TITLE:
ATTACHED DOCUMENTS:
1463-T-Q-029-Hydrostatic Test
1463-T-Q-024-Liquid Penetrant Testing
1463-T-Q-014- Radiographic Examination
1463-T-Q-026- Pneumatic Inspection Test
REFERENCE DOCUMENTS:
1. GENERALS
The procedures of the tanks and pipes inspection and testing will be developed
according to the following documents:
• Document VNG-T-Q-024 Liquid Penetrant Testing (PT): This test shall be used to
inspect the welding and the base material of the tanks temporary weld.
The Thermal Treatment Test (HT), the Magnetic Particles Test (MT) and the Ultrasonic
Test (UT) will not apply in this project. Instead of MT and UT we will use PT and RT.
1. OBJECT
The present procedure defines the steps to execute hydrostatic test on pressure
vessels, atmospheric tanks and piping.
2. SCOPE
The present document establish the procedure for hydrostatic test execution in
accordance with ASME Code, Section VIII Div. 1 (UG-99), applicable to pressure
vessels, API-650 and API-620 Code applicable to atmospheric tanks.
3. referencEs
4. TERM DEFINITION
5. INVOLVED UNITS
6. USED FORM
7.1. Production personnel shall prepare the hydrostatic test performance at the
workshop in accordance with the Fabrication Process. The Quality Control
Inspector (QCI) shall revised and authorized the preparation until the pressure is
collocated.
7.3. Hydrostatic test should be done before the equipment is protected with paint.
For atmospheric tanks, if paint is going to be applied before hydrostatic test due
to manufacture strategy, welds must be reserved and not painted
7.4.1. All the pressure vessels have to be test it with Hydrostatic test. Hydrostatic test
have to be done after vessel fabrication is finished, including post-weld heat
treatment. It will be better before metal surface conditioning and painting; and
after all non destructive test and applicable examinations have been approved in
accordance with the Manufacture Quality Control Plan, internal/external
inspection, and the final as built report
7.4.2. Minimum hydrostatic test pressure shall be equal to 1.3 times the Maximum
Allowable Working Pressure (MAWP), multiplied by the minor relation between
the stress face at test temperature and the stress at design temperature.. All
loadings that might exist during this test shall be given in consideration.
7.4.3. Shall be used calibrated pressure gauges according to the Process of Calibration
(VNG-Q-062). An indicating gage shall be connected directly to the vessel. If the
indicating gage is not readily visible to the controlling operator , an additional
indicating gage shall be provided in a visible place to the operator.
7.4.4. The range of the pressure gauge scale shall be approximately two times greater
than the test pressure, but not smaller than 1,5 times and not greater than 4
times of the test pressure.
7.4.5. The equipment position for test performance shall be indicated on calculation and
drawings design. If by reason of safety and space availability a vertical vessel
shall be tested in horizontal position, the water column pressure shall be
considered in the calculations and drawings design.
1463-Q871-1-006 Testing procedures FO-Q-001-2 Rev. 1 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-029
CHAPTER: III) PROCEDURES OF CONTROL DATE APPROV.: 07/04
SUBJECT: 10.- HYDROSTATIC TEST INSPECTION DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG.: 3 OF 10
7.4.6. Vent valve shall be located al highest position of the vessel to evacuate air during
the filling.
7.4.7. Before apply the pressure to the vessel, the quality control inspector has to verify
that all vessel accessories that are not subject to the test have been
disconnected, and equipment is hermetically sealed.
7.4.8. Pressure test shall be watched during all test period in order to avoid pressure
increases
7.4.10. Vessel designed for total or partial vacuum pressure, shall be submitted to
an internal hydrostatic test, and if the test is not applicable shall be made a
pneumatic test according with UG-100. Test shall be performed at pressure not
smaller than one a half times the difference between the atmospheric pressure
and de minimum absolute internal design pressure (UG-99(f)).
7.4.11. After the application of the hydrostatic test pressure, an inspection of all
joints and connections shall be made. This inspection shall be made to the test
pressure divided by 1.3.
7.5.1. Tank shall be filled with water to maximum design level or 2 inches over the
welded joint of the roof sheet, or over the last pipe connection according to API-
650 Code.
7.5.3. The vessel tanks fabricated under API 650 code, should be let with water at least
24 hours or according to the indications of the client inspector or the purchase
order. The atmospheric tanks that are not fabricated with a particular
specification will be with water at least 6 hours.
