Wadgaon, Nira&Walha).

Preparation of Detailed Project Reports

Supported by a large pool of experts, PriMove provides services for developing detailed
project reports for water infrastructure projects. The services include population
projections, topographical and geotechnical surveys, detailed designs and hydrolic
modelling, quantity survey, estimations, developing project reports to seek finance,
pretender activities as well as detailed engineering and construction level detailing to
help effective execution.
Indicative list of projects
 Preparation of DPR Preparation of DPR for Water supply scheme of Chandrapur
Municipal Council – India
 Planning and designing of Watersheds and storm water management system for
Pune City- India
 Preparation of detailed Project Reports (DPR) for Storm Water Project Phase-I in
Pune Municipal Corporation area for IL&FS – India
 Preparation of detailed Project Reports (DPR) for Storm Water Project Phase-II for
Pune Municipal Corporation under JNNURM (Govt. of India)
 Preparation of DPR for collection and 100 % treatment of sewerage of Pune City-
under NRCD – for MJP - India
 Preparation of DPR and storm water system in Kolhapur Municipal Corporation ,
Maharashtra – India
 Preparation of DPR for in storm water system Mira Bhyander Municipal
Corporation, Mumbai – India
 Preparation of DPR for sewerage system in Chandrapur Municipal Council – India
 Preparation of Detailed Project Report for Sewerage system in Shegaon City,
Maharashtra, India
 Feasibility & Design services for providing storm water drainage arrangement
from Diva village in Thane City
 Consultancy Services for preparation of Feasibility Study and Detailed Project
Report of Access Controlled Nagpur-Mumbai Super Communication Expressway.
Package-I - Nagpur Revenue Division.
Project Management Services

PriMove provides Project Management on infrastructure projects. Out team ensure that
projects are executed as per milestones with proper quality checks in place. The service
includes construction quality management, time and cost management, measurements
and records along with reporting as per client and project needs.
PriMove has managed implementation of water supply, storm water, sewerage and
sanitation, highways, tunnels, and urban road projects

Indicative list of projects


 Project management and capacity building services for implementation of more
than 100 water supply schemes under the Jalswarajya – The world bank aided
water supply project in three districts of Maharashtra
 Third party audit for quality management of urban water supply project for Navi
Mumbai municipal corporation, India
 Storm Water Management & landscaping work for Pimpri Chinchwad New Town
Development Authority, Pune – India
 Project Management Consultancy for Storm Water Drainage Project, Basin (M) –
Wadgaon Sheri for Pune City under JNNURM
 Project Management Consultancy for Strom Water Management System in
Kolhapur Municipal Corporation- India
 Project Management Consultancy for Drainage System in Karad under
Maharashtra Nagarotthan Mahaabhiyan Project - India

Capacity Building, Training &Institution Development

PriMove provides capacity building services to strengthen the abilities of individuals and
organizations to effectively perform their tasks. We provide services to develop capacity
building strategy and action plans, tailor made for specific projects and organizations.
We undertake training needs assessment, design and deliver trainings, develop systems
and tools for project implementation and also provide hand holding support.
Indicative list of projects
 Support agency for capacity building of local government staff, NGOs for village
water safety and security supported by UNICEF in Maharashtra India.
 Capacity building support to Implement Reforms in Rural Water Supply and
Sanitation Sector in Nanded and Raigad districts of Maharashtra under Water
Sector Reforms Program of Government of India
 Capacity Building Support to all stakeholders under the World Bank aided Water
supply & sanitation project - Jalswarajya- in Nashik, Sangli and Buldhana
districts of Maharashtra – India
 Participatory Rural Appraisal TOT for Ground water Surveys and Development
Agency (GSDA) of Govt. of Maharashtra
 Participatory Rural Appraisal TOT for Maharashtra Water Supply and Sewerage
Board renamed as MJP – India
 Engaging Resource Agencies to assist in promoting Community Led Total
Sanitation (CLTS)The World Bank Sanitation Program in South Asia
 Development &Testing of Modules for Training of Trainers and Capacity Building
Managers under public programme for watershed management in India for GTZ,
New Delhi – India
 Implementation of Village Water Safety & security program under Watson
component - NTPC WATSON

Evaluation, Monitoring

PriMove provides evaluation and monitoring services for various development projects.
Based on the evaluations and monitoring, we develop knowledge products to inform
policy and project development. Development of participatory monitoring and evaluation
systems for development projects is one of the strong areas of PriMove

Indicative list of projects


 Social Assessment for Sustainable Groundwater Management under Maharashtra
Water Sector Improvement Project funded by The World Bank for GSDA-
 Assessment of Drought Relief Program for Marathwada region in Maharashtra
commissioned by Oxfam GB
 Assessment of Improved community health through drinking water supply &
sanitation project under Himmothan Pariyojana Phase I –Sir RatanTata Trust,
Mumbai – India
 Maharashtra water sector reforms process assessment for -The World Bank
Sanitation Program in South Asia
 Conducting study on impact of high rainfall/ flooding on the ground water
resources in the state of Maharashtra, Karnataka &Andhra Pradesh for National
Rainfed Area Authority (NRAA) – New Delhi – India
 Conducting study on ground water management in the water scarcity areas in 13
district of western Rajansthan - for NRAA
 Evaluation of AdarshgaonYojana, Maharashtra

Rehabilitation and Resettlement

PriMove provides services to assess the impact of the development projects, identify the
project affected persons and develop rehabilitation action plans to mitigate the adverse
impacts and enhance the positive impacts of the project. We adopt participatory process
to develop the action plans in the framework of the relevant R&R policies and guidelines.
Indicative list of projects
 Developing rehabilitation action plan/ community development Plan for affected
villages of Mouda Thermal Power Plant for National Thermal Power Corporation (
NTPC ) near Nagpur – India
 Socio-Economic survey of project affected village under Birsi–Gondia District for
Airport Authority of India
 Social Assessment & Resettlement Action Plan for Andhra Pradesh/ Karnataka –
Avathi village (NH-7) Road Project –for Sheladia Associates – India
 Socio Economic Survey (SES) Stage-II, NTPC Mouda
Our Clients

 Government of India
 Government of Maharashtra
 Government of Gujarat
 Government of Punjab
 Ministry of Urban Development (Public Health Department)
 Rural and Urban local government agencies in India
 Pune Municipal Corporation
 Mira Bhyander Municipal Corporation,
 Mumbai Metropolitan Regional Development Authority (MMRDA)
 Chandrapur Municipal Corporation
 Nanded Municipal Corporation
 Kolhapur Municipal Corporation
 Sangli Municipal Corporation
 Thane Municipal Corporation
 Solapur Municipal Corporation
 Osmanabad Municipal Council
 Navi Mumbai Municipal Corporation
 Karad Municipal Council
 Vadgaon Municipal Council
 Pimpri Chinchwad New Town Development Authority, Pune
 Maharashtra Agricultural Competitiveness Project (MACP), Pune
 UNICEF
 KFW
 The World Bank
 German Technical co-operation (GTZ), Germany, formerly Known as GIZ
 Agricultural Finance Corporation Ltd.
 Power Finance Corporation Ltd.
 Local and International NGOs
 Tamilnadu Water Investment Co. Ltd, India
 Corporate in India
 Infrastructure Leasing & Finance Services (IL & FS) India
 Government of Lesotho
 Department for International Development (DFID), UK
 OXFAM GB
 Defence Research Development Organisation (DRDO), Pune
 National Thermal Power Corportion (NTPC) of India
 Sir Ratan Tata Trust (SRTT)
Our Empanelment’s

 Ministry of Urban Development (PHE Section), Government of India


 Ministry of Urban Development (Smart City), Government of India
 National Institute of Urban Affairs for „HRIDAY‟ Scheme of MoUD, GoI.
 Department of Urban Development, Housing & Local Self Government, Government
of Rajasthan.
 Water Supply & Sanitation Department, Government of Maharashtra
 Punjab Municipal Infrastructure Development Company, Government of Punjab
 Goa State Urban Development Agency, Government of Goa
 Madhya Pradesh Jal Nigam Maryadit, Government of Madhya Pradesh
 Uttarakhand Payjal Nigam, Government of Uttarakhand
 Odisha Urban Infrastructure Development Fund, /Government of Orissa
 Maharashtra Jeevan Pradhikaran, Ahmednagar, Government of Maharashtra
 Pune Municipal Corporation
 Bhivandi Nizampur city Municipal Corporation
 Kolhapur Municipal Corporation
 Navi Mumbai Municipal Corporation
 Yashvantrao Chavan Academy of Development Administration (YASHADA),
Government of Maharashtra.
Technical Staff
Name of the Area of
No Qualification Experience
Staff Expertise
Capacity building and
watershed expert in
1 Ajit Phadnis BE (Civil) integrated water resource 25 years
management at national and
international level
Water supply sanitation
2 Ajeet Oak BE (Civil) Engineer project management 25 Years
at Nation & International level

Electronics Engineers
Expert in Water Management,
3 Neelesh Kulkarni BE (Ele.) 25 years
Capacity Building and natural
resource management

Expert in irrigation project


design and construction
BE (Civil) management
4 S.L. Bhingare 45 years
ME (EQ Engg) Retired Executive Director,
Irrigation Department, Govt
of Maharashtra
Sewerage and continuous
M. E 24X7 water system
Environmental development.
5 Pradeep Gokhale 45 Years
Engg, MBA Retired Supretending Engineer
LLB (MJP)

Expert in planning, designing,


execution and maintenance of
6 S.D. Kulkarni BE (Civil) 35 years
water supply & sewerage
schemes
Hydraulic engineer Expert in
RCC & sewerage system and
7 P.V. Kulkarni D. C. E 35 years
water supply and sewage
system design,

M.Tech. (IIT Expert in water distribution


8 Rahul Kumbhar 4 years
Bombay) network modelling

ME
Water and sewerage network
9 Sunil Pote (Environmental 20 years
modelling expert
Engg)

Water, sewerage and storm


M.Tech. (IIT
10 Shailesh Patil water system modelling 5 years
Bombay)
expert
Expert in Hydrology, Water
Raosaheb BE (Civil) Resources Planning,
11 45 years
Gaikwad M. E (Hydrology) Integrated River Basin
Planning & Management.
MSC Expert in Environment, action
12 Gouri Thakar Environmental and research unit and natural 11 years
Science resource management
Technical Staff
Name of the Area of
No Qualification Experience
Staff Expertise
BSC Chemistry
13 Eknath Saste Expert in water quality 16 years

Expert in Sustainable and


14 Jitendra Naik MSC Agriculture 10 years
Community Development

MSW Expert in Community


15 Mahesh Kodgire 13 years
development

Expert in water supply and


16 Shital Kole D.C.E. 19 Years
Storm water

Expert in surveying of
17 K D Karhale D.C.E. watershed, roads, water 18 years
supply and drainage systems.

