ANALISA HARGA SATUAN BAHAN DAN UPAH TENAGA

BERDASARKAN SNI
TAHUN ANGGARAN 2011
KOTA PROBOLINGGO

KOEF HARGA HSPK


JUMLAH
NO JENIS PEKERJAAN BARU STN SATUAN 2011
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 1 m Pengukuran dan Pemasangan Bouwplank
- Kayu Perancah 5/7 0.012 M3 2,875,000.00 34,500.00
- Paku 0.020 Kg 17,500.00 350.00
- Kayu Papan 3/20 0.007 M3 862,500.00 6,037.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 54,737.50
2 1 m3 Bongkaran Beton Bertulang
- Pekerja 6.667 Oh 55,000.00 366,685.00
- Mandor 0.333 Oh 100,000.00 33,300.00
Alat
- Bodem 0.025 unit 135,000.00 3,375.00
- Keranjang 0.050 unit 11,500.00 575.00
- Gergaji Besi 0.068 unit 35,000.00 2,380.00
- Betel 0.025 unit 35,000.00 875.00 407,190.00
3 1 m3 Bongkaran Dinding tembok bata merah
- Pekerja 6.667 Oh 55,000.00 366,685.00
- Mandor 0.033 Oh 100,000.00 3,330.00 370,015.00
4 1 m2 Membersihkan lapangan dan perataan
- Pekerja 0.100 Oh 55,000.00 5,500.00
- Mandor 0.050 Oh 100,000.00 5,000.00 10,500.00
II PEKERJAAN TANAH
1 1 m3 Galian Tanah biasa sedalam 1 meter
- Pekerja 0.750 Oh 55,000.00 41,250.00
- Mandor 0.025 Oh 100,000.00 2,500.00 43,750.00
2 1 m3 Galian Tanah biasa 2 meter
- Pekerja 0.900 Oh 55,000.00 49,500.00
- Mandor 0.045 Oh 100,000.00 4,500.00 54,000.00
3 1 m3 Galian Tanah biasa 3 meter
- Pekerja 1.050 Oh 55,000.00 57,750.00
- Mandor 0.067 Oh 100,000.00 6,700.00 64,450.00
4 1 m3 Galian Tanah keras 1 meter
- Pekerja 1.000 Oh 55,000.00 55,000.00
- Mandor 0.032 Oh 100,000.00 3,200.00 58,200.00
5 1 m3 Galian cadas Keras 1 meter
- Pekerja 1.500 Oh 55,000.00 82,500.00
- Mandor 0.060 Oh 100,000.00 6,000.00 88,500.00
6 1 m3 Galian Lumpur sedalam 1 meter
- Pekerja 1.200 Oh 55,000.00 66,000.00
- Mandor 0.045 Oh 100,000.00 4,500.00 70,500.00
7 1 m' Galian bor Strouze (Dia =30 cm )
- Pekerja 0.735 Oh 55,000.00 40,425.00
- Mandor 0.073 Oh 100,000.00 7,300.00
- Sewa Peralatan bor 1.000 ls 8,500.00 8,500.00 56,225.00
8 1 m' Pengeboran air tanah (sumur pompa)
- Pekerja 0.750 Oh 55,000.00 41,250.00
- Mandor 0.072 Oh 100,000.00 7,200.00
- Sewa Peralatan bor / tradisionil 1.000 ls 4,500.00 4,500.00 52,950.00
9 1 m3 Urugan kembali
- Pekerja 0.250 Oh 55,000.00 13,750.00
1 2 3 4 5 6 7
- Mandor 0.008 Oh 100,000.00 833.33 14,583.33
10 1 m3 Pemadatan tanah ( per 20 cm )
- Pekerja 0.500 Oh 55,000.00 27,500.00
- Mandor 0.050 Oh 100,000.00 5,000.00 32,500.00
11 1 m3 Urugan Pasir Padat
- Pasir Urug 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 101,500.00
1 2 3 4 5 6 7
12 1 m3 Urugan Sirtu Padat
- Sirtu 1.200 M3 80,500.00 96,600.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 114,100.00
13 1 m3 Urugan Sirtu Padat untuk peninggian lantai bangunan
- Sirtu 1.200 M3 80,500.00 96,600.00
- Upah Pekerjaan
~ Pekerja 0.250 Oh 55,000.00 13,750.00
~ Mandor 0.025 Oh 100,000.00 2,500.00 112,850.00
14 1 m3 Urugan Tanah Padat
- Tanah urug 1.200 M3 60,000.00 72,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 89,500.00
15 1 m3 Urugan Paras Padat
- Tanah Paras 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 101,500.00

III PEKERJAAN PASANGAN


1 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 4 Ps
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 163.000 Kg 1,495.00 243,685.00
- Pasir Pasang 0.520 M3 90,400.00 47,008.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00 595,568.00
2 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 136.000 Kg 1,495.00 203,320.00