7.6.1. Test pressure in any location of the pipe system shall be at least 1.5 times
the design pressure
1463-Q871-1-006 Testing procedures FO-Q-001-2 Rev. 1 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-029
CHAPTER: III) PROCEDURES OF CONTROL DATE APPROV.: 07/04
SUBJECT: 10.- HYDROSTATIC TEST INSPECTION DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG.: 4 OF 10
7.6.2. During test pressure all joints shall be connected and inspected, unless
connections have been tested before.
7.6.3. Steam and gas pipes, shall be provided with supplementary supports to resist
the water weight, if necessary.
7.6.4. Equipment that does not require test pressure shall be disconnected.
7.6.5. The pressure gauge scale range and calibration shall be as described for
pressure vessels.
7.7.1. Hydrostatic test have to be done after tank fabrication, when post-weld heat
treatment (if apply) are finished; preferably before metal surface conditioning
and painting; and after all non destructive test and examination applicable have
been approved in accordance with the Manufacture Quality Control Plan,
internal/external inspection, and the final as built report and preliminary test.
7.7.2. Before water is introduced into the tank, the following Preliminary Test shall be
performed:
7.7.2.1. The attachment welding around all openings and their reinforcements in the
walls of the tank shall be examined by the penetrant liquid method both inside
and outside the tank.
7.7.2.2. After the examination specified in 7.7.2.1 is introduce air with a pressure of 15
lbf/in2 gauge between the tank wall and the reinforcing plate, saddle flange, or
integral reinforcing pad on each opening, using telltale holes. While each space
in subject to the pressure a solution film shall be applied to all attachment
welding around the reinforcement, both inside and outside the tank.
7.7.2.3. In case in which the bottom of the tank rest directly on the tank grade
(preventing access to the underside of the bottom of the tank), all joints between
the bottom plates shall be tested on the inside of the tank, applying a solution
film to the joints and pulling a partial vacuum of at least 3 lbf/in2 gauge by means
of a vacuum box with a transparent top.
7.7.2.4. After all the welding has been examined and tested and all defective welding
disclosed by such examination and testing has been repaired and retested, the
tank shall be filled with air to a pressure of 2 lbf/in2 gauge or one-half the
pressure Pg, for which the vapor space at the top of the tank is designed,
1463-Q871-1-006 Testing procedures FO-Q-001-2 Rev. 1 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-029
CHAPTER: III) PROCEDURES OF CONTROL DATE APPROV.: 07/04
SUBJECT: 10.- HYDROSTATIC TEST INSPECTION DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG.: 5 OF 10
whichever pressure is smaller. A solution film shall be applied to all joints in the
tank wall above the high liquid (capacity) design level. If any leaks appear, the
defects shall be removed and rewelded, and the applicable preliminary tightness
test specified shall be repeated.
7.7.3.1. Tanks that have not been designed to be filled with liquid to as test level higher
their specified capacity level shall be subject of a combination hydrostatic-
pneumatic pressure test in accordance with the following.
7.7.3.2. After the preliminary tightness test specified in 7.7.2. have been completed, the
pressure-vacuum relief valve or valves shall be blinded off. With the top vented
to the atmosphere to prevent accumulation of pressure, the tank shall be filled
with water to its high liquid (capacity) design level. Tank anchor retainers shall
be adjusted to a uniform tightness after the tank is filled with water. If the
pressure-vacuum valve or valves are not available at the time of the test, the
tank connections may be blinded off and the test procedure continued by
agreement between the purchaser and the manufacturer. With the vents at the
top of the tank closed, air shall be injected slowly into the top of the tank until the
pressure in the vapor space is about one-half the pressure Pg, for which this
space is designed. The air pressure shall be increased slowly until the pressure
in the vapor space is 1.25 times the pressure Pg for which the space is
designed.
7.7.3.3. An air test introduces some hazard. In view of the large amount of air that will be
present in the tank during this test, no one should be permitted to go near the
tank while pressure is being applied for the first time during the test. While the
pressure in the tank exceeds the pressure for which the vapor space is
designed, the inspection should be made at a reasonable distance from the tank
using field glasses as required for close-up observation of particular areas.
7.7.3.4. As the pressure is being increased, the tank shall be inspected for sings of
distress. The maximum test pressure of 1.25 times the vapor space design
pressure shall be held for at least one hour, after which the pressure shall be
released slowly and the blinds shall be removed from the pressure-vacuum relief
valves. The operation of the relief valves shall be checked by injecting air into
the top of the tank until the pressure in the vapor space equals the pressure Pg,
for which this space is designed, at which time the relief valves shall start to
release air.