Expert on water supply and


18 Sunil Warade D.C.E. 16 years
watershed development

Expert in Geology & Geo


19 V. Krishnamurty M.Sc. Geology 44 years
Hydrology
Expert in Finance
C.A.
20 Nitin Inamdar Management 17 years
CA by professional
21 Vishal Ujagare BE (Civil) Expert in project management 12 years
B.E.
22 Shweta Karekar (Environmental Expert in Design 05 years
Engg)
Expert Auto CAD and GIS
23 Mahesh Badure GIS Expert 06 years
software

Diploma in Auto Expert Auto CAD and GIS


24 Pratibha Jangade 08 years
CAD software

Expert Auto CAD and GIS


25 Aslam Janabade Dip Auto Cad 04 years
software

26 Gitan Bhojane Dip Auto Cad Auto CAD and GIS software 02 years

27 Sarang Mahajan BE Civil Expert in Design 2 Years

28 Deepak Muley B.E. Civil Expert in Estimation 07 years


BE
29 Prasad Oak Structural Engineer 17 years
(Construction)

30 Naresh Sawant DCE Expert in Project Management 13 years

Expert in Community
31 Gajanan Aspat MSW 10 years
development
Technical Staff
Name of the Area of
No Qualification Experience
Staff Expertise
Expert in water resource
32 Ramesh Petkar D.C.E 09 years
management

Expert in Community
33 Sachin Hattalge MSW 08 years
Mobilisation
Dr. Manohar Expert in Agronomy, Research
34 M. Sc. Agri Ph.D 45 years
Sawant & Capacity Building

Ashwini Project Coordination and


35 M A Economics 12 years
Kotasthane documentation
Expert in Hydro Geology
36 Santosh Salunkhe MSC Geology 01 years
Expert in Community
37 Pravin Kamble MSW development 10 years

M.Sc. Expert in Soil Sciences,


Dr. Gasjanan
38 (Agriculture) Agronomy, water 2 years
Jadhav
Ph. D Management
M. Tech Planning & Designing of
39 Sarvesh Rahate (Environmental Water, Sewerage & Eco 2.5 years
Engg) development Projects
M. Tech Planning & Designing of
40 Rohit Walvekar (Environmental Water, Sewerage & Eco 2 year
Engg) development Projects
B.E.
Sewerage new technology
41 Rohit Patankar (Environmental 2 years
development and testing
Engg)
Available Facilities

Hardware:

o 40 Pentium III/IV /Dual Core Work stations.


o 1 COMPAQ Proliant ML370 Server with 240 GB Snap Server / 5 Intel.
o Switches internally networked with all systems on Cat 6 cables.
o 1 A0-size Hp 500 Plus Plotter.
o 1 VIDAR 29” DESIGNER Color Scanner.
o 1 Canon C2220, Heavy Duty,A3 Size Colour Printer, Copier & Scanner

Software
o Arc GIS
o Arc View
o Bentley Sewer Gems
o Bentley Water Gems
o AutoCAD Civil-3D (for contouring)
o Auto plotter for L-Section & Cross Section
o AutoCAD Map
o Adobe Photoshop

Output Formats
o ESRI
o Bentley
o Autodesk

Survey/Photogrammetry and Remote Sensing Services:

o Aerial Photography & Drone Survey


o GPS Survey Control
o Contour Generation
o Cross-section and Linear-section Generation
o Digital Ortho Rectification
o Thematic Mapping from Satellite Data including SAR
o Vectors extraction from High Resolution Satellite imagery
o Total Stations-3 Nos
o Auto Level-2Nos
Organizational Structure

PriMove is governed by board of directors. It operates through three division‟s namely technical services division, development planning
division and capacity building division.
Along with the in house teams there is also a roster of professionals who have been working on various projects with PriMove. These are
senior level experts with specific specialization as required for the range of projects undertaken by PriMove.
The divisions are supported by Admin- HR, finance and business development teams.

BOD

Technical Capacity Development

Roaster of Consultants
Division Building planning
Division Division

Project Support
Project Project PM PM
Manager Services
Manager Manager Development Support
Design DPR PMC Training
Planning Services

Multidisciplinary Project Team Comprising Team Leader, Team Members and Assistants
Integration of local / National teams
Selected Relevant Assignments
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
1. Preparation and Pune 3rd & 4th NA Aug Ongoing Ongoing Formulation of strategies for vision for the
Implementation Metropolitan Floor, preparation & implementation of Town
of Town Region Maharaja 2017 Planning Scheme/s
Planning Development Sayajirao To update the data regarding Revenue
Scheme/s (TPS) Authority Gaikwad Records such as details of Land
as per (PMRDA) Udyog Bhavan, Ownership, area and tenure of each
Maharashtra Aundh, Pune, Original Plot available with the PMRDA.
Regional & Town Maharashtra
Planning Act, To collect irrevocable consents of land
1966 owners aggregating contiguous land area

To update the GIS based Detailed Survey


Map.
To assist in publication of intention of
Town Planning Scheme/s for the areas of
one or more than one village.

To prepare existing and proposed Road


network Plan Spatial Planning and
allotment of land (plots) for public use
To prepare reports, estimates for Cost of
the entire Town Planning Scheme/s

To prepare Development Control


Regulations for the Scheme/s.
To assist the PMRDA by way of supporting
the activities, duties. and responsibilities
in preparation and submission of
Preliminary and Final Town Planning
Scheme/s and to submit the same to the
State Government for sanction.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
2. Augmentation to Solapur Solapur 1241 Cr (CP) Dec Ongoing Aug Scope of work for the above scheme is to
Solapur water Municipal Municipal prepare the DPR for the Design period of
Supply scheme. Corporation Corporation, 2013 2014 30 years to include the following works,
Solapur, Aerial Survey of Water Systems.
Park Chowlk, Studying of the existing system and its
Solapur Dist: functioning. Gap analysis based on the
Solapur, standard service level Benchmarks.
Maharashtra Developing the techno-economical and
(India) reliable source potential for design period.
Population projection up to 2046
Hydraulic modeling of the entire network
using Water Gems software for existing
and projected Demands
Development of DMA based management
system
Metering from source to consumer with
pressure and level transducers and AMR
consumer meters to make the system
amenable for continuous water supply.
SCADA system for Monitoring and
controlling
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
3. Preparation of RSPMU, Water RSPMU, Water *DPR Mar Mar Mar preparation of DPRs for Peri-Urban Water
DPR for Water Supply & Supply & supply and Sullage Management Schemes
Supply & Sanitation Sanitation Preparation is 2015 2016 2016 in 12 districts under Jalswarajaya - 2
Sewerage Department, Department, Programme
schemes under GoM GoM in Process
Jalswarajya-II for CIDCO prefeasibility study report including
Satara & Bhavan, Navi various alternative options along with
Chandrapur Mumbai. present status of WSS/Sewerage/ODEP
District. Undertake performance assessment of
existing assets and prepare rehabilitation
proposals
Conducting detailed engineering survey,
detailed field survey, geo technical
investigations,
Consumer Survey for house connection,
Prepare village road maps on GIS with
contours
Designs of economical size of pumping
main with surge analysis.
Preparation of detailed engineering
hydraulic designs of proposed water
supply scheme with population forecast,
service level, storage capacity, residual
pressure etc.
Preparation of various O & M options and
O & M estimate.
SCADA System
Preparation of Bid Documents, BOQ.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
4. Preparation of Thane Zilla Thane Zilla 191 Cr (CP) Nov Feb Feb 2016
DPR for the RRWS Parishad Parishad, The services included- Preparation of
for 97 Tribal Thane 2015 2016 detailed project report including
villages in Collection/Studying of the data of existing
Shahpur Taluka, water supply scheme and its functioning.
Dist. Thane, Carrying out survey using total station &
Maharashtra GPS.
State. Getting administrative approval from
Water & Sanitation Dept, Govt. Of
Maharashtra.
Detailed survey & Strata Explorations:
Carry out detail survey of water
components using total station.
Preparation of plans & L-section using
CAD software. Carrying out contour
survey of all structural components.
Design of water components viz. WTP (35
MLD), raw water gravity mains, pure
water conveyance mains, storage
reservoirs (MBR, ESR/GSR).
Hydraulic modelling of 250 kms proposed
gravity system using WaterGEMS
software.
Detailed design of Automation of Bulk
metered water supply system including
SCADA .
Prepare detail estimates
Preparation of Detailed Project Report..
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
5. Consultancy Punjab Water Water Supply 21.08 Cr (CP) Dec Mar Mar Preparation of Detailed Project Report for
services for Supply & & Sanitation group water supply scheme based on
preparation of Sanitation Div. No-1, 2013 2014 2014 canal to provide surface water for
Detailed Department Rupnagar, at conjunctive use to quality affected
Project Report to Anandpur villages (45 Nos.) In Block Nurpur Bedi,
prepare group Sahib. Punjab District Rupnagar of Punjab. The villages
water supply have current water supply from tube wells
scheme based on and have quality problems due to high
canal concentrations of iron, TSS and alkalinity.
to provide surface The project aims at augmenting the
water for supply with water from a surface source
conjunctive use to (canal water). The scope of work involves
quality affected working out dilution quantities, systems
villages for dilution and supply of bulk water to
(45 Nos.) In Block villages, optimization of scheme,
Nurpur Bedi, preparation of Detailed Project report and
District Rupnagar tender documents. Draft final report has
of Punjab been prepared, tender packages have
been worked out and some tender
packages have been floated.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
6. Preparing Osmanabad Osmanabad 63.77 Lakh Oct Ongoing March Understanding the existing water supply
Designing Costing Municipal Municipal scheme.
and preparing Council Council, (CF) 2013 2015 Design of SCADA and communication
DPR, Tender Osmanabad, system.
papers Maharashtra To develop different alternatives models
and Project (India) of the SCADA & metering system.
Management Estimating Instrumentation/PLC/SCADA &
Consultancy for Communication system cost.
SCADA Preparing specification for the system.
system for Developing the tender documents.
drinking water Metering and instrumentation in water
supply supply network.
management and Project Management Consultancy.
control, Consumer
water metering
on EPC/BOT/PPP
options.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
7. Preparation of Fortress Fortress 19.86 Cr (CP) May Nov Nov Preparation of layout of proposed water
Customisable Infrastructure Infrastructure supply scheme.
framework of Advisory Advisory 2012 2012 2012 Detailed design of various components of
performance Services for Services, water supply scheme.
improvement Bhokar water Mumbai Preparation of DPR consisting of raw
planning for water supply water intake in dam, raw water
supply and conveyance pipelines of 450 mm dia.,
sewerage services Raw water pumping machinery 100HP,
at Bhokar WTP of 12 MLD, Construction of RCC ESR,
Construction of RCC GSR of capacity 0.85
ML & 2.7 ML resupply.

