Professional Documents
Culture Documents
Uts II Msi 2016310008 Suciyanti Ikhlasul Pratiwi
Uts II Msi 2016310008 Suciyanti Ikhlasul Pratiwi
Disusun Oleh :
Nim : 2016310008
Teknik Perkapalan
2018
SUCIYANTI IKHLASUL P (2016310008)
DAFTAR ISI
DAFTAR ISI i
BAB I PEMBAHASAN.....................................................................................................1
A. Initial Survey of IOPP (Annex I).................................................................................1
B. Annual Survey of NLS (Annex II)..............................................................................5
C. Renewal Survey of Sewage (Annex IV).....................................................................6
D. Initial Survey of Garbage (Annex V)..........................................................................9
E. Examined dari pelaksanaan sebuah Pre-Purchase Survey atau Condition Survey....11
DAFTAR LITERATURE.......................................................................................................26
BAB I
PEMBAHASAN
3) Survey consists of
1. Confirming the satisfactory installation and operation of, as appropriate, the oily-
water separating equipment fitted with either an oil discharge monitoring and
control system (including the operation of the automatic and manual operation of
the means provided to stop the discharge of effluent) or oil filtering equipment
(including the satisfactory operation of the alarm) or other installation;
2. Confirming, when applicable, that the oil content meter and its recording device
are operable and that there is a sufficient supply of consumables for the recording
device on board;
3. Testing, where fitted, the automatic stopping device required for discharges in
Special Areas;
4. Confirming the segregation of the oil fuel and water ballast system;
5. Confirming that the oily residue (sludge) tank and its discharge arrangements are
satisfactory and, when the size of the sludge tank is approved on the basis of such
installations, confirming the satisfactory operation of homogenisers, sludge
incinerators or other recognised means for the control of sludge;
6. Confirming the provision of the standard discharge connection;
7. Additional requirements for oil tankers:
a. Confirming that the arrangements of slop tanks or cargo tanks designed as
slop tanks and associated piping systems are satisfactory;
b. Confirming the satisfactory installation and operation of the oil discharge
monitoring and control system, including any audible or visual alarms, the
automatic and manual means to stop the discharge of effluent, the starting
interlock and the accuracy of the flow meter;
c. Confirming that the oil content meter and its recording device are operable and
that there is a sufficient supply of consumables for the recording device on
board;
d. Confirming that the approved oil/water interface detectors are on board and
are operational;
e. Confirming that the arrangements of pumps, pipes and valves are in
accordance with the requirements for segregated ballast systems an that there
are no crossconnections between the cargo and segregated ballast systems;
f. Where a portable spool piece is provided for the emergency discharge of
segregated ballast by connecting the segregated ballast system to a cargo
pump, confirming that non-return valves are fitted on the segregated ballast
connections and that the spool piece is mounted in a conspicuous position in
the pump room with a permanent notice restricting its use;
g. Testing ballast pipelines that pass through cargo tanks and those cargo
pipelines that pass through ballast tanks to ensure there is no cross
contamination;
h. Confirming that the crude oil washing system is installed in accordance with
the approved plans and, in particular:
Examining crude oil washing piping, pumps, valves and deck mounted
washing machines for signs of leakage and to check that all anchoring
devices for crude oil washing piping are intact and secure;
Carrying out pressure testing of the crude oil washing system to 1.5 times
the working pressure;
Confirming in those cases where drive units are not integral with the tank
washing machines, that the number of operational drive units specified in
the Manual are on board;
Checking that, when fitted, steam heaters for water washing can be
properly isolated during crude oil washing operations, either by double
shut-off valves or by clearly identifiable blanks;
Checking that an overpressure relief device (or other approved
arrangement) is fitted to the pumps supplying the crude oil washing
system;
Verifying that flexible hoses for supply of oil to the washing machines on
combination carriers are of an approved type, are properly stored and are
in good condition;
i. Verifying the effectiveness of the crude oil washing system and, in particular:
Checking tanks containing departure and/or arrival ballast water, as
applicable, to confirm the effectiveness of the cleaning and stripping;
Checking that the crude oil washing machines are operable and to observe
the proper operation of the washing machines by means of the movement
indicators and/or sound patterns or other approved methods;
Checking the effectiveness of the stripping system in appropriate cargo
tanks by observing the monitoring equipment and by hand-dipping or
other approved means;
Verifying by internal tank inspection after crude oil washing that the
installation and operational procedures laid down in the Operations and
Equipment Manual are satisfactory;
j. Confirming that, where there is a crude oil washing system, an inert gas
system has been installed and tested in accordance with the requirements of
SOLAS 74/88;
k. Confirming, as appropriate, that the arrangements for the prevention of oil
pollution in the event of collision or stranding are in accordance with the
approved plans;
l. Confirming that the piping systems associated with the discharge of dirty
ballast water or oil-contaminated water are satisfactory;
m. Confirming that the observation and discharge control positions for visually
observing the discharge of oilcontaminated water, including the testing of the
communication system between the two positions are satisfactory;