- Pasir Pasang 0.544 M3 90,400.00 49,177.60
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00 557,372.60
3 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 91.000 Kg 1,495.00 136,045.00
- Pasir Pasang 0.584 M3 90,400.00 52,793.60
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00 493,713.60
4 1 m3 Pasang Pondasi Batu Kali, 1 : 3 : 10
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 61.000 Kg 1,495.00 91,195.00
- Pasir Pasang 0.492 M3 90,400.00 44,476.80
- Kapur pasang 0.147 M3 488,750.00 71,846.25
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00 512,393.05
5 1 m3 Pasang Aanstampeng Batu Kali termasuk urugan pasir
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Pasir Urug 0.432 M3 70,000.00 30,240.00
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.780 Oh 55,000.00 42,900.00
~ Tukang Batu 0.390 Oh 70,000.00 27,300.00
~ Kepala Tukang 0.039 Oh 85,000.00 3,315.00
~ Mandor 0.039 Oh 100,000.00 3,900.00 263,655.00
6 1 m2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 3 Ps
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 14.370 Kg 1,495.00 21,483.15
- Pasir Pasang 0.040 M3 90,400.00 3,616.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 92,949.15
1 2 3 4 5 6 7
7 1 m2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 5 Ps
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 9.680 Kg 1,495.00 14,471.60
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 86,389.60
8 1 m2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 8Ps
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 6.500 Kg 1,495.00 9,717.50
- Pasir Pasang 0.050 M3 90,400.00 4,520.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 82,087.50
9 1 m2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 2 Ps
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 43.500 Kg 1,495.00 65,032.50
- Pasir Pasang 0.080 M3 90,400.00 7,232.00
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00 207,964.50
10 1 m2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 3 Ps
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 32.950 Kg 1,495.00 49,260.25
- Pasir Pasang 0.091 M3 90,400.00 8,226.40
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00 193,186.65
11 1 m2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 4 Ps
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 26.550 Kg 1,495.00 39,692.25
- Pasir Pasang 0.093 M3 90,400.00 8,407.20
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00 183,799.45
12 1 m2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 5 Ps
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 22.200 Kg 1,495.00 33,189.00
- Pasir Pasang 0.102 M3 90,400.00 9,220.80
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00 178,109.80
14 1 m2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 6 Ps
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 18.500 Kg 1,495.00 27,657.50
- Pasir Pasang 0.122 M3 90,400.00 11,028.80
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00 174,386.30
1 2 3 4 5 6 7
14 1 m2 Pasang dinding pemisah plywood rangkap, rangka kayu kamper
- Kayu Kamper, balok 0.0280 M3 0.00 -
- Paku biasa 2" - 5" 0.150 Kg 17,500.00 2,625.00
- Lem kayu 0.560 Lt 12,500.00 7,000.00
- Plywood 120 cm x 240 mm x 4 mm 0.860 Lbr 54,700.00 47,042.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.600 Oh 70,000.00 42,000.00