8. Preparation of Chandrapur Chandrapur 143.86 Cr Nov Aug Aug Preparation of DPR including detailed
DPR for the water Municipal Municipal Council,(CP) design, GIS base data, technical
supply system of Council, India Maharashtra 2007 2008 2008 specifications, bill of quantities, rate
Chandrapur city, India analysis and cost estimates, Preparation
Maharashtra, of bid document, support for evaluation of
India bids, Project management services during
execution including project scheduling,
quality management, bill certification and
on the site technical support.
Project of 60 MLD capacity consisted of
raw water intake, pumps, conveyance by
900 mm pipes, 60 MLD WTP, 110 HP
pumps for treated water, 8 nos. ESRs of
1.65 to 4 ML capacity, Distribution
network of 100 to 600 mm, 14.22 Km
length.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
9. Improvement to Studio Galli Studio Galli 522 Cr (CP) Dec Nov Nov Pune city has a population of 3.5 million.
water supply to Ingeneria (SGI) Ingeneria The work completed till date includes
Pune city (SGI) 2011 2012 2012 following-
Shivajinagar, survey of 5000 domestic and commercial
Pune consumer connections,
GIS based updation of entire water
network and assets which included
procurement of satellite image,
digitization & network updation for 2450
Kms of distribution, 400 Kms of
transmission system,7 WTPs,
Service Reservoirs.
Actual implementation in 5 Pilot DMA
Population projection up to 2047
Hydraulic modeling of the entire network
using Water Gems and EPANET softwares
for existing and projected population
Development of DMA based management
system
Metering from source to consumer with
pressure and level transducers and AMR
consumer meters to make the system
amenable for continuous water audit.
SCADA system for Monitoring and
controlling
Community Awareness
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
10. Third Party Navi Mumbai 300 Cr (CP) Mar Mar Mar Independent third party verification of
C.B.D.
Technical Audit Municipal implementation of quality assurance
Belapur, Navi
for Buildings, Corporation 2012 2014 2014 manual, extent of controls exercised by
Mumbai
Water Supply, contractors and supervisory
Sewerage in staff/technique. Third party verification on
public health AMR metering and water scheme works of
engineering the Navi Mumbai, a town of 2 Million
department population
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
11. Augmentation and Crisil Risk & Crisil House, 5.2 Lakh (CF) Sept Dec Dec Primary and Secondary data collection on
improvement in Infrastructure Central existing situation of water supply in the
Distribution Solutions ltd Avenue, 2013 2013 2013 LMC and assessing the impact of the
system for 24X7 Hiranandani proposed project.
Supply and Business Park, Consultations with stakeholders viz. LMC
Reduction of Pawai, Mumbai (its various departments), Maharashtra
Non-revenue Urban Development Department,
Water through prominent Civil society/ NGOs active in
100% Metering urban infrastructure including potential
and Operation & developers etc
Maintenance of Review of project including the
Water Supply assessment of present water conditions to
System for develop: a. base case project costs for
Lonavala City capital investment, b. timelines for
(Maharashtra) on implementation and operation. C. inputs
PPP Modality for operation and maintenance costs over
the life of the project
Value for Money (VFM) Analysis.
Development of Financial plan, Financial
Model, Economic model, Customer
Service framework.
Recommended PPP option, Market
Consultation exercise & Request for
qualification documents
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
12. Preparation of JSW ISPAT JSW 68.95 Lakh May June June Preparation of DPR including detailed
Detailed Steel Limited ISPAT STEEL (CP) design, Geographic Survey, bill of
Engineering and LTD, Dolvi, 2013 2013 2013 quantities, rate analysis and cost
route finalization, Pen, Raigad, estimates, Preparation of bid document,
pipe selection and Maharashtra support evaluation of bids, Project
survey for water management services during execution
supply pipeline including project scheduling, quality
From Nagaothane management, bill certification and on the
to JSW ISPAT, site technical support
Dolvi & Hetwane
To JSW ISPAT,
Dolvi

13. Reform Work Infraplan 109, Raoji 53.55 Lakh June Dec Dec Carrying out consumer survey to collect
under Sujal Engineering Complex, (CP & CF) details of consumption of water usage,
Nirmal Abhiyan Services Pvt. Shahupuri, 2012 2013 2013 fixing of EMF, US, and mechanical meters
for Indapur Ltd. First lane, for carrying out water audit by studying
NagarPalika , Kolhapur – the losses in DMA‟s. Supply and
Pune Dist. 416001, Installation of International standard
Maharashtra software for single user for Hydraulic
designing and modeling, Modeling and
calibration of Hydraulic model of existing
and proposed water supply scheme.
Comprehensive Maintance of flow meters
for one year. Supply and installation of
GIS software, procurement of quick bird.
Digitization of satellite image, Asset
mapping, physical survey and contour
mapping of the town. Providing and
installing computer etc.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
14. Water Audit, Vadgaon, 52 Lakh June March March Carrying out consumer survey to collect
Vadgaon
Energy Audit Municipal (CP & CF) details of consumption of water usage,
Municipal
Hydraulic Council 2012 2014 2014 fixing of EMF, US, and mechanical meters
Council, Dist:
modeling in the for carrying out water audit by studying
Kolhapur
Reform Work the losses in DMA‟s. Supply and
under Sujal Installation of International standard
Nirmal Abhiyan software for single user for Hydraulic
for Vadagaon designing and modeling, Modeling and
Municipal Council, calibration of Hydraulic model of existing
Kolhapur Dist., and proposed water supply scheme.
Maharashtra, Comprehensive Maintenance of flow
India. meters for one year. Supply and
installation of GIS software, procurement
of quick bird. Digitization of satellite
image, Asset mapping, physical survey
and contour mapping of the town.
Providing and installing computer etc.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
15. Preparation of Pune Municipal Pune Municipal 461.73 Cr April Ongoing Mar Pretender Activities:
DPR and PMC for Corporation Corporation, Carrying out reconnaissance survey,
Storm water ShivajiNagar, (CP) 2013 2016 topographic surveys of Nallas & Road side
drainage master Pune drainages, cross drainages, calves in
plan of Pune selected basins under the project.
Under Preparation of Hydraulic designs of storm
JNNURM Phase-II water drains as per CPHEEO manual
norms.
Follow up and obtaining approval from
PMC, Govt of Maharashtra, Govt of India
& other funding agencies.
Preparation of Tender documents, B.O.Q
and specifications of items to be
executed.
Post-Tender Activities:
Monitor the progress of project and
prepare various reports such as monthly
progress report, quarterly progress
reports etc & submit to PMC & funding
agency.
Supervision and quality monitoring during
execution of works.
Certification of quantities of executed
works and bills of contractors on behalf of
P.M.C.
Co-ordination between contractor and
Pune Municipal Corporation.
All other works and activities required for
the progress of the project.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
16. Preparation of Tamil Nadu IL&FS Ltd. Bandra 399 Cr (CP) Nov Apr April Developing a detailed project report for
DPR and Pre- Water Kurla Complex , execution of storm water drainage project
Mumbai
tender activities Investment 2007 2008 2008 for Pune City (3.7 Million populations) –
for Storm water Company Ltd. with an area of 300 sq. km. Preparation
drainage master (TWIC) which is of detailed drawings, designs, GIS base
plan of Pune a group data, estimates, tender documents and
Under JNNURM company of follow up with JNNURM for funding.
Infrastructure
Leasing &
Financial
Services Ltd.
(IL& FS)