7.7.3.5. This latter pressure shall be held for a sufficient period of time to permit a close
visual examination of all joints in the walls of the tank and of all welding around
manways, nozzles, and other connection. As part of this examination, a solution
1463-Q871-1-006 Testing procedures FO-Q-001-2 Rev. 1 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-029
CHAPTER: III) PROCEDURES OF CONTROL DATE APPROV.: 07/04
SUBJECT: 10.- HYDROSTATIC TEST INSPECTION DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG.: 6 OF 10
film shall be applied to all of the welding involved above the high liquid (capacity)
design level for which the tank is designed.
7.7.4.1. Following the preliminary test called it in 7.7.2, the pressure-vacuum relief valve
or valves shall be blinded off; with the top of the tank vented to the atmosphere,
the tank shall be filled with water to the top of the roof while allowing all air to
escape to prevent the accumulation of pressure. If the pressure-vacuum valve or
valves are not available at the time of the test, the tank connections may be
blinded off and the test procedure continued by agreement between the
purchaser and the manufacturer. The vents used during water filling of the tank
shall then be closed, and the pressure in the tank shall be increased slowly until
the hydrostatic pressure under the topmost point in the roof is 1.25 times the
pressure Pg, which the vapor space is designed withstand when in operation
with the tank filled to its specified high liquid (capacity) level.
7.7.4.2. This test procedure shall be held for at least one hour. The hydrostatic pressure
under the topmost point in the roof shall then be reduces to the pressure Pg, for
which the vapor space is designed and shall be held at this level for a sufficient
time to permit close visual inspection of all joints in the walls of the tank and all
welding around manways, nozzles and other connections.
7.7.4.3. The tank shall then be vented to atmosphere, the water level shall be lowered
below the inlets to the pressure-relief valves, and the blinds shall be removed
from the relief valves. The operation of the relief valves shall be checked by
injecting air into the top of the tank until the pressure in the vapor space equals
the pressure Pg, for which this space is designed, at which time the relief valves
shall start to release air.
7.7.5.1. Upon completion of all the foregoing test, the pressure in the tank shall be
released and a thorough visual inspection shall be made of both the inside and
outside of the tank, giving particular attention to all internal ties, braces, trusses,
and their attachments to the wall of the tank.
7.8.1. In the case of the test fail due to leakage or another cause, the ICC has to
proceed in accordance with the document VNG-T-Q-010, Used and disposition
of non conforming products.
7.8.2. Thereafter the test is made, the QCI shall be indicated the status of
inspection and examination in accordance with the document VNG-T-Q-006.
• Lamp or flashlight.
• Helmet
• Safety Boots
8. FORMS
8.1.1. Title
Hydrostatic test.
8.1.2. Objective
The present form establish the conditions for performance the hydrostatic test
and the results.
8.1.3. Characteristic
8.1.4. Origin
8.1.5. Distribution
TIEMPO / TIME ( )
____________________________________________________________________________________
____________________________________________________________________________________
(13)
____________________ ____________________ ____________________ ____________________
I.C.C / Q.C.I. G.C.A.C / Q.C.A.M. I.A. / A.I. CUSTOMER / CLIENTE
1. OBJECT
2. SCOPE
This procedure establish the required steps to carry on a liquid penetrant examination in
accordance with ASME Code Section V Article 6, with data evaluation results and
acceptance criteria in accordance with ASME Code Section VIII Div. 1 Appendix 8 for
surfaces between 10ºC to 52ºC (50ºF a 125ºF)
3. REFERENCES
4. term definition
4.1. Liquid Penetrant Examination (PT): A nondestructive test that use suitable
liquids that penetrate in the open discontinuities of the solid materials surface
and, after the appropriate treatment the presence of those are shown.
4.5. Cleaning:. Is defined as the cleaning required to remove all grease, oil, paint,
dust, etc., from material surface, so that they will not interfere with the
examination process. Solvents might be used.
