MONTHLY WORK PROGRAM FOR MONTH JUNE 2018, JULY UPTO DATE DATE:- 09th June 2018

Sr. No. Task Name Tatget Achivement Slipage Remark


1 Underpass R-05
Ch. 0+323.5 to 0+340
Water Proofing & Pile Treatment 6/8/2018 6/14/2018 06 Days
Raft Reinforcement/Shuttering 6/20/2018 6/20/2018 00 Days
Raft Concreting 6/21/2018 6/21/2018 00 Days
Foot path concrete 6/28/2018 7/5/2018 07 Days
Ch. 0+340 to 0+380
PCC for raft 6/14/2018 6/14/2018 00 Days
Pile Chipping 6/15/2018 6/20/2018 05 Days
Pile Integrity test 6/18/2018 6/20/2018 02 Days
Water Proofing & Pile Treatment 6/19/2018 7/4/2018 15 Days
Raft Reinforcement/Shuttering 6/28/2018 7/8/2018 10 Days
Raft Concreting 6/29/2018 7/8/2018 09 Days
Foot path concrete
Ch. 0+380 to 0+420
P C C for raft 6/26/2018 6/30/2018 04 Days
Pile Chipping 6/29/2018 7/3/2018 04 Days
Pile Integrity test 7/2/2018 6/4/2018
Water Proofing & Pile Treatment 7/4/2018 NOT YET START
Raft Reinforcement/Shuttering 7/11/2018 NOT YET START
Raft Concreting 12-07-208 NOT YET START
2 DRP CSB (SWAP 03)
P3 Pile Cap & Pier

Underpass wall Reinforcement (2nd Lift)

Shuttring 6/11/2018 6/15/2018 04 Days


Concreting 6/12/2018 6/16/2018 04 Days
Deshuttering 6/14/2018 6/18/2018 04 Days
Backfilling 6/20/2018 6/26/2018 06 Days
Sheet Pile Removal 6/22/2018 6/27/2018 05 Days
A2 Above Ground Level
Abutment wall Steel Fixing 6/7/2018 6/10/2018 03 Days
Shuttring 7/12/2018 6/15/2018 03 Days
Concreting 6/13/2018 6/16/2018 03 Days
Deshuttering 6/18/2018 6/18/2018 00 Days
Backfilling 6/20/2018 6/22/2018 02 Days
P1 Pile Cap Pier
Sheet Pile bracing 6/5/2018 6/8/2018 03 Days
Excavation Beyond 3.5m level 6/11/2018 6/12/2018 01 Day
PCC 6/13/2018 6/14/2018 01 Day
A1 Abutment
Sheet Pile Driving 6/5/2018 6/8/2018 03 Days
Excavation Upto 3.5m Level 6/14/2018 6/16/2018 02 Days
Sheet Pile bracing 6/19/2018 6/22/2018 03 Days
Excavation Beyond 3.5m level 6/28/2018 6/29/2018 01 Day
PCC 7/2/2018 7/2/2018 00 Days
3 CBS (SWAP 01 ) BPSC
P3 PYLON
Diaphragm Beam 7/9/2018 NOT YET READY 80% COMP.
P2 PYLON
Earth Work 6/19/2018 6/20/2018 01 Day
PCC 6/21/2018 6/24/2018 03 Days
Pile Chipping 7/3/2018 7/7/2018 04 Days
MONTHLY WORK PROGRAM FOR MONTH JUNE 2018, JULY UPTO DATE DATE:- 09th June 2018
Sr. No. Task Name Tatget Achivement Slipage
1 Underpass R-05
Ch. 0+323.5 to 0+340

Water Proofing & Pile Treatment 6/8/2018 6/14/2018 06 Days

Raft Reinforcement/Shuttering 6/20/2018 6/20/2018 00 Days

Raft Concreting 6/21/2018 6/21/2018 00 Days


Foot path concrete 6/28/2018 7/5/2018 07 Days
Ch. 0+340 to 0+380
PCC for raft 6/14/2018 6/14/2018 00 Days
Pile Chipping 6/15/2018 6/20/2018 05 Days
Pile Integrity test 6/18/2018 6/20/2018 02 Days

Water Proofing & Pile Treatment 6/19/2018 7/4/2018 15 Days

Raft Reinforcement/Shuttering 6/28/2018 7/8/2018 10 Days

Raft Concreting 6/29/2018 7/8/2018 09 Days


Foot path concrete
Ch. 0+380 to 0+420
P C C for raft 6/26/2018 6/30/2018 04 Days
Pile Chipping 6/29/2018 7/3/2018 04 Days
Pile Integrity test 7/2/2018 6/4/2018
Water Proofing & Pile Treatment 7/4/2018 NOT YET START
Raft Reinforcement/Shuttering 7/11/2018 NOT YET START
Raft Concreting 12-07-208 NOT YET START
2 DRP CSB (SWAP 03)
P3 Pile Cap & Pier

Underpass wall Reinforcement (2nd Lift)

Shuttring 6/11/2018 6/15/2018 04 Days


Concreting 6/12/2018 6/16/2018 04 Days
Deshuttering 6/14/2018 6/18/2018 04 Days
Backfilling 6/20/2018 6/26/2018 06 Days
Sheet Pile Removal 6/22/2018 6/27/2018 05 Days
A2 Above Ground Level
Abutment wall Steel Fixing 6/7/2018 6/10/2018 03 Days
Shuttring 7/12/2018 6/15/2018 03 Days
Concreting 6/13/2018 6/16/2018 03 Days
Deshuttering 6/18/2018 6/18/2018 00 Days
Backfilling 6/20/2018 6/22/2018 02 Days
P1 Pile Cap Pier
Sheet Pile bracing 6/5/2018 6/8/2018 03 Days
Excavation Beyond 3.5m level 6/11/2018 6/12/2018 01 Day
PCC 6/13/2018 6/14/2018 01 Day
A1 Abutment
Sheet Pile Driving 6/5/2018 6/8/2018 03 Days
Excavation Upto 3.5m Level 6/14/2018 6/16/2018 02 Days
Sheet Pile bracing 6/19/2018 6/22/2018 03 Days
Excavation Beyond 3.5m level 6/28/2018 6/29/2018 01 Day
PCC 7/2/2018 7/2/2018 00 Days
3 CBS (SWAP 01 ) BPSC
P3 PYLON
Diaphragm Beam 7/9/2018 NOT YET READY
P2 PYLON
Earth Work 6/19/2018 6/20/2018 01 Day
PCC 6/21/2018 6/24/2018 03 Days
Pile Chipping 7/3/2018 7/7/2018 04 Days
E:- 09th June 2018
Remark
80% COMP.