Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Work

 Priority  Plan  For  Oct  4th  2018

S.no Project  Name Description Plan Status Remarks


Prestige Rivets  to  be  ordered  with   Drill  bits  &  Gun  to  be  
Mahesh  team Vertical  fin  works   same  color  as  per  client   arranged
approvals Send  for  PC  today
Spider  Glass  works Surender  to  release  After  
Spider  glass To  order  today
Pharmacy  &  ATM approvals
Additional  Area Material  to  order Satish  to  check  &  confirm Mtl  Ordered
Openable  windows  19  completed,  9  
Openable  window  installation balance Completion  today
Acp  horizontal  capping  and  terrace   Additional  works  to  
1 ACP  works Completed
coping  by  Mahesh   start
Canopy  ACP  works After  fin  completion Oct  20th
Spider  glazing  for  ATM  and  
Awaiting  for  Consultant  
Glass  Installation   pharmacy,  fittings  available,  glass     Approved
approval
fixing  in  4  days
Bill  Submission GM  sir  to  Submit Today Scrap  to  Remove
Mahesh  to  Install  the  openable   2  days    6  person  work
Handle  for  Openable hardware  After  completion  of  fin  
works
ITC Handing  over   Issac/Raghu  signed    By  sumanth All  docs  &  Statutory Submitted
Kohenur Billing GST  Bill  submited Payment  by  10th  Oct
 meeting  room  area  1  window  glass  
crack to  be  cleared  Anand
2
1  balcony  door  is  not  opening   Heavy  duty  door  closer  for   PI  to  get  from  Kinlong
smoothly 800kg  to  be  ordered Doubtful______________
GM  sir  &  Reddy  to  send  all  the  
necessary  docs  to  HR Submitted  by  GM  sir
GVK Shop  Drawings Drawings  approved 21st  sep
Bio Material Ordered
Bill  of  material  to  be  prepared  as  per  
Global  Delivery-­‐PI  Sign
revised  shop  drawings  for  Powder    by  Sumanth  today
Vidyasagar  Delivery
coating
by  10th  +  PC.
Fabrication  &  installation To  be  planned  for  Execution Ashok  Team  /  Vikram Both  WO  Issued
3  to  co-­‐orinate  for  site  clearence  for  
Site  clearences Marking  2nd  floor debris  to  be  removed
Site  supervisor Biswanath  assigned
Marking  done  for  1st  floor  &  2nd  floor  
Anand  
Site  survey /  Ground  floor  markings  done
Fabrication  &  installation  Team   Fabrication  &  installation  team  to  be   Work  order  to  be  released  
Stand  by  Vikram
allotment finalised for  Ashok
Preston Final  RA  Bill/Letter/Scaff  bill With  Sonusingh to  submit Check
To  explain  the  breakage  
Broken  glass Broken  glass  order  to  be  checked   Ordered
reason  with  Rajsekher
4 Billing ACP  works  to  be  submitted
Email    sent  for  Tension  
Bruce  to  handover  the  installation   Wating  for  PO  name  
Handing  over   Rod  vertical  &  horizontal  
certificate  for  Cable-­‐net  glazing  works change  to  Preston
readings
Pioneer Pioneer  Rev  dwg  &  Structural  to  get  
Awaiting  Comments  &
Approval  from  Facet  today  -­‐  
Dwg Resubmitted Approval  
Comments  to  incorporate  &  Resubmit  
Today  by  Phani
today
5 Pioneer  (Scaffolding  or  Cradle  added  
in  our  cost  for  Externally  glass  fixing

