Jadwal Produksi 3 (Sisa 6 Hari)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROGNOSA PRODUKSI PERIODE SEPTEMBER 2018

September Tota
Volume Sisa
Proyek Owner Plant Koordinator Produk Sat 24 25 26 27 28 29 30
PMO Produksi Btg
Sn Sl Rb Km Jm Sb Mg
Proyek Cirebon-2 Coal Fired Power Plant Hyundai Engineering & Construction CO.,LTD Plant Karawang 60 A3 M 15 Btg 2050 766 128
128
Proyek Cirebon-2 Coal Fired Power Plant Hyundai Engineering & Construction CO.,LTD Plant Karawang 60 A3 B (Mamira Shoes) 15 Btg 2050 1117 30 30 30 30 30 5 441
286
Proyek Tol Cibitung-Cilincing Seksi 2 PT. Waskita Karya Divisi VII Plant Cibitung 60 B0 B 12 Btg 2221 530 50 50 50 50 50 25 867
592
Proyek Tol Cibitung-Cilincing Seksi 2 PT. Waskita Karya Divisi VII Plant Cibitung 60 B0 B 10 Btg 161 148 10 10 10 10 10 5 68
13
Proyek Tol Cibitung-Cilincing Seksi 2 PT. Waskita Karya Divisi VII Plant Cibitung 60 B0 M 10 Btg 1670 1327 20 20 20 20 20 5 281
176
Proyek Tol Cibitung-Cilincing Seksi 2 PT. Waskita Karya Divisi VII Plant Cibitung 60 B0 M 9 Btg 782 672 15 15 15 15 15 5 174
94
Proyek Tol Cibitung-Cilincing Seksi 3 PT. Waskita Karya Divisi VII Plant Cibitung 60 B0 M 9 Btg 2274 2272 15 15 15 15 15 5 82
2
Tol Bekasi Cawang Kampung Melayu 1 A PT. Kresna Kusuma Dyandra Marga Plant Sadang U-ditch 800x1000x1200 Blk 1475 270 60 60 60 60 30 270
0
Tol Bekasi Cawang Kampung Melayu 1 A PT. Kresna Kusuma Dyandra Marga Plant Sadang PCI Girder H=1,85 L=20,90 CTC : 2.40 m Blk 6 0 6
6
Total Rencana 140 140 140 140 140 50 0 2041
Realisasi Produksi yang di PU 0 0 0 0 0 0 0 1291
Deviasi -140 -140 -140 -140 -140 -50 0 0