~ Kepala Tukang 0.060 Oh 85,000.00 5,100.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 115,767.00
1 2 3 4 5 6 7
15 1 m2 Pasang dinding pemisah plywood rangkap, rangka kayu meranti
- Kayu Meranti, balok 0.0280 M3 6,210,000.00 173,880.00
- Paku biasa 2" - 5" 0.150 Kg 17,500.00 2,625.00
- Lem kayu 0.560 Lt 12,500.00 7,000.00
- Plywood 120 cm x 240 mm x 4 mm 0.860 Lbr 54,700.00 47,042.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.600 Oh 70,000.00 42,000.00
~ Kepala Tukang 0.060 Oh 85,000.00 5,100.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 289,647.00
16 1 m2 Pasangan dinding roster terawang bakar (12x11x24), 1 Pc : 4 Pp
- Roster/terawang 30.000 Bh 4,600.00 138,000.00
- Semen Portland 11.000 Kg 1,495.00 16,445.00
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.0100 Oh 85,000.00 850.00
~ Mandor 0.0150 Oh 100,000.00 1,500.00 183,459.00
17 1 m2 Pasangan Platelaag ( 1 Lapis )
- Bata Merah 5 x 11 x 22 cm 35.000 Bh 600.00 21,000.00
- Semen Portland 0.605 kg 1,495.00 904.48
- Pasir Pasang 0.023 M3 90,400.00 2,034.00
- Upah Pekerjaan
~ Pekerja 0.160 Oh 55,000.00 8,800.00
~ Tukang Batu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.008 Oh 100,000.00 750.00 37,413.48

IV PEKERJAAN PLESTERAN
1 1 m2 Plesteran 1 Pc : 2 Ps, tebal 15 mm
- Semen Portland 10.224 Kg 1,495.00 15,284.88
- Pasir Pasang 0.020 M3 90,400.00 1,808.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 46,867.88
2 1 m2 Plesteran 1 Pc : 3 Ps, tebal 15 mm
- Semen Portland 7.776 Kg 1,495.00 11,625.12
- Pasir Pasang 0.023 M3 90,400.00 2,079.20
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 43,479.32
3 1 m2 Plesteran Halus 1 Pc : 5 Ps, tebal 15 mm
- Semen Portland 5.184 Kg 1,495.00 7,750.08
- Pasir Pasang 0.026 M3 90,400.00 2,350.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 39,875.48
4 1 m2 Plesteran Halus 1 Pc : 6 Ps, tebal 15 mm
- Semen Portland 4.416 Kg 1,495.00 6,601.92
- Pasir Pasang 0.027 M3 90,400.00 2,440.80
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 38,817.72
5 1 m2 Plesteran 1 Pc : 8 Ps, tebal 15 mm
1 2 3 4 5 6 7
- Semen Portland 3.456 Kg 1,495.00 5,166.72
- Pasir Pasang 0.029 M3 90,400.00 2,621.60
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 37,563.32
6 1 m2 Plesteran 1 Pc : 2 Ps, tebal 20 mm
- Semen Portland 13.632 Kg 1,495.00 20,379.84
- Pasir Pasang 0.027 M3 90,400.00 2,440.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.0220 Oh 100,000.00 2,200.00 62,720.64
1 2 3 4 5 6 7
7 1 m2 Plesteran 1 Pc : 3 Ps, tebal 20 mm
- Semen Portland 10.368 Kg 1,495.00 15,500.16
- Pasir Pasang 0.031 M3 90,400.00 2,802.40
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.0220 Oh 100,000.00 2,200.00 58,202.56
8 1 m2 Plesteran Halus 1 Pc : 5 Ps, tebal 20 mm
- Semen Portland 6.912 Kg 1,495.00 10,333.44
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.022 Oh 100,000.00 2,200.00 53,397.44
9 1 m2 Plesteran Ciprat 1 Pc : 2 Ps
- Semen Portland 4.320 Kg 1,495.00 6,458.40
- Pasir Pasang 0.006 M3 90,400.00 542.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 32,850.80
10 1 m2 Finishing Siar Pas. Dinding
- Semen Portland 3.108 Kg 1,495.00 4,646.46
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Batu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00 19,626.46
11 1 m2 Finishing Siar 1 Pc : 2 Ps, Pas. Batu Kali
- Semen Portland 6.340 Kg 1,495.00 9,478.30
- Pasir Pasang 0.012 M3 90,400.00 1,084.80