Revised  Quote  to  submit


To  prepare  &  Submit Awaiting Madhu  sir  to  confirm
All  Drawings  with  Structural
SRMT Approved  copy  of  ANTZ  sent  to  
As  built  drawing Completed
Dakshinamurty
Structural  Stability  report  &  
 Completed Completed
6 warranty  Letter
Additional  ACP  Qty Direct  order  by  SRMT Uday  raj  executing
To  Co-­‐ordinate  with  Shiva  for  Sending  
By  5th  Siva  will  Report
Site  Scrap  Material  &  Final  Bill Back  material GM  Sir
Rajapushpa Groove  Marking  to  be  done  for  UTZ   Surender  to  release  the   Done  up  to  9th  Flr
Site  survey
SUMMIT Glazing drawings  After  approvals only
Mail  have  to  be  sent  for  Concrete  
Today
upstand  preparation  to  Rajapushpa
UTZ  curtain  wall  drawings  to  be  
Awaiting  Approval
Shop  drawings submitted by  Surender  today
Curtain  Wall  Alum  /  HW  /  BOM Alum Cut  Lengths  given  to  Global HW  &  MTO  Pending
Unitized  Alum  /  HW  /  BOM Alum Yet  to  Order ALUM  &  MTO  Pending
Shop  drawings  for  curtain  wall  to  be   Approvals  from  aspect  
submitted   expecting  today
ACP/Bull  nose/Powder  coating  Ral   Approval  pending  from  
colour/Glass  railings Architect
The  total  areas  to  be  checked  as  per  
Pending
Total  area  as  per  DWG drawings  by  santosh
Corner  die  drawings  to  be  updated  as   Confirmation  to  be  sent  by   Awaiting  New  dies
Die  Drawings per  Anil  comments surender by  7th
to  be  revised  as  per  
Received  with  approved  comments
Structural  report   comments

Rajapushpa
SUMMIT
Sealant  byte  &  spacer  approval  email   Awaiting  Comments  &
sent  to  dow  corning Approval
Given  to  global  for  Die  preparation  
Pending
Rajapushpa Material  order  for  Aluminium received  5th  oct
SUMMIT Tentiative  Material  order  given  for   Payment  to  collect  from  
curtain  wall,Bull  Nose  &  Louvers  are   Rajapushpa  for  142  tons  to   Hardcopy  submitted
placed,   Handover  Global
Fasteners/Screws/GI  
panels/Gaskets/sealants  to  place  the  
order
Material  delivery  for  
UTZ  brackets  released  ,Curtain  wall   to  follow  for  delivery  of  
MS  Bracket  for  UTZ  &  curtain  wall Ramu  (Rejected  &  New  
brackets  to  be  released. 100  brackets  from  Ramu
Material  to  get  Today)
Materials  for  Brackets  delivered  to   Fabrication  schedule  to  be  
Ramu  &  Rafiq followed
Store  setup Dharamveer  to  complete  gate Anand
7 Dharamveer  to  start  the  
Office  set  up GI  sheet  &  screws    delivered work
WCA  &  CAR  policy To  co-­‐ordinate  with  GM  sir
Test  certificates  for  Glazing  to  be   Unitized  Checklist  
Test    certificates   submitted To  be  discussed prepared
Work  flow  chart,sequence  of  works  to  
Flow  Chart be  submitted Submission  on  Oct  1st
Site  Team Subcon  WO  issued Assigned Only  ACP  WO  to  issue
UTZ  Fab-­‐  prasanjah                      
UTZ  Instaln  -­‐  Mahesh  team                  
Fabrication/Installation  team   Curtain  wall  instal  -­‐  Ashok  
Team  Finalisation ACP  by  Munna  /  Shiv
finalised team                              Spider  Glazing  
-­‐  1  team                                  Acp  
Cladding  -­‐  3  Team
Anand  to  Start  Today
New  Mock  up  Pending
Mockup  works  Glazing Mock-­‐up  installation  done Glass  size  by  Surender
Mockup  works  Railing Mtl  ordered  with  Seshu Yet  to  install Materials  Today
Work  schedule  to  client Project  work  Schedule  revised  &  sent Sent  by  email
Shop  drawings  for  UTZ  curtain  wall  
,Glass  production  &  requirements  
Client  requirements schedule  with  qty,cash  flow   to  be  sent Pending
statement,Bracket  design,structural  
report,
Site  area  provided
Bracket  works  going  
Steel  works  for  Mezanine  floorby  
on,Frame  works  completed  
Nazim  khan To  plan  for  all  M/c  
for  external  fencing  area
Factory  setup dispatch  &  Setup
Factory  setup  with  Land  extension GM  sir Under  progress
Glazing  m/c,Jib  crane,Copy   Silicone  machine  advance  
Machinery  tools
router,Notching  m/c,Air  compressor, paid
Materials  Order
A-­‐  frames,Trollies,Assemly   Glazing  Machine
tables,Power  tools,Electric  power   Rectification  pending
Tools
links,pneumatic  hose,Lifting   Mail  sent  Repair  by  
belts,Racks,safety  belts 10th
Building  ONE Drawings  received Architectural  drawings    received Quote  sent
Sy  ni.  89 Drawing  review Surender  to  study  dwgs   Under  Review
Structural  report  to  prepare  by  
santosh
Revised  Quote  &  Costing To  prepare  &  Submit Today  -­‐  Ready
AIG Automatic  door  testing  &   Automatic  door  testing  &   upto  9th  floor  
Mahesh  on  work
Hospital commisioning commisioning completed
Pending  Payment Madhu  sir  discussing  with  Chandu
Installation  to  be  
Automatic  door   Material  delivered
completed  

