Professional Documents
Culture Documents
Hostel
Hostel
Supervisor Student
Technology (S.I.M.T.),
fn;sA
CERTIFICATE
Contents
ABSTACT OF COST
(In Rs.)
PROBLEM
Reports :
PREFACE
3
INTRODUCTION
Hkou fuekZ.k flfoy bUth0 dh ,d eq[; 'kk[kk gSA
bUth0 dh vU; 'kk[kkvksa esa Hkh cM+s iSekus ij
Hkou fuekZ.k dk;Z viuk;s tkrs gSA ,d flfoy bUth dks
Hkou cukus rFkk vuqj{k.k esa vPNh n{krk izkIr
gksuh pkfg,A Hkou mi;ksfxrk lqUnjrk rFkk lkeF;Z dh
n`f"V ls mÙke o U;wure O;; okyk gksuk pkfg,A
;gk¡ ij ,d ,slk gkWLVy fcfYMax dk izkstsDV rS;kj
djuk gS tks Nk=ksa dh lkjh O;oLFkkvksa dks /;ku
esa j[kdj rFkk lkjh lqfo/kkvksa dks ns[krs gq,
gkWLVy fcfYMax dk ferO;;h vkdkj iznku djus dk
Hkjiwj izz;kl fd;k x;k gSA
izkstsDV dks rS;kj djus ds fy, bls fofHkUu Hkkxksa
esa ck¡Vk x;k gS ftldk laf{kIr fooj.k fuEufyf[kr gSA
Literature Review
Planning
Surveying
Analysis and Design
Estimating and Costing
Analysis of Rates
Project Scheduling
Conclusions and Recommendation
Bibliography
Drawing
4
LITERATURE REVIEW
Literature Review: Chapter two literature review deals with various references that
has been taken from Various book including vastushastra it has been attempted to
give basic ideas over concrete construction planning principle. A consideration has
been given the current rates.
Planning : Chapter three deals with planning of various aspects of orientation keeping
in view the solar and wind orientation. An attempted has also been made to maintain
the Rooom various reventant factors has also been considered during planning.
Survey: Chapter four deals with Surveying in which it has been tried to Explain about
the instrument used in surveying mover ever the working is also included along with
it a first problem as been given which are faced during the surveying of the proposed
area.
Analysis and design : Chapter five deals with various loads which have calculated as
per I.S. Code 875 Based upon these loads positions of blons and columns are planned
the designs for slab, became columns doubly reinforced beam and T. Beam has also
been shown.
Estimating and Coasting: Chapter ix deals with the estimation of the building as the
values costing has also has been done with the C.P.M. Cherls the whole work has been
divided into the number of activities and attempt has made to find out the parallel
activities the critical path of the network has been calculated and the schedelle time
comptition has been also.
Conclusions and Recomendation: Chapter nine deals with conclusion and
recommendation on variou topic due to time schedule it was not possible to provide a
C.A.P. Programming on the whole project how ever it is recommended that it would
been better if such technology been given more consideration. In this project the
design based upon limit state method are most economical from space point of view
looking to the scaraty of the space it is recommended that such project should also be
developed based on limit state method.
5
PLANNING
10
IN FRONT- IykV ds ihNs dh lkbM ls de 6-5 ,e
[kqykLFkku gksuk pkfg,A ;fn Hkou ds ihNs dksbZ
lM+d ij rks lM+d ds nwljh vksj cus Hkou ds dkV ds
fcUnq ls 67 1@2 dk m/okZ/kj dks.k Hkou ds fdlh
Hkkx dks dkVuk pkfg,A
11
SURVEY
13
14
lery og izfØ;k gS ftlesa lery iVy ds fcUnq ds Åij
ik.kly j[kdj lery fd;k tkrk gSA iVy leryu ds leryu iV
dks LVs'ku fcUnq ds Åij LFkkfir djds f=ikn ds
Vk¡xksa dks QSykdj iVy dk yxHkx lery dj fy;k tkrk
gSA rRi'pkr lery ikn isapksa dh lgk;rk ls Iysu Vscy
dks ?kqekdj lery dj ysrs gSA ,slh fLFkfr esa ccy
dsUnz esa jgrk gSA lery iVy dks ftl dks.k ij ?kqek;k
tkrk gS rks Hkh iVy lery jgrk gSA
3. OREINTATION
;g og izfØ;k gS ftlds }kjk igy dks izR;sd vkxkeh
LVs'ku ij LFkkfir fd;k tkrk gSA rkfd og viuh iwoZ
fLFkfr ds lE;Urj gks tk, ;g nks fof/k;ksa ls fd;k tkrk
gSA
1- By trough compass
2- By Back Sighting
pSu o dEikl losZ{k.k }kjk rS;kj uewuk uD'ks ls {ks=
dh Å¡pkbZ o xgjkbZ ds ckjs esa dksbZ tkudkjh izkIr
ugh gksrh gSA tcfd bathfu;fjax esa bldh vko';drk
iM+rh gSA vr% flfoy bath0 dk;Z ds {ks= dk leksPp
uD'kk rS;kj fd;k tkrk gSA blls {ks= ds ckjs esa
tkudkjh izkIr gksrh gSA leksPp js[kk {ks= esa le;
mPprk dks feykus okyh dkfYifud js[kk gksrh gSA
OBJECT OF CONTOUR - leksPp uDs'ks dk fuekZ.k djus ls
gksrh gSA
1- Level Contour
2- Grade Contour
LEVEL CONTOUR - leku mPprk okys fcUnqvksa dks
feykus okyh js[kk dks lery leksPp js[kk vFkok leksPp
js[kk dgrs gSA
16
2. GRADE CONTOUR - Hkwfe ij ,d fuf'pr <ky ij yxk;s x;s
METHOD OF CONTOUR
1- Direct Method
2- Indirect Method
DIRECT METHOD : leksPp js[k.k dh bl fof/k esa okafNr
M = 280/3 cbc
= 280/ (3 7) = 13.33
(1) Design Constant -
(2) Assumedepth - 170 MM
Cover 20 MM
Depth = 170 - 20 = 150 MM
assume b= 1000 MM
(3) Load /M2
i. Live load = 2000 N
ii. Self Weight ( 110.7125000)= 4250 N
iii. Wb of finishing ( 110.02524000)= 600 N
Total Weight= 6850 N
= 6.85 kN
(4) Bending Moment coefficient
Case 2 One Short edge discontinuous
for Pannels (1), (2), (3) (4) (5) (6) (7) (8) (9) (10)
(11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
(21) (22) (23) (24) (25) (26) (27) (28) (29) (30)
(31) (32) (33)
Effective Span for Shorter Span For longer Span
(i) 4.5 + 0.3 = 4.8 m (i) 5.4 +0.3 = 5.7 M
(ii) 4.5+0.15 = 4.65 M (ii) 5.4+0.15 = 5.55 M
19