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00 40,338.10
12 1 m2 Acian
- Semen Portland 3.250 Kg 1,495.00 4,858.75
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 24,708.75
13 1 m1 Benangan
- Semen Portland 1.440 Kg 1,495.00 2,152.80
- Pasir Pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 0.105 Oh 55,000.00 5,775.00
~ Tukang Batu 0.049 Oh 70,000.00 3,430.00
~ Kepala Tukang 0.005 Oh 85,000.00 416.50
~ Mandor 0.006 Oh 100,000.00 560.00 13,238.30
14 1 m1 Tali air
- Semen Portland 0.600 Kg 1,495.00 897.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.033 Oh 70,000.00 2,286.67
~ Kepala Tukang 0.003 Oh 85,000.00 277.67
~ Mandor 0.004 Oh 100,000.00 373.33 7,684.67

V PEKERJAAN LANTAI
1 2 3 4 5 6 7
1 1 m2 Pasang Lantai Keramik 30 X 30 cm Putih KW I
- Keramik 30 x 30 cm 1.080 M2 36,300.00 39,204.00
- Semen Portland 10.000 Kg 1,495.00 14,950.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 107,659.50
1 2 3 4 5 6 7
2 1 m2 Pasang Lantai Keramik 40 x 40 cm putih KW I
- Keramik 40 x 40 cm 1.105 M2 45,500.00 50,277.50
- Semen Portland 9.800 Kg 1,495.00 14,651.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 116,474.00
3 1 m2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm
- Keramik 20 x 20 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 10.400 Kg 1,495.00 15,548.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 123,908.50
4 1 m2 Pasang Lantai Keramik 30 x 30 cm Warna KW I
- Keramik 30 x 30 cm 1.080 M2 48,900.00 52,812.00
- Semen Portland 10.000 Kg 1,495.00 14,950.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 121,267.50
5 1 m2 Pasang Lantai Keramik 30 x 30 cm Motif Kasar KW1
- Keramik 30 x 30 cm Kasar 1.080 M2 52,900.00 57,132.00
- Semen Portland 10.000 Kg 1,495.00 14,950.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 125,587.50
6 1 m2 Pasang Lantai Keramik 40 x 40 cm warna KW I
- Keramik 40 x 40 cm 1.105 M2 57,500.00 63,537.50
- Semen Portland 9.800 Kg 1,495.00 14,651.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00 129,734.00
7 1 m2 Pasang Keramik Dinding 20 x 25 cm putih KW I
- Keramik 20 x 25 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 9.300 Kg 1,495.00 13,903.50
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00 129,748.20
8 1 m2 Pasang Keramik Dinding 20 x 25 cm warna KW I
- Keramik 20 x 25 cm 1.060 M2 55,200.00 58,512.00
- Semen Portland 9.300 Kg 1,495.00 13,903.50
1 2 3 4 5 6 7
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00 133,405.20
9 1 m1 Pasang List Keramik Dinding 5 x 20 cm warna KW I
- List Keramik 5 x 20 cm 5.300 bh 3,500.00 18,550.00
- Semen Portland 0.493 Kg 1,495.00 736.89
- Pasir Pasang 0.0010 M3 90,400.00 90.40
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.048 Oh 55,000.00 2,623.50
~ Tukang Batu 0.024 Oh 70,000.00 1,666.00
~ Kepala Tukang 0.002 Oh 85,000.00 204.00
~ Mandor 0.0024 Oh 100,000.00 240.00 38,810.79
1 2 3 4 5 6 7
10 1 m2 Pasang Lantai Tegel Abu-abu
- Tegel Abu-abu 1.060 M2 46,000.00 48,760.00
- Semen Portland 10.400 Kg 1,495.00 15,548.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Upah Pekerjaan
~ Pekerja 0.270 Oh 55,000.00 14,850.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.014 Oh 85,000.00 1,190.00
~ Mandor 0.0140 Oh 100,000.00 1,400.00 95,266.00
11 1 m2 Pasang Batu Alam Candi
- Batu Alam Candi 1.100 M2 115,000.00 126,500.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 181,967.75
12 1 m2 Pasang Batu Alam Garis
