Professional Documents
Culture Documents
Emediong U. - Risk Assessment Matrix 1 Working
Emediong U. - Risk Assessment Matrix 1 Working
4. Plant, vehicular
traffic, persons
colliding with
structure
Excavations Personnel Accurate location of underground Construction Immediately Project
Excavators and other
1. Cutting into services by operatives trained in the use Engineer Completio
plant to be operated by
underground of locating equipment (CAT scan) and n
trained, certified and
electricity cables and fencing of overhead power lines.
authorized operators.
contact with
overhead power
lines. Adequate fencing or covering for
Planned provision and
2. Collapse of excavations and excavations back filled
use of trench support
unsupported as soon as practicable.
equipment.
excavations.
3. Falling into
unfenced
excavations
4. Materials or plant
falling into
excavations
5. Breaking into gas
or water mains.
6. Struck by
excavator
Working In Personnel Safety Engineer Project
Atmosphere must be tested before entry. Workers to be trained in
Confined Spaces Completio
the use of monitoring
1. Working n
Atmosphere must be constantly equipment and
atmosphere toxic,
monitored during work. evacuation procedures.
explosive or deficient
in Oxygen
Where workmen are to
2. In rush of liquid
operate, using
gasses or solids
breathing apparatus,
3. Exposure to
special training must be
disease bearing
given.
organisms
4. Evacuation of sick
or injured workmen
5. Falls down shafts
or sumps
Working Near Personnel Prior to commencement of excavations The depth at which the Immediately Project
Safety Personnel
Buried Services Properties all public and local utilities must be services are situated Completio
1. Contact with requested to provide information of should be established n
underground power services in the ground in proposed work by hand digging trial
cables causing area. holes.
danger to persons
2. Rupturing of gas Where services are believed to be
pipes leading to present, steps must be taken to establish
leaks, fire or exact positions and routes which should
explosion be identified and marked.
3. Rupturing of water
pipes causing
flooding and damage
4. Cutting of
underground
telecommunications
and interrupting
services
5. Rupturing of
drains, sewers,
culverts etc., causing
health hazards
Crane Operations Personnel Craning operations must be supervised Slingers and bankers Immediately Project
Safety Personnel
1. Crane overturning Properties by a competent person other than crane should be responsible Completio
– ground unsuitable, driver. for examining all lifting n
overloading etc. gear before use,
2. Arcing or contact Appropriate test certificates in respect of ensuring
with overhead appliance and lifting gear should be stability and security of
cables or other examined and copies loads.
obstructions retained on site.
3. Materials falling
during lifting Driver of crane must hold a certificate of
operations competence to drive (copy to be on site)
4. Failure of lifting and responsible
gear or equipment for daily maintenance and completion of
records.
Use Of Excavators Personnel Before excavation ground survey must An excavator should Immediately Project
Safety Personnel
1. Machine be made to locate any underground not be used unless it Completio
Overturning services and prevent has been thoroughly n
2. Materials or damage or injury. examined during
equipment falling preceding 12
from machine months and certificate
3. Members of public of test is provided for
or workmen being site records.
endangered by
machine operation
4. Machine arcing
with or coming into
contact with
overhead cables or
underground
services
Work Creating Personnel Noise must be reduced to lowest level Noise Assessments Safety Engineer Immediately Project
Excessive Noise Residents possible and where persons are exposed should be conducted on Completio
1. Damage to Environment to noise at or above first action level or all plant and where n
hearing peak action level. Assessments must be necessary information
2. Nuisance to local made by a competent person should be given and
residents and action taken in accordance with protective equipment
Noise at Work Regulations 1989 to provided.
protect both operatives and members of
public.