= ly/lx = 5.55/4.65 = 1.1935 Kg
Negative Moment at Continuous Edge -
x = 0.043 + (0.048-0.043)0.0935 = 0.047677
0.1
x = 0.047677
y = 0.028
for pannel (8)
Effective Span for shorter span For longer span
(i) 4.95 + 0.3 = 5.25 M (i) 5.4 +0.3 = 5.7 M
(ii) 4.95+0.15 = 5.05 M (ii) 5.4+0.15 = 5.55 M
lx=5.05 M ly = 5.55 M
= ly/lx = 5.55/5.05 = 1.099009
Negative Moment at Continuous edge -
x = 0.037 + (0.043-0.037)0.099009 = 0.042940
0.1
x = 0.042940
y = 0.037
Positive Moment of Mid Span -
x = 0.028 + (0.033-0.028)0.099009 = 0.0032950
0.1
y = 0.028
for pannel (36)
Effective Span for shorter span For longer span
(i) 4.5 + 0.3 = 4.8 M (i) 4.8 +0.3 = 5.1 M
(ii) 4.5+0.15 = 4.65 M (ii) 4.8+0.15 = 4.95 M
lx=4.65 M ly = 4.95 M
= ly/lx = 4.95/4.65 = 1.064516
20
Negative Moment at Continuous edge -
x = 0.037 + (0.043-0.037) 0.064516 = 0.0408709
0.1
y = 0.037
Positive Moment of Mid Span -
x = 0.028 + (0.033-0.028) 0.064516
0.1
x = 0.0312258
y = 0.028
for pannel (18)
Effective Span for shorter span For longer span
(i) 3.6 + 0.3 = 3.9 M (i) 5.4 +0.3 = 5.70 M
(ii) 3.6+0.15 = 3.75 M (ii) 5.4+0.15 = 5.55 M
lx=3.75 M ly = 5.55 M
= ly/lx = 5.55/3.75 = 1.48
Negative Moment at Continuous edge -
x = 0.055 + (0.057-0.055) 0.08 = 0.0566
0.1
y = 0.037
Positive Moment of Mid Span -
x = 0.041 + (0.044-0.041) 0.08
0.1
x = 0.0434
y = 0.028
Case 4 Two Ajecent edges Discontinuous (9), (34) (35) for Pannel (9)
21
Effective Span for shorter span For longer span
23
BENDING MOMENT
For Pannels - 1, 2, 3, 4, 5, 6, 7, 10, 11, 12, 13, 14, 15, 16, 17, 19, 20, 21, 22, 23, 24,
25, 26, 27, 28, 29, 30, 31, 32, 33.
lx = 4.65 M
Supports - Mx = x Wl2x = 0.0476776.85 4.652 = 7.061637 KN-M
My = y W2x = 0.0376.85 4.652 = 5.480222 KN-M
Mid Span - Mx = 0.035741 6.85 4.652 = 5.293746 kN-M
My = 0.0286.85 4.652 = 4.147195 KN-M
For Pannels - (8)
lx = 5.05 M
Supports - Mx = 0.0429406.85 5.052 = 7.501279 KN-M
My = 0.0376.85 5.052 = 6.463608 KN-M
Mid Span - Mx = 0.032950 6.85 5.052 = 5.756105 kN-M
My = 0.0286.85 5.052 = 4.891379 KN-M
For Pannels - (36)
lx = 4.65 M
Supports - Mx = 0.04087096.85 4.652 = 6.053557 KN-M
My = 0.0376.85 4.652 = 5.480222 KN-M
Mid Span - Mx = 0.0312258 6.85 4.652 = 4.624982 kN-M
My = 0.0286.85 4.652 = 4.147195 KN-M
For Pannels - (18)
lx = 3.75 M
Supports - Mx = 0.05666.85 3.752 = 5.452171 KN-M
My = 0.0376.85 3.752 = 3.564140 KN-M
Mid Span - Mx = 0.0434 6.85 3.752 = 4.180640 kN-M
My = 0.0286.85 3.752 = 2.697187 KN-M
For Pannels - (3)
lx = 5.05 M
Supports - Mx = 0.0529406.85 5.052 = 9.248201 KN-M
My = 0.0476.85 5.052 = 8.210529 KN-M
24
Mid Span - Mx = 0.039950 6.85 5.052 = 6.978950 kN-M
My = 0.0356.85 5.052 = 6.114224 KN-M
For Pannels - (34)
lx = 5.55 M
Supports - Mx = 0.0635136.85 5.552 = 13.401060 KN-M
My = 0.0476.85 5.552 = 9.916864 KN-M
Mid Span - Mx = 0.047810 6.85 5.552 = 10.148961 kN-M
My = 0.0356.85 5.552 = 6.092098 KN-M
For Pannels - (35)
lx = 4.35 M
Supports - Mx = 0.0556556.85 4.352 = 7.213952 KN-M
My = 0.0476.85 4.352 = 6.092098 KN-M
Mid Span - Mx = 0.041896 6.85 4.352 = 5.430522 kN-M
My = 0.0356.85 4.352 = 4.536693 KN-M
MAX BENDING MOMENT
Supports - Mx = 13.401060 KN-M My = 9.916864 KN-M
Mid Span - Mx = 10.148961 kN-M My = 7.384899 KN-M
Men L.B. M. = 13.401066 KN- M
6. DEPTH OF SLAB = d = M/rb
R = 1.22 b= 1000 MM
d = 104.806 MM
D= 140 + 20 = 160 mm
7. Area of Steel - for all pannels
Main Steel - provide 10 mm of bar both ways
Short span lx = 5.55
Mid Span Ast. = Mx / st 1d = 10.148961 106 = 595.177 mm2
1400.87140
Spacing = 78.539 1000 = 131.96 or 130 mm
595.177
Provided 10 MM bar @ 130 MMN C/c
25
Support = Ast2 = 13.401060106 = 785.89
1400.87140
Alternate bew are bent up all from support is both direction Balance Steel = 785.89 -
595.177 = 190.71 mm2
Spacing = 78.539 1000 = 165.805 mm2
473.682
Additional steel comm bar @ 480 C/c
8. CHECK FOR SHEAR
(1) Sher force for shorter span = 1/3 Wlx = 1/3 x 6850 x 5.55
Vdx = 12672.5 N
Shear force for longer span (ly/lx/2+ly/lx)x Wlx
= 1.27027/3.27027 x 6850x 5.55
Vly = 14767.12 N
Max S.F. = 14767.12
Shear Stress Z v= 14767.12/ 1000 x 140 = 0.105 N/mm2 {Zv2 V/bd}
d = 140 mm fy;k tk,xk D;ksafd uhpyh iafMr dh NM+s drZu ea igys
izHkkfor [k.M gksxh blesa bLikr dk izfr'kr
9. Check for development length
(i) for shorter span -
M1 = st Ast/2 : 1d
= (140595.1770.81 140 )/ 2 = 5074429.10 N-MM
DESIGN CONTINUOUS SLAB (ONE WAY)
Given data - Concrete Grade M20 cbe = 7 N/mm2
Steel Grade Fe250 = 140 N/mm2
M = 13.33
1- DESIGN CONSTANT -
(1) k = 0.4 (2) J = 0.87 (3) R =1.22
2- Assume depth of slab D = 4000/26 = 153.84 = 160 mm
3- deff. = 160-20 = 140 MM
26
3.- EFFECTIVE SPAN - fljksa okys ikVks dk 'kq) ikV4.0 - 0.15 =
3.85
Hkhrjh ikVks dk 'kq) ikV 4-0 & 3 ¾ 3-70 ,e fljs okys ikV dh
izHkkoh yEckbZ ¼1½ 3-70$ 0-3 ¾4-0 ,e ¼2½ 3-70$0-14
¾3-8 ,e
l2 eff = 3.84 M
4- LOAD/M - 25 cm the floor finishing (1 x1x0.025x24000) = 600 N
Self Wt of Slab (1x0.16x25000) = 4000 N
Dead load (wt) = 4600 N
Live load (Ws) = 2000 N
Total = 11200 N
5- Max. B.M. = 10861.04 NM
6- Depth of Slab -
27
Ao < Ast Hence Ok
10. Check For shear Force - Max. S.F. V = 15800.4 N
Nominal Shear stress =
Percentage of Steel provided =
Hence Ok
DESIGN OF T. BEAM
Given data
28
M20 = cbc = 7 N/mm2
Fe415 = st = 230 N/mm2
M=
1. DFESIGN CONSTANT
a.