5. INVOLVED UNITS
1463-Q871-1-006 Testing procedures FO-Q-001-1 Rev. 5 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-024
CHAPTER: III) CONTROL PROCEDURES DATE APPROV.: 07/04
SUBJECT: 5.- LIQUID PENETRANT TESTING DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG: 2 OF 12
6. USED FORMs
7.1. Responsibilities
Those material are: steel, aluminum, magnesium, bronze, titanium and high
temperature alloys
7.3. Equipment
a) Penetrant Materials:
• Cleaner: SKC-S
• Penetrant: SKL-SP1
• Developer: SKD-S2
b) White light lamp shall be used when natural light is not enough.
7.5. Temperature
1463-Q871-1-006 Testing procedures FO-Q-001-1 Rev. 5 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-024
CHAPTER: III) CONTROL PROCEDURES DATE APPROV.: 07/04
SUBJECT: 5.- LIQUID PENETRANT TESTING DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG: 3 OF 12
7.6.1. Metal surface would be examinate in the as-welded, as-rolled, as-cast or as-
forged condition. If surface irregularities would mask indications of unacceptable
discontinuities, it is necessary to prepare the surface by grinding or machining.
The Q.C.I. shall indicate what kind of surface conditioning is required.
7.6.2. All material parts to be inspected shall be clean, dry and free of grease, dust,
rust and any other extraneous material that could interfere with the examination.
7.6.3. The cleaning shall be done with solvents. Cleaning solvents have to meet the
requirements of the section 7.4 in accordance with the kind of material to that is
going to be examinate.
7.6.4. In case of welded surfaces, they shall be cleaned at least 25 mm wide (1”) at
both adjacent sides of the weld.
7.8. Techniques
7.8.1. A color contrast (visible) shall be made with the following penetrant processe:
• Water washable
• Post-emulsifying
• Solvent removable
7.8.2. The process that will be apply by VENEAGUA is: Solvent removable
7.9.1. The penetrant might be applied with brush, sprayed or by immersion; if the piece
is small, it could be placed in previously cleaned basket for further immersion. If
the piece is large or presents a complex geometry, it could be tested using
penetrant spray or brush.
7.9.2. Any excess of penetrant liquid shall be avoid during application process.
Penetration time is critical. The minimum penetration time shall be for castings
and welds, it is five minutes; and for wrought materials (extrusions, forgings,
plates) it is ten minutes, at standard temperature range from 10°C-52°C (50°F-
125°F). At other temperature range shall be qualified in accordance with T-653
ASME Code Section, article 6.
7.11.1. After the specified penetration time has elapsed, solvent and penetrant in
excess shall be removed by wiping with a cloth or absorbent, repeating the
operation until most traces of penetrant have been removed. To minimize
removal of penetrant from discontinuities, care shall be taken to avoid the use
of excess solvent.
7.11.2. Flushing the surface with solvent, following the application of the penetrant and
prior to developing, is prohibited.
The surfaces shall be dried by normal evaporation for one minute. The time
interval shall not exceed the established.
7.13.1. The developer shall be applied by spraying. Metal surface shall be dry and free
of penetrant excess and the developer shall be spray a thin and uniform coating,
excessive coating thickness may mask indications.
7.13.3. The developer process time shall be not less than 10 minutes. Develop process
time starts to count at the moment in which developer is dry.
7.14. Interpretation
7.14.1. Interpretation starts after developer process time has finished. If the surface to
be examined is to big for established test periods, the essay shall be done
dividing the surface subject in small areas.
7.14.2. Surface Inspection shall be done using natural or artificial white light.
7.15.2. Acceptance
7.15.3. Repairs
The method of post cleaning shall be the indicated for the removed of penetrant
in accordance with 7.4.
• Penetrant Materials
• Cloth
• Lamp or flashlight
• Vernier
• Helmet
• Safety Boots
8. STEPS
8.1. The Workshop Chiefs (W.CH.) request from the warehouse absorbent clothes,
grinding madrine and material by means of form FO-T-M-030-2.
8.2. The W.CH. prepare form FO-T-P-001-1 for penetrant liquids test request and
assign to Q.C.I. an assistant who will help in the test performance.
8.3. The Quality Control Inspector Q.C.I., takes the Quality Control flashlight, and
request to the warehouseman the material for the test (solvent, developer,
penetrant tint), assigned to the project.
8.5. The Q.C.I. verifies the kind of material subject to examination and surface
temperature according to the described on section 7.5. and process with
penetrant liquid test as described in section 7.1.
8.6. The assistant prepares metal surface in accordance with description in section
7.6.1. (generally by means of grinding).
