CLIENT
Siam City Cement
MV TESTING AND
COMMISSIONING
REPORT
ELECTRICAL CONTRACTOR ee
Troubleshooting, Testing and
Commissioning of MV
System
DIMO (PVT) LTD.
TECHNOLOGY
nnn)
PREPARED BY
NAME
| DATE
Eng. Krishan Rajapaksha
19.09.2018Date: 19/09/2018
Project : Troubleshooting, Testing and Commissioning of MV System
Subject : Troubleshooting, Testing and Commissioning of MV System in Siam City
Cement, Galle.
Employer : Siam City Cement
Sub-Contractor : Dimo (Pvt) Ltd.
(MY system)
This document contains the site test reports according to the following order. We hear by +
certify that our organization has been completed the troubleshooting and testing of medium
voltage system and is in satisfactory working condition.
Item Description Doc. No.
1. 33kV Incomer Relay Testing SCMVOO1
2. 33kV Outgoing-I Relay I Testing SCMV002
3. 33kV Outgoing-I Relay Il Testing SCMV003
4, 33kV Outgoing-II Relay I Testing SCMV004
5. 3.3kV Incomer Relay Testing SCMVO00S
6. 3.3kV Mill Motor-I Relay Testing SCMV006
7. 3.3kV Mill Motor-II Relay Testing SCMVO007
8. Insulation Resistance Test SCMVO008
9. Replaced Parts Reports SCMVO009
10. Recommendations for further Improvements SCMV010
It is recommended to energize the medium voltage side up to 3.3kV Loads.
Krishan RajapakshaPOWER SOLUTIONS
PME ono evr) unired
Doc. Des. ‘Commissioning test report
rot jon Relay Te
Project SIAM CITY Protection Relay Testing a ee
Project No. Object ‘Numeric Protection Relay
ocation Galle SAM City ae *
‘Bay Incomer Object Des.
Voltage 33 KV =
4. General Data and information
Mansfacturer | SIEMENS
MLFB No, "75J6001-4EA00.00A0BB
Seria No. ‘BF 0509065715
‘Aux Volage | 110VDC
2. Settings
Description ‘Symbot Value
‘Secondary Rated Current tn 5A
CT ratio cr 60:5 a
Virato vir
Phase Over Current
Derived Earth Faut
Enabled Functions
Phase Over Current (61)
Pickup Current 3m
Teme Mutiplior Tw 0.05 5 (ND)
Phase Over Current (60)
Pickup Current 2510
Time Delay 50™ms
Derived Earth Fault (61N)
Pickup Current le (0.05in
Time Delay Tw 0.058 (N)
Derived Earth Fault (60N)
Pickup Current le tin
Time Delay Te 100m s
Tested by KR Date 10.08.18 | Customer
‘Checked by KR ate_| 10.00.18 | Customer Ap. Sig Date
‘Approved by Date Rev. No.