b.
c.
2. Assume Depth -
29
5. MAXIMUM B.M.
6. DEPTH OF BEAM
deff = 460 MM & cover = 40 MM D= 500 MM
7. LEVER ARM
Z = 0.9 460
Z = 414 MM
8. APPROX AREA OF STEEL
= 2061.99 MM2
SNOS of 24 MM
Actual Area Of Steel Ast = 2261.946 MM2
9. EFFECTIVE WIDTH OF FLANGE -
(i) bf = l0/6 + bw * 6Df (ii) bf = bw +c/c distance between
panels
= 9000/6 + 300 + 6 160 = 300 +4000 -300
= 2760 MM = 4000 MM
bf = 2760 MM
30
10.DEPTH OF N.A.
31
12.CHECK FOR MINIMUM STEEL REINFORCEMENT
Shear stress
Spacing
Sv = 751.182 MM = 750 mm
8 mm of bar @ 250 mm c/c
ijUrq ;g vUrjky 0.75 x d = 0.75 x 460 = 345 ;k 300 MM
Which is less
U;wure drZu izcyu ds vk/kkj ij mnxz NYyks dk
vUrjky
33
Dead loadwd
(i)
(ii)
(iii) Wt of Self wt = 110.3425000 = 8500 N
TOTAL = 19540 N
Dead load Wd2
= 1643 MM2
% of Steel =
Zmax = 1.8
Zmax >Zv >Zc vr% Shear reinforcement djuk iM+sxkA
Vs = V - Zcbd
= 52861.5 - 0.39 300 300 = 17341.5 N
Use 8 mm leg stirrup then
Spacing =
S = 397.88 MM C/C
9- U;wure drZu cy
vr% Provided 8mm 2 leg sterrups @ 225 C/c
36
SUMMARY OF DESIGN
1. Depth of beam = 360 mm
2. Steel Reinforcement in tension side 3Nos of 20mm bar
3. Steel Reinforcement in Compression side 5Nos of 22mm bar
4. Shear Reinforcement 2 leg Stirrup 8 mm of bar @ 22 mm c/c
DESIGN OF COLUMN
Data M20 cbc = 7 N/mm2 cc = 5 N/MM2
Fe415 st = 230 N/mm2 sc = 190 N/mm2
M = 18.33
37
1. DESIGN CONSTANT (i) K = 0.29 (ii) J = 0.90 (iii) R = 0.92
2. LOAD
Wt of Slab = (20.60 0.162500) = 82400 N
Wt of finishing = (20.60 0.02524000) = 12390 N
Wt of beam = (7.5 0.3425000) = 63750 N
Wt of load = (20.66 2000) = 41200 N
TOTAL WT = 199740 N
3. Assume as a certain 1% of A (gross area)
Considering a short Column
Acc cc + Asc sc = W
(A-Asc) cc + Ascsc = W
(A-0.01A)cc + 0.01A sc = W
A = 199740/6.85 = 29159.12 mm2
for rectangular column one dimensions I.S. Code = 300 MM
b= 29159.12/300 = 97.19 mm
Provided 300 200 mm column
check l.eff /5 =
=
39
4- DEPTH OF FOOTING -
¼d½ ladu vk?kw.kZ ds vk/kkj ij ikn dh xgjkbZ LrEHk
ij 20 ls-eh- okyksa Qyd ij cadu vk?kw.kZ &
M1 ¾ js[kkPNfnr {ks=Qy ØkfUrd dkV ls xq#Ro
dsUnz
= 1.2 1.1133133.330.55
= 96654.7975 N MM
V = P [(AB)+(a'b')]
= 133133.33 [(1.22.5)-(0.930.83)]
= 296634.37 N
lsD'ku dks lUrqfyr ekurs gq, vFkkZr iwcyu bLikr 0-
31 izfr'kr ysrs gq,
40
Zc = 0.24 N/mm2
V = Zv b0 d
d= V/ b0Zv = b= 2 (93+83) = 352 cm
depth of footing 850 + 50 = 900 MM
5. STEEL REINFORCEMENT
(1) 20 cm Qyd ds fy, ruu bLikr dk {ks=Qy
10 No bar 12 mm bar
41
DESIGN OF LINTEL
Know data
M20 - cbc = 7 N/mm2
Fe415 - st = 230 N/mm2 Clarspan = 1.2 M
M = 13.33
1. DESIGN CONSTANT - (1) K = 0.29 (II) J = 0.29
(III)R=0.92
2. Assume depth 150 MM 8 cover 20 MM
deff = 150-20 = 130 MM
3. EFFECTIVE SPAN -
1.2 + 0.13 = 1.33 M
1.2 + 0.3 = 1.50 M
eff - 1.33 M
4. LOAD-
(1) f=Hkqt dk fpukbZ Hkkj W1 =
= 2547.216 N
(2) fyUVj dk Lo;a Hkkj W2 =
= 1125 N/M
5. BENDING MOMENT (Maximum)
M1 =
M2 =
Total Max B.M. = 564.63 + 248.75 = 813.38 N-M
42
6. DEPTH OF LINTEL
= 100 mm
Over all depth = 100 + 20 = 120 MM
7. Steel Reinforcement
= 39.29 MM2
Minimum Steel
43
ESTIMATING
44
walls
PART
AA'BB'CC'DD'
Column footing 36 2.50 1.20 0.9 97.2m3 C/C=30 M
Wall foundation
(i) long wall 4 12.5 0.9 0.9 40.5m3 L=30-
7x2.5=12.5M
(ii) Short wall 16 4.6 0.9 0.9 59.62m3 C/C=5.6+0.2=5
8M
3
A'B'C'D' Wall 2 9.0 0.9 0.9 7.29m L=5.8-
1.2=4.6M
L=10.2-1.2-
