BARUS CONSTRUCTION CO LTD

BANYAN GROVE - APPOINTMENT SCHEDULE Updated : 15/09/2015 Rev 1

C D E F G H I J

Client Client's Required Lead in Time


Drwgs & Tender List Tender
Design Tender Out Tender In approval & Appointment / Duration Lead Time
Work Group Specs Approval Report POW Start date Status
Approval (G-28d) (H-14d) Award Nomination Date (working in Months
(F-21d) (F-5d) (I-7d)
(D-14d) (J-14d) days)

22-May-15 5-Jun-15 21-Jun-15 26-Jun-15 24-Jul-15 7-Aug-15 14-Aug-15 28-Aug-15 28-Oct-15 40 1.3
Appointment of MEPD Subcontractor
8-Jun-15 22-Jun-15 8-Jul-15 13-Jul-15 10-Aug-15 24-Aug-15 31-Aug-15 14-Sep-15 28-Oct-15 30 1.0
Appointment of lift supplier
27-Apr-15 11-May-15 27-May-15 1-Jun-15 29-Jun-15 13-Jul-15 20-Jul-15 3-Aug-15 20-Oct-15 65 2.1
Appointment of Waterproofing Subcontractor
3-Jul-15 17-Jul-15 2-Aug-15 7-Aug-15 4-Sep-15 18-Sep-15 25-Sep-15 9-Oct-15 10-Dec-15 40 1.3
Appointment of Antitermite Subcontractor
12-Aug-15 26-Aug-15 11-Sep-15 16-Sep-15 14-Oct-15 28-Oct-15 4-Nov-15 18-Nov-15 9-May-16 100 3.3
Appointment of Pool & Water Feature Equipment Supplier
1-Oct-15 15-Oct-15 31-Oct-15 5-Nov-15 3-Dec-15 17-Dec-15 24-Dec-15 7-Jan-16 19-Apr-16 65 2.1
Appointment of Conceal Mixer Supplier
16-Nov-15 30-Nov-15 16-Dec-15 21-Dec-15 18-Jan-16 1-Feb-16 8-Feb-16 22-Feb-16 10-Jun-16 65 2.1
Appointment of Suspended Ceiling Subcontrcator
7-Oct-15 21-Oct-15 6-Nov-15 11-Nov-15 9-Dec-15 23-Dec-15 30-Dec-15 13-Jan-16 31-May-16 90 3.0
Appointment of Floor & Wall Tiles Supplier
18-Jan-16 1-Feb-16 17-Feb-16 22-Feb-16 21-Mar-16 4-Apr-16 11-Apr-16 25-Apr-16 21-Jun-16 40 1.3
Appointment of Painting Subcontractor
20-Oct-15 3-Nov-15 19-Nov-15 24-Nov-15 22-Dec-15 5-Jan-16 12-Jan-16 26-Jan-16 24-Jun-16 100 3.3
Appointment of Alumnium Opening Subcontractor
16-Nov-15 30-Nov-15 16-Dec-15 21-Dec-15 18-Jan-16 1-Feb-16 8-Feb-16 22-Feb-16 19-Jul-16 100 3.3
Appointment of Shopfitting Subcontractor
4-Dec-15 18-Dec-15 3-Jan-16 8-Jan-16 5-Feb-16 19-Feb-16 26-Feb-16 11-Mar-16 5-Aug-16 100 3.3
Appointment of Kithcen Fit Out Subcontractor
4-Jan-16 18-Jan-16 3-Feb-16 8-Feb-16 7-Mar-16 21-Mar-16 28-Mar-16 11-Apr-16 22-Aug-16 90 3.0
Appointment of Granite Supplier
18-Jan-16 1-Feb-16 17-Feb-16 22-Feb-16 21-Mar-16 4-Apr-16 11-Apr-16 25-Apr-16 2-Sep-16 90 3.0
Appointment of Sanware & Toilet Accessories Supplier
21-Jan-16 4-Feb-16 20-Feb-16 25-Feb-16 24-Mar-16 7-Apr-16 14-Apr-16 28-Apr-16 7-Sep-16 90 3.0
Appointment of Light Fitting Supplier
11-Mar-16 25-Mar-16 10-Apr-16 15-Apr-16 13-May-16 27-May-16 3-Jun-16 17-Jun-16 14-Sep-16 60 2.0
Appointment of Tel/Data/MATV Subcontractor
23-Feb-16 8-Mar-16 24-Mar-16 29-Mar-16 26-Apr-16 10-May-16 17-May-16 31-May-16 16-Sep-16 75 2.5
Appointment of Shower Door Supplier
22-Apr-16 6-May-16 22-May-16 27-May-16 24-Jun-16 8-Jul-16 15-Jul-16 29-Jul-16 13-Dec-16 90 3.0
Appointment of External Joinery Subcontractor
13-Jun-16 27-Jun-16 13-Jul-16 18-Jul-16 15-Aug-16 29-Aug-16 5-Sep-16 19-Sep-16 13-Dec-16 75 2.5
Appointment of Balustrade Subcontractor
14-Apr-16 28-Apr-16 14-May-16 19-May-16 16-Jun-16 30-Jun-16 7-Jul-16 21-Jul-16 25-Nov-16 100 3.3
Appointment of Landscape Subcontractor