The document outlines the monthly work program and progress for various construction tasks in June and July 2018. It lists 3 main tasks - an underpass from Ch. 0+323.5 to 0+420, a DRP CSB at SWAP 03, and a CBS at SWAP 01 BPSC. The status of each sub-task is provided along with actual vs. targeted start and end dates and any slippages. The progress is mostly on or ahead of schedule except for some upcoming tasks of the underpass and CBS projects.
The document outlines the monthly work program and progress for various construction tasks in June and July 2018. It lists 3 main tasks - an underpass from Ch. 0+323.5 to 0+420, a DRP CSB at SWAP 03, and a CBS at SWAP 01 BPSC. The status of each sub-task is provided along with actual vs. targeted start and end dates and any slippages. The progress is mostly on or ahead of schedule except for some upcoming tasks of the underpass and CBS projects.
The document outlines the monthly work program and progress for various construction tasks in June and July 2018. It lists 3 main tasks - an underpass from Ch. 0+323.5 to 0+420, a DRP CSB at SWAP 03, and a CBS at SWAP 01 BPSC. The status of each sub-task is provided along with actual vs. targeted start and end dates and any slippages. The progress is mostly on or ahead of schedule except for some upcoming tasks of the underpass and CBS projects.
MONTHLY WORK PROGRAM FOR MONTH JUNE 2018, JULY UPTO DATE DATE:- 09th June 2018
Sr. No. Task Name Tatget Achivement Slipage Remark
1 Underpass R-05 Ch. 0+323.5 to 0+340 Water Proofing & Pile Treatment 6/8/2018 6/14/2018 06 Days Raft Reinforcement/Shuttering 6/20/2018 6/20/2018 00 Days Raft Concreting 6/21/2018 6/21/2018 00 Days Foot path concrete 6/28/2018 7/5/2018 07 Days Ch. 0+340 to 0+380 PCC for raft 6/14/2018 6/14/2018 00 Days Pile Chipping 6/15/2018 6/20/2018 05 Days Pile Integrity test 6/18/2018 6/20/2018 02 Days Water Proofing & Pile Treatment 6/19/2018 7/4/2018 15 Days Raft Reinforcement/Shuttering 6/28/2018 7/8/2018 10 Days Raft Concreting 6/29/2018 7/8/2018 09 Days Foot path concrete Ch. 0+380 to 0+420 P C C for raft 6/26/2018 6/30/2018 04 Days Pile Chipping 6/29/2018 7/3/2018 04 Days Pile Integrity test 7/2/2018 6/4/2018 Water Proofing & Pile Treatment 7/4/2018 NOT YET START Raft Reinforcement/Shuttering 7/11/2018 NOT YET START Raft Concreting 12-07-208 NOT YET START 2 DRP CSB (SWAP 03) P3 Pile Cap & Pier
Underpass wall Reinforcement (2nd Lift)
Shuttring 6/11/2018 6/15/2018 04 Days