9.0M
3
TOTAL 204.61M
PART EGH
Column footing 22 2.50 1.20 0.9 59.62m3 C/C=34.7 M
wall
foundation L=34.7 -22.5 =
12.2
long wall 2 12.2 0.9 0.9 59.62m3 c/c=9.2 m
L=9.2-
1.25=7.95
Short wall 2 7.95 0.9 0.9 59.62m3 C/C=4.2 M
for stair Room L =4.2-0.6 =3.6
M
Long Wall 2 3.6 0.9 0.9 59.62m3 C/C=3.8
Short Wall 1 2.9 0.9 0.9 59.62m3 L=3.8-
0.9=2.9M
3
F6 Wall 1 9.2 0.9 0.9 3.40m C/C=9.2
L=9.2-
2*2.5=4.2M
3
1 18.5 0.9 0.9 10.94m C/C=14.2+0.2=
14.4
L=14.4-9=13.5
3
TOTAL 114.56 m
PARK HIJK
Column footing 20 2.5 1.2 0.9 54.0 m3
wall foundation
long wall 2 21.7 0.9 0.9 35.15 m3 C/C=44.2
L=49.2-
9*2.5=21.5
3
Short Wall 7 4.6 0.9 0.9 29.81m C/C=5.6X0.2=5
.8
L=5.8-1.2=4.6
W.C. ROOM
W.C. Wall C/C=7.2
long Wall 1 6.75 0.9 0.9 5.47 L=7.2-
0.45=6.75
Short Wall 6 0.5 0.9 0.9 2.43 l=1.4-0.9=0.5
BATH ROOM
Long Wall 2 4.9 0.9 0.9 7.94 L=5.8-0.9=4.9
Short Wall 6 0.8 0.9 0.9 3.89 L=1.7-0.9=0.8
total 138.63m3
PART LMND
Column footing 19 2.5 1.2 0.9 51.3m3 C/C = 41.1-
wall foundation 2x0.2/2=39.9M
long wall 2 19.9 0.9 0.9 32.24 L=39.9-
8x2.5=19.9
Short wall 9 4.6 0.9 0.9 33.53 L=5.8-
1.2=4.6M
117.07m3 D
45
PART PQRS
Column footing 12 2.5 1.2 0.9 32.4 C/C =28.2M
wall foundation
long wall 2 15.7 0.9 0.9 25.43 L=28.2-5x2.5
Short wall 6 4.6 0.9 0.9 22.37 L=5.8-1.2=4.6
80.20m3 E
PART FF'LM
Column footing 2 2.5 1.2 0.9 5.4m3 C/C=5.2
wall foundation
(Mess Room)
long wall 2 2.7 0.9 0.9 4.37 m3 L=5.2-2.5=2.7
Short wall 2 3.8 0.9 0.9 6.16 m3 L=4.6-1.2=3.8
W.C. Room C/C=8.4
long wall 2 9.3 0.9 0.9 15.07 L=8.4+0.9=9.3
Short wall 5 0.8 0.9 0.9 3.24 m3 L=1.7-0.9=0.8
34.24 m3 F
GRAND TOTAL A+B+C+D+E+F 689.31m3
2 Cement Concrete
in the Wall
foundation with
1:8:16 proportion
PART
AA'BB'CC'DD'
long wall 4 12.5 0.9 0.3 13.50m3
Short wall 16 4.6 0.9 0.3 19.87 m3
AB'C'D' 2 9.0 0.9 0.3 4.86 m3
total 38.23 m3 A
PART EFGH
long wall 2 12.2 0.9 0.3 6.59
Short wall 2 7.95 0.9 0.3 4.29
Stair Room
long wall 2 3.6 46
0.9 0.3 1.94
Short wall 1 2.9 0.9 0.3 0.78 m3
F6 Wall 1 4.2 0.9 0.3 1.13 m3
1x1 13.5 0.9 0.3 3.65 m3
Total 18.38 m3 B
PART HIJK
Long Wall 2 21.7 0.9 0.3 11.72m3
Short Wall 8 4.6 0.9 0.3 9.94m3
W.C. Wall
long wall 1 6.75 0.9 0.3 1.82m3
Short wall 6 0.5 0.9 0.3 0.81 m3
BATHROOM
long wall 2 0.9 0.3 2.45 m3
Short wall 3 0.9 0.3 1.30 m3
Total 28.04 m3 C
PART LMND
long wall 2 19.9 0.9 0.3 10.75 m3
Short wall 9 4.6 0.9 0.3 11.19 m3
Total 21.94 m3 D
PART PQRS
long wall 2 15.7 0.9 0.3 8.48m3
Short wall 6 4.6 0.9 0.3 7.45 m3
Total 15.93 m3 E
PART FF'LM
long wall 2 2.7 0.9 0.3 1.47 m3
Short wall 2 3.8 0.9 0.3 2.48 m3
W.C. ROOM
long wall 2 9.3 0.9 0.3 5.02 m3
Short wall 5 0.8 0.9 0.3 1.08 m3
Total 10.05 m3 F
GRAND TOTAL A+B+C+D+E+F 132.57 m3
3. Reinforced Cement 47
Concrete work in
Column footing
with 1:1½:3
Proportion up to
plinth w/o
reinforced
column footing 111 2.5 1.2 0.9 299.7m3
column upto plenth 111 0.3 0.2 0.4 2.7m3
levels
Total 302.4 m3
4. B/W in foundation
up to PL with 1:6
Cement concrete
Ist footing
PART
AA'BB'CC'DD'
long Wall 4 12.5 0.6 0.2 6.0
Short Wall 16 4.6 0.6 0.2 8.83
AB'C'D Wall 2 9.0 0.6 0.2 2.16
Total 16.99m3 A
PART EFGH
long Wall 2 12.2 0.6 0.2 2.93m3
Short Wall 2 7.95 0.6 0.2 1.91 m3
Stair Room
long Wall 2 3.6 0.6 0.2 0.86 m3
Short Wall 1 2.9 0.6 0.2 0.357 m3
FG Wall 1 4.2 0.6 0.2 0.50 m3
1 13.5 0.6 0.2 1.62 m3 B
Total 8.17m3
PART HIJK