ACP  boxing  works  requested  by  


ACP  works
Client

Commissioning  to  be  done  for  all  


Commissioning
doors
After  completion
DRL VMZ  Material Received Shekar  to  Submit  the  bill
Biologics Scaffolding  for  West  &  south  
Site  clearences elevation  for  RCC  coping   boomlift  arranged
10 Perforated  Panel Sizes  to  be  confirmed  with  VMZINC Delivery  by  today

Payment  raised  for  current  


Billing bill,payment  to  be  followed By  GM  sir
GAR  T-­‐3 Sign  off  by  inspection  with  
West  elevation/South  west/South   Cradle  Check  by  GM
Smoke  seal,  Internal  flashing Mahesh/Bheemsen  
elevation  completed Sir
Thursday
West  elevation/South  west/South  
Panel  Alignement
elevation  completed
Flashing  issue
West  elevation/South  west/South  
Terrace  flashing Madhu  sir  to  close
elevation  completed
[RANDOM  Check]
West  elevation/South  west/South   Mild  steel  works  to  follow   Anand  Team  to  start  
ACP  Coping  
elevation  pending for  completion after  Steel  rectification
 T3  Openable  hardware  to  
West  elevation  staircase  areas  28nos   check  &  order  balance  
Openable  Hardware  installation Hardware  by  6th
pending damaged  today  by  
bheemsen
T3  staircase  openable  Glazing  to  
complete  -­‐  Lingam  completed  -­‐  
Installation  with  Cradle  -­‐  Lip  notching  
pending  by  Lingam
Southwest  &  south  elevation   to  be  completed  before  
completed  upto  7th  floor sep29th  
West  elevation  completion  on  Sep  
Expansion  works
26th
Additional  Cradle  requirement  for  T3  
1  Cradle  installation  
Stair  case  areas  &  south  elevation  
Cradle  Requirement arrangement  scheduled   Kept  on  Hold  by  Anand
Broken  glass  &  bull  nose  installation  
today
works
Openable  hardwares  to  be  installation  
Openable  hardware Hardware  to  deliver
to  be  completed  as  a  top  priority
 T3  Bullnose  &  Broken  glass  
replacement  with  Cradle  by  max  10th  
Oct.
Bill  for  T3  Recon  submission  today-­‐  
as  per  Mahesh  checklist  removing  5%   UPDATED  &  GIVEN  FOR  
Billing
of  HO-­‐  certified  by  Mahesh  handed   GST
over  to  Kotaiah