- Batu Alam Garis 1.100 M2 109,250.00 120,175.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 175,642.75
13 1 m2 Pasang Batu Alam Koral/Ampyang
- Batu Alam Koral/Ampyang 1.100 M2 23,000.00 25,300.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 80,767.75
14 1 m2 Pasang Batu Alam Palimanan, Sukabumi, Lempeng 10/10
- Batu Alam Palimanan 1.100 M2 103,500.00 113,850.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 169,317.75
15 1 m2 Pasang Batu Alam Lempeng/Piring
- Batu Alam Lempeng 1.100 M2 28,750.00 31,625.00
- Semen Portland 11.750 kg 1,495.00 17,566.25
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00 87,092.75
16 1 Bh Pasang Glass Block
- Glass Block 1.000 Bh 20,700.00 20,700.00
- Semen Portland 0.150 kg 1,495.00 224.25
- Upah Pekerjaan 1.000 ls 3,000.00 3,000.00 23,924.25
17 1 m2 Pasang Wall covering lebar 50 cm
- Vinyl wall covering, lebar 50 cm 2.200 M 70,000.00 154,000.00
- Lem 0.250 Kg 12,500.00 3,125.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
1 2 3 4 5 6 7
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.170 Oh 85,000.00 14,450.00
~ Mandor 0.0200 Oh 100,000.00 2,000.00 205,075.00

VI PEKERJAAN ATAP
1 1 m3 Pasang Konstruksi Kuda-kuda Ekspose Kayu Jati ( Klas I)
- Kayu Jati, balok 1.200 M3 16,100,000.00 19,320,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 6.700 Oh 55,000.00 368,500.00
~ Tukang Kayu 20.100 Oh 70,000.00 1,407,000.00
~ Kepala Tukang 2.010 Oh 85,000.00 170,850.00
~ Mandor 0.335 Oh 100,000.00 33,500.00 21,577,850.00
1 2 3 4 5 6 7
2 1 m3 Pasang Konstruksi Kuda-kuda Kayu Jati ( Klas I)
- Kayu Jati, balok 1.100 M3 16,100,000.00 17,710,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 19,170,000.00
4 1 m3 Pasang Konstruksi Kuda-kuda Kayu Meranti Asli (MA)
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 8,291,000.00
5 1 m3 Pasang Konstruksi Kuda-kuda Kayu Kruing
- Kayu Kruing, balok 1.100 M3 5,750,000.00 6,325,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 7,785,000.00
6 1 m3 Pasang Konstruksi Gording Kayu Kruing
- Kayu Kruing, balok 1.100 M3 5,750,000.00 6,325,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 3.00 Kg 17,500.00 52,500.00
- Upah Pekerjaan
~ Pekerja 2.400 Oh 55,000.00 132,000.00
~ Tukang Kayu 7.200 Oh 70,000.00 504,000.00
~ Kepala Tukang 0.720 Oh 85,000.00 61,200.00
~ Mandor 0.120 Oh 100,000.00 12,000.00 7,266,700.00
7 1 m3 Pasang Konstruksi Gording Kayu Meranti Asli (MA)
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 3.00 Kg 17,500.00 52,500.00
- Upah Pekerjaan
~ Pekerja 2.400 Oh 55,000.00 132,000.00
~ Tukang Kayu 7.200 Oh 70,000.00 504,000.00
~ Kepala Tukang 0.720 Oh 85,000.00 61,200.00
~ Mandor 0.120 Oh 100,000.00 12,000.00 7,772,700.00
8 1 m2 Pasang Kaso (5/7) + Reng (2/3) Kayu Kruing
- Kayu Kruing, balok 0.010 M3 5,750,000.00 57,500.00
- Kayu Kruing, balok 0.004 M3 5,750,000.00 23,000.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 98,725.00
9 1 m2 Pasang Kaso (5/7) + Reng (2/3) Kayu Meranti (MA)
- Kayu Meranti. Balok 0.010 M3 6,210,000.00 62,100.00
- Kayu Meranti, balok 0.004 M3 6,210,000.00 24,840.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 105,165.00
1 2 3 4 5 6 7
10 1 m2 Pasang Kaso (5/7) Kruing + Reng (2/3) Kayu Meranti MA
- Kayu Kruing, balok 0.010 M3 5,750,000.00 57,500.00
- Kayu Meranti, balok 0.004 M3 6,210,000.00 24,840.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 100,565.00