17. Feasibility & Thane Municipal Thane 47.94 Cr (CP) Feb Sept. Sept. Preparing alternative augmentation
Design services Corporation. Municipal schemes and checking their feasibility.
for providing Corporation. 2011 2012 2012 Carrying out Cost/Benefit analysis of
storm water Mahanagarpali various schemes.
drainage ka Bhava, Recommending Best Suited Scheme to
arrangement for Dr.Almeda Thane Municipal Corporation for approval.
Diva village in Road, Detail Report on the rehabilitation of
Thane City Panchpakhadi, people residing nearby Natural drain area.
Thane – 400 Preparing detailed hydraulic designs of
602. the augmentation scheme.
Finalizing formation levels of the road and
nearby developing properties.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
18. Preparation of Mira Bhayandar Mira Bhayandar 220 Cr (CP) June July July Developing a detailed project report for
DPR and Pre- Municipal Municipal execution of storm water drainage project
tender activities Corporation Corporation 2007 2009 2009 for Mira Bhayandar City (0.8 Million
for Storm water population) – with an area of 79.4 sqkm.
drainage master Preparation of detailed drawings, designs,
plan Under GIS base data, estimates, and tender
JNNURM for Mira documents and follow up with JNNURM for
Bhanyandar funding.
Under MMRDA

19. Preparation of Kolhapur Kolhapur 200 Cr (CP) Dec March March Developing a detailed project report for
DPR for Strom Municipal Municipal execution of storm water drainage project
Water Corporation, Corporation, 2009 2013 2013 for Kolhapur City (0.5 Million population).
Management Kolhapur Kolhapur Preparation of detailed drawings, designs,
System in GIS base data, estimates, tender
Kolhapur City documents and follow up for funding.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
20. Preparation of Sangli Municipal 198.56 Cr Mar March March Developing a detailed project report for
Sangli
DPR and Strom Corporation, (CP) execution of storm water drainage project
Municipal
Water Sangli 2011 2013 2013 for Sangli City. Preparation of detailed
Corporation,
Management drawings, designs, GIS base data,
Sangli
System in Sangli, estimates, tender documents and follow
Miraj and Kupwad up for funding.
City Municipal
Corporation

21. Project Pune Municipal Pune Municipal 54.43 Cr (CP) Aug June June Project Management Consultancy for
Management corporation, corporation, Infrastructure Projects under JNNURM in
Consultancy for Pune Pune 2010 2013 2013 Pune – Basin (M). Includes post tender
Storm Water activity – keeping upto date record of
Drainage Project, measurements required for billing,
Basin (M) – preparation and checking, carrying all
Wadgaon Seri for necessary quality checks as per tender
Pune City under specifications. Project management for
JNNURM storm water drainage system, preparation
of GIS base data. Submission of work
completion report, records and drawings
etc.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
22. Preparation of Pimpri Pimpri 26.70 Cr (CP) July Nov Nov Includes design pre-tender and project
DPR for Storm Chinchwad Chinchwad management for storm water drainage
Water, landscape, New Town New Township 2008 2011 2011 system and landscape development
beautification of Development Development including bridges, lake development,
nallas system in Authority, Pune Authority theme parks, water supply system etc.
PCNTDA AREA. (PCNTDA)
Nigadi
Pune 411 044

23. Rain Water Shirine Garden Shirine Garden 12 Lakhs May Aug Aug Roof Top Rain Water Harvesting
Harvesting at Co-operative Society, (CP) Existing Borewell flashing
Shirine Garden Housing Society Aundh, Pune 2013 2013 2013 Construction of Recharge pit.
Society Rain Water Piping works

(Trunkey Project)

24. Rain Water Fortress Fortress 75 Lakhs June June June Water Shed Management
Harvesting & Infrastructure Infrastructure (CP) Construction of CCT, Loose bolders,
Water shed Advisory Advisory 2012 2014 2014 Cement bunds, KT Wier, FSC &
Management at Services Services, construction of wells.
Sun Vally, At. Marine line Digging of borewells & Construction of
Jambhulpada, Mumbai Recharge pit
Tal: Pen Dist:
Raigad
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
25. Consultancy For Chief Engineer, HQ Chief 10 Cr (CP) Oct Mar Mar DPR for collection and treatment of
Central Sewage Military Engineer sewerage of Military Station Luchibari,
Treatment Engineering Shillong Zone 2015 2016 2016 Jorhat, Assam & Leimakhong (Pocket-1),
Plant(STP) at GE Services. Spread Eagle Manipur. Design of sewerage collecting
(Jorhat) And GE Falls mains throughout the area. The work
869 EWS Shillong- consists of 8km & 5km of collection
(Leimakhong) 793011 system of variable diameter. Design and
Under Chief detailing of 2 STPs of 0.5 MLD capacities
Engineer Shillong with different technology like MMBR, MBR,
FBBR etc.

1) Creating a base map of the project


area showing major building units and
elevation. 2) Preparing the network for
sewerage collection from first manhole
based on this base map. 3) Designing the
best suitable sewage treatment
technology based on the sewerage
generation quantity and its chemical
properties. 4) Providing the Detailed
Project Report for both the locations
comprising specifications of RCC, electro-
mechanical, tendering for contractor,
Operation & maintenance of the STP.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
26. Consultancy for Uttarakhand Office of GM, 430.60 Cr Sept Mar Mar Preparation of DPR including conducting
Rishikesh Peyjal Construction (CP) topographic and detailed engineering
Comprehensive Sansadhan Circle (Ganga), 2015 2017 2017 survey, zone finalization, preparation of
Municipal Waste Vikas evam Haridwar design, drawings, feasibility study, rate
Water Project Nirman Nigam analysis and cost estimation and
specification of various infrastructural
services. Preparation of Tender document,
evaluation of tenders. Present technical
aspect of the project, approval of project/
sanctioning of grant etc.

27. Preparation of Maharashtra 674 Cr (CP) Oct March March Collection of 100% sewerage of Pune city
Maharashtra
DPR for collection Jeevan and treatment of it. Augmentation of
Jeevan
and treatment of Pradhikaran 2010 2013 2013 existing STPs and intermediate Pumping
Pradhikaran
sewerage of Pune Development stations. Design of sewerage collecting
Development
City Division, Pune mains throughout the Pune city and
Division, Pune-
collection system of Baner and Balewadi.
411001
The work consist of 113.5 Km of collection
system of dia 450 to 1800 mm. design
and detailing of 9 STPs ranging from 8
MLD to 125 MLD with different technology
like ASP, Modified ASP, Extended
aeration, SBR MMBR, MBR etc.
DPR submitted to Government of India for
financing under NRCP
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
28. Preparation of Alandi Municipal Alandi 122 Cr (CP) Sept Jan Jan Carrying out reconnaissance survey,
DPR for Pollution Council Municipal topographic surveys of project area and
Abetment of Council, 2014 2015 2015 River, Natural drains etc.
Indrayani River at Alandi, Tal- Preparation of feasibility report for
Alandi under Khed, Sewerage scheme, Solid waste
NRCP Dist - Pune management, Community sanitation,
River front Development and other allied
works under the guidelines of NRCP
Preparation of Hydraulic designs of
sewage collection network as per CPHEEO
manual norms by use of SewerGEMS,
Preparation detailed design of Solid Waste
Management in the project area as per
CPHEEO manual norms and preparation of
detailed conceptual plan and drawings of
the River front development and allied
works
Preparation of detailed cost estimates and
BOQ as per latest CSR
Submission & sanctioning of DPR from
Alandi Municipal council, State level nodal
agency, State Government & Central
Government
To take the technical sanctioning of the
DPR from the concerned authority
Follow up and obtaining approval from
AMC, Government of Maharashtra,
Government of India & other funding
agencies
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
29. Geotechnical NJS Consultants 6-8, Tomihisa- 674 Cr (CP) Sept Nov Nov Under this assignment, the topographic
Survey, Social Co., Ltd., cho, Shinjuku- survey & Geotechnical Investigations
Condition Survey, Tokyo, Japan & ku, Tokyo 162- 2014 2014 2014 including sample testing are carried out at
Meteorological & 0067, JAPAN, proposed STP sites (8Nos). The route
Hydrological Nippon Koei and survey of proposed collection network
Survey, Social CO., Ltd., 4, Kojimachi, (43km) sewer lines, trunk sewers (73
Survey, Tokyo, Japan 5-chome, Km) and approach road of proposed STP
Topographic Chiyoda-ku, is confirmed on site. The opinion of the
Survey, Route Tokyo 102- local people is studied under social survey
Inspection Survey 8539, Japan including House hold survey, group
for the discussion etc.
preparatory Meteorological (Rainfall & wind) and
survey on Project hydrological data (Flood line data of River
for “Pollution Mula Mutha) is collected from respective
Abatement of Government departments.
River Mula-Mutha
In Pune”
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
30. Detailed Project Khed Economic Pride Parmar 6.37 Cr (CP) Sept Nov Nov Collect & review of available data.
Report for Infrastructure Galaxy First Details of type industry Location, type of
Sewerage Pvt Ltd, Pune Floor, CTS no 2014 2014 2014 waste.
Collection and 10,10A,Behind Sewage chemical report and analysis.
Treatment system Parmar Trade Residential population and projected
in Domestic Tariff Centre population forecast .
Area ( DTA ) of ,Cannought Projected year and water supply.
Khed city Taluka road Pune Sewerage line alignment.
– Khed Dist - 411001 Sewage treatment plant design and
Pune layout.
Detail Project report.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
31. Preparation of Pune Municipal Pune Municipal 232 Cr (CP) Sept July July Prevent untreated sewage from entering
Master Plan & Corporation, Corporation, natural water bodies such as Nallas and
DPR for sewerage Pune ShivajiNagar, 2008 2009 2009 rivers etc. Augment the collection system
System of Pune Pune of sewage to tap and transport all the
City. sewage generated in the city.
Augment existing sewage treatment
facilities and construct new sewage
treatment facilities to treat all the sewage
generated in the city.
Use of technologies that will efficiently
treat the sewage to achieve required
effluent haracteristics
Preparation of master plan of sewerage
system for pune city.
Preparation of detailed project report for
sewage system phase II for submission of
JNNURM, consisting design of STPS and
pumping stations.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
32. Preparation of Chandrapur Chandrapur 96.16 Cr (CP) Jan Mar Mar Preparation of DPR including detailed
master plan and Municipal Municipal design, technical specifications, GIS base
DPR for the Council Council 2007 2007 2007 data, bill of quantities, rate analysis and
sewerage system cost estimates, Preparation of bid
of Chandrapur document, support for evaluation of bids,
city Project management services during
(Area 56.4 sq. execution including project scheduling,
KM) quality management, bill certification and
on the site technical support. The project
consisted of sewer system 179 Km of
diameters ranging from 150 to 1200 mm.
Two STPs of 25 and 45 MLD capacity