n. Confirming that the means of draining cargo pumps and cargo lines, including
the provision of a stripping device and the connections for pumping to the slop
or cargo tanks or ashore are satisfactory;
o. Confirming that the arrangements for the part flow system, where fitted, are
satisfactory;
p. Confirming that closing devices installed in the cargo transfer system and
cargo piping as appropriate are satisfactory;
q. Confirming that the subdivision and stability arrangements to prevent
progressive flooding are satisfactory;
6. Confirming that the underwater discharge outlet(s) are in accordance with the
approved plans;
7. Confirming that means are provided in the common discharge piping to isolate
openings provided above the waterline;
8. Verifying by actual test that the discharge rate of the pumps, where a variable rate
type is used, can be controlled as specified in the Procedures and Arrangements
Manual;
9. Verifying that means for restricting the discharge flow of fixed rate pumps to the
specified rates have been fitted;
10. Confirming the satisfactory operation of the recording device, as fitted, and
verifying by an actual flow test that it has an accuracy of +/- 15% or better;
11. Confirming that the ventilation equipment for residue removal is installed in
accordance with the approved plan and is in working order and that the pressure in
the driving medium for portable fans for ventilation equipment for residue removal
can be achieved to give the required fan capacity;
12. Confirming that the heating system for solidifying and high viscosity substances is
installed in accordance with the approved plan;
2) Survey consists of
1. External examination of the sewage treatment plant including equipment, units and
devices (where installed on board).
The operation of pumping and blast apparatus, metering devices for the supply of
required chemicals including the disinfecting agent, level sensors located in the
plant chambers, alarm signalling, electrical equipment and cable system of the
plant are to be checked.
The operation of the plant in the manual and automatic modes is to be checked.
Absence of leakage from the plant is to be checked. The extent of the functional
serviceability test is specified depending on the type of sewage treatment plant
(physiochemical, biochemical and electrochemical, etc.) and the requirements
specified in the plant operating manual.
The operation test of the plant is to be carried out using the sewage produced on
board or seawater depending on the survey conditions. During the operation test of
the plant, simulating methods may be used where they ensure the sufficient
efficiency of the operation test of the plant, its equipment and machinery.
2. External examination of the sewage comminution and disinfection plant together
with the completing equipment and machinery (where installed on board).
The operation of pumping units, metering devices for supplying the disinfecting
agent, level sensors located in the plant chambers (where available), alarm
signalling, electrical equipment and cable system of the plant are to be checked.
The manual an automatic operation of the plant shall be checked.
The extent of the functional serviceability test is specified depending on the plant
type and the requirements stated in the plant operating manual. The operation test
of the plant is to be carried out using either the sewage produced on board or
seawater, depending on the survey conditions.
During the operation test of the plant, simulating methods may be used where they
ensure the sufficient efficiency of the operation test of the plant, its equipment and
machinery;
3. External examination of sewage collecting tanks together with their equipment,
pipelines and pumping units.
Absence of leakage from the collecting tanks and pipelines is to be checked by
external examination. The operation test of sewage pumping units (and sewage
ejectors, where available) is to be carried out. The operation of visual and audible
alarms on high level in the tanks (where such alarms are installed) is to be tested.
For the operation test of signalling simulating methods may be used;
4. External examination of the pipeline for sewage discharge into reception facilities
and outlet pipes fitted with standard discharge connections;
5. Survey of sewage treatment plants (where installed on board) including their
equipment, units and devices, sewage comminution and disinfection plants (where
installed on board) including equipment an machinery, sewage collecting tanks
including equipment, pipelines and sewage pumping units, pipelines for sewage
discharge into reception facilities with outlet pipes fitted with standard discharge
connections;
6. Examination of inner surfaces of the sewage treatment plant and hydraulic test of
the plant to evaluate its technical condition after the long-term period of operation.
The above mentioned examination and hydraulic test of the sewage treatment plant
shall be carried out under the Surveyor’s request as far as it is reasonable and
practically feasible;
7. Inspection of inner surfaces of the sewage comminution and disinfection system
shall be carried out under the Surveyor’s request as far as it is reasonable and
practically feasible;
8. Examination of inner surfaces of the sewage collecting tanks for evaluation of
technical condition of the tanks. The examination shall be conducted under the
Survyeor’s request as far as it is reasonable and practically feasible.
Hydraulic test of the sewage collecting tanks shall be carried out (when the
documents on the hydraulic test with the positive results being conducted prior the
survey for renewal of the International Sewage Pollution Prevention Certificate
were not submitted).
In all cases the absence of leakage from the tanks and functioning of light and
audible alarms on the tanks high level (where such alarm is fitted) shall be checked.
It is allowed to check of alarm signalling by the simulation method;
9. Hydraulic test of sewage piping (including the pipeline for sewage discharge to the
reception facilities) which shall be conducted under the Surveyor’s request as far
as it is reasonable and practically feasible.