11 1 m2 Pasang Kaso (5/7) Kayu Kruing
- Kayu Meranti, balok 0.0100 M3 5,750,000.00 57,500.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 66,612.50
1 2 3 4 5 6 7
12 1 m2 Pasang Kaso (5/7) Kayu Meranti MA
- Kayu Meranti, balok 0.0100 M3 6,210,000.00 62,100.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 71,212.50
13 1 m2 Reng (2/3) Kayu Meranti MA
- Kayu Meranti, balok 0.004 M3 6,210,000.00 22,356.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 31,468.50
14 1 m2 Reng (3/5) Kayu Meranti MA
- Kayu Meranti, balok MA 0.008 M3 6,210,000.00 49,680.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 58,792.50
15 1 m2 Reng (2/3) Kayu Meranti MC
- Kayu Meranti, balok 0.004 M3 4,025,000.00 14,490.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 23,602.50
16 1 m2 Reng (3/5) Kayu Meranti MC
- Kayu Meranti, balok MC 0.008 M3 4,025,000.00 32,200.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 41,312.50
17 1 m2 Pasang Atap Genteng Karang Pilang besar
- Genteng Karang Pilang 13.500 Bh 5,750.00 77,625.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.008 Oh 100,000.00 800.00 91,385.00
18 1 m2 Pasang Atap Genteng Model Karang Pilang (ex Ambulu)
- Genteng model Karang Pilang 25.000 Bh 2,550.00 63,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00 78,730.00
19 1 m2 Pasang Atap Genteng Pres Kedung Bajul (biasa)
- Genteng Pres Kedung Bajul 25.000 Bh 1,500.00 37,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00 52,480.00
20 1 m2 Pasang Atap Genteng Beton
- Genteng Beton 11.000 Bh 5,750.00 63,250.00
1 2 3 4 5 6 7
- Paku 0.030 Kg 17,500.00 525.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.008 Oh 100,000.00 800.00 77,535.00
21 1 m Pasang Bubung Genteng Karang Pilang
- Genteng bubung karang pilang 5.000 Bh 6,900.00 34,500.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 87,252.80
1 2 3 4 5 6 7
22 1 m Pasang Bubung Genteng Model Karang Pilang
- Genteng bubung model karang pilang 5.000 Bh 5,750.00 28,750.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 81,502.80
23 1 m Pasang Bubung Pres Kedung Bajul
- Genteng Bubung pres kedung bajul 5.000 Bh 4,050.00 20,250.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 73,002.80
24 1 m Pasang Bubung Pres Beton
- Genteng Bubung beton 4.000 Bh 8,650.00 34,600.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00 87,352.80
25 1 m Pasang Bubung Asbes Gelombang kecil
- Asbes Bubung Gelombang 1.000 m 32,800.00 32,800.00
- Paku Sekrup 2.000 bj 1,750.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.084 Oh 55,000.00 4,620.00
~ Tukang Kayu 0.125 Oh 70,000.00 8,750.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,105.00
~ Mandor 0.004 Oh 100,000.00 400.00 51,175.00
1 m Pasang Bubung Asbes Gelombang besar
- Asbes Bubung Gelombang 1.000 m 57,000.00 57,000.00
- Paku Sekrup 2.000 bj 1,750.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.084 Oh 55,000.00 4,620.00
~ Tukang Kayu 0.125 Oh 70,000.00 8,750.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,105.00
~ Mandor 0.004 Oh 100,000.00 400.00 75,375.00
26 1 m2 Pasang Atap Asbes Gelombang 4 mm (Kecil)
- Asbes Gelombang kecil 0.750 Lbr 34,500.00 25,875.00
- Paku Pancing 0.120 Kg 23,000.00 2,760.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 42,530.00
27 1 m2 Pasang Atap Asbes Gelombang 6 mm (Besar)
- Asbes Gelombang besar 0.570 Lbr 79,100.00 45,087.00