8.8. The Q.C.I. waits for drying time consumption according to section 7.7.
8.9. The Q.C.I. applies the penetrant liquid in accordance with description in section
7.9., and waits for penetration time consumption according to section 7.10.
8.10. The Q.C.I. removes the penetrant agent excess according to section 7.11.
8.11. The Q.C.I. waits the time consumption for drying according to section 7.12.
8.13. The Q.C.I. performs the inspection applying the criteria of acceptance described
in 7.14., 7.15.1 y 7.15.2.
8.14. If important signs appear the Q.C.I. marks them and orders to the assistant to
proceed with material removal.
8.15. The assistant reduces the signs, and the procedure starts again in step 8.1.6.
8.16. If non acceptable signs do not exist the assistant proceed with post-cleaning.
8.17. The Q.C.I. records on form FO-P-003-1 the test results and submit it to W.CH.
and the Quality and Assurance Control Manager.
8.18. The W.CH. returns to the warehouse the material request in section 8.1.1.
8.19. The Q.C.I. returns to the warehouse the penetrant tint materials and keeps the
lantern.
8.20. The Q.C.I. records the penetrant liquid register on form FO-T-Q-024-1.
QUALITY CONTROL
WORKSHOP CHIEFS WAREHOUSEMAN ASSISTANT
INSPECTOR
INICIO 1
2
8.1
8.4
The workshop chiefs (W.CH.)
request from warehouse absorbent The Warehouseman give the
clothes, grinding madrine and material request 8.5
material by means of form FO-T- 8.6
M-030-2 The Q.C.I. verifies kinds of
material subject to examination The assistant prepares metal
2 and surface temperature according surface in accordance with
8.2 as described on section 7.5. and description in section 7.6.1.
process with penetrant liquid test (generally by means of grinding).
The W.CH. prepare form FO-T-P- as described in section 7 1
001-1 for penetrant liquids test
request and assign to Q.C.I. an 1 8.7 / 8.8
assistant who will help in the test
performance The Q.C.I. does previous cleaning
with solvent. The Q.C.I. waits for
drying time consumption according
to section 7.7
3
2 8.9 8.15
The Q.C.I. applies the penetrant The assistant reduces the signs,
liquid in accordance with and the procedure starts again in
description in section 7.9., and step 8.1.6.
waits for penetration time
consumption according to section
8.10 / 8.11
The Q.C.I. removes the penetrant
agent excess according to section
7.11. The Q.C.I. waits the time
consumption for drying according
to section 7 12
8.12
The Q.C.I. spreads the developer
according to section 7.13.
8.13
The Q.C.I. performs the inspection
applying the criteria of acceptance
described in 7.14., 7.15.1 y 7.15.2.
8.16 / 8.18
SI
Aceptables If non acceptable signs do not
indications exist the assistant proceed with
post-cleaning. The W.CH. returns
to the warehouse the material
NOI request in section 8.1.1
8.14
the Q.C.I. marks then and orders
to the assistant to proceed with 3
material removal
8.17
The Q.C.I. records on form FO-P-
003-1 the test results and submit it
to W.CH. and the Quality and
Assurance Control Manager
8.19 / 8.20
The Q.C.I. returns to the
warehouse the penetrant tint
materials and keeps the lantern
and records the penetrant liquid
register on form FO-T-Q-024-1
End
11. FORMS
11.1.2. Objective
This form has the objective of register the results of the liquid penetrant inspection.
11.1.3. Characteristic
11.1.4. Origin
11.1.5. Distribution
(12) Surface Condition: It writes the surface condition (gringing, etc.) according to the
1463-Q871-1-006 Testing procedures FO-Q-001-1 Rev. 5 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
VNG-T-Q-024
CHAPTER: III) CONTROL PROCEDURES DATE APPROV.: 04/03
SUBJECT: 5.- LIQUID PENETRANT TESTING DATE REV.: 04/03
SUB-SUBJECT: REV.: 0 PAG: 11 OF 12
point 7.6.
(19)
(20) (21)
_______________________________________ _______________________________________
I.C.C. / Q.C.I. CLIENTE / CUSTOMER
1. ObjeCt
This procedure establish the activities for the radiographic examination on pressure
vessel in accordance with ASME code, Section VIII, Div 1.
2. SCOPE
This procedure is applicable to welds of pressure vessel and materials specified by the
ASME code, section VIII, Div 1, part UG-4 to UG-9.