33. Preparation of Fortress Fortress 46.29 Cr (CP) April June June Preparation of DPR including conducting
Detailed Project Infrastructure Infrastructure topographic and detailed engineering
Report for Advisory Advisory 2010 2010 2010 survey, zone finalization, preparation of
Sewerage system Services Services for design, drawings, feasibility study, rate
in Shegaon City, Shegaon analysis and cost estimation and
Maharashtra, Tirthkshetra specification of various infrastructural
India Development services. Preparation of Tender document,
Plan. Shegaon, evaluation of tenders. Present technical
Maharashtra, aspect of the project, approval of project/
sanctioning of grant etc. Project
management services during execution
including supervision of works. Post
tender activities. The project consist of
61.42 Km of sewers from 150 to 700 mm
dia., STP of capacity 9.67 MLD
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
34. Project Karad Municipal Karad 43.22 Cr (CP) Oct Ongoing May Preparation of tender documents and
Management Council Municipal evaluation of tenders received.
Consultancy for Council, Karad, 2012 2015 Finalization of contractor, award of work
Underground Dist. Satara, to the selected contractor after approval
Drainage System Maharashtra from Council. Site supervision, checking
in Karad under layouts and working drawings, quality
Maharashtra control, scrutinize and certify ongoing
Nagarotthan work and certification of bills of
Maha abhiyan contractor. Preparation of project
Project completion report, compilation of as built
drawings and technical data.

35. Project Malkapur Nagar Malkapur 40.97 Cr (CP) Mar Ongoing Feb Preparation of tender documents and
Management Panchayat Nagar evaluation of tenders received.
Consultant for Panchayat, 2014 2016 Finalization of contractor, award of work
Underground Malkapur, Tk: to the selected contractor after approval
Drainage System Karad, Dist: from Council. Site supervision, checking
in Malkapur Nagar Satara layouts and working drawings, quality
Panchayat under control, scrutinize and certify ongoing
UIDSSMT work and certification of bills of
contractor. Preparation of project
completion report, compilation of as built
drawings and technical data.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
36. Designing Defence R & D Defence R & D 1 Lakh (CF) March July July Design of 0.20 MLD capacities Sewerage
Sewerage Org. (DRDO), Org. (DRDO), Treatment Plant with connected civil
Treatment Plant GoI, Post Box 2008 2008 2008 works. Conducting study of various STP
of 0.20 MLD No. 1, and preparation of preliminary scheme.
capacity with Armament Finalization of details with CCE (R & D),
connected civil Post, Pashan, West, Pune. Development of approved
works services at Pune – 411 scheme and submission of tender
Defence R & D 021 documents. Preparation of detailed
Org. (DRDO), technical specifications for the work.
Pune Approval of design.

37. Preparation of Rural Water Zilla Parishad 139.94 Cr Jan Dec Dec Preliminary visit
DPR for Liquid Supply Division, Kolhapur, (CP) Categorization of villages – Villages
and Solid waste Zilla Parishad, Nagala 2013 2013 2013 polluting the river/ villages not polluting
Management in Kolhapur Park,Kolhapur the river
39 Villages and Flow measurement at all the outfalls
Prefeasibility Sewage Sample Testing from Laboratory
Report for 135 Land requirement assessment for solid
villages in and liquid waste treatment plants
Panchganga River Suggesting proper technology for liquid
basin Causing and solid waste management
pollution Topographical survey
Preparing detailed project report
Assistance to Kolhapur Zilla Parishad in
sourcing funds for the project
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
38. Carrying out Various Various NA April May May Carrying out various Road surveys using
various Road Employers (i.e. Employers (i.e. Unmanned Aerial Vehicles (UAV/Drones).
Surveys using MSRDC, MSRDC, 2016 2016 2016 Data collection using high definition
Unmanned Aerial AECOM, AECOM, imaginary.
Vehicles Eurostudios, Eurostudios, Data processing using high end software‟s
(UAV/Drones) Mechafree etc) Mechafree etc) & generation of desired digital elevation
models.
Total Length Creation of 2D, 3D & contour data.
surveyed: More Carrying out surveys in inaccessible areas
than 100 Kms. like. Tunnel, Mountainous areas.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
39. Consultancy Maharashtra Maharashtra NA April Dec Dec Fixing of alignment and its approval.
Services for State Road State Road Aerial Survey using (Drone) for green
preparation of Development Development 2016 2017 2017 field alignment of 90km, Processing
Feasibility Study Corporation Corporation the data on software’s. Traffic surveys
and Detailed Ltd. Ltd. and demand assessment
Project Report of Bandra Engineering surveys and investigations.
Access Controlled Mumbai Location and Proposals for revenue
Nagpur-Mumbai generation by commercial exploitation
Super along the corridor.
Communication Study, analysis, economics of different
Expressway.- land pooling/procurement models for
Nagpur Revenue expressway project
Division Location and layout of toll plazas, Trauma
(Package-I) Centre
Location and layout of truck lay byes
Location and layout of bus bays and bus
shelters
Social impact & Environment impact
assessment
Preliminary designs of road, bridges,
interchanges, VUPs, PUPs, ROBs, RUBs,
structures, etc.
Mapping of existing and proposed utilities
in the form 2D CAD Drawing and 3D CAD
models. Preparation of Land Plan
Schedules and Utility Relocation Plans
Preparation of indicative BOQ and
Detailed Cost Estimates .
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
40. Preparation of Maharashtra Maharashtra NA June Nov Nov 2017 PriMove is in association with S.N Bhobe
DPR of selected State Road State Road & Associates for this work.
stretches/corridor Development Development 2016 2017
of Road networks Corporation Corporation Topographical Survey of alignment,
in Sate of Ltd. Ltd. Prepration of contour drawings for
Maharashtra for Bandra existing alignments.
Package No. 5 Mumbai Collection of land plans/village maps,
(Tembhurni To 7/12, Geo-referencing of village maps.
Latur) Prepration of Land acquisition proposals.

41. Preparation of Maharashtra Maharashtra NA June Nov Nov 2017 PriMove is in association with S.N Bhobe
DPR of selected State Road State Road & Associates for this work.
stretches/corridor Development Development 2016 2017
of Road networks Corporation Corporation Topographical Survey of alignment,
in Sate of Ltd. Ltd. Prepration of contour drawings for
Maharashtra for Bandra existing alignments.
Package No. 16 Mumbai Collection of land plans/village maps,
(Phaltan To 7/12, Geo-referencing of village maps.
Mhaisal) Prepration of Land acquisition proposals.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
42. Preparation of S. N. Bhobe & S. N. Bhobe & NA Aug Dec Dec 2017 Topographical Survey of alignment,
DPR for Two lane Associates Associates Prepration of contour drawings for
with paved 2016 2017 existing alignments.
shoulder for Navi Mumbai Collection of land plans/village maps,
costal road MSH4 7/12, Geo-referencing of village maps.
from Jaigad to Prepration of Land acquisition proposals.
Khakshita thita in Feasibility of various suitable alignments.
Maharashtra Prepration of DPR, Estimates, BoQ‟s,
Tenders for Road Network, Bridges, Creek
bridges,

43. Preparation of S. N. Bhobe & S. N. Bhobe & NA Aug June June 2017 Topographical Survey of alignment,
DPR for Pune Ring Associates Associates Prepration of contour drawings for
Road (Westerly 2016 2017 existing alignments.
Section) Navi Mumbai Collection of land plans/village maps,
7/12, Geo-referencing of village maps.
Prepration of Land acquisition proposals.
Feasibility of various suitable alignments.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
44. Project Pune Municipal Pune Municipal 60 Cr (CP) Jan Dec Dec Project management consultants on new
Management Corporation, Corporation, and resurfacing of roads in a total of 7
consultants for Pune ShivajiNagar, 50 Lakhs 2007 2007 2007 different packages (Seven different
Road projects in Pune projects)
Pune City (CF) Quality Checking, Inspection
(7 Ring Road Project Monitoring & Report Preparation
projects) Co-ordination between Pune Municipal
Corporation and Contractors