- Paku Pancing 0.120 Kg 23,000.00 2,760.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 61,532.00
28 1 m2 Pasang Atap Seng Gelombang BJLS 30
- Seng Gelombang 0.700 Lbr 74,750.00 52,325.00
- Paku Pancing 0.020 Kg 23,000.00 460.00
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.120 Oh 55,000.00 6,600.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.006 Oh 100,000.00 600.00 64,695.00
29 1 m2 Pasang Atap Nok Seng
- Seng Plat BJLS 30 3x6 0.300 Lbr 45,450.00 13,635.00
- Paku Biasa 0.040 Kg 23,000.00 920.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.006 Oh 100,000.00 600.00 28,985.00
1 2 3 4 5 6 7
30 1 m2 Pasang Fiberglass Gelombang
- Fiberglass Gelombang 1.100 M2 86,250.00 94,875.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 109,435.00
31 1 m2 Pasang Fiberglass datar
- Fiberglass datar 1.100 M2 40,250.00 44,275.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00 58,835.00
30 1 Kg Pasang rangka atap baja WF
- Besi Profil WF 1.150 Kg 13,300.00 15,295.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 23,605.00
31 1 Kg Pasang Cannal C baja
- Besi Profil Cannal C 1.150 Kg 12,600.00 14,490.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 22,800.00
32 1 Kg Pasang Siku L baja
- Besi Profil Siku L 1.150 Kg 12,000.00 13,800.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 22,110.00
33 100 Kg Pekerjaan Perakitan
- Solar 1.000 Ltr 4,500.00 4,500.00
- Minyak Pelumas 0.100 Ltr 42,600.00 4,260.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Las 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.005 Oh 100,000.00 500.00
- Alat
~ Mesin Las 0.8 Jam 38,100.00 30,480.00 52,325.00
34 10 cm Pekerjaan Pengelasan
- Kawat Las Listrik 0.400 Kg 28,750.00 11,500.00
- Solar 0.300 Ltr 4,500.00 1,350.00
- Minyak Pelumas 0.040 Ltr 42,600.00 1,704.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Las 0.020 Oh 70,000.00 1,400.00
~ Kepala Tukang 0.002 Oh 85,000.00 170.00
~ Mandor 0.002 Oh 100,000.00 200.00
- Alat
~ Mesin Las 0.170 Jam 38,100.00 6,477.00 25,001.00
35 1 Kg Pasang Plat Ezyer baja Tebal 8 s/d 22 mm
- Besi Plat Ezyer 1.000 Kg 12,000.00 12,000.00
- Kawat las/Electroda (Perlengkapan) 0.020 Kg 28,750.00 575.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
1 2 3 4 5 6 7
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Tukang Las / welder 0.050 Oh 70,000.00 3,500.00
- Alat
~ Mesin Las 0.01 Jam 38,100.00 381.00
~ Genset 0.01 Jam 81,000.00 810.00 23,516.00
1 2 3 4 5 6 7
36 1 Bh Pasang Trektank (Jarum keras)
- Treaktank 1.000 Bh 31,700.00 31,700.00
- Perlengkapan 10.000 % 3,170.00 31,700.00
- Upah Pekerjaan
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Mandor 0.050 Oh 70,000.00 3,500.00 70,400.00
37 1 Kg Pasang Beton Ezyer Regel
- Besi Beton Ezyer 1.000 Kg 11,800.00 11,800.00
- Kawat las/Electroda (Perlengkapan) 0.100 Kg 28,750.00 2,875.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Tukang Las / welder 0.050 Oh 70,000.00 3,500.00
- Alat
~ Mesin Las 0.01 Jam 38,100.00 381.00
~ Genset 0.01 Jam 81,000.00 810.00 25,616.00
38 1 m' Pasang Lisplank ukuran (3x20) cm, Kayu jati
- Kayu Jati, Papan 0.0108 M3 16,675,000.00 180,090.00
- Paku Biasa 2" - 5" 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 203,540.00
39 1 m' Pasang Lisplank ukuran (3x20) cm, Kayu Kamper
- Kayu Kamper, Papan 0.0108 M3 0.00 -
- Paku Biasa 2" - 5" 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 23,450.00