long Wall 2 21.7 0.6 0.2 5.21
Short Wall 8 4.6 48
0.6 0.2 4.42
W.C. Wall
long Wall 1 6.75 0.6 0.2 0.81
Short Wall 6 0.5 0.6 0.2 0.36
Bath Room
long Wall 2 4.9 0.6 0.2 1.18
Short Wall 6 0.8 0.6 0.2 0.58
Total 12.20m3 C
PART LMNO
long Wall 2 19.9 0.6 0.2 4.78
Short Wall 9 4.6 0.6 0.2 4.97
Total 9.75m3 D
PART PQRS
long Wall 2 15.7 0.6 0.2 3.77
Short Wall 6 4.6 0.6 0.2 3.31
Total 7.08m3 E
PART FF'LM
long Wall 2 2.7 0.6 0.2 0.65
Short Wall 2 3.8 0.6 0.2 0.91
Total 4.27m3 F
Grand Total A+B+C+D+E+F 58.46 m3
PART
A'A'BB'CC'DD'
long Wall
2nd footing 4 12.5 0.5 0.20 5.00
3rd footing 4 12.5 0.4 0.20 4.00
4rth footing (P.L.) 4 12.5 0.3 0.40 6.00
Short Wall
2nd footing 16 4.6 0.5 0.20 7.36
3rd footing 16 4.6 0.4 0.20 5.89
4rth footing 16 4.6 0.3 0.40 8.83
AB'C'D Wall
2nd footing 2 9.0 49
0.5 0.20 1.8
3rd footing 2 9.0 0.4 0.20 1.44
4rth footing 2 9.0 0.3 0.20 2.16
Total 42.48m3 A
PART EFGH
(Mess Room)
Long Wall
2nd footing 2 12.2 0.5 0.2 2.44
3rd footing 2 12.2 0.4 0.2 1.95
4rth footing 2 12.2 0.3 0.4 2.93
Short Wall
2nd footing 2 7.95 0.5 0.2 1.59
3rd footing 2 7.95 0.4 0.2 1.27
4rth footing 2 7.95 0.3 0.4 1.91
Stair Wall
Long Wall
2nd footing 2 3.6 0.5 0.2 0.72
3rd footing 2 3.6 0.4 0.2 0.58
4rth footing 2 3.6 0.3 0.4 0.86
Short Wall
2nd footing 1 2.9 0.5 0.2 0.29
3rd footing 1 0.29 0.4 0.2 0.23
4rth footing 1 2.9 0.3 0.4 0.35
FG Wall
2nd footing 1 4.2 0.5 0.2 0.42
3rd footing 1 4.2 0.4 0.2 0.34
50
4rth footing 1 4.2 0.3 0.4 0.50
P. Wall
2nd footing 1 13.5 0.5 0.2 1.35
3rd footing 1 13.5 0.4 0.2 1.08
4rth footing 1 13.5 0.3 0.4 1.62
Total 20.43m3
PART HIJK
long Wall
2nd footing 2 21.7 0.5 0.2 4.34
3rd footing 2 21.7 0.4 0.2 3.47
4rth footing 2 21.7 0.3 0.4 5.21
Short Wall
2nd footing 8 4.6 0.5 0.2 3.68
3rd footing 8 4.6 0.4 0.2 2.44
4rth footing 8 4.6 0.3 0.4 4.42
W.C. Wall
2nd footing 1 6.75 0.5 0.2 0.68
3rd footing 1 6.75 0.4 0.2 0.58
4rth footing 1 6.75 0.3 0.4 0.81
Short Wall
2nd footing 6 0.5 0.5 0.2 0.30
3rd footing 6 0.5 0.4 0.2 0.24
4rth footing 6 0.5 0.3 0.4 0.36
BATH ROOM
long Wall
2nd footing 2 4.9 0.5 0.2 0.98
3rd footing 2 4.9 0.4 0.2 0.78
4rth footing 2 4.9 0.3 0.4 1.18
Short Wall
2nd footing 6 0.8 0.5 0.2 0.98
3rd footing 6 0.8 0.4 0.2 0.78
4rth footing 6 0.8 0.3 0.4 1.18
BATHROOM
Long Wall
2nd footing 2 4.9 0.5 0.2 0.98
3rd footing 2 4.9 0.4 0.2 0.78
4rth footing 2 4.9 0.3 0.4 1.18
Short Wall 51
2nd footing 6 0.8 0.5 0.2 0.48
3rd footing 6 0.8 0.4 0.2 0.38
4rth footing 6 0.8 0.3 0.4 0.58
Total 31.37m3 C
PART LMND
Long Wall
2nd footing 2 19.9 0.5 0.2 3.98
3rd footing 2 19.9 0.4 0.2 3.18
4rth footing 2 19.9 0.3 0.4 4.78
Short Wall
2nd footing 9 4.6 0.5 0.2 4.14
3rd footing 9 4.6 0.4 0.2 3.31
4rth footing 9 4.6 0.3 0.4 4.97
Total 24.36m3 D
PART PQRS
Long Wall
2nd footing 2 15.7 0.5 0.2 3.14
3rd footing 2 15.7 0.4 0.2 2.41
4rth footing 2 15.7 0.3 0.4 3.77
Short Wall
2nd footing 6 4.6 0.5 0.2 2.76
3rd footing 6 4.6 0.4 0.2 2.21
4rth footing 6 4.6 0.3 0.4 3.31
Total 17.70 E
PART FFLM
Long Wall
2nd footing 2 2.7 0.5 0.2 0.54
3rd footing 2 2.7 0.4 0.2 0.43
4rth footing 2 2.7 0.3 0.4 0.65
Short Wall
2nd footing 2 3.8 0.5 0.2 0.76
3rd footing 2 3.8 52
0.4 0.2 0.61
4rth footing 2 3.8 0.3 0.4 0.91
6. RCC Work in
Column8 beams
and lintel with
1:1½:3 proportion
W/o reinforcement
PART
AA'BB'CC'DD'
Column 2x36 0.3 0.2 3.3 14.26 L=30+0.22=30.