45. Project Nanded Nanded 35 Cr (CP) Oct Nov Nov Finalisation of road alignments based on
management Municipal Municipal the development plan & transferring it on
consultancy and Corporation Corporation 65 Lakhs 2006 2008 2008 the ground, Preparation of land
Preparation of Nanded acquisition proposal is government
DPR for South (CF) prescribed format , Preparation of DPR
Nanded Road including detailed design, GIS Base data,
development technical specifications, bill of quantities,
Project rate analysis and cost estimates,
Preparation of bid document, support
evaluation of bids, Project management
services during execution including
project scheduling, quality management,
bill certification and on the site technical
support
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
46. Preparation of Fortress Fortress 40 Cr (CP) Feb Dec Dec Total survey of entire road. Preparation of
DPR for Mahur Infrastructure Infrastructure detailed design, estimate and specification
Road Advisory Advisory 28 Lakhs 2010 2010 2010 of various infrastructures. Preparation and
Development Services Services evaluation of tender document.
Project for Daryanagar (CF) Supervision of work, post tender activities
Department of House, of Mahur Road (Hilly Terrain) project
Tourism & Maharashi
Culture, Govt. of Karve Road,
Maharashtra Marine Lines,
Mumbai

47. Project Fortress Fortress 36 Cr (CP) April Nov Nov Total survey of entire road (15.5 KM BT
Management Infrastructure Infrastructure road) and 3 KM (concrete) Parikrama
consultancy and Advisory Advisory 32 Lakhs 2010 2010 2010 Marg. Preparation of detailed design,
preparation of Services for Services estimate and specification of various
DPR for Shegaon Department of Daryanagar (CF) infrastructures. Preparation and
BT & concrete Tourism and House, evaluation of tender document.
Road Culture, Govt. Maharashi Supervision of work, post tender activities
development of Maharahstra Karve Road, of Shegaon Road development including
including Marine Lines, Parikrama Marg Project.
Parikrama Mumbai
Project.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
48. Fixing alternative ATR ATR 40 Cr (CP) April Nov Nov Alternative alignment for NH4 at
alignment for NH4 Infrastructure Infrastructure Khambatki ghat. Survey and preparation
at Khambatki Pvt. Ltd. Pvt. Ltd. 2.5 Lakhs 1997 1998 1998 of detailed working estimates including
Ghat India India alignment finalisation, tunnel alignment,
(CF) for a section of Pune to Bangalore
highway (NH4) at Khambatki Ghat
including tunnel alignment, Encoding the
data, preparing computerized design and
GIS, Quality control and quantity checking
for works done and monitoring earthwork
vis-à-vis planned alignment

49. Preparation of Prasad Thane 100 Cr (CP) April Jan Jan Plane table survey for city roads and
Integrated Road Architect/ Municipal chowks, Marking boundaries as per
Development Thane Municipal Corporaion, 10 Lakhs 1997 1998 1998 Development Plan, Preparing Autocad
Phase I and III in Corporation Mumbai drawings for surveyed length of road,
Thane city (CF) Marking of boundaries on site as per DP
Plan for execution, L section and Cross
section survey of roads, Surveyed length
of roads 100 Km and 33 crossings and
junctions
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
50. 3D Remote The World Bank The World 23.75 Lakhs Jan April April Image Classification to prepare Land use
sensed Minor Bank (CF) & Land cover maps from 1990 to 2015
Irrigation New Delhi 2015 2015 2015 (Pre monsoon and Post monsoon).
Modeling & Crop The image classification of Pre Monsoon
Suitability Atlas & Post Monsoon images of Landsat 7 or
for West Bengal LISS 3 images which are freely available
Accelarated on NRSC website for year 1990 to 2000
Development of and latest images (2014-2015) will be
Minor Irrigation procured from NRSC for both districts
Project (Bankura & West Midnapur).
Change Detection study will be done by
using classified images , field visit
(ground verification) & Google earth
images
Base map preparation from topo sheets &
Digitization of Soil Maps for two districts.
DEM (Digital Elevation Model) Generation
i-e Surface Generation from imagery
Image Classification to prepare Land use
land cover maps for 1990 -1991 and 2000
for two districts (Bankura & West
Midnapur)
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
51. Preparation of Collector office 96.40 Lakh Sept Aug Aug Defining the project area
Zilla Parishad,
Environmental campus, (CF) Collection of base line data / information
Solapur
Development Plan Solapur 2014 2015 2015 to understand the present status of the
of 10 Villages in
village
Tal: Malshiras,
Pandharpur & Preparation of the base map and other
Madha in Solapur theme maps
District Preparation various Environmental action
plans
Development of vision for the process and
plan.
Identification of techno-economically
viable projects
52. Consultancy for RSPMU, Water RSPMU, Water 1.90 Cr May Jan Jan Identifying capacity building
Preparation of Supply & Supply & requirements at various levels (Needs
Capacity Building Sanitation Sanitation 2015 2017 2017 assessment)
Plan & Modules Department, Department, Assessing and improving the existing
under GoM GoM Maharashtra State Training Policy of the
Jalswarajya-Phase CIDCO sector
II Bhavan, Navi Developing a five year capacity building
Mumbai. plan for Maharashtra State including
resources requirement (internal/ external)
Developing a Capacity building
Implementation Plan for Maharashtra
State
Developing standard modules for key
trainings to be imparted
Develop a framework for monitoring the
effectiveness of implementation of
capacity building plan and its outcomes,
Train the Master Trainers
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
53. Capacity Building United Nations Unicef, UN 25.06 Lakhs July Dec Dec 5 days training of Master Trainers (State
& Handholding Children's Fund House, Plot (CF) 2017 2017 2017 level-5 days training on Orientation on
support for (Unicef) No:-41-42, status of WASH in MP, community
Community based Polytechnic approaches water safety and security,
village Water Colony, detail description of community level
Safety & Security Shyamla Hills, processes VWSS.
(VWSS) approach Bhopal 3 days workshop for newly recruited sub-
in Madhya engineers on community led water safety
Pradesh. and security planning.
3 divisional workshops of Madhya Pradesh
divisions namely Jabalpur and Gwalior on
brief orientation on community
approaches for water safety and security
processes, convergence from various line
department and preparation &
implementation of VWSS plans in
respective districts.
Handholding support by resource persons
for preparation and implementation of
community led VWSS plans.

Handholding support to trained Master


trainers and district level PHED team in
piloting the VWSS approaches in 10
villages in 2 districts.
Guidance on implementation process,
reviews, cross learning events, onsite
capacity building of tem, communication
with block and district level officials and
presentation of key learnings in DWSM.
Preparation of action plan on key actions,
capacity building plans.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
54. Support services United Nations United Nations 27.40 Lakhs July Dec Dec 3 days training of Master Trainers on
for Capacity Children's Fund Children's (CF) 2017 2017 2017 community approaches water safety and
Building on (Unicef) Fund (Unicef) security, detail description of community
Community Led 3/194 Vishal level processes VWSS.
Village Water Khand, Gomti 1 day orientation training on community
Safety Security Nagar approaches for water safety and security
(VWSS) in Uttar Lucknow processes, convergence from various line
Pradesh department and preparation &
implementation of VWSS plans in
respective GPs.
2 Nos of refresher trainings of one day
each at regular intervals.
Capacity building of government officials
on fluoride mitigation in one legislative
consultancy.
Handholding support by resource persons
for preparation and implementation of
community led VWSS plans in pilot GPs.
Adapt knowledge products (training
manuals for officials and community,
Guidelines/SoP on VWSS, O & M
standards for hand pumps and piped
water supply for learning and advocacy.
Suggest and demonstrate models of
integrated fluoride mitigation.
Preparation of monitoring framework for
water safety planning roll out.
Preparation of VWSS plans, training
reports, training methodology, IEC tools,
Key actions plans.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
55. Support services Water and Water and 29.47 Lakhs Aug Feb Feb 2018 Capacity Building of district level officials
for demonstration Sanitation Sanitation (CF) 2017 2018 Orientation meeting for district officials
and roll out of Support Support A state level orientation meeting with
Village Drinking Organisation, Organisation,
water quality consultants from all districts
Water Safety and Water Supply Water Supply
Security Plan in and Sanitation and Sanitation will be organized to share the concept and
Maharashtra Department, Department, methodology for VDWSS. The criteria of
Govt. of Govt. of Village Selection will be finalised.
Mahrashtra, Mahrashtra, Preparation of VDWSP Plans
CIDCO A 3 day participatory VDWSS process will
Bhavan, South be conducted in selected one GP from 34
Wing, 1st districts.
Floor,, CBD Training on convergence for the district
Belapur Navi officials
Mumbai,
Mumbai, Three trainings of three days each on
Maharashtra convergence for implementation of
VDWSS plan will be conducted for district
officials. The officials will be oriented on
implementation of plan through
convergence and also its roll out.