Concreting 6/12/2018 6/16/2018 04 Days Deshuttering 6/14/2018 6/18/2018 04 Days Backfilling 6/20/2018 6/26/2018 06 Days Sheet Pile Removal 6/22/2018 6/27/2018 05 Days A2 Above Ground Level Abutment wall Steel Fixing 6/7/2018 6/10/2018 03 Days Shuttring 7/12/2018 6/15/2018 03 Days Concreting 6/13/2018 6/16/2018 03 Days Deshuttering 6/18/2018 6/18/2018 00 Days Backfilling 6/20/2018 6/22/2018 02 Days P1 Pile Cap Pier Sheet Pile bracing 6/5/2018 6/8/2018 03 Days Excavation Beyond 3.5m level 6/11/2018 6/12/2018 01 Day PCC 6/13/2018 6/14/2018 01 Day A1 Abutment Sheet Pile Driving 6/5/2018 6/8/2018 03 Days Excavation Upto 3.5m Level 6/14/2018 6/16/2018 02 Days Sheet Pile bracing 6/19/2018 6/22/2018 03 Days Excavation Beyond 3.5m level 6/28/2018 6/29/2018 01 Day PCC 7/2/2018 7/2/2018 00 Days 3 CBS (SWAP 01 ) BPSC P3 PYLON Diaphragm Beam 7/9/2018 NOT YET READY 80% COMP. P2 PYLON Earth Work 6/19/2018 6/20/2018 01 Day PCC 6/21/2018 6/24/2018 03 Days Pile Chipping 7/3/2018 7/7/2018 04 Days MONTHLY WORK PROGRAM FOR MONTH JUNE 2018, JULY UPTO DATE DATE:- 09th June 2018 Sr. No. Task Name Tatget Achivement Slipage 1 Underpass R-05 Ch. 0+323.5 to 0+340
Water Proofing & Pile Treatment 6/8/2018 6/14/2018 06 Days
Raft Reinforcement/Shuttering 6/20/2018 6/20/2018 00 Days
Raft Concreting 6/21/2018 6/21/2018 00 Days
Foot path concrete 6/28/2018 7/5/2018 07 Days Ch. 0+340 to 0+380 PCC for raft 6/14/2018 6/14/2018 00 Days Pile Chipping 6/15/2018 6/20/2018 05 Days Pile Integrity test 6/18/2018 6/20/2018 02 Days
Water Proofing & Pile Treatment 6/19/2018 7/4/2018 15 Days
Raft Reinforcement/Shuttering 6/28/2018 7/8/2018 10 Days
Raft Concreting 6/29/2018 7/8/2018 09 Days
Foot path concrete Ch. 0+380 to 0+420 P C C for raft 6/26/2018 6/30/2018 04 Days Pile Chipping 6/29/2018 7/3/2018 04 Days Pile Integrity test 7/2/2018 6/4/2018 Water Proofing & Pile Treatment 7/4/2018 NOT YET START Raft Reinforcement/Shuttering 7/11/2018 NOT YET START Raft Concreting 12-07-208 NOT YET START 2 DRP CSB (SWAP 03) P3 Pile Cap & Pier
Underpass wall Reinforcement (2nd Lift)
Shuttring 6/11/2018 6/15/2018 04 Days
Concreting 6/12/2018 6/16/2018 04 Days Deshuttering 6/14/2018 6/18/2018 04 Days Backfilling 6/20/2018 6/26/2018 06 Days Sheet Pile Removal 6/22/2018 6/27/2018 05 Days A2 Above Ground Level Abutment wall Steel Fixing 6/7/2018 6/10/2018 03 Days Shuttring 7/12/2018 6/15/2018 03 Days Concreting 6/13/2018 6/16/2018 03 Days Deshuttering 6/18/2018 6/18/2018 00 Days Backfilling 6/20/2018 6/22/2018 02 Days P1 Pile Cap Pier Sheet Pile bracing 6/5/2018 6/8/2018 03 Days Excavation Beyond 3.5m level 6/11/2018 6/12/2018 01 Day PCC 6/13/2018 6/14/2018 01 Day A1 Abutment Sheet Pile Driving 6/5/2018 6/8/2018 03 Days Excavation Upto 3.5m Level 6/14/2018 6/16/2018 02 Days Sheet Pile bracing 6/19/2018 6/22/2018 03 Days Excavation Beyond 3.5m level 6/28/2018 6/29/2018 01 Day PCC 7/2/2018 7/2/2018 00 Days 3 CBS (SWAP 01 ) BPSC P3 PYLON Diaphragm Beam 7/9/2018 NOT YET READY P2 PYLON Earth Work 6/19/2018 6/20/2018 01 Day PCC 6/21/2018 6/24/2018 03 Days Pile Chipping 7/3/2018 7/7/2018 04 Days E:- 09th June 2018 Remark 80% COMP.