2
Beam 2x4 30.2 0.3 0.34 24.64 L=5.8-0.3=5.5
2x16 5.5 0.3 0.34 17.94
2x2 10.0 0.3 0.34 13.80
lintel over door 12x2 1.5 0.2 0.12 0.86
lintel over window 24x2 1.5 0.2 0.12 1.72
lintel over 24x2 0.9 0.2 0.12 1.04
ventilator
lintel over almira 36x2 1.2 0.2 0.12 2.08 A
Total 76.36
PART EFGH
Column Beam 22x2 0.3 0.2 3.3 8.72 L=34.7+0.22=3
4.9
Doubly beam 2x2 34.9 0.3 0.34 14.24 L=9.4-0.229.2
Singly beam 5x2 9.2 0.3 0.34 9.38
(T.beam)
lintel over door 4x2 9.6 0.3 0.34 9.84
D1 2x2 1.8 0.2 0.12 0.18
D2 5x2 1.5 0.2
55 0.12 0.36
lintel Window 8x2 1.8 0.2 0.12 0.70
lintel over 8x2 0.9 0.2 0.12 0.34
Ventilator
Total 41.76 B
PART HIJK
Column 20x2 0.3 0.2 3.3 7.92 L=44.2-
0.1=44.01
Beam 2x2 44.1 0.3 0.34 18.00 L=5.8-0.22=5.6
8x2 5.6 0.3 0.34 9.14
lintel over door
D1 1x2 1.8 0.2 0.12 0.08
D2 7x2 1.5 0.2 0.12 0.50
lintel Window 14x2 1.5 0.2 0.12 1.02
lintel over 14x2 0.9 0.2 0.12 0.60
Ventilator
Total 37.26m3 C
PART LMNO
Column 19x2 0.3 0.2 3.3 7.52
Beam 2x2 41.1 0.3 0.34 16.76 L=39.9+0.2=41
1
9x2 5.6 0.3 0.34 10.28 L=5.8-0.2=5.6
lintel over door 9x2 1.5 0.2 0.12 0.64
lintel over Window 16x2 1.5 0.2 0.12 1.16
W1
W2 1x2 1.8 0.2 0.12 0.08
lintel Over Vent 17x2 0.9 0.2 0.12 0.74
lintel Almira A1 41x2 1.2 0.2 0.12 2.30
A1 2x2 1.5 0.2 0.12 0.14
Total 78.42m3 D
PART PQRS
Column 12x2 0.3 0.2 3.3 4.76
Beam 2x2 28 0.3 0.34 11.42 L=28.2-0.2=28
6x2 5.6 0.3
56 0.34 6.86
lintel Over door
D1 1x2 1.8 0.2 0.12 0.08
D2 4x2 1.5 0.2 0.12 0.30
LIntelOverWindow 9x2 1.5 0.2 0.12 0.69
LIntel Over Almira 12x2 1.2 0.2 0.12 0.70
Lintel Over vent 9x2 0.9 0.2 0.12 0.38
Total 25.14m3
PART FF'LM
Column 2x2 0.3 0.2 3.3 0.80
Beam 3x2 5.0 0.3 0.34 3.06
lintel Over door
D1 1x2 1.5 0.2 0.12 0.08
D2 10x2 1.05 0.2 0.12 0.50
LIntelOver 1x2 1.80 0.2 0.12 0.08
Window
Total 4.52m3
Grand Total A+B+C+D+E+F 263.96m3 F
7 Brick Work Super
Structure with 1:6
Cement send
morder
PART
AA'BB'CC'DD'
Long Wall 4x2 27.9 0.2 3.3 147.32 L=30-
7x0.3=27.9
Short Wall 16x2 5.6 0.2 3.3 118.28
Total 265.50m3 A
PART EFGH
Long Wall 2x2 32.0 0.2 3.3 84.48
Short Wall 2x2 9.0 0.2 3.3 23.76
Stair Room
Long Wall 2x2 4.1 0.2 3.3 10.82
Short Wall 1x2 3.6 0.2
57 3.3 4.76
FG Wall 1x2 8.6 0.2 3.3 11.36
Total 135.22m3
PART HIJK
Long Wall 2x2 39.5 0.2 3.3 104.28
Short Wall 8x2 5.6 0.2 3.3 59.14
W.C. Wall
Long Wall 1x2 7.1 0.2 3.3 4.38
Short Wall 6x2 1.2 0.2 3.3 9.50
BATHROOM
Long Wall 2x2 5.6 0.2 3.3 14.78
Short Wall 6x2 1.5 0.2 3.3 17.88
Total 315.88m3 C
PART LMNO
Long Wall 2x2 37.5 0.2 3.3 99.00
Short Wall 4x2 5.6 0.2 3.3 66.00
Total 165.52m D
3
PART PQRS
Long Wall 2x2 26.9 0.2 3.3 70.48
Short Wall 6x2 5.6 0.2 3.3 44.36
Total 114.84m3 E
PART FF'LM
Long Wall 2x2 4.9 0.2 3.3 12.44
Short Wall 2x2 4.4 0.2 3.3 11.62
W.C. Room
Long Wall 2x2 8.6 0.2 3.3 27.70
Short Wall 5x2 1.5 0.2 3.3 9.90
Total 57.16m3 F
Grand Total A+B+C+D+E+F 1054.12m3
Parafit Wall
Long Wall
Short Wall
58
Deduction of
Opening
Door D1 4x2 1.5 0.2 2.1 5.04
D2 36x2 1.2 0.2 2.1 36.28
D3 25x2 0.75 0.2 2.1 15.72
Total 4330.73m2
PART EFGH
Long Wall 1 32.0 8.82 282.24
Outer Side 3 31.6 8.82 836.14
Inner Side 5 9.2 8.82 405.72
Short Wall 1 19.6 8.82 84.67
Stair Room
long Wall (Both) 4 4.1 7.92 129.89
Short Wall
Outer Side 1 4.0 7.92 31.68
Inner Side 1 3.6 7.92 28.51
Beam
Singly Beam (both 8x2 9.2 0.34 50.05
Side)
Doubly beam (both 6x2 9.2 0.34 37.54
Side)
Celling 2 34 9.2 625.60
2486.04 cm2 B
PART HIJK
Long Wall
Outer Side 1 44.2 8.82 389.94 L=44.2-
8x0.2=42.6
Inner Side 3 42.6 7.92 1012.76
Short Wall
OuterSide 1 6.0 7.92 47.52
Inner Side 15 5.6 7.92 665.28
Celling 14 5.6 4.6 360.64
2 10.2 5.6 114.24
W.C. Room
Long Wall (Both 2 6.6 7.92 194.54
61
Side)
Short Wall (Both 12 1.2 7.92 114.05
Side)
BATHROOM
Long Wall 4 5.6 7.92 177.41
Short Wall 12 1.5 7.92 142.56
Total 3128.84m3
PART LMND
Long Wall
Outer Side 1 41.1 8.92 366.61
Inner Side 3 39.7 7.92 943.27
Celling 14 5.6 4.6 360.64
H. Morder Celling 2 7.1 5.6 79.52
Total 1750.04m2
PART PQRS
long Wall 2 28.0 8.92 499.52
2 26.8 7.92 424.51
Short Wall 12 5.6 7.92 532.22
Celling 8 5.6 4.6 206.08
2 5.6 3.6 40.32
Total 1702.65 E
Long Wall
Outer Side 1 5.0 - 8.92 44.6
Inner Side 3 4.8 7.92 114.05
Short Wall
OuterSide 1 4.4 8.92 39.25
Inner Side 2 4.2 7.92 66.53
BATH & OUTER
WALL
Long Wall 4 8.2 7.92 259.78 L=8.6-0.4=8.2
Short Wall 5 1.5 7.92 59.40
W.C.