Preparation of VDWSS Action Plan Format


and guidance note on District VWSS Plan

Based on the 6 pilot VDWSS action plans,


a format for preparation of VDWSS Action
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
56. Technical Support UNICEF UNICEF, 19, 40.78 Lakh April Mar Mar Development of state level operational
to bring sanitation , Mumbai Parsi (CF) manual of district water safety plan
to scale in Latur Panchayat 2014 2016 2016 implementation
and Chandrapur Road, Andheri Development of State operational manual
ZP (Maharashtra) (East), for NBA
with focus on Mumbai Designing and facilitation of state level
thematic capacity TOTs on ODEP
building and Support to development of Chandrapur
institutional district water safety plan
strengthening at District level support to bring sanitation at
state level scale in Chandrapur and Latur
Sharing Knowledge Products/Experiences
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
57. Evaluation Plan India, New E-12 Kailash 20.23 Lakh May Dec Dec 2014 Assignment understanding through the
/Assessment of Delhi Colony, New (CF) briefing meeting with client and WASHI
capacity building Delhi 110048 2014 2014 Review of documents
programs
Designing of Training evaluation
conducted by
WASH Institute. framework and finalization of study
tools
Conduct consultative workshop
Conduct Training assessment exercise in
7 states and 1 UT
Documentation of best practices
showing training impact.
Conduct interview with state department
officials
Consultation with the officials from
Ministry of Drinking Water Supply and
Sanitation, GoI
Data Analysis and reporting
Sharing assessment findings with the
officials from Plan India, WASHI,
MDWSS, GoI
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
58. Rolling out of Child in Need Plot No. 441 A, 15.62 Lakhs April Feb Feb 2015 Organize and facilitate Orientation
Village Water Institute (CINI) Road No.5 (CF) training for professionals and filed
Safety and Ashok Nagar, 2014 2015 workers of the partner NGOs
Security Module, Ranchi
VWSS Planning Demonstration in 3 GP
in Jharkhand
state Visits and support to remaining PUs
during VWSS planning process
Organize and support during quarterly
Review meetings and monitoring with
each PU
Preparation of process document
capturing learning based on the basic
documentation done by local partners.
Preparation and submission of Report
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
59. Capacity Building YASHADA Yashada 80 Lakhs June May May 2016 The aim of the assignment is to build the
of District Rajbhavan (CF) capacity of representatives from District
resource Agencies Complex, 2010 2016 Resource Organization, Project Training
under Integrated Baner Road, Organization and Agriculture department
Watershed Pune for effective planning and implementation
Management of IWMP.
Programme This is ongoinig assignment. To complete
(IWMP) above task, PriMove undertake in depth
TNA of potential trainees from three
agriculture division i.e. Pune, Nashik and
Thane. Further team involved in
preparing training modules and manuals
on livelihood action planning, social
mobilization, project finance and
monitoring etc .and facilitated designed
5/10 day trainings.

Under this assignment so far PriMove


has facilitated around twenty trainings
for 660 members of DRO, PTO and
officials from Agriculture department in
Pune, Nashik and Thane agriculture
division of Maharashtra.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
60. Training on Water and 1st Floor, 22 Lakhs Mar Ongoing Ongoing Develop modules and manuals
„Community Led Sanitation South Wing, (CF) Organise capacity building activities for
Open Defecation Support CIDCO 2015 state, district and block level
Elimination Action Orgnisation Bhawan,
functionaries.
Planning Process (WSSO) CbdBelapur,
with focus on IPC‟ Navi Mumbai Develop knowledge bank and
For Key Resource disseminate technical knowledge to
Canters (KRCs) district and block.
To evaluate activities at various stages
of the program, impact analysis study,
monitor district level activities and share
experiences with state.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
61. consulting Maharashtra Market Yard, 87.63 Lakhs Nov Nov Nov 2016 Assessment of the Existing / Newly
services for Agriculture Gultekadi, (CF) formed Producer Groups for adopting
linking Producer Competitivenes Pune 2014 2016 them for PAs formation.
Groups (PGs) to s Project, raining Needs Assessment (TNA) on
forward Market Department of market linkages and agribusiness of
linkage and Agricultural, selected PGs. Assisting PAs for collection
formation of GoM of share capital.
Producer Identification of Business activities and
Associations (PAs) prepare commercially viable & bankable
& establishment Business Plan for PAs, Formation of
of Farmer
Procurement Committee.
Common Service
Centres (FCSC) Identification & capacity building of
Community Resource Persons (CRP).
Assist the Producers Associations (PAs) to
develop and strengthen the linkages for
marketing with other stakeholders, Hand
holding support and oversight for
operation and management of business
plans (with documentary evidence of
establishment of PAs).
Hand holding support and oversight for
operation and management of business
plans (with documentary evidence of
successful & sustainable PAs). Final
Report on achievements regarding
developing commercially viable successful
FCSCs by documenting the entire
activities and results thereof.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
62. Provide Support UNICEF, UNICEF, 19, 22.22 Lakhs May April Apr To facilitate environmentally responsible
agency for the Mumbai Parsi (CF) sustainable rural development RDD &
Eco Village Panchayat 2011 2012 2012 UNICEF appointed M/s PriMove as State
Program of Road, Andheri Level Support Agency. So far PriMove has
Government of (East), carried out various tasks it included
Maharashtra Mumbai Development strategy for big village,
compilation of various technological
options for environmental sanitation,
Preparation of role out plan for effective
implementation of the project, Develop
capacity building strategy, development
of process tools to be used for planning
and implementation, develop criteria for
identification of support organizations and
their procurement.
63. Support to Zilla Zilla Parishad – Zilla Parishad 4.5
– Lakhs Jan Dec Dec To train GP members, VWSC members
Parishad for Ratnagiri, Ratnagiri, (CF) Water persons and village as well as block
conducting Sindhudurg, Sindhudurg, 2008 2009 2009 level officials on Operation and
training on Satara, Satara, Kolhapur Maintenance of Water Supply and
Operation and Kolhapur etc. etc. Sanitation facilities using participatory
Maintenance of approach.
Water Supply and The method mainly consists of power
Sanitation point presentations, Group works,
facilities for practical‟s and demonstrations etc.
Village and Block
level Institutions
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
64. Training on GSDA/ UNICEF GSDA/ 18.36 Lakhs July March March Under this assignment PriMove extended
“Preparation of UNICEF (CF) services to train the GSDA staff and
Water safety and 2008 2010 2010 Unicef Partner NGOs working in IPD
security action districts on concept of water safety and
plans using PRA security plan of a particular village and
approach and also to develop their skill for preparing
tools” water safety and security plan using
participatory approach. The method
mainly consists of the different PRA tools
and techniques. The training results with
preparation of 3-action plans viz. (1)
Village water management plan (2) O & M
of water facilities (3) water quality action
plan.
65. Provide capacity KfW funded RSPMU, Water 25 Lakhs Dec Dec Dec Under this assignment, PriMove
Development project, Local Supply and (CF) formulated district capacity building plan
Experts in and state Sanitation 2009 2009 2009 in association with ZP and RSPMU after
“AaplePani” government of Department, detailed TNA exercise and conducted
project for Pune Maharashtra, Government of various in-house and practical trainings
district India Maharashtra, for NGOs, district teams and villagers
Mumbai referring phases of the project.
Besides above PriMove extended support
for preparing DPR, quality monitoring and
preparing progress report.
PriMove also extended services for
establishing settlement of community
monitoring and monthly reporting
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
66. Development & German GTZ, 8.48 Lakhs April Mar Mar Identification of stakeholders in the
Testing of Technical JorBaug, New
(CF) implementation of water shed
Modules for Corporation Delhi 2008 2009 2009 management program from the states.
Training of (GTZ) Assessment of the functions of the
Trainers and various stakeholders, identification of
Capacity Building required and existing competencies,
Managers under assessment of the training needs to
public programme bridge the capacity gaps. Review of
for watershed existing modules and identification of
management gaps in modules. Design a training of
trainers based on training needs
assessment and module review. Deliver
the designed module
67. Scoping Exercise Government of GTZ, 3.55 Lakh May Aug Aug Review present capacity development
for the national Himachal JorBaug, New (CF) system of the large public investment
capacity building Pradesh, GTZ Delhi 2007 2007 2007 programs, analyse new approached for
project for (German capacity building and recommend scope
decentralized Technical of interventions and operational plan for
water Cooperation) the project.
management
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
68. Capacity Building ZP Sangli, RSPMU, Water 300 Lakh June Dec Dec To achieve the goal of sustainable
Support to all Nashik and Supply and (CF) management of water supply facilities at
stakeholders Buldhana, Sanitation 2004 2007 2007 village level through community
under the RSPMU, Department, participation, Government of Maharashtra
Jalswarajya Government of Government of had appointed PriMove as a Capacity
Project in Nashik, Maharashtra Maharashtra, Building Organization in three districts.
Sangli and Mumbai Under this assignment PriMove extended
Buldhana districts following services.
Preparation and execution of district
capacity building plan.
Actively support communities in a total of
10 villages in two districts to implement
the components of Jalswarajya projects
and help them become Demo villages for
other communities.
Preparation of various assessment DPR
templates, training module, monitoring
formats etc. required for effective
implantation of project.
Establish effective reporting and
monitoring system for progress tracking.
Provide on the job support to the District,
Block and SO teams during
implementation of project.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
69. Conducting RSPMU, Govt. RSPMU, Govt. 11.50 Lakhs Oct Mar Mar Increasing rural households‟ access to
evaluation of 50 of Maharashtra of Maharashtra (CF) improved and sustainable water and
Tribal Project CIDCO 2009 2010 2010 sanitation services and institutional
Gram Panchayats Bhavan, Navi decentralisation of the rural water supply
spread over all Mumbai. and sanitation service delivery was the
the six revenue key objective of Jalswarajya project. This
divisions of the programme included some special
state – provision for tribal villages to improve the
Jalswarajya level of participation of these villages and
Project. TRIBAL to further improve water supply and
IEC sanitation status of these villages. This
evaluation was conducted in 50 GPs with
special emphasis on the project process
and the impact in tribal villages.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
70. Assessment of Sir Ratan Tata Sir Ratan Tata 7 Lakhs (CF) Sep Dec Dec Under this assignment, PriMove
impact on Trust Trust, Mumbai conducted Technical, economical and
community health 2009 2009 2009 social impact assessment of project
through drinking villages under Himmothan project in
water supply & Uttarakhad state. For that purpose
sanitation project PriMove
under Himmothan Developed require tools for data collection
Pariyojana Phase Developed indicators for assessment of
I, Uttaranchal technical and social impact of various
activities carried out under WATSAN
components of Phase – I
Assessed water quality/ sanitary situation
around drinking water sources
This project covers 112 households in
eight villages.
Transit walks of full project area and
assess the impact for the same.
Developed impact assessment report with
suggestive measures.
71. Conducting SES National NTPC Limited, 9 Lakhs (CF) April Feb Feb This includes rapid assessment of project
and Development Thermal Mumbai villages and PAFs to identify impact
of Power 2011 2012 2012 followed by review of NRRP 2007, MID
Entitlement Corporation- Act, NTPC R & R policy for designing R &
matrix for WRHQ-Mumbai R Framework & identifying mitigation
The Dhurvan measures,
Super Besides above PriMove extended services
Thermal Power for finalization of community development
Project, Anand activities and preparing land acquisition
district of Gujrat proposal.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
72. Conducting study National National 27.95 Lakh March Feb Feb Hydrological data analysis
on impact of high Rainfed Area Rainfed Area (CF) Geological data analysis
rainfall/ flooding Authority Policy Authority 2010 2011 2011 Assessment of the impact of floods based
on the ground & Plan Policy & Plan on above analysis
water resources Coordination Coordination Confirmation of the findings through
in the state of Unit Unit stakeholder consultations at government
Maharashtra, and community level
Karnataka & Estimation of ground water status
Andhra Identification of interventions for
Pradesh(NRAA) appropriate utilization of flood and
increased ground water table for various
purposes in the river basin.

