Analisa Harga Satuan Bahan Dan Upah Tenaga Berdasarkan Sni Tahun Anggaran 2011 Kota Probolinggo
Analisa Harga Satuan Bahan Dan Upah Tenaga Berdasarkan Sni Tahun Anggaran 2011 Kota Probolinggo
BERDASARKAN SNI
TAHUN ANGGARAN 2011
KOTA PROBOLINGGO
IV PEKERJAAN PLESTERAN
1 1 m2 Plesteran 1 Pc : 2 Ps, tebal 15 mm
- Semen Portland 10.224 Kg 1,495.00 15,284.88
- Pasir Pasang 0.020 M3 90,400.00 1,808.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 46,867.88
2 1 m2 Plesteran 1 Pc : 3 Ps, tebal 15 mm
- Semen Portland 7.776 Kg 1,495.00 11,625.12
- Pasir Pasang 0.023 M3 90,400.00 2,079.20
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 43,479.32
3 1 m2 Plesteran Halus 1 Pc : 5 Ps, tebal 15 mm
- Semen Portland 5.184 Kg 1,495.00 7,750.08
- Pasir Pasang 0.026 M3 90,400.00 2,350.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 39,875.48
4 1 m2 Plesteran Halus 1 Pc : 6 Ps, tebal 15 mm
- Semen Portland 4.416 Kg 1,495.00 6,601.92
- Pasir Pasang 0.027 M3 90,400.00 2,440.80
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 38,817.72
5 1 m2 Plesteran 1 Pc : 8 Ps, tebal 15 mm
1 2 3 4 5 6 7
- Semen Portland 3.456 Kg 1,495.00 5,166.72
- Pasir Pasang 0.029 M3 90,400.00 2,621.60
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 37,563.32
6 1 m2 Plesteran 1 Pc : 2 Ps, tebal 20 mm
- Semen Portland 13.632 Kg 1,495.00 20,379.84
- Pasir Pasang 0.027 M3 90,400.00 2,440.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.0220 Oh 100,000.00 2,200.00 62,720.64
1 2 3 4 5 6 7
7 1 m2 Plesteran 1 Pc : 3 Ps, tebal 20 mm
- Semen Portland 10.368 Kg 1,495.00 15,500.16
- Pasir Pasang 0.031 M3 90,400.00 2,802.40
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.0220 Oh 100,000.00 2,200.00 58,202.56
8 1 m2 Plesteran Halus 1 Pc : 5 Ps, tebal 20 mm
- Semen Portland 6.912 Kg 1,495.00 10,333.44
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.022 Oh 100,000.00 2,200.00 53,397.44
9 1 m2 Plesteran Ciprat 1 Pc : 2 Ps
- Semen Portland 4.320 Kg 1,495.00 6,458.40
- Pasir Pasang 0.006 M3 90,400.00 542.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 32,850.80
10 1 m2 Finishing Siar Pas. Dinding
- Semen Portland 3.108 Kg 1,495.00 4,646.46
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Batu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00 19,626.46
11 1 m2 Finishing Siar 1 Pc : 2 Ps, Pas. Batu Kali
- Semen Portland 6.340 Kg 1,495.00 9,478.30
- Pasir Pasang 0.012 M3 90,400.00 1,084.80
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 40,338.10
12 1 m2 Acian
- Semen Portland 3.250 Kg 1,495.00 4,858.75
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 24,708.75
13 1 m1 Benangan
- Semen Portland 1.440 Kg 1,495.00 2,152.80
- Pasir Pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 0.105 Oh 55,000.00 5,775.00
~ Tukang Batu 0.049 Oh 70,000.00 3,430.00
~ Kepala Tukang 0.005 Oh 85,000.00 416.50
~ Mandor 0.006 Oh 100,000.00 560.00 13,238.30
14 1 m1 Tali air
- Semen Portland 0.600 Kg 1,495.00 897.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.033 Oh 70,000.00 2,286.67
~ Kepala Tukang 0.003 Oh 85,000.00 277.67
~ Mandor 0.004 Oh 100,000.00 373.33 7,684.67
V PEKERJAAN LANTAI
1 2 3 4 5 6 7
1 1 m2 Pasang Lantai Keramik 30 X 30 cm Putih KW I
- Keramik 30 x 30 cm 1.080 M2 36,300.00 39,204.00
- Semen Portland 10.000 Kg 1,495.00 14,950.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 107,659.50
1 2 3 4 5 6 7
2 1 m2 Pasang Lantai Keramik 40 x 40 cm putih KW I
- Keramik 40 x 40 cm 1.105 M2 45,500.00 50,277.50
- Semen Portland 9.800 Kg 1,495.00 14,651.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 116,474.00
3 1 m2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm
- Keramik 20 x 20 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 10.400 Kg 1,495.00 15,548.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 123,908.50
4 1 m2 Pasang Lantai Keramik 30 x 30 cm Warna KW I
- Keramik 30 x 30 cm 1.080 M2 48,900.00 52,812.00
- Semen Portland 10.000 Kg 1,495.00 14,950.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 121,267.50
5 1 m2 Pasang Lantai Keramik 30 x 30 cm Motif Kasar KW1
- Keramik 30 x 30 cm Kasar 1.080 M2 52,900.00 57,132.00
- Semen Portland 10.000 Kg 1,495.00 14,950.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 125,587.50
6 1 m2 Pasang Lantai Keramik 40 x 40 cm warna KW I
- Keramik 40 x 40 cm 1.105 M2 57,500.00 63,537.50
- Semen Portland 9.800 Kg 1,495.00 14,651.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 129,734.00
7 1 m2 Pasang Keramik Dinding 20 x 25 cm putih KW I
- Keramik 20 x 25 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 9.300 Kg 1,495.00 13,903.50
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00 129,748.20
8 1 m2 Pasang Keramik Dinding 20 x 25 cm warna KW I
- Keramik 20 x 25 cm 1.060 M2 55,200.00 58,512.00
- Semen Portland 9.300 Kg 1,495.00 13,903.50
1 2 3 4 5 6 7
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00 133,405.20
9 1 m1 Pasang List Keramik Dinding 5 x 20 cm warna KW I
- List Keramik 5 x 20 cm 5.300 bh 3,500.00 18,550.00
- Semen Portland 0.493 Kg 1,495.00 736.89
- Pasir Pasang 0.0010 M3 90,400.00 90.40
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.048 Oh 55,000.00 2,623.50
~ Tukang Batu 0.024 Oh 70,000.00 1,666.00
~ Kepala Tukang 0.002 Oh 85,000.00 204.00
~ Mandor 0.0024 Oh 100,000.00 240.00 38,810.79
1 2 3 4 5 6 7
10 1 m2 Pasang Lantai Tegel Abu-abu
- Tegel Abu-abu 1.060 M2 46,000.00 48,760.00
- Semen Portland 10.400 Kg 1,495.00 15,548.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Upah Pekerjaan
~ Pekerja 0.270 Oh 55,000.00 14,850.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.014 Oh 85,000.00 1,190.00
~ Mandor 0.0140 Oh 100,000.00 1,400.00 95,266.00
11 1 m2 Pasang Batu Alam Candi
- Batu Alam Candi 1.100 M2 115,000.00 126,500.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 181,967.75
12 1 m2 Pasang Batu Alam Garis
- Batu Alam Garis 1.100 M2 109,250.00 120,175.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 175,642.75
13 1 m2 Pasang Batu Alam Koral/Ampyang
- Batu Alam Koral/Ampyang 1.100 M2 23,000.00 25,300.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 80,767.75
14 1 m2 Pasang Batu Alam Palimanan, Sukabumi, Lempeng 10/10
- Batu Alam Palimanan 1.100 M2 103,500.00 113,850.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 169,317.75
15 1 m2 Pasang Batu Alam Lempeng/Piring
- Batu Alam Lempeng 1.100 M2 28,750.00 31,625.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 87,092.75
16 1 Bh Pasang Glass Block
- Glass Block 1.000 Bh 20,700.00 20,700.00
- Semen Portland 0.150 kg 1,495.00 224.25
- Upah Pekerjaan 1.000 ls 3,000.00 3,000.00 23,924.25
17 1 m2 Pasang Wall covering lebar 50 cm
- Vinyl wall covering, lebar 50 cm 2.200 M 70,000.00 154,000.00
- Lem 0.250 Kg 12,500.00 3,125.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
1 2 3 4 5 6 7
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.170 Oh 85,000.00 14,450.00
~ Mandor 0.0200 Oh 100,000.00 2,000.00 205,075.00
VI PEKERJAAN ATAP
1 1 m3 Pasang Konstruksi Kuda-kuda Ekspose Kayu Jati ( Klas I)
- Kayu Jati, balok 1.200 M3 16,100,000.00 19,320,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 6.700 Oh 55,000.00 368,500.00
~ Tukang Kayu 20.100 Oh 70,000.00 1,407,000.00
~ Kepala Tukang 2.010 Oh 85,000.00 170,850.00
~ Mandor 0.335 Oh 100,000.00 33,500.00 21,577,850.00
1 2 3 4 5 6 7
2 1 m3 Pasang Konstruksi Kuda-kuda Kayu Jati ( Klas I)
- Kayu Jati, balok 1.100 M3 16,100,000.00 17,710,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 19,170,000.00
4 1 m3 Pasang Konstruksi Kuda-kuda Kayu Meranti Asli (MA)
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 8,291,000.00
5 1 m3 Pasang Konstruksi Kuda-kuda Kayu Kruing
- Kayu Kruing, balok 1.100 M3 5,750,000.00 6,325,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 7,785,000.00
6 1 m3 Pasang Konstruksi Gording Kayu Kruing
- Kayu Kruing, balok 1.100 M3 5,750,000.00 6,325,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 3.00 Kg 17,500.00 52,500.00
- Upah Pekerjaan
~ Pekerja 2.400 Oh 55,000.00 132,000.00
~ Tukang Kayu 7.200 Oh 70,000.00 504,000.00
~ Kepala Tukang 0.720 Oh 85,000.00 61,200.00
~ Mandor 0.120 Oh 100,000.00 12,000.00 7,266,700.00
7 1 m3 Pasang Konstruksi Gording Kayu Meranti Asli (MA)
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 3.00 Kg 17,500.00 52,500.00
- Upah Pekerjaan
~ Pekerja 2.400 Oh 55,000.00 132,000.00
~ Tukang Kayu 7.200 Oh 70,000.00 504,000.00
~ Kepala Tukang 0.720 Oh 85,000.00 61,200.00
~ Mandor 0.120 Oh 100,000.00 12,000.00 7,772,700.00
8 1 m2 Pasang Kaso (5/7) + Reng (2/3) Kayu Kruing
- Kayu Kruing, balok 0.010 M3 5,750,000.00 57,500.00
- Kayu Kruing, balok 0.004 M3 5,750,000.00 23,000.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 98,725.00
9 1 m2 Pasang Kaso (5/7) + Reng (2/3) Kayu Meranti (MA)
- Kayu Meranti. Balok 0.010 M3 6,210,000.00 62,100.00
- Kayu Meranti, balok 0.004 M3 6,210,000.00 24,840.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 105,165.00
1 2 3 4 5 6 7
10 1 m2 Pasang Kaso (5/7) Kruing + Reng (2/3) Kayu Meranti MA
- Kayu Kruing, balok 0.010 M3 5,750,000.00 57,500.00
- Kayu Meranti, balok 0.004 M3 6,210,000.00 24,840.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 100,565.00
11 1 m2 Pasang Kaso (5/7) Kayu Kruing
- Kayu Meranti, balok 0.0100 M3 5,750,000.00 57,500.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 66,612.50
1 2 3 4 5 6 7
12 1 m2 Pasang Kaso (5/7) Kayu Meranti MA
- Kayu Meranti, balok 0.0100 M3 6,210,000.00 62,100.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 71,212.50
13 1 m2 Reng (2/3) Kayu Meranti MA
- Kayu Meranti, balok 0.004 M3 6,210,000.00 22,356.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 31,468.50
14 1 m2 Reng (3/5) Kayu Meranti MA
- Kayu Meranti, balok MA 0.008 M3 6,210,000.00 49,680.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 58,792.50