8. Temperature in the furnace exceeds 220℃ (in case the incinerator is not equipped
with the feed lock);
9. Fit condition of the lock to prevent opening of the doors to remove the ash during
the garbage combustion or when the temperature in the furnace exceeds 220℃.
10. Good order of the inspection window to provided observation of the garbage
combustion process;
11. Condition of electrical equipment of the incinerator an service machinery, devices
and arrangements, condition and good order of cable networks;
12. Condition of warning plates fixed on the incinerator’s casing regarding the
prohibition to open the combustion chamber (chambers) doors during the
incinerator’s operation and against the incinerator’s overloading, and other plates
provided by the technical description and the incinerator’s overloading, and other
plates provided by the technical description and the incinerator’s operation manual;
13. Fit condition of the emergency switch for electric power supply to the incinerator’s
equipment, including the fuel nozzles;
14. Operation of safety devices for disconnection of the incinerator in case of fuel non
firing or flame extinction during the ignition. At the same time the safety device
shall close the fuel valves to the nozzles no later than 5 s after the flame extinction;
15. Operation of safety device for automatic cut-off fuel supply to the nozzles if no
fuel ignition occurred during 10 s in attempting of fuel ignition;
16. Operation of safety devices (relays) blocking the possibility of fuel supply to the
nozzle and oil residues to oil residues combustion nozzle at fuel (oil residue)
pressure drop below the value prescribed by the Manufacturer;
17. Automatic stop of the incinerator’s operation in case of power outage to the
incinerator’s control panel and signalling.
3. Examination that every ship of 400 gross tonnage and above, and every ship which
is certified to carry 15 persons or more, shall be provided with a Garbage Record
Book.
4. Examination of type approval certificate as applicable of incinerators and of
garbage plants.
2. Certification
VESSEL " CP-MILLION TRADER, "
Issued Expires
Certificate of registry
Safety Construction Certificate
Safety Equipment Certificate
Safety Radio Certificate
International Load Line Certificate
Exemption Load Line Certificate
International Tonnage Certificate
Suez Canal Tonnage Certificate
Panama Canal Tonnage Certificate
IOPP Certificate
Financial responsability Certificate (water pollution)
Cranes, Derricks, Booms Certificate
Derating Certificate
Potable water Certificate
Safe Manning Certificate
Grain loading file
1. Survey Records
Issued Expires
Hull Special Survey
Hull Annual Survey
Machinery Special Survey
Machinery Annual Survey
Boiler Survey
Tailshaft Survey
Annual Load Line Survey
Quadrennial cargo gear survey
Annual cargo gear Survey
Enhanced Survey records
Date of Last drydocking
Date of next scheduled drydocking
1. Information
Yes No
Approved stability information
Tank sounding table
IMO codes of practice
Cargo stowage reference book
Collision regulations
Pilot books for current trading areas
Nautical almanach for current year
Tide tables for current year
Lights list (corrected)
List of radio signals
Notice to Mariner
Manoeuvring data
SOLAS & MARPOL publications
International Code of Signals
Medical reference guide
Manufacturers ' manuals
West of England Rule book
Nb Maker Type
3. Radio Equipment
Nb Maker Type
Main transmitter
Main receiver
Emergency transmitter
Emergency receiver
Emergency batteries
Lifeboat radio
Auto alarms
EPIRB / COSPAS
Transponder SART
1. Communication
Nb Maker Type
Satcom
VHF radio telephone
Walkie talkie
Public Adress system
Bridge to aft & fore deck & talkbacks
Bridge to steering gear & talkback
Emergency telephone bridge to engine room & talkback
Yes No Nb Condition
Fire pump
fire main
Fire hydrants
Hose boxes
Fire suits
Yes No Nb Condition
Lifeboats
Lifejackets
Immersion suits
Condition
Cathodic protection
2. Cargo Spaces
Condition
Hatchcovers
Coatings
Spar ceiling
Lighting
Tank anodes
Heating coils
1. Ballast Tanks
Condition
Number of ballast tanks
Internal plating
Coatings
Anodes
Winches
Deck lighting
Cargo manifold
Cargo valves
COW system
Butterworth plates
Deck tanks
1. Machinery Space
Condition
Boiler
Steering gear
Sewage tank
Compressors
Turbo blowers
Sanitation arrangement
Bilge system
Ballast system
Workshops
Lighting
Emergency lighting
Pump room
1. Accomodating,Galley,Storerooms
Condition
Cleanliness of hospital
Cleanliness of galley
DAFTAR LITERATURE
Buku diktat perkuliahan Surver, Inspeksi kapal, dan bangunan lepas pantai, Ir. Doniarsal
Nurdin
2.7 SIK-ISI-B-StatSvy-MARPOL-167-264.pdf
3.2 Condition Survey Rep Form-STS.pdf