Long Wall 2 4.8 62 7.92 76.03
Short Wall 4 1.2 7.92 38.02
Celling 2 12.3 4.8 118.08
Total 814.46m3 C
Grand Total A+B+C+D+E+F 14213.76m2
Deduction of
opening
Door D1 8 1.5 2.1 25.2
D2 72 1.2 2.1 181.44
D3 50 0.75 2.1 78.75
Window W1 20 1.5 1.2 36.00
W2 126 1.2 1.2 181.44
Ventilator 158 0.6 0.3 28.44
total -531.27m2
Net Total 14376.09m2
Varandah Celling 4 28 3.0 - 3340m2
357.6
Total 693.6m2
Net Total 14376.09
10 Earth work in
filling in Plinth
Area same as for
covered
Area/2 by celling 1 153 1.2 0.25 382.8m3
1..5 M Wide 1 28 1.5 0.25 10.5m3
opening
Total 78.66m3
11 Sand filling in 1 15 31.2 0.05 76.56
plinth with local
sand
1 28 1.5 0.05 2.10
78.66m3
12 7.5 cm lime 1 151.2 1.2 0.1 153.12
concrete base 82.5 63
cement concrete
brick ballast 40
mm
1 28 1.5 0.1 4.20
Total 157.32m3
13 Dislempering two 14213.76m2
coat with one coat
while washing,
Quantity same as
for Plaster in Item
No.
14 Wood Work
Door D1 8 1.5 2.1 25.2m2
D2 72 1.2 2.1 181.44m2
D3 50 0.75 2.1 78.75m2
Total 285.39m2
Window W1 20 1.5 1.2 36.00
W2 126 1.2 1.2 181.44
Total 217.44m2
Net Total 502.83m2
15 Glass Work in Vent 158 0.6 0.3 28.44m2
Total 28.44m2
16 Two coats Painting 1005.66m2
17 Steel Work in
Column, beam
slab, lintal and stair
case
1. Column
(a) column fooling
12mm
long side 10 2.4M 24 M
short side 6 1.1M 64 6.6 M
30.6
=3396.6M
Total 3022.97Kg
(b) Column Main 4 8.05 32.2
reinforcement 20 111 Nos
mm
3385.94
Total 744.91
Net Total 12596.14 126
Kg
(ii) beam (Doubly)
(a) Main bar texsile 3 119.2 357.6M
side 20mm
3 216.0 648.0 M
3 45.0 135.0 M
3 51.8 155.4 M
3 80.0 240.0 M
3 178.0 534.0 M
3 38.0 114.0 M
2184 M @2.47 Kg/M
=5394.48Kg
b. Main bar Comp 5 119.2 596.0
side 22mm
5 216.0 1080.0
5 45.0 225.0
5 51.0 259.0
5 80.0 400.00
5 178.0 890.0
5 38.0 190.0
3640M @2.98 Kg/M
=10847.2
Kg
c. Band stimurups 3235 1.272 65 4114.92M L=210.28+0.26
+24x0.08=1.27
1604.82Kg
Total 3569299
=357q
(iii) Single Beam 7.752 7850/100 6.09q 034x0.3x9.5x8=
x1 7.752
(iv)RCC Slabs & 370q
Sun shade case
0.8%
10q
Total 869.1q
Net Total 869.97q
66
COSTING
68
RATE ANALYSIS
EXCAVATION IN FOUNDATION
UNIT OF ANALYSIS - 100 m3
UNIT OF PAYMENT - Per Cu. Meter
S.No. Item No Unit Rate Per Cost Rs.
1 Material
2 Labour
Head ½ No 180 Day 90
Masion
Masion 1 No 160 Day 160
Mazdoor 35 No 100 Day 3500
3 Tools & L&S 100
Plants
TotalP 3850Rs
Adding Contractor profit 385.00
Grand Total 4235.00Rs
70
S.No. Item No Unit Rate Per Cost Rs.
1 Material
Cement 22.5 Cum 230 Bag 5175
Fine Sand 2.56 Cum 700 Cum 791
Stone Grit 5000 No. 1100 2816
170Kg 170.0 Kg 12 Kg 2040
Bitumen
2 Labour
Head ½ No 180 Day 90
Masion
Masion 2 No 160 Day 320
Mazdoor 24 No 100 Day 400
Bhists 4 No 100 Day 2400
Form 1 No 150 150
Work
3 Tools & 1 No 100 100
plants
TotalP 14282.00Rs
Add 1.5% Water charge 214.23
Add 1.0% contractor Charge 1428.20Rs
Rate =30876.85/10= 3087.65Rs 15924.48
Per m3
71
1ST CLASS BRICK WORK IN SUPERSTRUCTURE WITH (1:6) CEMENT
MORTER
UNIT OF ANALYSIS = 10M3
S.No. Item No Unit Rate Per Cost Rs.
1 Material
Brick 5000 4000 % 20000.00
Cement 13.5 Bag 230 Bag 3105.00
Sand 2.7 Cum 700 M3 1890.00
2 Labour
Head ½ No 180 Day 90
Masion
Masion 2 No 160 Day 1600
Mazdoor 24 No 100 Day 700
Bhists 4 No 100 Day 200
Form Work 1 No 150 1000
3 Tools & 1 No 100 300
plants
TotalP 14282.00Rs
Add 1.5% Water charge 214.23
Add 1.0% contractor Charge 1428.20Rs
Rate =30876.85/10= 3087.65Rs 15924.48
Per m3
UNIT OF ANALYSIS = 10 M3
S.No. Item No Unit Rate Per Cost Rs.
1 Material
Cement 84 Bag 230 day 19320.00
Course Sand 4.2 m3 1000 m3 4200.00
Stone Grid 8.4 m3 1100 m3 9240.00
Binding Wire 3.0 Kg 50.0 Kg 150.00
2 Labour
Head Masion 1/2 No 180 Day 90.00
Masion 6 No 160 Day 960.00
Mazdoor 30 No 100 Day 3000.00
Bhists 7 No 100 Day 700.00
3 Tools & plants - L&S 500 500
4. Shuttering
Wooden - L&S 1000 1000.00
Carpenter 10 No 170 Day 1700.00
Mazdoor 10 No 100 Day 1000.00
Total P 47860.00Rs
T&P L&S 200 200.00
5. Reinforcement
Bar cutting & 73
binding Smith
Mazdoor
Smith 8 No 170 Day 1360.00
Mazdoor 8 No 100 Day 800.00
T&P - L&P 50 50.00
Total 44270.00
Add 1.5% Water charge 664.05
Add 1.0% contractor Charge 4427.00Rs
Rate =4936.10 & Say 74.50 Rs 49361.05
Per m3
2.5 CM CEMENT FLOORING (1:2:4) WIH 7.5 CM LIME CONC BASE (1:6:12)
UNIT OF ANALYSIS = 100 Sq. Meter
S.No. Item No Unit Rate Per Cost Rs.
1 Material
Cement 42 Bag 230 day 9660.00
Course Sand 1.2 Cum 1000 m3 1200.00
Stone Grid 2.4 Cum 1100 m3 2640.00
Brick Ballast 7.2 Cum 900 m3 6480.00
Sand 3.6 Cum 700 m3 2520.00
2 Labour
Head Masion 2 No 180 Day 360.00
Masion 11 No 160 Day 1760.00
Mazdoor 32 No 100 Day 3200.00
Bhists 3 No 100 Day 300.00
3 Tools & plants - L&S 200 200
Total 28320.00
Add 1.5% Water charge 424.80
Add 1.0% contractor Charge 2832.00Rs
Rate =4936.10 & Say 74.50 Rs 31576.80
Per m3
76
PROJECT SCHEDULING
NETWORK PROGRAMMING
With the increasing complexity of large projects necessity for the planning and
scheduling is increasing. Projects such as hostel building where many
professions are involved a planning method which will benable manager. The
Critical with method involves or provides an up to date method of planning.