3. REFERENCES
4. term definition
4.1 None.
5. INVOLVED UNITS
6. USED FORMs
The gamma radiation source is isotope Iridium 192, calibrated and certified by
manufacturer or supplier.
7.2. Films
Intensifying screens have to be use of plumb with 125 Kev, free of lines or
imperfections which may produced effects non desirable. The thickness of the
screens shall be as follows:
7.4. Chassis
Lead location markers shall be placed on the part, not on the exposure
holder/cassette. Their location shall be permanently marked on the surface of
the part being radiographed or on a map (FO-T-Q-014-1) in a manner permitting
the area of interest to be accurately traceable to its location on the part. Location
markers shall be placed according with ASME Code, Section V T-275 and fig. T-
275.
IQI (penetrameter) shall be either hole type or wire type. ASME standard IQI
shall be used and they consist of those in ASME Code, Section V tables T233.1
and T233.2.
7.7.3 Size
7.7.4.1 The penetrameter shall be placed on the source side of the part being
examined. Where inaccessibility prevents hand placing the penetrameter on the
source side, the penetrameter shall be placed in the film side in contact with the
part being examined. A lead letter ‘F’ shall be placed adjacent to the
penetrameter, but should not mask the essential hole.
7.7.4.2 Penetrameter location for welds: The penetrameter may be placed adjacent or
on the weld. The identification numbers and, when used, the letter F shall not be
in the area of interest, except when geometric configuration makes it impractical.
When one or more film holders are used for an exposure, at least one
penetrameter image shall appear on each radiography except as outlined below:
7.7.5.1 For cylindrical components where the source is placed on the axis of the
component for a single exposure, at least three penetrameters spaced
approximately 120 deg apart are required under the following conditions:
7.7.5.1.1 When the complete circumference is radiographed using one or more film
holders or,
7.7.5.1.2 When a section or sections of the circumference, where the length between
the ends of the outermost sections span 240 or more deg., is radiographed
using one or more film holders. Additional film locations might be required to
obtain necessary penetrameter spacing
1463-Q871-1-006 Testing procedures FO-Q-001-1 Rev. 5 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-014
CHAPTER: III) CONTROL PROCEDURES DATE APPROV.: 07/04
SUBJECT: 5.- RADIOGRAPHIC EXAMINATION DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG: 4 OF 12
7.7.5.2 For cylindrical components where the source is placed on the axis of the
component for a single exposure, at least three penetrameters with one
placed at each end of the span of the circumference being radiographed and
one in the approximate center of the span is required under the following
conditions:
7.7.5.2.1 When a section of the circumference with a length greater than 120 deg and
less than 240 deg is radiographed using just one film holder.
7.7.5.2.2 When a section or sections of the circumference where the lengths between
the ends of the outermost sections span are less than 240 deg.
7.7.5.2.3 In above stated points where sections of longitudinal welds adjoining the
circumferential weld an additional penetrameter shall be placed on each
longitudinal weld at the end of the section most remote from the junction with
the circumferential weld being radiographed.
7.7.5.3 For spherical components where the source is placed at the center of the
component for a single exposure, at least three penetrameters spaced aprox.
120 deg are required under the following conditions:
7.7.5.3.1 When the complete circumference is radiographed using one or more film
holders or,
7.7.5.3.2 When a section or sections of the circumference, where the length between
the ends of the outermost sections span 240 or more deg., is radiographed
using one or more film holders. Additional film locations might be required to
obtain necessary penetrameter spacing.
7.7.5.4. For spherical components where the source is placed on the axis of the
component for a single exposure, at least three penetrameters with one
placed at each end of the span of the circumference being radiographed and
one at the center of the radiographed span of the circumference radiographed
in the approximate center of the span, are required under the following
conditions:
7.7.5.4.1 When a section of a circumference the length of which is greater than 120
deg and less than 240 deg is radiographed using just one film holder.
7.7.5.4.2 When a section or sections of a circumference where the lengths between the
ends of the outermost sections span less than 240 deg is radiographed using
more than one film holder or,
7.7.5.5. Where other welds are simultaneously radiographed with the circumferential
weld, one additional penetrameter shall be placed on each other weld.
For welds, a shim of material radiographically similar to the weld metal shall be
placed between the part and the penetrameter, if needed, so that the
radiographic density throughout the area of interest is no more than minus 15 %
from (lighter than) the radiographic density through the penetrameter.