GAR  T-­‐2 PO  released  to  Global  for  Balane   Need  to  follow  for  delivery  
by  4th    -­‐  Under  Packing
Material aluminium for  Sep  30th
Floor  mounted,Corner,hook  on  
brackets  delivery  schedule  to  be  
Check  with  Ramu Recon  by  Sukant
100  set  Brackets    will  be  
Hook  on  brackets
delivered
Kick  Bracket Rectification  by  Ramu
Ramu  &  Seshu  delivery  to   1200nos  delivery  Seshu  
T  bolt  for  bull  nose
be  followed on  today
Back  Panel New  order  placed  to  gowri Delivery  date  to  check
Curtain  Soffit  by  
Acp  team  finalization  for  Refuge  by  
50%  area  by  new  team   Bimlesh
ACP  Team  finalizing Dharamveer  &  Terrace  Coping  by  
Anand  to  confirm  today &  Refuge  Soffit  by  
Anand  &  T2  Soffits  by  Bimlesh  50%
Ashok
October  30th  despatching  
Glazing  total  297m2  is  pending  from   Corner  Glasses  Pending
Glazing to  be  confirmed  with  
saint  gobain Delivery  by  5th  Evening
Raghu
East  elevation  fall  protection  &  
Site  clearences to  be  followed East  side  after  10th
platforms  to  be  removed
Openable  Fixing Hardware  by  6th
Gar  T2  Kt  series  un  ordered  atick   SKN  230  SQM
stock  30  glasses  to  order  by  Mahesh   CORNER  13  Nos.  & Ordered
All  T-­‐2  Pending  Glasses today KT  30  Glasses
Gar  VMZ  &  Louver  Boq  to  submit  with  
Drawings  Approved/DGF  
MTO  (Sarfaraz  to  confirm  Surender   Site  Height
shaft  area  dwgs  by  
design)  &  DG  shaft  louvers  sent  for   Suresh  to  confirm
surender  oct  05th
Dwg  approval
Jupiter  team  to  be  monitored  by   Completion  on  Octobet  
Smoke  seal  &  flashing  work
Suresh  &  Bheemsen 15th
Necessary Hardware for Spider to
Spider  Glazing Today  delivery Mtls  to  order
deliver today
T2  MS  Bracket  /  Alum  Bracket  &  
Broken  glass  to  check  &  order  
immediately   by  Lingam  &  Sukanth
bheemsen  to  start  handing  
Smoke  seal  &  Openable  checklist  
over  with  Mahesh  from  
provided  
today
Work  order  qty  for  Amendment  mail  
by  Kotaiah  to  send  today  to  
workorder  Amendment for  Steel  &  Glazing  /  Spandrel  /   Awaiting  Mail
Naveen
Smoke  seal  
to  send  a  credit  note  for  
CW  scrap  handed  over  -­‐  Sgf  scrap  
SCRAP scrap  material  for                            
Removed
Rs  2,13,000/-­‐
to  be  given  by  Lingam  /  
Broken  Glass Broken  &  shortage  glass  for  T2   Kapil  &  Surender  for   Lingam  to  confirm
immediate  order
Acp  team  finalization  for  Refuge  by  
Acp  to  reach  by  
ACP  works Dharamveer  &  Terrace  Coping  by   Hardware,  Alum  Ordered
Saturday
Anand  &  T2  Soffits  by  Bimlesh for   A pprox   Q ty
 T3  -­‐  Re-­‐concillation  &  retention/  T2   Bill  Prepared  Today
Billing Forwarded  to  Client
RA  Bills/T2  MS  bills GM  sir  to  Submit
Bill  for  T2  As  on  date  works  to  
submitted  
Sukanth  to  re-­‐check  for  Material   Prepared
Aluminium  Comsumption wastage yet  to  submit
 T2  &  T3  dwg  total  areas  to  be  cross  
Santosh by  3rd
GAR  T2  &  T3  Area checked  with  actual  &  workorder
Bill  for  T2  As  on  date  works  to    certified  by  Mahesh  
submitted  -­‐ handed  over  to  Kotaiah
Completion schedule to provide for
VMZ, Louvers, Spider at Pre Anand  to  check  &   VMZ  sizes  as  per  site
Function, T2 Soffit & T3 Terrace confirm given  to  Surender
Coping acp cladding works
Gar Pending issues given by Mahesh &
Kotaiah - Surender to close by EOD
statement for delivered Glass &
installed area in & value to be prepared
& submitted

You might also like