73. Preparing of Govt. Of Govt. Of 92 Lakh (CF) Sep Feb Feb This included preparation of a Master Plan
Master Plan for Maharashtra, Maharashtra, for integrated Development and
Integrated Water Resource Water 2008 2011 2011 Management of Water resources of Terna,
Development and Department, Resource Lendi and Manar Sub–basins.
Management of Aurangabad Department, To identify and set priorities for promoting
Resources of Aurangabad water resources development projects in
Terna, Lendi and each sub-basin. Short and long term
Manar sub-basins action plan consistent with finance
allocations and priorities of the state
Govt. in each sub-basin.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
74. Conducting SES National NTPC limited 11 Lakhs Mar Oct Oct This includes rapid assessment of project
and Development Thermal (CF) villages to identify impact , review of
of Power 2010 2010 2010 NRRP 2007, MID Act,
Rehabilitation Corporation R & R policy for designing R & R
Action Plan for Framework, Participatory process to
Mouda Super identify mitigation measures and
Thermal Power finalization of community development
Project-Stage-II activities and
Compensation package. Designing of RAP
implementation framework
75. Social Groundwater GSDA, Govt. of 13 Lakhs Jun Feb Feb This is an innovative project initiated
Assessment for Surveys and Maharashtra, (CF) under Maharashtra Water Sector
Sustainable Development Shivajinagar, 2007 2008 2008 Improvement Project funded by the world
Groundwater Agency Pune 5. bank focusing at four aquifers. The social
Management (GSDA), Water assessment is aimed at understanding
under Supply & potentials and constraints for social
Maharashtra Sanitation acceptance of the proposed aquifer
Water Sector Department, management approach.
Improvement Govt. of
Project (MWSIP), Maharashtra,
India the World Bank
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
76. Maharashtra The World Bank Water and 6.38 Lakhs Nov Feb Feb The project is aimed at understanding
Reforms Process Sanitation (CF) current status of reform process in Water
Assessment Program – 2007 2008 2008 supply sector in Maharashtra and to seek
South Asia further directions for implementation of
(WSP – SA), reforms. The study evaluates reform
New Delhi process in all programs related to drinking
water supply in six districts spread across
the state.
PriMove is contributing is designing of
evaluation, data collection/ interactions at
the state, district and village level, writing
report and presentations.

77. Engaging The World Bank Water and


89.36 Lakh June Dec Dec To achieve the goal of total sanitation
Resource Sanitation (CF) campaign WSP - SA has empanelled
Agencies to assist Program – South 2007 2008 2008 resource agencies to support various
in promoting Asia (WSP - SA), state governments in India. The approach
Community Led New Delhi adopted triggers the community action
Total Sanitation leading towards behaviour change.
Currently PriMove is working with MP
Government. The assignment covers
varied types of trainings including ToT for
creating open defecation free
environment.
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
78. Support Services UNICEF UNICEF, 19, 27.95 Lakh Mar Feb Feb Creation of knowledge products,
to Latur and , Mumbai Parsi (CF) specifically training manuals, capacity
Chandrapur Zilla Panchayat 2013 2014 2014 building framework, scheme convergence
Parishad to Road, Andheri
booklets through documentation
implement village (East),
water safety and Mumbai Inculcating decentralized planning under
security and NBA and NRDWP and inform the learning
community led at state level for up scaling.
open defecation Developing a systematic capacity building
free villages plan for DWSM and BRCs for Latur and
programme under
Chandrapur ZP to implement village water
Nirmal Bharat
Abhiyan (NBA) & safety security and Open defecation
National Rural elimination plans and make a village open
Drinking Water defecation free
Programme Advocacy to integrate WASH agenda in
(NRDWP) (Latur the VHNDs and support districts to
and Chandrapur) mainstream VHNDs to develop a
framework on diarrhoea prevention and
management at the district level
79. Support Service UNICEF, UNICEF, 19, 19.76 Lakh Aug Aug Aug Provide technical and process
for Water Safety Mumbai Parsi (CF) management support to UNICEF partner
and Security Panchayat 2010 2011 2011 NGOs engaged in implementation of bio-
Component Under Road, Andheri
village programme in three IPDs and
Bio Village (East),
Program in IPDs Mumbai relevant district and block level staff to
of Maharashtra prepare and implement bio-village and
VWSS interventions in project villages
from three integrated districts through
training, hand holding process monitoring
and documentation
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
80. Development of a Plan EE-12, Kailash 22.75 Lakh May March March Access to safe drinking water and
Training Manual International Colony, New (CF) hygienic sanitation are vital for the
on Child Centered (India Chapter) Delhi - 110 2012 2013 2013 survival and development of children and
048
School & youth, as well as for the economic well-
Community being of their families and communities.
Water, Sanitation Recognizing this, Plan India is supporting
& Hygiene development of manuals on Child
Promotion Centered School and Community Water,
Sanitation and Hygiene Promotion. The
objective of this exercise is to have a
healthy linkage between the school and
community and vice versa to ensure
sustainability of the program intervention.
81. Support services NTPC Ltd Mouda Super 14.91 Lakh Sept Jan Jan Undertaking Base line information of
for Thermal Power (CF) project villages
implementation Project, Mouda 2012 2014 2014 Designing of training module
– Ramtek
of Village Water Preparation of workbook on VWSS and
Road, Mouda
Safety &Security District - Guidance booklets on Participatory Rural
Program under Nagpur Appraisal, Environmental Sanitation,
WATSAN Water Resource Management, Water
component Quality Monitoring and Operation and
Maintenance of WS facilities.
Facilitation of village and Block level
trainings
Support in village level Planning,
Implementation and monitoring under
VWSS project
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
82. Evaluation of Director Soil & Director Soil & 24.93 Lakh July Ongoing Aug Design frame work for evaluating
Ideal village Water Water (CF) Aadarshgaon Yojana
Scheme Conservation Conservation 2013 2014 Evaluation of 15 % project villages
(Aadarshgaon Agricultural Agricultural representing agro climatic zone of
Yojana) of Rural Dept GoM Dept GoM, Maharashtra
development & Shivajinager, To assess the impact of saptasutri at
Water Pune village level
Conservation To analyze quality of interventions
Department, GoM To assess impact of core and noncore
activities in project area
To study Impact of the program in the
village and surrounding area
Prepare strategy for scaling up of the
approach
Suggest changes to enhance effective
implementation of the scheme

Preparation of evaluation report


83. Development of Government of Government of 5.74 Lakh Sept Oct Oct Development of program strategy to
watershed Lesotho, Lesotho, GTZ (CF) operationalize watershed management
management Bos. 988 2005 2005 2005 program through Local government in
program strategy Laseru- 100 Lesotho
in Lesotho
Lesotho
(Maseru-Africa)
Name of the Name of the Address of Total Cost Duration of the assignment Description of the
Sr.
Project Employer’s the of the Assignment/Services
No.
Employer’s Project From To Expected
(CP)* Aprx/ (Date) (Date) /
Consultancy Complet
Fees (CF) ed in
In INR year
84. Expansion of Gannon A/501, 170 Cr (CP) May June June 2013 Preparation of Bidding documents. Design
Upper Ruvu water Dunkelrey & Business 2013 2013 of 137MLD treatment plant, Pumping
treatment plant, Co. Ltd. and Square, 6.74 Lakh mains, Cost Estimation and preparation of
Dar-Es-Salam, Jain Irrigation Building No (CF) drawings.
Tanzania Systems Ltd. 151, Opposite
Popular Car
Bazar,
Chakala, Andh
eri Kurla
Road, Andheri
East, Mumbai -
400093
85. Technical Advisors Oxfam GB Oxfam GB 5 Lakh (CF) June Sept Sept 2000 Making assessments in newly accessible
Water Supply & 274 Banbury 2000 2000 areas after the civil war to design and
Sanitation Road, Oxford, implement public health projects with
Eritrea, East OX2, 7 DZ, focus on water and sanitation.
Africa U.K. Setting up emergency water supply and
sanitation infrastructure in refugee and
internally displaced peoples‟ camps.
Identifying and strengthening local NGOs
and government departments to operate
and maintain the infrastructure.
Representing the lead Watson
organization in the country, on water and
sanitation co ordination forum to guide
the national program and formulate
policies.
Infrastructure Development
Consultants Pvt. Ltd
C-3,304 B, Saudamini Complex, Bhusari Colony,
Paud Road, Kothrud, Pune -4311038. Maharashtra,
INDIA
+91 20 25280200/01
info@primoveindia.com ; www.primoveindia.com

You might also like