The shim dimensions shall exceed the penetrameter dimensions such that the
outline of at least three sides of the penetrameter image shall be visible in the
radiograph.
The weld ripples or weld surfaces irregularities on both the inside (where
accessible) and outside shall be removed by any suitable process to such a
degree that the resulting radiographic image due to any surface irregularities
cannot mask or be confused with the image of any discontinuity.
The finished surface of all butt-weld joints might be flush with the base material
or may have reasonably uniform crowns, with reinforcement not to exceed that
specified in the referencing code section.
F ⋅d
Ug =
D
Where:
Ug = geometric unsharpness
1463-Q871-1-006 Testing procedures FO-Q-001-1 Rev. 5 Sep. 02
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
1463-T-Q-014
CHAPTER: III) CONTROL PROCEDURES DATE APPROV.: 07/04
SUBJECT: 5.- RADIOGRAPHIC EXAMINATION DATE REV.: 07/04
SUB-SUBJECT: REV.: 0 PAG: 6 OF 12
F = source size
D = distance from the source of radiation to weld or object being radiographed
d = distance from source side of weld or object being radiographed to the film.
7.12.1. The transmitted film density through the radiographic image of the body of the
appropriate hole penetrameter or adjacent to the wire of a wire penetrameter
and the area of interest shall be 1.8 minimum for single film viewing for
radiographs made with an X-ray source and 2.0 viewing for radiographs made
with gamma ray source. For composite viewing of multiple film exposures each
film of the composite set shall have a minimum density of 1.3. The maximum
density shall be 4.0 for either single or composite viewing. A tolerance of 0.05 in
density is allowed for variations between densitometer readings.
7.12.2. If the density of the radiograph anywhere through the area of interest varies by
more than minus 15% or plus 30% from the density through the body of the hole
penetrameter or adjacent to the designated wire of a wire penetrameter, within
the minimum/maximum allowable density ranges according to 4.13.1. then an
additional penetrameter shall be used for each exceptional area or areas and
the radiograph is retaken.
Such blemishes include, but are not limited to: fogging, streaks, watermarks,
chemical stains, scratches, finger marks, crimps, dirtiness, static marks,
smudges, or tears and false indications due to defective screens.
8. FORMS
8.1.1 Title
Weld Map
8.1.2 Objective
This form has by objective to register the location weld, identification weld and
marking welders on vessels.
8.1.3 Characteristic
8.1.4 Origin
8.1.5 Distribution
(3)
PROYECTO N° (4)
EQUIPO: (5)
ICC: (6)
PROJET N° ITEM QCI
8.2.1. Title
Radiographic Inspection.
8.2.2. Objective
This form has by objective to register the results of the radiographic inspection,
indicated the welds accepted and rejected.
8.2.3. Characteristic
8.2.4. Origin
8.2.5. Distribution
File Project.
FO-T-Q-014-1-Mapa de soldaduras
NUMBER MANUAL:
QUALITY CONTROL PROCEDURE VNG-T-Q-MA-001
veneagua c.a. MANUAL NUMBER PROCEDURE:
VNG-T-Q-014
CHAPTER: III) CONTROL PROCEDURES DATE APPROV.: 05/03
SUBJECT: 5.- RADIOGRAPHIC EXAMINATION DATE REV.: 05/03
SUB-SUBJECT: REV.: 0 PAG: 11 OF 12
FO-T-Q-014-1-Mapa de soldaduras
GERENCIA DE CONTROL Y FECHA: (1)
INSPECCIÓN RADIOGRÁFICA DATE
ASEGURAMIENTO DE LA CALIDAD
RADIOGRAPHIC INSPECTION PAG.: DE:
veneagua c.a. QUALITY CONTROL AND ASSURANCE
PAGE OF
MANAGEMENT
DENSIDAD
JUNTA SECCION TIPO DE DEFECTO SOLDADOR RESULTADO DENSITY
JOINT SECTION TYPE OF DEFECTS WELDER RESULT PENETRAMETRO
PENETRAMETER MIN MAX
(18) (19) (20) (21) (22) (23) (23) (23)
SIMBOLOS SYMBOLS
A : ACEPTADO REP : REPARAR RT : REPETIR A : ACEPTEC REP : REPAIR RT : REPEAT
PA: PORO AISLADO, FF: FALTA DE FUSION, I PA: SINGLE POROSITY , FF: LECK OF FUSION,
GL: GRIETA LONGITUDINAL, GT: GRIETA TRANSVERSAL, S: SOCAVADURA GL: LONGITUDINAL CRACK, GT: TRANSVERSAL CRACK, S: UNDERCUT
FP: FALTA DE PENETRACIÓN, PAG: POROS AGRUPADOS FP: LECK OF PENETRATION, PAG: CROWDED POROSITY
FS: FALTA DE SOLDADURA, DP: DEFECTO DE PELÍCULA FS: LECK OF WELD, DP: FILM DEFECT
IT: INCLUSION DE TUGNSTENO; IE: INCLUSION DE ESCORIA IT: TUNGSTENO INCLUSION; IE:: SLAG INCLUSION
1.8. OBJECT
The object of this procedure is to establish the steps to follow, to make the inspection of the
pneumatic test of the reinforcement connection and the tubular internals of the Brine Clarifier.