15 1 m2 Reng (2/3) Kayu Meranti MC
- Kayu Meranti, balok 0.004 M3 4,025,000.00 14,490.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 23,602.50
16 1 m2 Reng (3/5) Kayu Meranti MC
- Kayu Meranti, balok MC 0.008 M3 4,025,000.00 32,200.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 41,312.50
17 1 m2 Pasang Atap Genteng Karang Pilang besar
- Genteng Karang Pilang 13.500 Bh 5,750.00 77,625.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.008 Oh 100,000.00 800.00 91,385.00
18 1 m2 Pasang Atap Genteng Model Karang Pilang (ex Ambulu)
- Genteng model Karang Pilang 25.000 Bh 2,550.00 63,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00 78,730.00
19 1 m2 Pasang Atap Genteng Pres Kedung Bajul (biasa)
- Genteng Pres Kedung Bajul 25.000 Bh 1,500.00 37,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00 52,480.00
20 1 m2 Pasang Atap Genteng Beton
- Genteng Beton 11.000 Bh 5,750.00 63,250.00
1 2 3 4 5 6 7
- Paku 0.030 Kg 17,500.00 525.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.008 Oh 100,000.00 800.00 77,535.00
21 1 m Pasang Bubung Genteng Karang Pilang
- Genteng bubung karang pilang 5.000 Bh 6,900.00 34,500.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 87,252.80
1 2 3 4 5 6 7
22 1 m Pasang Bubung Genteng Model Karang Pilang
- Genteng bubung model karang pilang 5.000 Bh 5,750.00 28,750.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 81,502.80
23 1 m Pasang Bubung Pres Kedung Bajul
- Genteng Bubung pres kedung bajul 5.000 Bh 4,050.00 20,250.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 73,002.80
24 1 m Pasang Bubung Pres Beton
- Genteng Bubung beton 4.000 Bh 8,650.00 34,600.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 87,352.80
25 1 m Pasang Bubung Asbes Gelombang kecil
- Asbes Bubung Gelombang 1.000 m 32,800.00 32,800.00
- Paku Sekrup 2.000 bj 1,750.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.084 Oh 55,000.00 4,620.00
~ Tukang Kayu 0.125 Oh 70,000.00 8,750.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,105.00
~ Mandor 0.004 Oh 100,000.00 400.00 51,175.00
1 m Pasang Bubung Asbes Gelombang besar
- Asbes Bubung Gelombang 1.000 m 57,000.00 57,000.00
- Paku Sekrup 2.000 bj 1,750.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.084 Oh 55,000.00 4,620.00
~ Tukang Kayu 0.125 Oh 70,000.00 8,750.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,105.00
~ Mandor 0.004 Oh 100,000.00 400.00 75,375.00
26 1 m2 Pasang Atap Asbes Gelombang 4 mm (Kecil)
- Asbes Gelombang kecil 0.750 Lbr 34,500.00 25,875.00
- Paku Pancing 0.120 Kg 23,000.00 2,760.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 42,530.00
27 1 m2 Pasang Atap Asbes Gelombang 6 mm (Besar)
- Asbes Gelombang besar 0.570 Lbr 79,100.00 45,087.00
- Paku Pancing 0.120 Kg 23,000.00 2,760.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 61,532.00
28 1 m2 Pasang Atap Seng Gelombang BJLS 30
- Seng Gelombang 0.700 Lbr 74,750.00 52,325.00
- Paku Pancing 0.020 Kg 23,000.00 460.00
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.120 Oh 55,000.00 6,600.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.006 Oh 100,000.00 600.00 64,695.00
29 1 m2 Pasang Atap Nok Seng
- Seng Plat BJLS 30 3x6 0.300 Lbr 45,450.00 13,635.00
- Paku Biasa 0.040 Kg 23,000.00 920.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.006 Oh 100,000.00 600.00 28,985.00
1 2 3 4 5 6 7
30 1 m2 Pasang Fiberglass Gelombang
- Fiberglass Gelombang 1.100 M2 86,250.00 94,875.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 109,435.00
31 1 m2 Pasang Fiberglass datar
- Fiberglass datar 1.100 M2 40,250.00 44,275.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 58,835.00
30 1 Kg Pasang rangka atap baja WF
- Besi Profil WF 1.150 Kg 13,300.00 15,295.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 23,605.00
31 1 Kg Pasang Cannal C baja
- Besi Profil Cannal C 1.150 Kg 12,600.00 14,490.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 22,800.00
32 1 Kg Pasang Siku L baja
- Besi Profil Siku L 1.150 Kg 12,000.00 13,800.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 22,110.00
33 100 Kg Pekerjaan Perakitan
- Solar 1.000 Ltr 4,500.00 4,500.00
- Minyak Pelumas 0.100 Ltr 42,600.00 4,260.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Las 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.005 Oh 100,000.00 500.00
- Alat
~ Mesin Las 0.8 Jam 38,100.00 30,480.00 52,325.00
34 10 cm Pekerjaan Pengelasan
- Kawat Las Listrik 0.400 Kg 28,750.00 11,500.00
- Solar 0.300 Ltr 4,500.00 1,350.00
- Minyak Pelumas 0.040 Ltr 42,600.00 1,704.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Las 0.020 Oh 70,000.00 1,400.00
~ Kepala Tukang 0.002 Oh 85,000.00 170.00
~ Mandor 0.002 Oh 100,000.00 200.00
- Alat
~ Mesin Las 0.170 Jam 38,100.00 6,477.00 25,001.00
35 1 Kg Pasang Plat Ezyer baja Tebal 8 s/d 22 mm
- Besi Plat Ezyer 1.000 Kg 12,000.00 12,000.00
- Kawat las/Electroda (Perlengkapan) 0.020 Kg 28,750.00 575.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
1 2 3 4 5 6 7
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Tukang Las / welder 0.050 Oh 70,000.00 3,500.00
- Alat
~ Mesin Las 0.01 Jam 38,100.00 381.00
~ Genset 0.01 Jam 81,000.00 810.00 23,516.00
1 2 3 4 5 6 7
36 1 Bh Pasang Trektank (Jarum keras)
- Treaktank 1.000 Bh 31,700.00 31,700.00
- Perlengkapan 10.000 % 3,170.00 31,700.00
- Upah Pekerjaan
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Mandor 0.050 Oh 70,000.00 3,500.00 70,400.00
37 1 Kg Pasang Beton Ezyer Regel
- Besi Beton Ezyer 1.000 Kg 11,800.00 11,800.00
- Kawat las/Electroda (Perlengkapan) 0.100 Kg 28,750.00 2,875.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Tukang Las / welder 0.050 Oh 70,000.00 3,500.00
- Alat
~ Mesin Las 0.01 Jam 38,100.00 381.00
~ Genset 0.01 Jam 81,000.00 810.00 25,616.00
38 1 m' Pasang Lisplank ukuran (3x20) cm, Kayu jati
- Kayu Jati, Papan 0.0108 M3 16,675,000.00 180,090.00
- Paku Biasa 2" - 5" 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 203,540.00
39 1 m' Pasang Lisplank ukuran (3x20) cm, Kayu Kamper
- Kayu Kamper, Papan 0.0108 M3 0.00 -
- Paku Biasa 2" - 5" 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 23,450.00
40 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Jati
- Kayu Jati, Papan 0.011 M3 16,675,000.00 183,425.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 206,000.00
41 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Kamper
- Kayu Kamper, Papan 0.011 M3 0.00 -
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 22,575.00
42 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Meranti (MA)
- Kayu Meranti, Papan 0.011 M3 6,250,000.00 68,750.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 91,325.00
43 1 m' Pasang Lisplank ukuran 2x(3x20) cm, Kayu Kamper (Atas bawah)
- Kayu Kamper, Papan 0.0145 M3 0.00 -
- Paku Biasa 2" - 5" 0.060 Kg 17,500.00 1,050.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.450 Oh 70,000.00 31,500.00
~ Kepala Tukang 0.045 Oh 85,000.00 3,825.00
1 2 3 4 5 6 7
~ Mandor 0.075 Oh 100,000.00 7,500.00 52,125.00
44 1 m' Pasang Lisplank ukuran (2x20) cm, Kayu Meranti (MA)
- Kayu Meranti, Papan 0.0040 M3 6,250,000.00 25,000.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.005 Oh 100,000.00 500.00 48,000.00
1 2 3 4 5 6 7
45 1 m' Pasang Lisplank ukuran (2x20) cm, Kayu Meranti (MC)
- Kayu Meranti, Papan 0.0040 M3 4,400,000.00 17,600.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.005 Oh 100,000.00 500.00 40,600.00
46 1 m' Pasang Lisplank Kalsium ukuran 20 cm tebal 8 mm
- Kalsium Plank 1.000 M1 14,400.00 14,400.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Kayu Meranti 3/5 0.004 M3 4,025,000.00 15,697.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,062.50
~ Mandor 0.003 Oh 100,000.00 250.00 42,035.00
47 1 m' Pasang Lisplank Kalsium ukuran 30 cm tebal 8 mm
- Kalsium Plank 1.000 M1 17,250.00 17,250.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Kayu Meranti 3/5 0.005 M3 4,025,000.00 18,112.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,062.50
~ Mandor 0.003 Oh 100,000.00 250.00 47,300.00
48 1 M' Pasang talang datar, seng BJLS 30
- Seng Plat BJLS 30 (90 cm) 1.050 M1 45,450.00 47,722.50
- Paku biasa 0.015 Kg 17,500.00 262.50
- Kayu Meranti (MA), papan 0.0096 M3 6,250,000.00 60,000.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.400 Oh 70,000.00 28,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.01 Oh 100,000.00 1,000.00 150,110.00
49 1 M' Pasang talang U PVC 15 x 15
- Talang U PVC 15 1.050 M1 26,562.50 27,890.63
- Plat Strip 0.146 kg 12,000.00 1,753.92
- Paku 0.015 Kg 17,500.00 262.50
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Besi 0.400 Oh 70,000.00 28,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.01 Oh 100,000.00 1,000.00 72,032.05
50 1 m2 Pasang Atap Polycarbonat
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Perlengkapan 1.000 ls 5,000.00 5,000.00
- Upah Pekerjaan 1.000 ls 30,000.00 30,000.00 161,500.00
51 1 m2 Pasang Atap Polycarbonat rangka pipa gas/besi kotak
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Gas + Pengecatan 1.000 ls 240,000.00 240,000.00
- Upah Pekerjaan 1.000 ls 70,000.00 70,000.00 436,500.00
52 1 m2 Pasang Atap Polycarbonat rangka pipa air
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Air + Pengecatan 1.000 ls 276,000.00 276,000.00
- Upah Pekerjaan 1.000 ls 70,000.00 70,000.00 472,500.00
53 1 m2 Pasang Atap Polycarbonat rangka pipa stainless
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Stainless 1.000 ls 396,000.00 396,000.00
- Upah Pekerjaan 1.000 ls 70,000.00 70,000.00 592,500.00
54 1 m' Papan Roiter 2/20
- Kayu meranti, papan 0.004 M3 4,370,000.00 17,480.00
- Paku 0.050 Kg 17,500.00 875.00
1 2 3 4 5 6 7
- Upah Pekerjaan 1.000 Ls 10,000.00 10,000.00 28,355.00
55 1 m' Papan Kompres kayu Meranti (MA)
- Kayu Meranti, papan 0.003 M3 6,900,000.00 20,700.00
- Seng BJLS 30 0.250 m2 26,562.50 6,640.63
- Paku 0.100 Kg 23,000.00 2,300.00
- Upah Pekerjaan 1.000 Ls 12,500.00 12,500.00 42,140.63
56 1 m' Papan Kompres kayu Meranti (MC)
- Kayu Meranti, papan 0.003 M3 4,370,000.00 13,110.00
- Seng BJLS 30 0.250 m2 26,562.50 6,640.63
- Paku 0.100 Kg 23,000.00 2,300.00
- Upah Pekerjaan 1.000 Ls 12,500.00 12,500.00 34,550.63
PEKERJAAN
X PENGECATAN
1 1 m2 mendempul dan menggosok kayu
- Plamir Kayu 0.080 Kg 31,600.00 2,528.00
- Minyak Cat 0.020 kg 26,450.00 529.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Cat 0.040 Oh 70,000.00 2,800.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.0025 Oh 100,000.00 250.00 8,682.00
2 1 m2 Pengecatan bidang kayu lama
- Cat Kayu 0.142 Kg 55,000.00 7,810.00
- Minyak cat 0.019 Lt 26,450.00 502.55
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 18,300.05
3 1 m2 Pengecatan bidang kayu baru
- Cat Kayu 0.260 Kg 55,000.00 14,300.00
- Plamir 0.150 Kg 31,600.00 4,740.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 35,402.50
4 1 m2 Pengecatan besi baru
- Cat besi Emco 0.260 Kg 55,000.00 14,300.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Plamir 0.150 Kg 31,600.00 4,740.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 35,402.50
1 2 3 4 5 6 7
5 1 m2 Pengecatan besi Finishing baru (Tanpa Cat dasar)
- Cat besi Emco Finishing ( 3 Lapis ) 0.260 Kg 55,000.00 14,300.00
- Upah Pekerjaan
~ Pekerja 0.035 Oh 55,000.00 1,925.00
~ Tukang Cat 0.053 Oh 70,000.00 3,710.00
~ Kepala Tukang 0.0020 Oh 85,000.00 170.00
~ Mandor 0.0013 Oh 100,000.00 130.00 20,235.00
1 2 3 4 5 6 7
6 1 m2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
- Residu atau Ter 0.350 Ltr 16,350.00 5,722.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Mandor 0.006 Oh 100,000.00 600.00 11,822.50
7 1 m2 Pelaburan Bidang Kayu dengan Politur
- Politur 0.372 Ltr 66,700.00 24,812.40
- Ampelas 2.000 Lbr 3,500.00 7,000.00
- Upah Pekerjaan
~ Tukang Cat 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00 37,622.40
8 1 m2 Pelaburan Bidang Kayu dengan Vernis
- Vernis 0.150 Ltr 88,550.00 13,282.50
- Dempul 0.050 Kg 31,600.00 1,580.00
- Ampelas 0.100 Lbr 3,500.00 350.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.160 Oh 55,000.00 8,800.00
~ Tukang Cat 0.160 Oh 70,000.00 11,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00 36,995.00
9 1 m2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis cat Penutup)
- Plamir 0.100 Kg 17,250.00 1,725.00
- Cat Dasar 0.100 Kg 23,000.00 2,300.00
- Cat Penutup 2x 0.260 Kg 23,000.00 5,980.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.063 Oh 70,000.00 4,410.00
~ Kepala Tukang 0.0063 Oh 85,000.00 535.50
~ Mandor 0.0025 Oh 100,000.00 250.00 16,300.50
10 1 m2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar, 2 x pengecatan)
- Cat Dasar 0.120 Kg 23,000.00 2,760.00
- Cat Penutup 2x 0.180 Kg 23,000.00 4,140.00
- Upah Pekerjaan
~ Pekerja 0.028 Oh 55,000.00 1,540.00
~ Tukang Cat 0.042 Oh 70,000.00 2,940.00
~ Kepala Tukang 0.0042 Oh 85,000.00 357.00
~ Mandor 0.0025 Oh 100,000.00 250.00 11,987.00
11 1 m2 Pengecatan permukaan baja dengan meni besi
- Meni Besi 0.100 Kg 31,700.00 3,170.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 21,142.50
12 1 m2 Pengecatan Genteng Baru
- Cat 0.300 Kg 34,500.00 10,350.00
- Kuas 0.100 Bh 17,250.00 1,725.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 22,062.50
13 1 m2 Coating transparan (doff) untuk batu alam
- Coating 0.2000 Ltr 69,000.00 13,800.00
- Kuas 0.0100 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 23,960.00
1 2 3 4 5 6 7
14 1 m2 Coating Waterproffing
- Waterproffing 0.6000 Kg 46,000.00 27,600.00
- Serabut Kasa 1.0000 m2 69,000.00 69,000.00
- Upah Pekerjaan
~ Pekerja 0.1200 Oh 55,000.00 6,600.00
~ Tukang Cat 0.0800 Oh 70,000.00 5,600.00
~ Kepala Tukang 0.0070 Oh 85,000.00 595.00
~ Mandor 0.0800 Oh 100,000.00 8,000.00 117,395.00
15 1 m2 Coating Waterproffing tanpa serabut kasa
- Waterproffing 0.3000 Kg 46,000.00 13,800.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 23,787.50
1 2 3 4 5 6 7
16 1 m2. Lapis melamin duco (2x lapis sampai rata)
- Cat Titan lux 0.500 kg 89,050.00 44,525.00
- Kertas gosok no. 150 1.000 lbr 3,500.00 3,500.00
- Clear 0.200 kg 65,000.00 13,000.00
- Thinner A 0.837 ltr 26,450.00 22,138.65
- Alat
- Sewa alat bantu @ 3 alat 1.00 set 10,000.00 10,000.00
- Sewa compresor 0.625 jam 134,900.00 84,312.50
- Upah Pekerjaan
- Pekerja Terampil 0.075 Oh 55,000.00 4,125.00
- Tukang cat 0.9 Oh 70,000.00 63,000.00
- Kepala tukang cat 0.09 Oh 85,000.00 7,650.00
- Mandor 0.0025 Oh 100,000.00 250.00 252,501.15
17 1 m2 Pengecatan Weathershield
- Plamir 0.100 Kg 17,250.00 1,725.00
- Cat Weathershield 0.100 Kg 90,000.00 9,000.00
- Cat Penutup 2x 0.260 Kg 90,000.00 23,400.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.063 Oh 70,000.00 4,410.00
~ Kepala Tukang 0.0063 Oh 85,000.00 535.50
~ Mandor 0.0025 Oh 100,000.00 250.00 40,420.50
XI PEKERJAAN SANITAIR
1 Memasang 1 buah kloset duduk / monoblok
- Kloset duduk / monoblok 1.000 Bh 1,207,500.00 1,207,500.00
- Perlengkapan 0.060 hrg 1,207,500.00 72,450.00
- Upah Pekerjaan
~ Pekerja 3.300 Oh 55,000.00 181,500.00
~ Tukang Batu 1.100 Oh 45,000.00 49,500.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.160 Oh 100,000.00 16,000.00 1,527,035.00
2 Memasang 1 buah kloset jongkok porselen
- Kloset jongkok porselen 1.000 Bh 126,500.00 126,500.00
- Semen portland 6.000 Kg 1,397.50 8,385.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.500 Oh 45,000.00 67,500.00
~ Kepala Tukang 1.500 Oh 85,000.00 127,500.00
~ Mandor 0.160 Oh 100,000.00 16,000.00 401,789.00
3 Memasang 1 buah urinoir
- Urinoir 1.000 Bh 980,000.00 980,000.00
- Perlengkapan 0.300 hrg 980,000.00 294,000.00
- Semen portland 6.000 Kg 1,397.50 8,385.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.000 Oh 45,000.00 45,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 8,500.00
~ Mandor 0.100 Oh 100,000.00 10,000.00 1,401,789.00
4 Memasang 1 buah wastafel
- Wastafel 1.000 Bh 300,000.00 300,000.00
- Perlengkapan 0.120 hrg 300,000.00 36,000.00
- Semen portland 6.000 Kg 1,397.50 8,385.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 55,000.00 66,000.00
~ Tukang Batu 1.450 Oh 45,000.00 65,250.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 490,289.00
5 Memasang 1 buah bak cuci stainless
- Bak cuci stainless 1.000 Bh 180,000.00 180,000.00
- Water drain dan accessories 1.000 set 30,000.00 30,000.00
1 2 3 4 5 6 7
- Upah Pekerjaan
~ Pekerja 0.030 Oh 55,000.00 1,650.00
~ Tukang Batu 0.300 Oh 45,000.00 13,500.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0015 Oh 100,000.00 150.00 227,850.00
6 Memasang 1 buah bak mandi fiber glass
- Bak fiberglass 1.000 Bh 316,250.00 316,250.00
- Perlengkapan 0.180 hrg 316,250.00 56,925.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 45,000.00 121,500.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00 650,575.00
1 2 3 4 5 6 7
7 Memasang 1 pintu KM PVC
- Pintu PVC 1.000 Bh 316,250.00 316,250.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 45,000.00 121,500.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00 593,650.00
8 Pasang Buis Beton U 20
- Buis Beton 1.000 M 21,000.00 21,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.0035 Oh 100,000.00 350.00 27,072.50
9 Pasang Buis Beton U 30
- Buis Beton 1.000 M 26,500.00 26,500.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00 32,572.50
10 Pasang Buis Beton O 20
- Buis Beton 1.000 M 35,000.00 35,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00 41,072.50
11 Pasang Buis Beton O 30
- Buis Beton 1.000 M 51,000.00 51,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00 57,072.50
12 Memasang 1 buah kran diameter 3/4" atau 1/2"
- Kran air 1.000 Bh 20,000.00 20,000.00
- Seal Tape 0.025 Bh 3,450.00 86.25
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Batu 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 26,486.25
13 Memasang 1 m' pipa PVC diameter 0,5" (AW)
- Pipa PVC 1.000 M' 6,475.00 6,475.00
- Perlengkapan 0.350 Hrg 6,475.00 2,266.25
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00 14,111.25
14 Memasang 1 m' pipa PVC diameter 3/4" (AW)
- Pipa PVC 1.000 M' 7,912.50 7,912.50
- Perlengkapan 0.350 Hrg 7,912.50 2,769.38
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00 16,051.88
15 Memasang 1 m' pipa PVC diameter 1" (AW)
- Pipa PVC 1.000 M' 10,062.50 10,062.50
- Perlengkapan 0.350 Hrg 10,062.50 3,521.88
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00 18,954.38
1 2 3 4 5 6 7
16 Memasang 1 m' pipa PVC diameter 2" (AW)
- Pipa PVC 1.000 M' 27,025.00 27,025.00
- Perlengkapan 0.350 Hrg 27,025.00 9,458.75
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0027 Oh 100,000.00 270.00 44,538.75
17 Memasang 1 m' pipa PVC diameter 3" (AW)
- Pipa PVC 1.000 M' 49,312.50 49,312.50
- Perlengkapan 0.350 Hrg 49,312.50 17,259.38
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 78,659.38
18 Memasang 1 m' pipa PVC diameter 4" (AW)
- Pipa PVC 1.000 M' 71,875.00 71,875.00
- Perlengkapan 0.350 Hrg 71,875.00 25,156.25
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 109,118.75
19 Memasang 1 m' pipa PVC diameter 2" (D)
- Pipa PVC 1.000 M' 15,000.00 15,000.00
- Perlengkapan 0.350 Hrg 15,000.00 5,250.00
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0027 Oh 100,000.00 270.00 28,305.00
20 Memasang 1 m' pipa PVC diameter 3" (D)
- Pipa PVC 1.000 M' 22,000.00 22,000.00
- Perlengkapan 0.350 Hrg 22,000.00 7,700.00
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 41,787.50
21 Memasang 1 m' pipa PVC diameter 4" (D)
- Pipa PVC 1.000 M' 33,750.00 33,750.00
- Perlengkapan 0.350 Hrg 33,750.00 11,812.50
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 57,650.00
22 Memasang 1 m' pipa galvanis diameter 1/2"
- Pipa Galvanis 1.000 M' 23,958.33 23,958.33
- Perlengkapan 0.350 Hrg 23,958.33 8,385.42
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00 42,828.75
23 Memasang 1 m' pipa Galvanis diameter 3/4"
- Pipa Galvanis 1.000 M' 28,750.00 28,750.00
- Perlengkapan 0.350 Hrg 28,750.00 10,062.50
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
1 2 3 4 5 6 7
~ Mandor 0.0270 Oh 100,000.00 2,700.00 49,297.50
24 Memasang 1 m' pipa Galvanis diameter 1"
- Pipa Galvanis 1.000 M' 43,125.00 43,125.00
- Perlengkapan 0.350 Hrg 43,125.00 15,093.75
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00 68,703.75
1 2 3 4 5 6 7
25 Memasang 1 m' pipa Galvanis diameter 1 1/2"
- Pipa Galvanis medium 1.000 M' 64,700.00 64,700.00
- Perlengkapan 0.350 Hrg 64,700.00 22,645.00
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 103,455.00
26 Memasang 1 m' pipa Galvanis diameter 2"
- Pipa Galvanis Medium 1.000 M' 88,166.67 88,166.67
- Perlengkapan 0.350 Hrg 88,166.67 30,858.33
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 135,135.00
27 Memasang 1 m' pipa Galvanis diameter 2 1/2"
- Pipa Galvanis tebal 1.000 M' 110,208.33 110,208.33
- Perlengkapan 0.350 Hrg 110,208.33 38,572.92
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 164,891.25
28 Memasang 1 m' pipa Galvanis diameter 3"
- Pipa Galvanis tebal 1.000 M' 142,791.67 142,791.67
- Perlengkapan 0.350 Hrg 142,791.67 49,977.08
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 208,878.75
29 Memasang 1 m' pipa Galvanis diameter 4"
- Pipa Galvanis tebal 1.000 M' 208,916.67 208,916.67
- Perlengkapan 0.350 Hrg 208,916.67 73,120.83
- Upah Pekerjaan
~ Pekerja 0.135 Oh 55,000.00 7,425.00
~ Tukang Batu 0.225 Oh 45,000.00 10,125.00
~ Kepala Tukang 0.0225 Oh 85,000.00 1,912.50
~ Mandor 0.0068 Oh 100,000.00 680.00 302,180.00
30 1 Unit Septictank ( h = 1,7 m , L = 1,3 m , P = 2,15 m )
- Galian Tanah 4.752 m3 54,000.00 256,608.00
- Pas. batu bata tebal 1/2 bata, 1 : 3 12.105 m2 92,949.15 1,125,149.46
- Plesteran t = 15 mm, 1Pc : 3Ps 14.005 m2 43,479.32 608,927.88
- Pas. Pipa Pembuangan gas PVC 2" 1.000 m1 44,538.75 44,538.75
- Pek. Beton Bertulang K 175 0.309 m3 2,924,392.86 903,637.39 2,938,861.48
31 1 Unit Resapan ( h = 2,1 m diameter 1,9 m)
- Galian Tanah 3.990 m3 54,000.00 215,460.00
- Pas. batu bata kosong tebal 1 bata 4.396 m2 109,850.00 482,900.60
- Pas. batu bata tebal 1 bata, 1 : 5 1.884 m2 178,109.80 335,558.86
- Plesteran t = 15 mm, 1Pc : 3Ps 1.884 m2 43,479.32 81,915.04
- Pas. Pipa Pembuangan gas PVC 2" 1.000 m1 44,538.75 44,538.75
- Pek. Beton Bertulang K 175 0.118 m3 2,924,392.86 345,078.36
- Kerikil Bulat 2 - 3 cm 0.200 m3 149,500.00 29,900.00
- Ijuk 5.000 kg 8,750.00 43,750.00 1,579,101.61
32 Memasang 1 bh Floor drain
- Floor drain 1.000 Bh 74,750.00 74,750.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Batu 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.0100 Oh 85,000.00 850.00
~ Mandor 0.0050 Oh 100,000.00 500.00 81,150.00
1 2 3 4 5 6 7
XII PEKERJAAN PAVING
1 1 m2 Pasang Paving K 300 abu-abu
- Paving stone K 300 abu-abu 1.000 M2 60,000.00 60,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 100,400.00
2 1 m2 Pasang Paving K 300 warna
- Paving stone K 300 warna 1.000 M2 72,000.00 72,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 112,400.00
1 2 3 4 5 6 7
3 1 m2 Pasang Paving K 200 abu-abu
- Paving stone K 200 abu-abu 1.000 M2 54,000.00 54,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 94,400.00
4 1 m2 Pasang Paving K 200 warna
- Paving stone K 200 warna 1.000 M2 66,000.00 66,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 106,400.00
5 1 m2 Pasang Paving K 100 abu-abu
- Paving stone K 100 abu-abu 1.000 M2 38,400.00 38,400.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 78,800.00
6 1 m2 Pasang Paving K 100 warna
- Paving stone K 100 warna 1.000 M2 44,400.00 44,400.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 84,800.00
7 1 m1 Pasang Kanstin 10,20,50
- Kanstin 2.000 Bh #REF! #REF!
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 #REF!
8 1 m1 Pasang Kanstin 10,30,50
- Kanstin 2.000 Bh #REF! #REF!
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 #REF!
9 1 m1 Pasang Kanstin 15,20,50 (ex pandaan)
- Kanstin 2.000 Bh 31,500.00 63,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 85,044.71
10 1 m1 Pasang Kanstin 15,30,50 (ex pandaan)
- Kanstin 2.000 Bh 33,000.00 66,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
1 2 3 4 5 6 7
~ Mandor 0.0228 Oh 100,000.00 2,280.00 88,044.71
11 1 m1 Pasang Kanstin 15,25,40 (ex pandaan)
- Kanstin 2.500 Bh 16,800.00 42,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 64,044.71
1 2 3 4 5 6 7
XIII PEKERJAAN PAGAR BESI
1 1 M1 Pasang Pagar BRC tinggi 90 cm
- Kawat BRC t=90 cm 1.000 M1 212,750.00 212,750.00
- Kawat Las RB 0.200 kg 28,750.00 5,750.00
- Upah Pekerjaan 1.000 Org 50,000.00 50,000.00 268,500.00
2 1 M1 Pasang Pagar BRC tinggi 120 cm
- Kawat BRC t=120 cm 1.000 M1 258,750.00 258,750.00
- Kawat Las RB 0.200 kg 28,750.00 5,750.00
- Upah Pekerjaan 1.000 Org 50,000.00 50,000.00 314,500.00
3 1 m2 Pasang pintu besi plat baja tebal 2 mm, rangka baja siku
- Besi siku L 30.30.3 15.000 Kg 12,000.00 180,000.00
- Besi plat baja 32.800 Kg 12,000.00 393,600.00
- Kawat las 0.050 Kg 28,750.00 1,437.50
- Upah Pekerjaan
~ Pekerja 1.050 Oh 55,000.00 57,750.00
~ Tukang besi konstruksi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.105 Oh 85,000.00 8,925.00
~ Mandor 0.052 Oh 100,000.00 5,200.00 720,412.50
4 1 m2 Pasang Pagar besi
- Pagar besi 1.000 M2 450,000.00 450,000.00
- Upah Pekerjaan
~ Pekerja 1.050 Oh 55,000.00 57,750.00
~ Tukang besi konstruksi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.105 Oh 85,000.00 8,925.00
~ Mandor 0.00525 Oh 100,000.00 525.00 590,700.00
5 1 m2 Pasang Pintu Harmonika
- Pintu harmonika 1.000 M2 1,124,125.00 1,124,125.00
- Upah Pekerjaan
~ Pekerja 1.050 Oh 55,000.00 57,750.00
~ Tukang besi konstruksi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.105 Oh 85,000.00 8,925.00
~ Mandor 0.00525 Oh 100,000.00 525.00 1,264,825.00
6 1 m2 Pasang Teralis besi strip (2 x 3) mm
- Besi Plat Strip 6.177 Kg 12,000.00 74,124.00
- Pengelasan 27.080 cm 2,500.10 67,702.71
- Upah Pekerjaan
~ Pekerja 1.670 Oh 55,000.00 91,850.00
~ Tukang besi konstruksi 1.670 Oh 70,000.00 116,900.00
~ Kepala Tukang 0.167 Oh 85,000.00 14,195.00
~ Mandor 0.08300 Oh 100,000.00 8,300.00 298,947.71
7 1 m2 Pasang kawat harmonika
- Kawat harmonika 1.100 M2 43,200.00 47,520.00
- Pengelasan 11.110 Cm 2,500.10 27,776.11
- Baja Strip (0,2x2) cm 1.7160 Kg 12,000.00 20,592.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang besi konstruksi 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.0005 Oh 100,000.00 50.00 106,788.11
8 1 m2 Pasang kawat nyamuk kassa
- Kawat nyamuk kassa alumunium 1.100 M2 28,750.00 31,625.00
- Pengelasan 11.110 Cm 2,500.10 27,776.11
- Baja Strip (0,2x2) cm 1.7160 Kg 12,000.00 20,592.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang besi konstruksi 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.0005 Oh 100,000.00 50.00 90,893.11
BIDANG PENGAIRAN
HARGA SATUAN JUMLAH HSPK 2011
NO JENIS PEKERJAAN KOEF. STN
(Rp) (Rp) (Rp)
1 2 3 4 5 6 7
I KEGIATAN PENGUKURAN
1 Pengukuran Bendung untuk MC. 1.000 bh
TENAGA
1. Juru ukur 1.500 Org/hr 60,000.00 90,000.00
2. Pekerja 4.500 Org/hr 37,000.00 166,500.00
BAHAN
1. Patok kayu uk. 4 x 6 x 50 cm 0.012 m3 2,400,000.00 28,800.00
2. Cat meni 0.120 kg 22,800.00 2,736.00
3. Paku payung 0.050 kg 23,000.00 1,150.00
ALAT
1. Pesawat ukur 1.000 unit 150,000.00 150,000.00
2. Meteran 0.030 bh 14,000.00 420.00
3. Palu 0.060 bh 35,000.00 2,100.00 441,706.00
2 Pengukuran Saluran Untuk MC. 1.000 bh
TENAGA
1. Juru ukur 2.000 Org/hr 60,000.00 120,000.00
2. Pekerja 6.000 Org/hr 37,000.00 222,000.00
BAHAN
1. Patok kayu uk. 4 x 6 x 50 cm 0.012 m3 2,400,000.00 28,800.00
2. Cat meni 0.120 kg 22,800.00 2,736.00
3. Paku payung 0.050 kg 23,000.00 1,150.00
ALAT
1. Pesawat ukur 2.000 unit 150,000.00 300,000.00
2. Meteran 0.045 bh 14,000.00 630.00
3. Palu 0.090 bh 35,000.00 3,150.00
678,466.00
3 Pengukuran Bangunan untuk MC. 1.000 bh
TENAGA
1. Juru ukur 0.250 Org/hr 60,000.00 15,000.00
2. Pekerja 0.750 Org/hr 37,000.00 27,750.00
BAHAN
1. Patok kayu uk. 4 x 6 x 50 cm 0.002 m3 2,400,000.00 4,800.00
2. Cat meni 0.020 kg 22,800.00 456.00
3. Paku payung 0.010 kg 23,000.00 230.00
ALAT
1. Pesawat ukur 0.250 unit 150,000.00 37,500.00
2. Meteran 0.020 bh 14,000.00 280.00
3. Palu 0.030 bh 35,000.00 1,050.00 87,066.00
II KEGIATAN PERSIAPAN
1 Pembuatan bouwplank Pertitik 1.000 m
TENAGA
1. Kep. Tukang Kayu 0.010 Org/hr 50,000.00 500.00
2. Tukang Kayu 0.100 Org/hr 70,000.00 7,000.00
3. Pekerja 0.100 Org/hr 37,000.00 3,700.00
4. Mandor 0.005 Org/hr 55,000.00 275.00
BAHAN
1. Kayu perancah 5/7 0.012 m3 2,200,000.00 26,400.00
3. Paku usuk 0.020 kg 15,000.00 300.00 38,175.00
III PEMBERSIHAN:
1 Pembersihan saluran 1.000 m2
TENAGA
1. Mandor 0.008 Org/hr 55,000.00 440.00
2. Pekerja 0.050 Org/hr 37,000.00 1,850.00 2,290.00
2 Angkutan Pembersihan Saluran 1.000 m3
TENAGA
1. Mandor 0.002 Org/hr 55,000.00 110.00
2. Pekerja Terampil 0.050 Org/hr 37,000.00 1,850.00
ALAT
1 2 3 4 5 6 7
1. Sewa Truck (min 5 jam) 0.020 Jam 151,646.00 3,032.92 4,992.92
IV KEGIATAN PENGGALIAN
1 Menggali Tanah Dengan Alat Berat 1.000 m3
TENAGA
1. Pekerja 0.226 Jam 37,000.00 8,362.00
2. Mandor 0.007 Jam 55,000.00 385.00
ALAT
1. Sewa Excavator 0.076 Jam 297,651.00 22,621.48
2. Sewa Truck (min 5 jam) 0.074 Jam 151,646.00 11,221.80 42,590.28
1 2 3 4 5 6 7
2 Bongkaran Pas. Batu Kali dan dibersihkan 1.000 m3
TENAGA
1. Mandor 0.205 Org/hr 55,000.00 11,275.00
2. Pekerja 2.048 Org/hr 37,000.00 75,776.00
ALAT
1. Bodem 0.010 unit 135,000.00 1,350.00
2. Keranjang 0.083 bh 11,500.00 954.50 89,355.50
3 Bongkaran beton bertulang (mesin) 1.000 m3
TENAGA
Pekerja 1.000 Org/hr 37,000.00 37,000.00
Mandor 0.050 Org/hr 55,000.00 2,750.00
BAHAN .
1. Solar 2.000 Ltr 4,500.00 9,000.00
ALAT
1. Jack hammer 4.000 Jam 25,800.00 103,200.00 151,950.00
V KEGIATAN PENDONGKELAN
1 Pendongkelan rumpun bambu dan menimbun kembali 1.000 m2 0.90
bekas dongkelan
TENAGA
1. Mandor 0.054 Org/hr 55,000.00 2,970.00
2. Pekerja 1.575 Org/hr 37,000.00 58,275.00
BAHAN
1. Tanah urug 0.900 m3 58,500.00 52,650.00
ALAT
1. Ganco 0.050 bh 60,000.00 3,000.00
2. Keranjang 0.225 bh 11,500.00 2,587.50
3. Kereta dorong / alat angkut 0.042 bh 200,000.00 8,400.00
4. Pemadat timbunan (Vibro roller/stamper) 0.900 Jam 33,900.00 30,510.00 158,392.50
2 Pendongkelan rumpun bambu 1.000 m2
TENAGA
1. Mandor 0.045 Org/hr 55,000.00 2,475.00
2. Pekerja 1.327 Org/hr 37,000.00 49,099.00
ALAT
1. Ganco 0.050 bh 60,000.00 3,000.00
2. Keranjang 0.225 bh 11,500.00 2,587.50 57,161.50
3 Pendongkelan pohon keliling >0.75 m 1.000 btg
TENAGA
1. Mandor 0.400 Org/hr 55,000.00 22,000.00
2. Pekerja 3.000 Org/hr 37,000.00 111,000.00
ALAT
1. Gergaji 0.034 bh 35,000.00 1,190.00
2. Ganco 0.050 bh 60,000.00 3,000.00
3. Sabit besar 0.040 bh 40,000.00 1,600.00 138,790.00
4 Pendongkelan pohon keliling >0.75 m dan menimbun 1.000 btg
kembali bekas dongkelan
TENAGA
1. Mandor 0.412 Org/hr 55,000.00 22,660.00
2. Pekerja 3.330 Org/hr 37,000.00 123,210.00
BAHAN
1. Tanah urug 1.200 m3 58,500.00 70,200.00
ALAT
1. Gergaji 0.034 bh 35,000.00 1,190.00
2. Ganco 0.050 bh 60,000.00 3,000.00
3. Sabit besar 0.040 bh 40,000.00 1,600.00
4. Pemadat timbunan (Vibro roller/stamper) 1.200 Jam 33,900.00 40,680.00
5. Kereta dorong / alat angkut 0.042 bh 200,000.00 8,400.00 270,940.00
5 Kosrekan tanah setebal 15 cm dan dibuang keluar 1.000 m2
TENAGA
1. Mandor 0.019 Org/hr 55,000.00 1,045.00
2. Pekerja 0.156 Org/hr 37,000.00 5,772.00
ALAT
1. Keranjang 0.083 bh 11,500.00 954.50 7,771.50
6 Pengeringan / Pompa Air 1.000 Jam
TENAGA
1 2 3 4 5 6 7
1. Operator 0.042 Org/hr 125,000.00 5,250.00
2. Mekanik 0.042 Org/hr 75,000.00 3,150.00
BAHAN
1. Solar 1.500 ltr 4,500.00 6,750.00
ALAT
1. Pompa Air 0.042 unit 40,000.00 1,680.00 16,830.00
IX KEGIATAN PERKAWATAN
1 Bronjong kawat galvanis d = 4mm 1.000 m3
TENAGA
1. Mandor pengisi 0.024 Org/hr 55,000.00 1,320.00
2. Penganyam 0.704 Org/hr 55,000.00 38,720.00
3. Mandor penganyam 0.026 Org/hr 55,000.00 1,430.00
4. Pekerja pengisi 1.382 Org/hr 37,000.00 51,134.00
5. Pekerja penganyam 0.567 Org/hr 37,000.00 20,979.00
BAHAN
1. Batu kali 1.100 m3 130,000.00 143,000.00
2. Kawat galvanize 15.000 kg 23,000.00 345,000.00
ALAT
1. Tang pemotong kawat 0.010 bh 25,000.00 250.00
2. Palu 0.010 bh 35,000.00 350.00 602,183.00
XI PENGANGKUTAN TANAH:
1 Pengangkutan tanah sejauh 30m 1.000 m3
TENAGA
1. Pekerja 0.330 Org/hr 55,000.00 18,150.00
2. Mandor 0.010 Org/hr 100,000.00 1,000.00 19,150.00
2 Mengangkut tanah dari lubang galian dalamnya lebih 1.000 m3
dari 1 m
TENAGA
1. Pekerja 0.150 Org/hr 55,000.00 8,250.00
2. Mandor 0.008 Org/hr 100,000.00 800.00 9,050.00
3 Mengangkut lumpur dari lubang galian dalamnya lebih 1.000 m3
dari 1 m
TENAGA
1. Pekerja 0.250 Org/hr 55,000.00 13,750.00
2. Mandor 0.010 Org/hr 100,000.00 1,000.00 14,750.00
4 Mengangkut lumpur Pada lokasi yang sulit 1.000 m3
TENAGA
1. Pekerja 1.400 Org/hr 55,000.00 77,000.00
2. Mandor 0.024 Org/hr 100,000.00 2,400.00 79,400.00
5 Angkutan Tanah Keluar Proyek 1.000 m3
TENAGA
1. Pekerja 0.250 Org/hr 55,000.00 13,750.00
ALAT
1. Sewa Truck (min 5 jam) 0.250 Jam 196,800.00 49,200.00 62,950.00
6 Pengerukan lumpur Pada lokasi sulit (Gorong-2) 1.000 m3
TENAGA
1. Mandor 0.024 Org/hr 100,000.00 2,400.00
2. Pekerja 1.400 Org/hr 55,000.00 77,000.00 79,400.00
7 BIAYA LANGSIRAN >50 m' s/d 100 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.450 Org/hr 55,000.00 24,750.00 24,750.00
8 BIAYA LANGSIRAN s/d 200 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.545 Org/hr 55,000.00 29,975.00 29,975.00
1 2 3 4 5 6 7
9 BIAYA LANGSIRAN s/d 300 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.725 Org/hr 55,000.00 39,875.00 39,875.00
10 BIAYA LANGSIRAN s/d 400 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.909 Org/hr 55,000.00 49,995.00 49,995.00
11 BIAYA LANGSIRAN s/d 500 m' 1.000 m3
Upah Pekerjaan
- Pekerja 1.090 Org/hr 55,000.00 59,950.00 59,950.00
12 BIAYA LANGSIRAN >700 m' 1.000 m3
Upah Pekerjaan
- Pekerja 1.452 Org/hr 55,000.00 79,860.00 79,860.00
13 Gebalan rumput 1.000 m2
TENAGA
1. Mandor 0.010 Org/hr 100,000.00 1,000.00
2. Pekerja 0.144 Org/hr 55,000.00 7,920.00
BAHAN
1. Gebalan rumput 1.000 m2 15,650.00 15,650.00 24,570.00
14 Pasang Lubang Drainase 1.000 bh
TENAGA
1. Mandor 0.020 Org/hr 100,000.00 2,000.00
2. Kepala Tukang Batu 0.001 Org/hr 85,000.00 85.00
3. Tukang Batu 0.010 Org/hr 70,000.00 700.00
4. Pekerja 0.001 Org/hr 55,000.00 55.00
BAHAN
1. Pipa PVC diameter 1,25" 0.500 m' 8,625.00 4,312.50
2. Ijuk 0.050 kg 8,750.00 437.50 7,590.00
5123 BAJA
TENAGA
Besi
Kawat TULANG
Pekerja
Tukang
Mandor
BAHAN BetonPolosPOLOS
Beton
PERALATAN
Alat Bantu 1 Kg
0.1050
0.0350
1.1000
0.0100
1.0000 Jam
Kg
M3
Ls #REF! #REF!
#REF!
5 BAJA TULANG POLOS 1 Kg #REF!
BAHAN
1 Besi beton (polos) 1.0500 Kg #REF! #REF!
2 Kawat beton 0.0150 Kg #REF! #REF!
TENAGA
1 Pekerja 0.0070 Oh #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
2 Tukang Besi 0.0070 Oh #REF! #REF!
3 Kepala Tukang 0.0007 Oh #REF! #REF!
4 Mandor 0.0003 Oh #REF! #REF!
XI BAHAN PLASTIK
1 Keni PVC 1/2" Bh 2,500.00
2 Keni PVC 3/4" Bh 3,000.00
3 Keni PVC 1" Bh 4,000.00
4 Keni PVC 1 1/4" Bh 4,000.00
5 Keni PVC 1 1/2" Bh 4,000.00
6 Keni PVC 2" Bh 5,000.00
7 Keni PVC 2,5" Bh 6,000.00
8 Keni PVC 3" Bh 7,000.00
9 Keni PVC 4" Bh 9,000.00
10 Shock 1/2" Bh 1,500.00
11 Shock 3/4" Bh 1,500.00
12 Shock 1" Bh 2,000.00
13 Shock 1 1/4" Bh 3,000.00
14 Shock 1 1/2" Bh 3,000.00
15 Shock 2" Bh 3,000.00
16 Shock 2,5" Bh 4,500.00
17 Shock 3" Bh 7,000.00
18 Shock 4" Bh 8,000.00
19 Shock drat luar 1" Bh 3,450.00
20 Stop Kran 1" Bh 132,250.00
21 Stop Kran 3/4" Bh 100,650.00
22 Tee 1/2" Bh 2,900.00
23 Tee 3/4" Bh 3,450.00
24 Tee 1" Bh 4,600.00
25 Tee 1 1/4" Bh 5,200.00
26 Tee 1 1/2" Bh 7,500.00
27 Tee 2" Bh 9,800.00
28 Tee 4" Bh 43,150.00
29 Tee Verloop PVC 1" x 3/4" Bh 4,600.00
30 Keni Verloop PVC 1" x 3/4" Bh 7,500.00
31 Keni Drat 3/4" x 1/2" Bh 9,800.00
32 Keni Galvanis 1/2" Bh 5,750.00
33 Seal Tape Bh 3,450.00
34 Lem PVC /Sealent Bh 6,900.00
35 Pelampung Otomatis Bh 172,500.00
36 Klem Pipa Bh 5,200.00
37 Filter Pipa /kleb pipa Bh 7,500.00
1 2 3 4
38 Corong W Bh 20,700.00
39 Corong U Bh 23,000.00
40 Pipa paralon 5/8" panjang 4 Ljr 5,500.00
41 Pipa PVC 1/2" (AW) Ljr 25,900.00
42 Pipa PVC 3/4" (AW) Ljr 31,650.00
43 Pipa PVC 1" (AW) Ljr 40,250.00
44 Pipa PVC 1 1/4" (AW) Ljr 55,800.00
45 Pipa PVC 1 1/2" (AW) Ljr 73,600.00
46 Pipa PVC 2" (AW) Ljr 108,100.00
47 Pipa PVC 2,5" (AW) Ljr 138,600.00
48 Pipa PVC 3" (AW) Ljr 197,250.00
49 Pipa PVC 4" (AW) Ljr 287,500.00
50 Pipa PVC 6" (AW) Ljr 598,000.00
51 Pipa PVC 8" (AW) Ljr 931,500.00
52 Pipa PVC 10" (AW) Ljr 1,322,500.00
53 PVC 1" D Ljr 32,200.00
54 PVC 1,25" D Ljr 34,500.00
55 PVC 1,5" D Ljr 40,250.00
56 PVC 2" D Ljr 60,000.00
57 PVC 3" D Ljr 88,000.00
58 PVC 4" D Ljr 135,000.00
59 PVC 5" D Ljr 165,000.00
60 PVC 6" D Ljr 201,500.00
61 PVC U 15 Ljr 106,250.00
XV LAIN-LAIN
1 Karung Plastik Bh 3,900.00
2 Ijuk Kg 8,750.00
3 Gabalan Rumput M 2
15,650.00
DAFTAR HARGA UPAH PEKERJA
PEKERJAAN :
TAHUN ANGGARAN : 2018
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 1.00 ls Rp 200,000.00 Rp 200,000.00
Sub Jumlah Rp 200,000.00
II PEKERJAAN TANAH DAN URUGAN
1 Galian tanah 39.50 m3 Rp 62,750.00 Rp 2,478,625.00
2 Urugan tanah kembali 11.85 m3 Rp 20,916.67 Rp 247,862.50
3 Urugan pasir 1.38 m3 Rp 160,100.00 Rp 221,338.25
4 Urugan tanah - m3 Rp 220,400.00 Rp -
Sub Jumlah Rp 2,947,825.75
III PEKERJAAN BETON BERTULANG
1 Rabatan 2.95 m3 Rp 945,726.80 Rp 2,789,894.06
4 Sloof 15/30 1.78 m3 Rp 3,899,868.50 Rp 6,932,016.26
5 Kolom 15/15 1.46 m3 Rp 6,289,072.00 Rp 9,197,767.80
7 Balok latai teras 20/30 - m3 Rp 6,340,358.00 Rp -
8 Balok latai 15/15 - m3 Rp 6,340,358.00 Rp -
9 Plaat leufell 5 cm - m3 Rp 7,687,542.00 Rp -
10 Ring balok 15/20 0.89 m3 Rp 6,340,358.00 Rp 5,634,993.17
Sub Jumlah Rp 24,554,671.29
IV PEKERJAAN PONDASI
1 Aanstamping 5.53 m3 Rp 334,290.00 Rp 1,848,623.70
2 Pondasi bt kali 8.89 m3 Rp 686,250.00 Rp 6,099,046.88
Sub Jumlah Rp 7,947,670.58
V PEK. PASANGAN & PLESTERAN
1 Pas. Batu bata tembok 1pc : 4ps m2 Rp 104,232.50 Rp -
2 Plesteran 1pc : 4 ps m2 Rp 51,351.00 Rp -
3 Acian m2 Rp 31,975.00 Rp -
4 Benangan sudut m' Rp 17,201.00 Rp -
5 Pas keramik 40/40 m2 Rp 252,177.50 Rp -
6 Pas batu alur m2 Rp 324,768.00 Rp -
7 Pas. Batu bobos m2 Rp 324,768.00 Rp -
Sub Jumlah Rp -
VI PEKERJAAN ATAP
1 Pasang Kuda-kuda moorplat ky kruing 8/12 m3 Rp 7,566,280.00 Rp -
2 Pasang Kuda-kuda moorplat ky lama m3 Rp 2,425,980.00 Rp -
3 Gording kayu kruing 8/12 m3 Rp 7,566,280.00 Rp -
4 Gording kayu bongkaran m3 Rp 2,425,980.00 Rp -
5 Pas.usuk kruing/reng kamper kayu 5/7, 3/6 m3 Rp 179,056.25 Rp -
6 Pas.usuk lama /reng baru kayu kamper 5/7, 3/5 m2 Rp 109,056.25 Rp -
7 Genteng model karangpilang m2 Rp 170,430.00 Rp -
8 Genteng bubungan m' Rp 102,820.00 Rp -
9 Pasang Lisplank ukuran 30 cm tebal 8 mm m' Rp 79,332.50 Rp -
10 Pas. Plafond rangka hollow gypsumboard m2 Rp 166,425.00 Rp -
11 Pas. List Gypsum m' Rp 32,084.25 Rp -
Sub Jumlah Rp -
VII PEKERJAAN KUSEN
1 Kusen pintu dan jendela kamper 0.47 m3 Rp 17,373,531.25 Rp 8,177,721.16
2 Daun pintu kamper 5.13 m2 Rp 1,029,622.00 Rp 5,276,812.75
3 Daun jendela 1.00 m2 Rp 575,850.00 Rp 575,850.00
4 Kaca 5 mm rayben 3.92 m2 Rp 236,282.50 Rp 927,290.67
5 Pasang 1 buah kunci tanam silinder + pegangan 2.00 unit Rp 432,732.60 Rp 865,465.20
6 Engsel jendela 4.00 bh Rp 40,665.00 Rp 162,660.00
7 Engsel pintu 12.00 bh Rp 66,662.50 Rp 799,950.00
8 Grendel jendela 2.00 bh Rp 26,025.10 Rp 52,050.20
9 Grendel pintu 2.00 bh Rp 41,194.10 Rp 82,388.20
10 Hak angin 2.00 bh Rp 49,282.50 Rp 98,565.00
Sub Jumlah Rp 17,018,753.18
VIII PEKERJAAN CAT
1 Cat tembok baru - m2 Rp 32,805.00 Rp -
2 Cat kayu m2 Rp 48,890.80 Rp -
3 Cat plafond - m2 Rp 29,085.00 Rp -
Sub Jumlah Rp -
IX PEKERJAAN LAMPU
1 Pasang Instalasi listrik + lampu XL 10 watt 13.00 ttk Rp 278,600.00 Rp 3,621,800.00
2 Pasang Instalasi listrik + lampu XL 18 watt 3.00 ttk Rp 295,020.00 Rp 885,060.00
3 Pasang Instalasi listrik + Pas. Stop kontak 8.00 ttk Rp 246,420.00 Rp 1,971,360.00
4 Pasang Instalasi listrik + Pas. Saklar ganda 4.00 ttk Rp 240,365.00 Rp 961,460.00
5 Pasang Instalasi listrik + Pas. Saklar tunggal 6.00 ttk Rp 302,580.00 Rp 1,815,480.00
Sub Jumlah Rp 9,255,160.00
ANALISA HARGA SATUAN BAHAN DAN UPAH TENAGA
BERDASARKAN SNI
TAHUN ANGGARAN 2018
HARGA HSPK
JUMLAH
NO JENIS PEKERJAAN KOEF. SAT. SATUAN 2013
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
2 1 m Pengukuran & Pemasangan Bouwplank 109,096.54
- Patok Kayu 0.012 M3 4,715,370.00 56,584.44
- Paku 0.020 Kg 16,425.00 328.50
- Kayu Papan 3/20 0.007 M3 4,804,800.00 33,633.60
- Upah Pekerjaan
~ Pekerja 0.100 Oh 80,000.00 8,000.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.005 Oh 110,000.00 550.00
II PEKERJAAN TANAH
1 1 m 3 Galian Tanah biasa sedalam 1 meter 62,750.00
- Pekerja 0.750 Oh 80,000.00 60,000.00
- Mandor 0.025 Oh 110,000.00 2,750.00
2 1 m 3 Galian Tanah biasa 2 meter 76,950.00
- Pekerja 0.900 Oh 80,000.00 72,000.00
- Mandor 0.045 Oh 110,000.00 4,950.00
19 1 m 1 Benangan 17,201.00
- Semen Portland 1.440 Kg 1,500.00 2,160.00
- Pasir Pasang 0.010 M3 112,500.00 1,125.00
- Upah Pekerjaan
~ Pekerja 0.105 Oh 80,000.00 8,400.00
~ Tukang Batu 0.049 Oh 90,000.00 4,410.00
~ Kepala Tukang 0.005 Oh 100,000.00 490.00
~ Mandor 0.006 Oh 110,000.00 616.00
20 1 m 1 Tali air 10,177.33
- Semen Portland 0.600 Kg 1,500.00 900.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 80,000.00 5,600.00
~ Tukang Batu 0.033 Oh 90,000.00 2,940.00
~ Kepala Tukang 0.003 Oh 100,000.00 326.67
~ Mandor 0.004 Oh 110,000.00 410.67
IV PEKERJAAN LANTAI
1 1 m 2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm 192,137.50
- Keramik 20 x 20 cm 1.060 M2 60,000.00 63,600.00
- Semen Portland 10.400 Kg 1,500.00 15,600.00
- Pasir Pasang 0.045 M3 112,500.00 5,062.50
- Semen Warna 1.500 Kg 40,300.00 60,450.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.018 Oh 110,000.00 1,925.00
2 1 m 2 Pasang Lantai Keramik 40 x 40 cm warna KW I 252,177.50
- Keramik 40 x 40 cm 1.105 M2
120,000.00 132,600.00
- Semen Portland 9.800 Kg 1,500.00 14,700.00
- Pasir Pasang 0.045 M3 112,500.00 5,062.50
- Semen Warna 1.300 Kg 40,300.00 52,390.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.018 Oh 110,000.00 1,925.00
3 1 m 2 Pasang Keramik Dinding 20 x 25 cm KW I 238,100.00
- Keramik 20 x 25 cm 1.060 M2 95,000.00 100,700.00
- Semen Portland 9.300 Kg 1,500.00 13,950.00
- Pasir Pasang 0.018 M3 112,500.00 2,025.00
- Semen Warna 1.500 Kg 40,300.00 60,450.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 80,000.00 36,000.00
~ Tukang Batu 0.225 Oh 90,000.00 20,250.00
~ Kepala Tukang 0.023 Oh 100,000.00 2,250.00
~ Mandor 0.023 Oh 110,000.00 2,475.00
4 1 m Pasang List Keramik Dinding 5 x 20 cm warna KW I
1
44,532.65
- List Keramik 5 x 20 cm 5.300 bh 4,950.00 26,235.00
- Semen Portland 0.570 Kg 1,500.00 855.00
- Pasir Pasang 0.0015 M3 112,500.00 168.75
- Semen Warna 0.013 Kg 40,300.00 523.90
- Upah Pekerjaan
~ Pekerja 0.090 Oh 80,000.00 7,200.00
~ Tukang Batu 0.090 Oh 90,000.00 8,100.00
~ Kepala Tukang 0.009 Oh 100,000.00 900.00
~ Mandor 0.005 Oh 110,000.00 550.00
5 1 m Pasang Batu Alam Candi
2
259,562.50
- Batu Alam Candi 1.100 M2 173,250.00 190,575.00
- Semen Portland 11.750 kg 1,500.00 17,625.00
- Pasir Pasang 0.035 M3 112,500.00 3,937.50
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.0175 Oh 110,000.00 1,925.00
- Upah Pekerjaan
~ Pekerja 0.180 Oh 80,000.00 14,400.00
~ Tukang Batu 0.020 Oh 90,000.00 1,800.00
~ Tukang Kayu 0.020 Oh 90,000.00 1,800.00
~ Tukang Besi 0.020 Oh 90,000.00 1,800.00
~ Kepala Tukang 0.006 Oh 100,000.00 600.00
~ Mandor 0.009 Oh 110,000.00 990.00
14 1 m ' Membuat ring balok beton bertulang (10 x 15) cm 98,472.25
- Kayu Cetakan 0.003 M 3
948,750.00 2,846.25
- Paku Biasa 2 ' - 5' 0.020 Kg 16,425.00 328.50
- Besi beton (polos) 3.600 Kg 13,000.00 46,800.00
- Kawat beton 0.050 Kg 17,800.00 890.00
- Semen Portland 5.500 Kg 1,500.00 8,250.00
- Pasir Beton (Lumajang) 0.009 M3 212,500.00 1,912.50
- Batu Pecah Mesin 2/3 0.015 M3 141,666.67 2,125.00
- Upah Pekerjaan
~ Pekerja 0.297 Oh 80,000.00 23,760.00
~ Tukang Batu 0.033 Oh 90,000.00 2,970.00
~ Tukang Kayu 0.033 Oh 90,000.00 2,970.00
~ Tukang Besi 0.033 Oh 90,000.00 2,970.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
15 1 m 3 Membuat plat beton bertulang (150 kg besi + bekisting) 7,687,542.00
- Kayu Cetakan 0.320 M3 948,750.00 303,600.00
- Paku Biasa 2 ' - 5' 3.200 Kg 16,425.00 52,560.00
- Minyak Bekisting 1.600 Liter 3,960.00 6,336.00
- Besi beton (polos) 147.500 Kg 13,000.00 1,917,500.00
- Kawat beton 2.250 Kg 17,800.00 40,050.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Balok kayu 0.120 M3 4,804,800.00 576,576.00
- Plywood tebal 9 mm 2.800 Lbr 155,000.00 434,000.00
- Dolken Kayu galam 32.000 btg 90,860.00 2,907,520.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 80,000.00 424,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.300 Oh 90,000.00 117,000.00
~ Tukang Besi 1.050 Oh 90,000.00 94,500.00
~ Kepala Tukang 0.265 Oh 100,000.00 26,500.00
~ Mandor 0.265 Oh 110,000.00 29,150.00
VI PEKERJAAN KUSEN PINTU DAN JENDELA
1 1 M3 Pasang Kusen Pintu/jendela Kayu kamper 17,373,531.25
- kayu kamper kwalitas baik 1.200 M3 12,500,000.00 15,000,000.00
- Paku 10cm 1.250 kg 16,425.00 20,531.25
- Lem Kayu 1.000 kg 20,000.00 20,000.00
Upah Pekerjaan 0.00
~ Pekerja 6.000 Oh 80,000.00 480,000.00
~ Tukang Kayu 18.000 Oh 90,000.00 1,620,000.00
~ Kepala Tukang 2.000 Oh 100,000.00 200,000.00
~ Mandor 0.300 Oh 110,000.00 33,000.00
2 1 M2 Pasang pintu dan jendela kaca kayu kamper 575,850.00
- kayu kamper kwalitas baik 0.024 m³ 12,500,000.00 300,000.00
- Lem Kayu 0.300 kg 20,000.00 6,000.00
Upah Pekerjaan
~ Pekerja 0.700 Oh 80,000.00 56,000.00
~ Tukang Kayu 2.100 Oh 90,000.00 189,000.00
~ Kepala Tukang 0.210 Oh 100,000.00 21,000.00
~ Mandor 0.035 Oh 110,000.00 3,850.00
3 1 M2 Pasang Pintu Panil Kayu kamper 1,029,622.00
- Kayu Kamper papan 0.040 m³ 17,353,050.00 694,122.00
Upah Pekerjaan
~ Pekerja 1.000 Oh 80,000.00 80,000.00
~ Tukang Kayu 2.500 Oh 90,000.00 225,000.00
~ Kepala Tukang 0.250 Oh 100,000.00 25,000.00
~ Mandor 0.050 Oh 110,000.00 5,500.00
11 1 m' Menutup Bubungan genteng kodok dan sejenis Camp. 1PC : 3 Ps 102,820.00
~ P C ( 40 kg ) 0.200 zak 60,000.00 12,000.00
~ Pasir pasang 0.032 M3 112,500.00 3,600.00
~ bubung Gt.model kr.pilang 5.000 bh 7,000.00 35,000.00
Kepala Tukang Kayu -
~ Pekerja Biasa 0.400 Kg 80,000.00 32,000.00
~ Tukang Kayu 0.200 0 90,000.00 18,000.00
~ Kepala Tukang Kayu 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.002 Oh 110,000.00 220.00
12 1 m' Pasang listplang kayu meranti baik/waru tahun kwalitas bagus 3/20 79,332.50
- Upah Pekerjaan
~ Pekerja 0.000 Oh 80,000.00 -
~ Tukang Batu 0.000 Oh 90,000.00 -
~ Kepala Tukang 0.000 Oh 100,000.00 -
~ Mandor 0.000 Oh 110,000.00 -
A. TENAGA
B BAHAN
B BAHAN
Tenaga -
hariMandor @.Rp. 0.0005 110,000 55
hariKepala Tukang @.Rp. 0.0100 100,000 1,000
hariTukang Kayu @.Rp. 0.1000 90,000 9,000
hariPekerja @.Rp. 0.1000 80,000 8,000
Jumlah
Jumlah
Jumlah
Jumlah
( 1 m' Menutup Bubungan Asbes gel.kecil ) 6.24
m' Bubungan Asbes @.Rp. 1.1000 68,454 75,299
bh Paku skrup @.Rp. 4.0000 3,200 12,800
Jumlah
JENIS PEKERJAAN
SATUAN PEMBAYARAN
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B BAHAN
C PERALATAN
KODE ANALISA
JENIS PEKERJAAN
SATUAN PEMBAYARAN
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B BAHAN
C PERALATAN
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B BAHAN
C PERALATAN
JENIS :
SATUAN :
PERKIRAAN HARGA
NO.
KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B BAHAN
7,071,280.00
1 m 3 Pasang Kusen Pintu dan Jendela Kayu Kelas Awet III 7,811,681.25
- Kayu Meranti balok 1.200 M3 4,550,000.00 5,460,000.00
- Paku 10cm 1.250 kg 16,425.00 20,531.25
- Lem Kayu 1.000 kg 18,150.00 18,150.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 80,000.00 480,000.00
~ Tukang Kayu 18.000 Oh 90,000.00 1,620,000.00
~ Kepala Tukang 1.800 Oh 100,000.00 180,000.00
~ Mandor 0.300 Oh 110,000.00 33,000.00
Tenaga
###hariMandor @.Rp. 110,000 Rp. 138
###hariKepala Tukang @.Rp. 100,000 Rp. 2,500
###hariTukang Kayu @.Rp. 90,000 Rp. 36,000
###hariPekerja @.Rp. 80,000 Rp. 12,000
Jumlah
Jumlah
6.5 ( 1 m' Menutup Bubungan genteng kodok dan sejenis Camp. 1PC : 3 Ps )
Jumlah
KODE AN:
JENIS P :
SATUAN :
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B BAHAN
C PERALATAN
Jumlah
JENIS PE :
SATUAN :
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B BAHAN
C PERALATAN
6.5 ( 1 m' Menutup Bubungan genteng kodok dan sejenis Camp. 1PC : 3 Ps )
365477
8,000.00
11,000.00
1,000.00
450.00
20,450.00
57,475.00
55,550.00
17,846.40
8348671.4
Rp. 70095.26
Rp. 18055
Rp. 88150.26
Rp. 80800
Rp. 18700
Rp. 99500
Rp. 84443.3862433863
Rp. 18700
Rp. 103143.386243386
Rp. 95210
Rp. 19710
Rp. 114920
Rp. 88099.4
Rp. 19710
Rp. 107809.4
JUMLAH
HARGA
(Rp.)
30400
17100
1900
2090
#REF!
86625
7725
3431.25
6975.21
#REF!
232389.16
JUMLAH
HARGA
(Rp.)
8,640.00
16,200.00
1,800.00
594.00
27,234.00
240,000.00
98,000.00
338,000.00
365,234.00
JUMLAH
HARGA
(Rp.)
8,640.00
16,200.00
1,800.00
594.00
27,234.00
165,000.00
67,375.00
232,375.00
259,609.00
114,579.00
220,002.75
856,750.00
JUMLAH
HARGA
(Rp.)
Rp. 335500
Rp. 694122
Rp. 1,029,622
Rp. 268,400
Rp. 607,357
Rp. 875,757
Rp. 416,853
Rp. 20,430
= Rp. 20,430
= Rp. 103,630
= Rp. 20,430
Rp. 218,661
Rp. 50,638
Rp. 269,298
Rp. 50,505
Rp. 87,900
Rp. 138,405
= Rp. 138,405
= Rp. 138,405
= Rp. 138,405
= Rp. 258,405
Rp. 18,550
Rp. 57,064
Rp. 75,614
Rp. 15,600
Rp. 52,220
Rp. 67,820
= Rp. 327,820
= Rp.
Rp. 9,565
Rp. -
Rp. 9,565
JUMLAH
HARGA
(Rp.)
8000
9000
1000
550
18550
63700
4106.25
32760
100566.25
119,116
31500
190000
1620000
435000
Rp. 2276500
19878540
Rp. 19878540
22155040
Rp. 2,333,000
Rp. 15,000,000
Rp. 17,333,000
Rp. 0
Rp. #REF!
Rp. #REF!
JUMLAH
HARGA
(Rp.)
12600
27200
3040
900
43740
24752
29725
18000
3135
75612
119352
137920
22500 78750
16600 41500
25300 3795
80000 8000
95000 4750
105000 525
120000 600
43629.1
75000 27300
22310 2454.1
80000 8000
95000 4750
105000 525
120000 600
1PC : 3 Ps )
1542000
128800
3212800
ANALISA HARGA SATUAN BAHAN DAN UPAH TENAGA
BERDASARKAN SNI
TAHUN ANGGARAN 2016
HARGA HSPK
JUMLAH
NO JENIS PEKERJAAN KOEF. STN SATUAN 2013
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 1 m' Pagar sementara dari seng gelombang tinggi 2 m
Dolken kayu dia.8-10/400 1.250 Btg 17,250.00 21,562.50 220,778.75
Semen Portland 2.500 Kg 1,495.00 3,737.50
Seng Gelombang BJLS 30 1.200 Lbr 74,750.00 89,700.00
Pasir beton 0.005 M3 120,000.00 600.00
Koral Beton 0.009 M3 258,750.00 2,328.75
Kayu 5/7 0.072 M3 862,500.00 62,100.00
Paku 0.060 Kg 17,500.00 1,050.00
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.020 Oh 100,000.00 2,000.00
2 1 m Pengukuran dan Pemasangan Bouwplank 50,597.50
- Patok Kayu 0.012 M3 2,530,000.00 30,360.00
- Paku 0.020 Kg 17,500.00 350.00
- Kayu Papan 3/20 0.007 M3 862,500.00 6,037.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00
3 1 m2 Pembuatan gudang semen dan alat-alat 577,060.00
- Dolken kayu dia.8-10/400 1.700 Btg 17,250.00 29,325.00
- Kayu 0.210 M3 862,500.00 181,125.00
- Paku 0.300 Kg 17,500.00 5,250.00
- Semen Portland 10.500 Kg 1,495.00 15,697.50
- Pasir beton 0.030 M3 120,000.00 3,600.00
- Koral Beton 0.050 M3 258,750.00 12,937.50
- Seng Gelombang BJLS 30 1.500 Lbr 74,750.00 112,125.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 2.000 Oh 70,000.00 140,000.00
~ Kepala Tukang 0.200 Oh 85,000.00 17,000.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
4 1 m2 Pembuatan rumah jaga/konstruksi kayu 591,925.00
- Dolken kayu dia.8-10/400 3.000 Btg 17,250.00 51,750.00
- Kayu 0.276 M3 862,500.00 238,050.00
- Paku 0.700 Kg 17,500.00 12,250.00
- Seng Gelombang BJLS 30 1.500 Lbr 74,750.00 112,125.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 1.500 Oh 70,000.00 105,000.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
5 1 m2 Pembuatan Stegger dari bambu, ukuran (40x50x20) cm 35,847.50
- Bambu Ø 6-8 / 600 cm 1.000 Btg 17,250.00 17,250.00
- Tali ijuk 0.250 Kg 8,750.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.250 Oh 55,000.00 13,750.00
~ Tukang Kayu 0.017 Oh 70,000.00 1,190.00
~ Kepala Tukang 0.002 Oh 85,000.00 170.00
~ Mandor 0.013 Oh 100,000.00 1,300.00
6 1 m 3 Bongkaran Beton Bertulang 407,190.00
- Pekerja 6.667 Oh 55,000.00 366,685.00
- Mandor 0.333 Oh 100,000.00 33,300.00
Alat
- Bodem 0.025 unit 135,000.00 3,375.00
- Keranjang 0.050 unit 11,500.00 575.00
- Gergaji Besi 0.068 unit 35,000.00 2,380.00
- Betel 0.025 unit 35,000.00 875.00
II PEKERJAAN TANAH
1 1 m 3 Galian Tanah biasa sedalam 1 meter 43,750.00
- Pekerja 0.750 Oh 55,000.00 41,250.00
- Mandor 0.025 Oh 100,000.00 2,500.00
2 1 m 3 Galian Tanah biasa 2 meter 54,000.00
- Pekerja 0.900 Oh 55,000.00 49,500.00
- Mandor 0.045 Oh 100,000.00 4,500.00
3 1 m 3 Galian Tanah biasa 3 meter 64,450.00
- Pekerja 1.050 Oh 55,000.00 57,750.00
- Mandor 0.067 Oh 100,000.00 6,700.00
4 1 m 3 Galian Tanah keras 1 meter 58,200.00
- Pekerja 1.000 Oh 55,000.00 55,000.00
- Mandor 0.032 Oh 100,000.00 3,200.00
5 1 m 3 Galian cadas Keras 1 meter 88,500.00
- Pekerja 1.500 Oh 55,000.00 82,500.00
- Mandor 0.060 Oh 100,000.00 6,000.00
6 1 m 3 Galian Lumpur sedalam 1 meter 70,500.00
- Pekerja 1.200 Oh 55,000.00 66,000.00
- Mandor 0.045 Oh 100,000.00 4,500.00
7 1 m ' Galian bor Strouze (Dia =30 cm ) 69,725.00
- Pekerja 0.735 Oh 55,000.00 40,425.00
- Mandor 0.073 Oh 100,000.00 7,300.00
- Sewa Peralatan bor 1.000 ls 22,000.00 22,000.00
8 1 m ' Pengeboran air tanah (sumur pompa) 54,950.00
- Pekerja 0.750 Oh 55,000.00 41,250.00
- Mandor 0.072 Oh 100,000.00 7,200.00
- Sewa Peralatan bor / tradisionil 1.000 ls 6,500.00 6,500.00
9 1 m 3 Urugan kembali 14,583.33
- Pekerja 0.250 Oh 55,000.00 13,750.00
- Mandor 0.008 Oh 100,000.00 833.33
10 1 m 3 Pemadatan tanah ( per 20 cm ) 32,500.00
- Pekerja 0.500 Oh 55,000.00 27,500.00
- Mandor 0.050 Oh 100,000.00 5,000.00
11 1 m 3 Urugan Pasir Padat 101,500.00
- Pasir Urug 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
12 1 m 3 Urugan Sirtu Padat 114,100.00
- Sirtu 1.200 M3 80,500.00 96,600.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
13 1 m 3 Urugan Sirtu Padat untuk peninggian lantai bangunan 112,850.00
- Sirtu 1.200 M3 80,500.00 96,600.00
- Upah Pekerjaan
~ Pekerja 0.250 Oh 55,000.00 13,750.00
~ Mandor 0.025 Oh 100,000.00 2,500.00
14 1 m 3 Urugan Tanah Padat 89,500.00
- Tanah urug 1.200 M3 60,000.00 72,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
15 1 m 3 Urugan Paras Padat 101,500.00
- Tanah Paras 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
IV PEKERJAAN PLESTERAN
1 1 m 2 Plesteran 1 Pc : 2 Ps, tebal 15 mm #REF!
- Semen Portland 10.224 Kg #REF! #REF!
- Pasir Pasang 0.020 M3 90,400.00 1,808.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
2 1 m 2 Plesteran 1 Pc : 3 Ps, tebal 15 mm #REF!
- Semen Portland 7.776 Kg #REF! #REF!
- Pasir Pasang 0.023 M3 90,400.00 2,079.20
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
3 1 m 2 Plesteran 1 Pc : 5 Ps, tebal 15 mm #REF!
- Semen Portland 5.184 Kg #REF! #REF!
- Pasir Pasang 0.026 M3 90,400.00 2,350.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
V PEKERJAAN LANTAI
1 1 m 2 Pasang Lantai Keramik 30 X 30 cm Putih KW I #REF!
- Keramik 30 x 30 cm 1.080 M2 48,900.00 52,812.00
- Semen Portland 10.000 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
2 1 m 2 Pasang Lantai Keramik 40 x 40 cm putih KW I #REF!
- Keramik 40 x 40 cm 1.105 M2 #REF! #REF!
- Semen Portland 9.800 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
3 1 m 2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm #REF!
- Keramik 20 x 20 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 10.400 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
3 1 m 2 Pasang Lantai Keramik Warna KM/WC 25 x 25 cm #REF!
- Keramik 20 x 20 cm 1.060 M2 #REF! #REF!
- Semen Portland 10.400 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 85,000.00 29,750.00
~ Tukang Batu 0.175 Oh 100,000.00 17,500.00
~ Kepala Tukang 0.018 Oh 0.00 -
~ Mandor 0.018 Oh #REF! #REF!
4 1 m 2 Pasang Lantai Keramik 30 x 30 cm Warna KW I #REF!
- Keramik 30 x 30 cm 1.080 M2 48,900.00 52,812.00
- Semen Portland 10.000 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
5 1 m 2 Pasang Lantai Keramik 30 x 30 cm Motif Kasar KW1 #REF!
- Keramik 30 x 30 cm Kasar 1.080 M2 52,900.00 57,132.00
- Semen Portland 10.000 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
VI PEKERJAAN ATAP
1 1 m3 Pasang Konstruksi Kuda-kuda Ekspose Kayu Kelas Kuat I 21,577,850.00
- Kayu Jati, balok 1.200 M3 16,100,000.00 19,320,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 6.700 Oh 55,000.00 368,500.00
~ Tukang Kayu 20.100 Oh 70,000.00 1,407,000.00
~ Kepala Tukang 2.010 Oh 85,000.00 170,850.00
~ Mandor 0.335 Oh 100,000.00 33,500.00
2 1 m3 Pasang Konstruksi Kuda-kuda konvensional kayu kelas I 19,170,000.00
- Kayu Jati, balok 1.100 M3 16,100,000.00 17,710,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00
3 1 m3 Pasang Konstruksi Kuda-kuda Kayu Kamper
- Kayu Kamper, balok 1.100 M3 -
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 1,460,000.00
3 1 m3 Pasang Konstruksi Kuda-kuda Kayu kelas II 8,291,000.00
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00
PEKERJAAN
X PENGECATAN
1 1 m 2 mendempul dan menggosok kayu 8,682.00
- Plamir Kayu 0.080 Kg 31,600.00 2,528.00
- Minyak Cat 0.020 kg 26,450.00 529.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Cat 0.040 Oh 70,000.00 2,800.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.0025 Oh 100,000.00 250.00
2 1 m 2 Pengecatan bidang kayu lama 18,300.05
- Cat Kayu 0.142 Kg 55,000.00 7,810.00
- Minyak cat 0.019 Lt 26,450.00 502.55
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
3 1 m 2 Pengecatan bidang kayu baru 35,402.50
- Cat Kayu 0.260 Kg 55,000.00 14,300.00
- Plamir 0.150 Kg 31,600.00 4,740.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
4 1 m 2 Pengecatan besi baru 37,127.50
- Cat besi Emco 0.260 Kg 55,000.00 14,300.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Plamir 0.150 Kg 43,100.00 6,465.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
5 1 m 2 Pengecatan besi Finishing baru (Tanpa Cat dasar) 20,235.00
- Cat besi Emco Finishing ( 3 Lapis ) 0.260 Kg 55,000.00 14,300.00
- Upah Pekerjaan
~ Pekerja 0.035 Oh 55,000.00 1,925.00
~ Tukang Cat 0.053 Oh 70,000.00 3,710.00
~ Kepala Tukang 0.0020 Oh 85,000.00 170.00
~ Mandor 0.0013 Oh 100,000.00 130.00
6 1 m 2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter 11,822.50
- Residu atau Ter 0.350 Ltr 16,350.00 5,722.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Mandor 0.006 Oh 100,000.00 600.00
7 1 m 2 Pelaburan Bidang Kayu dengan Politur 37,622.40
- Politur 0.372 Ltr 66,700.00 24,812.40
- Ampelas 2.000 Lbr 3,500.00 7,000.00
- Upah Pekerjaan
~ Tukang Cat 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00
8 1 m 2 Pelaburan Bidang Kayu dengan Vernis 37,195.00
- Vernis 0.150 Ltr 88,550.00 13,282.50
- Dempul 0.050 Kg 35,600.00 1,780.00
- Ampelas 0.100 Lbr 3,500.00 350.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.160 Oh 55,000.00 8,800.00
~ Tukang Cat 0.160 Oh 70,000.00 11,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00
XI PEKERJAAN SANITAIR
1 Memasang 1 buah kloset duduk / monoblok 2,336,285.00
- Kloset duduk / monoblok 1.000 Bh 1,945,000.00 1,945,000.00
- Perlengkapan 0.060 hrg 1,945,000.00 116,700.00
- Upah Pekerjaan
~ Pekerja 3.300 Oh 55,000.00 181,500.00
~ Tukang Batu 1.100 Oh 70,000.00 77,000.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.160 Oh 100,000.00 16,000.00
2 Memasang 1 buah kloset jongkok porselen 439,874.00
- Kloset jongkok porselen 1.000 Bh 126,500.00 126,500.00
- Semen portland 6.000 Kg 1,495.00 8,970.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.500 Oh 70,000.00 105,000.00
~ Kepala Tukang 1.500 Oh 85,000.00 127,500.00
~ Mandor 0.160 Oh 100,000.00 16,000.00
3 Memasang 1 buah urinoir 1,427,374.00
- Urinoir 1.000 Bh 980,000.00 980,000.00
- Perlengkapan 0.300 hrg 980,000.00 294,000.00
- Semen portland 6.000 Kg 1,495.00 8,970.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.000 Oh 70,000.00 70,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 8,500.00
~ Mandor 0.100 Oh 100,000.00 10,000.00
4 Memasang 1 buah wastafel 527,124.00
- Wastafel 1.000 Bh 300,000.00 300,000.00
- Perlengkapan 0.120 hrg 300,000.00 36,000.00
- Semen portland 6.000 Kg 1,495.00 8,970.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 55,000.00 66,000.00
~ Tukang Batu 1.450 Oh 70,000.00 101,500.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
5 Memasang 1 buah bak cuci stainless 455,350.00
- Bak cuci stainless 1.000 Bh 400,000.00 400,000.00
- Water drain dan accessories 1.000 set 30,000.00 30,000.00
- Upah Pekerjaan
~ Pekerja 0.030 Oh 55,000.00 1,650.00
~ Tukang Batu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0015 Oh 100,000.00 150.00
6 Memasang 1 buah bak mandi fiber glass 1,617,718.80
- Bak fiberglass 1.000 Bh 1,078,660.00 1,078,660.00
- Perlengkapan 0.180 hrg 1,078,660.00 194,158.80
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 70,000.00 189,000.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00
7 Memasang 1 pintu KM PVC 661,150.00
- Pintu PVC 1.000 Bh 316,250.00 316,250.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 70,000.00 189,000.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00
JUMLAH
NO URAIAN - PEKERJAAN (RP)
JUMLAH Rp 61,924,080.79
PPN 10 % Rp 6,192,408
Rp 68,116,489
STANDART SATUAN HARGA BAHAN 2018
HARGA
NO JENIS BAHAN SATUAN (Rp.)
1 2 3 4