Piling Operations Personnel Survey must be conducted of area to be All hazards, which Safety Engineer Immediately Project
1. Contact with piled to locate underground and could affect stability of Completio
underground overhead services, location of which piling rig, should be Piling n
services should be marked, warning notices identified, e.g. Ground Coordinator
2. Arcing or contact posted and necessary barriers erected. conditions,
with overhead cellars etc. and
cables necessary precautions
3. Overturning of taken.
piling rig
4. Materials or
equipment falling
from piling rig
5. Falls from piling
rig
6. Overturning of
plant associated with
piling
Maintenance and Personnel Plant and equipment must be maintained Mobile plant or Maintenance Immediately Project
Repair of Plant Equipment in accordance with guidance contained in equipment to be Engineer Completio
1. Uncontrolled manufactures/suppliers manuals or worked on to have the n
movement of the instruction leaflets. wheels checked and Safety Engineer
plant under repairs hydraulically operated
2. Uncontrolled lifting arms at rest
movement of before work or braking
hydraulics systems hydraulics on
3. Uncontrolled wheels commences.
release of hot or
pressurized liquids
4. Collapse of
jacking equipment
5. Tyre explosion or
fuel fire
6. Hair or clothing
caught in moving
parts
Welding Personnel Welding must only be carried out by Adequate ventilation Welding Immediately Project
trained operatives. should be provided to Engineer Completio
1. Fire and prevent heat stress. n
explosives Operatives must wear protective clothing Safety Engineer
2. Burns and necessary eye, hearing and All cylinders used in
3. Eye Injuries and respiratory protection. welding should be kept
Arc Eye and moved in trolleys or
4. Electric Shock securely fastened in
5. Exposure to vertical
Fumes and Gases position.
6. Exposure to Heat
7. Respiratory
Disease
8. Hearing Damage
Demolition Personnel Local Authority and HSE must be Adjacent property, After concrete Project
Structural
1. Premature informed of proposed demolition if building or part of plan Completio
Engineers
collapse of building Materials necessary. building to be n
or part of building demolished should be
Safety Engineers
2. Damage to Environment surveyed and a report,
property adjacent to in writing, prepared as
Site Engineers
site of demolition to findings.
3. Falls from the
working place or
access
4. Falls of material
5. Explosion, fire or
electrocution
6. Health hazards to
operatives and
others e.g.
Contaminants,
asbestos, lead, dust
Hot Work, Burning Personnel Fire Safety Plan to be prepared, Electrical and gas Immediately Project
Fire Coordinator
or Ignition of Litter Equipment promulgated and implemented. supplies should be Completio
1. Building, installed and n
Safety Engineer
damaged or Highly flammable liquids and liquid maintained in
destroyed by fire petroleum gas must be stored in open air accordance with
2. Plant or and necessary signs posted. regulations and
equipment damaged Codes of Practice.
or destroyed Certificates of test must
3. Injury to persons be retained for
inspection.
This risk assessment shall be reviewed if the job process changes or is no longer valid.
Step 2 – Assess the level of Risk (Risk Assessment form - Appendix A2)
To ensure stability the height of base ratio of a mobile scaffold tower must not
exceed manufacturers’ instruction or 3.5:1 outside a building. Stabilisers may be
used to increase height to base ratio.
A safe means of access must always be provided either by way of internal inclined
stairway or a ladder lashed vertically to one of the shortest sides. Access should
never be permitted from a ladder leaning against a tower.
2 Working on Scaffold High All scaffolds and working platforms must be property constructed in accordance with
British Standards, Manufacturer’s instructions.
Protection against falling materials must be provided by use of nets, brick guards,
fans and toe boards as necessary.
Additional to requirement of fitting of toe boards and guard rails to platforms over
2m high, those over 1m high must be fitted with guard rails.
3 Excavations High Materials to be stock piled clear of the excavation 1.5m from the edge of the
excavation.
Wheel stops to be used when tipping back fill using dumpers or trucks.
4 Working in confined spaces High Rescue equipment to be provided and all workers to wear safety harnesses,
helmets and protective clothing.
Only the minimum number of workers required to carry out the work safely to enter.
Where permits to work are required, no work should be carried out until the
authorized person has
checked the permit requirements and signed the permit.
Work will not exceed the time limits or safety parameters of the permit, without the
authority of the authorized person.
Workers to be warned of health risks specific to their task and be provided with
written information on these risks, to present to their Doctor in the event of illness.
5 High Excavators and power tools should not be used within 0.5m of a buried service
Working near buried services
unless a permit to work system is used.
If an electricity cable is struck, everyone should be kept clear of the area until made
safe.
If a gas pipe is ruptured, persons in the area should be excavated and steps taken
to prevent ignition of gas.
6 Crane operations High Surface from which mobile crane is to operate should be prepared and checked to
ensure stability.
If driver of crane cannot see load during whole of lifting operation, additional
slinger/bankers should be used.
All overhead electric cables should be identified. Cranes will not operate within 6
metres plus extended jib length, unless permit to work be issued.
600mm clearance must be maintained between any slewing or travelling crane body
and any obstruction or area must be enclosed.
Site Management is responsible for the safe operation of cranes NOT the crane
driver.
7 High Excavators will only be driven by trained competent operatives over the age of 18
years, who are holders of a Certificate of Competence, copy of which should be
retained with site records.
Use of excavators
Excavator drivers must be in possession of machine manufacturer’s manual of
guidance or notes.
All lifting appliances and gear must have appropriate certificates of test, copies of
which should be retained at side level.
All operatives will wear safety helmets and use safety harness if necessary.
9 High Where hydraulically operated equipment has to be elevated for work to be carried
out it must be supported by ridged means, props or ram sleeves.
Where work involves engine cooling systems, hydraulic systems and compressed
air, arrangements must be made to depressurise them under controlled conditions.
When jacking is used to raise the equipment in order to facilitate access under the
machine, the jacking must take place on firm level ground and packing placed under
strong points, to prevent the collapse of the machine in the event of a jack failure.
Maintenance and repair of plant
No hot work to take place on wheels or fuel tanks unless the tyres are removed from
the wheels and the fuel tanks drained, purged and filled with water.
Where work is to be carried out near moving parts, long hair and clothing must be
kept clear.
All guards to power shafts, fans, fan belts and other moving parts to be replaced
when work is complete.
10 Welding High All equipment must be used in accordance with manufacturer’s instructions and
must be inspected before use to ensure it is safe.
Only competent and trained operatives should be permitted to carry out demolition
work and certificates of competence should be inspected and kept on site.
Refueling will not take place whilst engine is running. Funnels must be used when
refueling from canisters.
14 Use of ladders High Ladders will extend 1.07m above a landing and must not rest against surfaces that
can move or are fragile.
Operatives, working from a ladder, must not over-reach or ‘jump’ the ladder to
reposition.
Where there is a risk of falling from an edge, bank etc., a structure, scaffold,
guardrails or fencing shouldl be erected at that edge.
16 Portable power tools High Loose clothing and long hair to be kept clear of moving parts of power tools.
Eye protection to be worn at all times where there is a reasonably foreseeable risk
of eye injury.
Tools producing high levels of vibration to have padded handle to reduce the risks of
vibration white finger.
17 High Machines onto which abrasive wheels are to be mounted should be properly
maintained, marked with spindle speed and not misused.
Use of abrasive wheel machines
Abrasive wheel machines must not be used unless suitable guards are fitted to
contain fragments of bursting wheel.
All operatives and bystanders, where abrasive wheel machines are in use, must
wear suitable eye protection.
18 Refurbishment High Temporary support systems must be designed by a Structural Engineer with design
details held on site (drawings and calculations).
19 Manual handling High Where there is a risk of injury from the manual handling of materials, equipment etc.
an assessment should be made in writing, detailing control measures, and
operatives given instruction.
Step 3 – Monitor & Review of Control / Submission (Risk Assessment form - Appendix A3)
20 Shot blasting High All operatives engaged in shot blasting will wear protective equipment, i.e.
protective overalls, gauntlets, ‘air line’ helmet with face mask or similar, and hearing
protection, and be trained and supervised by a competent person.
All cleaning must ensure safe manual handling operations when emptying
equipment
Areas or buildings, where abrasive blasting operations are to take place, must be
totally enclosed in sheeting to prevent escape of dust, as far as is practicable.
Protective barriers should be erected, as necessary, to protect members of public or
other employees.
Other Details:
Yes No
1. Are the control measures sufficient and effective in minimizing the level of risk?
Yes No
2. Will there be changes to the control measures? (if yes, state period)
Yes No
3. Will there be need for further control measures in future?
4. Will there be need for training of workers? (if yes, state training type, for who and Yes No
when)
Yes No
5. Will there be need to review this assessment in the future? (if yes, state when)
Declaration / Submission
This activity should be conducted in accordance with this risk assessment, implementing the control measures outlined. Changes should be made to