2. SCOPE
This procedure considers the air turbine verification, the nozzles connection reinforcement and
others similar equipments that requires this test to prove their stagnantacy. It does not apply to
vessel tanks and atmospheric tanks.
3.9. referencEs
4.10. DEFINITIONS
4.1.10.2. Pneumatic Test: Test that consist in apply air to a pressure of 10 psi to verify
the equipment stagnantacy, or 15 psi to connection reinforcements; in order to
find any leak in the weld joint. To the internal structure of the Brine Clarifier (04-
S-10-21) is going to be use 25 psi.
5.11. FORMS
• Calibrated Manometer.
• Chalk.
• Water and Liquid Soap (Brisol or similar).
1463-Q871-1-006 Testing procedures FO-Q-001-1 Rev. 5 Sep. 02
MANUAL NUMERO:
MANUAL DE PROCEDIMIENTOS VNG-T-Q-MA-001
veneagua c.a. DE LA CALIDAD PROCEDIMIENTO NUMERO:
1463-T-Q-026
CAPITULO: III) PROCEDIMIENTOS DE CONTROL FECHA APROB.: 07/04
ASUNTO: 7.- PNEUMATIC TEST INSPECTION FECHA REV.: 07/04
SUB-ASUNTO: REV.: 0 PAG.: 2 DE 7
• Brush.
• Helmet.
• Safety boots
• Security lens.
8.14. STEPS
EQUIPMENT PSI
Desaireation turbine (e ≤ 4 mm). 10 psi. max
Turbines of (e > 4 mm). 15 psi. min
Nozzle reinforcements or connections. 15 psi. min
Tubular Internals of the Brine Clarifier 25 psi. min
8.5. Hold 15 minutes when the zone tested is under pressure. Then the ICC verify
all the welds applying with a brush a solution which contains water with soap.
8.6. If there is detected any leak the ICC mark with the chalk and follows the
procedure described in the document VNG-T-Q-010, “Uso y Disposición de
Productos No Conformes”. The pressure should be downing very slowly. The
defects areas has to be polish with an emery and re-welded. After correct the
leaks repeat after 8.1.
8.7. If there is not any leak, the inspection is approved and the ICC give to the
Production Coordinator the request of inspection. One copy is file in the project
folder.
8.8. The ICC elaborate the pneumatic test report in the form 1463-T-Q-026-1
8.9. The ICC signed the Traveler of the Manufacturer quality control plan if the
inspection is satisfactory.
8.10. The ICC file all documents in their folders
START
8.1 8.2
Emit the inspection request in the Verify the calibration of the manometer.
form FO-T-P-001-1
8.4 8.3
Visually inspect the tested zone of the equipment
Apply pressure as request
according to the operation sheets and plans.
8.5
8.6
Marc with shalk Yes
and proceed Leak?
according to
VNG-T-Q-010
No 8.7
Approve the inspection, give the original request to the
CP
8.8
Elaborate the pneumatic test report in the form
FO-T-Q-026-1
8.9
END
10. FORMS
10.1.1. Title
Pneumatic Test.
10.1.2. Objective
10.1.3. Characteristics
10.1.3. Origen
10.1.4. Distribution
(7)(13) Procedure: Fill the number of the procedure that is going to be used
and its revisión.
(1)
FECHA / DATE:
(2) (3)
PROYECTO / PROJECT: EQUIPO / EQUIPMENT:
(4)
PARTE PROBADA / TESTED ZONE:
(8)
MANÓMETRO UTILIZADO / USED MANOMETER: .
(10)
OBSERVACIONES / REMARKS: