PROJECT: TWO STOREY RESIDENTIAL BUILDING

CONTRACTOR: CGSC BUILDERS


LOCATION: BAYABASON MARAMAG BUKIDNON
SUBJECT: BREAKDOWN OF QUANTITIES
ITEMS DESCRIPTION OF WORK QTY. UNIT

2 EARTHWORKS
2.1 CLEARING AND GRUBING 600 Sq.m
2.2 SURVEY AND LAY-OUT 600 Sq.m
2.3 SOIL POISONING 32.04 Sq.m
2.4 EXCAVATION 118.41 Cu.m
2.5 BACKFILL AND COMPACTION Cu.m
2.5.1 MATERIAL:
BACKFILL MATERIAL 80.238 Cu.m
2.6 GRAVEL BASE
2.6.1 MATERIAL:
GRAVEL 44.815 Cu.m

3 FORMWORKS
FABRICATION
3.1 COLUMN FORMWORKS
3.1.1 MATERIAL:
1.2m X 2.4m X 6mm PLYWOOD 53 Pcs.
2” X 3” LUMBER 6737.3 Bd.ft
1 ½” NAILS 5 Kg
4” NAILS 110.5 Kg
3.2 GIRDER/BEAM FORMWORKS
3.2.1 MATERIAL:
1.2m X 2.4m X 6mm PLYWOOD 85 Pcs
2” X 3” LUMBER 9148 Bd.ft
1 ½” NAILS 8 Kg
4” NAILS 177.6 Kg
4 SUSPENDED SLAB FORMWORKS
4.1 MATERIAL:
1.2m X 2.4m X 6mm PLYWOOD 49 Pcs
2” X 3” LUMBER 5264 Bd.ft
1 ½” NAILS 4.62 Kg
4” NAILS 102.2 Kg
5 SCAFOLDING AND STAGING
5.1 MATERIAL:
H-FRAME 1.70 X 1.20m
CROSS BRACE
JOINT PIN
ADJUSTABLE BASE JACK 500mm
ADJUSTABLE STEEL PROPS 3.6m
U-HEAD 1.50m
6 REMOVAL
6.1 COLUMN FORMWORKS REMOVAL 151.4 Sq.m
6.2 GIRDER/BEAM REMOVAL 243.3 Sq.m
6.3 SUSPENDED SLAB FORMWORKS REMOVAL 140 Sq.m
PROJECT: TWO STOREY RESIDENTIAL BUILDING
CONTRACTOR: CGSC BUILDERS
LOCATION: BAYABASON MARAMAG BUKIDNON
SUBJECT: BREAKDOWN OF QUANTITIES