Developed a few years ago in the western centuries is new being extensively
used in planning of projects and controlling the execution of the various part
and works.
The Main advantages of the CRITICAL PATH METHOD are simplicity
flexibility and over all control. It is a most usefull for management of a project
critical prath method is a net work technique for planning execution and
controll over a project. the use of this technique is specially usefull for
management of a project critical path method is a net work technique for
planning execution and control over a project. The use of this technique is
specially usefull .
In Civil Engineering in analying each project in Several activity groups and
thus tracing the activity points where battenek can actually rise promp rexedial
action in the spotting of bottle necks and removal help in completion of a civil
Engg. project in time with in the estirates cost application of network planning
and scheduling. Technique better described as critical path method and
programme evolution and review technique has because scope in existing
completion of vcivil Engg. project in time and within cast review of scaree
resources and scheduing is new unable Since time is mong completion of
projects. In time because a must incivil Engineering proejct.
In determining the date completion of any civil project like hostel building. It is
not only necessary to prepare any estimate of cost but also are estimate are plan
of various activities envolved for the completion of each activity network
scheduling and planning technique is a study of these activities in relation to
toal project time.
77
OBJECTIVE OF NETWORK PLANNING AND SCHEDULING
TECHNIQUES
For the success of any project. It is necessary that the objectives and time
scheduling should be defined with reference to allianable target taking into
account all the problems and difficulties which many be existing at the time of
drawing up the plane on drawing the course of Construction period tNetwork
planning and scheduling technique needs an efficient integerated Management
requiring.
(1) Detailed integrated planning of the project task to be accomplished.
(2) Developing realistic excersing effective control which requires
periodic checking and evolution of presness on the project
completion time and taking any action required in time.
(3) The secure resource time and money planning analysis and
scheduling and controlling are three district phases by which the
objective can be affectived. The basic principle and Mechanics of
network technique is the application of planning analysis and
scheduling and controlling of event and activities involved in a
project in relation to time and interpendence of each activity.
PLANNING A NETWORK :-
The base phases as suffested earlier of network analysis are planning analysing
and controlling of each event and activity in relation to time and interpredence
of each activity a controution project can be spilt into a number of events and
activities planning of project essentially Mvalues a detailed planning.
79
NETWORK DIAGRAM HOSTEL BUILDING
THE SCHEDULE
Once a project is planned in teams of event and activities. It is necessary to
plan time required for completing each activity time requened for completing
each job has to fixed with reference to attainable factors a short time as to long
time will provide realistic time duration has to fixed with reference to
experience general availability of men and Materials and completion of
procedence after time duration of each activity is eslimated the earliest and
even time for each activity can be estimated by adding up durations of various
activity.
80
ANALYSING THE NETWORK
Total project time is the shortlest time in which project can be completed . This is
determind by a sequence of activities known as critical path for constuction of Hostal
Building time schedule can be allotted in the following way.
Event No. Activity Activity Particular No. of Days
Symbol
1-2 A Study Plan layout 1
2-3 B Clearance of Site 2
3-4 C Earth Work 12
2-4 D Procurement of time Sand 4
Cement and Concrete
4-5 E Laying of Foundation 15
2-5 F Procurment of Bricks 25
5-8 G Laying Conduit pipe for 15
electrical waves
5-6 H(1) Erection of Building 40
6-8 H(2) Laying Electrical Wire 5
5-7 I(1) Laying of Drain and Draige 15
System
7-8 I(2) Concept building to electrical 5
8-9 I City and Water 12
9-10 K Finishing
Graphic presentation of the Network and time alloted will appear as below :
Network Diagram Hostel Building Critical Path
Notes :- (i) Arrow indicates sequence of activity
(ii) Circle and number indicate event and sequence of events.
(iii) Alphabet Symbol A to K indicate each activity in Sequence
(iv) Thick black line indicate critical path
(v) Rectangular Indicate earliest event time
(vi) Triangular indicate latest event time
81
(vii) Activity symbol D.F.H. and I are non critical (FLOAT) activities. The
diagram indicates the following term as used in the network planning and
scheduling technique very clearly.
CRITICAL PATH
It is represented by a thick time indicates the line of sequence of activity which
must be completed on scheduling any delay on the critical path activity will
cause delay in other activity
TOTAL PROJECT TIME
This is total of all activities following in the criical which has been shown in
this black times activity which are not an critical path are important but not
erictied to the activities following with in the critical path
ARROWS
These represent the sequence of activity an completion of which the entire
project can be completed.
CIRCLES NDS
The symbol by which each event is represented
REFERENCE CALENDER
After the network diagram has been known latest and earliest event time
determined critical path. Slep have to be taken to mark the olates an calender
for the completion of each activity
PROJECT SCHEDULING
In this project is divided into different operations All the operations are put in a
sequence after knowing their inter relationship. The suitable time for the
completion of project is predecided.
BAR CHART
PESSIMISTIC TIME
The estimate of maximum time taken by an activity if thene is a delay at every
stage except natural calamities is called pessimistic time.
86
CONCLUSIONS AND RECOMMENDATION
This project on hostel building has been done by the working stress Method in
which concrete and steelis considered clastic. Permissible are working stress in
comcrete and steel are based on factor of safety modular ratio concepts also
used in this Method. The actual stresses developed in structure at the working
loads after differed comparably from theoretical values. The reasons is that the
assumption that concrete is a perfectly clastic method is not correct in this
Method. The section designed are larger. This they are quite expensive.
In planning have considered the various factors affecting the planning. A brief
idea regarding them has been explained to have a generalize over it ventilation
in the room has been given the prime.
Importance more over ideas from Vaslush astra has also been in corporated for
continuous Water and clear supply planning has been done Drainage Systems
has also been considered during planning in estimating and casting latest
schedule of rates are taken as per P.W.D. estimation has been done as per the
decision and drawing the hostel building Attempt has been made to cover
aspect of the work.
Considering the importance of computer in to days fast moving wantd. In these
dimension of view of a room been given to show how these.
In Survey various tools that are used are taken attempt has been made to given
brief idea of the tools and the process through which the work has been done.
However, is recommended that it would have been better if the project has been
completed thraish limit state method as this method is pusely bassed upon the
principle of elasticity. This method is less expensive. In planning more ideas
can be put regarding vastushastra. In continuous. With this it is recommended
that three dimensional view of the hostal building can be given and in
Surveying Modern instrument and techniques have been employed for
completing the survey work.
87
BIBLIOGRAPHY
88
DRAWINGS
PROJECT WORK