40 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Jati
- Kayu Jati, Papan 0.011 M3 16,675,000.00 183,425.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 206,000.00
41 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Kamper
- Kayu Kamper, Papan 0.011 M3 0.00 -
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 22,575.00
42 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Meranti (MA)
- Kayu Meranti, Papan 0.011 M3 6,250,000.00 68,750.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00 91,325.00
43 1 m' Pasang Lisplank ukuran 2x(3x20) cm, Kayu Kamper (Atas bawah)
- Kayu Kamper, Papan 0.0145 M3 0.00 -
- Paku Biasa 2" - 5" 0.060 Kg 17,500.00 1,050.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.450 Oh 70,000.00 31,500.00
~ Kepala Tukang 0.045 Oh 85,000.00 3,825.00
1 2 3 4 5 6 7
~ Mandor 0.075 Oh 100,000.00 7,500.00 52,125.00
44 1 m' Pasang Lisplank ukuran (2x20) cm, Kayu Meranti (MA)
- Kayu Meranti, Papan 0.0040 M3 6,250,000.00 25,000.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.005 Oh 100,000.00 500.00 48,000.00
1 2 3 4 5 6 7
45 1 m' Pasang Lisplank ukuran (2x20) cm, Kayu Meranti (MC)
- Kayu Meranti, Papan 0.0040 M3 4,400,000.00 17,600.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.005 Oh 100,000.00 500.00 40,600.00
46 1 m' Pasang Lisplank Kalsium ukuran 20 cm tebal 8 mm
- Kalsium Plank 1.000 M1 14,400.00 14,400.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Kayu Meranti 3/5 0.004 M3 4,025,000.00 15,697.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,062.50
~ Mandor 0.003 Oh 100,000.00 250.00 42,035.00
47 1 m' Pasang Lisplank Kalsium ukuran 30 cm tebal 8 mm
- Kalsium Plank 1.000 M1 17,250.00 17,250.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Kayu Meranti 3/5 0.005 M3 4,025,000.00 18,112.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,062.50
~ Mandor 0.003 Oh 100,000.00 250.00 47,300.00
48 1 M' Pasang talang datar, seng BJLS 30
- Seng Plat BJLS 30 (90 cm) 1.050 M1 45,450.00 47,722.50
- Paku biasa 0.015 Kg 17,500.00 262.50
- Kayu Meranti (MA), papan 0.0096 M3 6,250,000.00 60,000.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.400 Oh 70,000.00 28,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.01 Oh 100,000.00 1,000.00 150,110.00
49 1 M' Pasang talang U PVC 15 x 15
- Talang U PVC 15 1.050 M1 26,562.50 27,890.63
- Plat Strip 0.146 kg 12,000.00 1,753.92
- Paku 0.015 Kg 17,500.00 262.50
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Besi 0.400 Oh 70,000.00 28,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.01 Oh 100,000.00 1,000.00 72,032.05
50 1 m2 Pasang Atap Polycarbonat
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Perlengkapan 1.000 ls 5,000.00 5,000.00
- Upah Pekerjaan 1.000 ls 30,000.00 30,000.00 161,500.00
51 1 m2 Pasang Atap Polycarbonat rangka pipa gas/besi kotak
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Gas + Pengecatan 1.000 ls 240,000.00 240,000.00
- Upah Pekerjaan 1.000 ls 70,000.00 70,000.00 436,500.00
52 1 m2 Pasang Atap Polycarbonat rangka pipa air
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Air + Pengecatan 1.000 ls 276,000.00 276,000.00
- Upah Pekerjaan 1.000 ls 70,000.00 70,000.00 472,500.00
53 1 m2 Pasang Atap Polycarbonat rangka pipa stainless
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Stainless 1.000 ls 396,000.00 396,000.00
- Upah Pekerjaan 1.000 ls 70,000.00 70,000.00 592,500.00
54 1 m' Papan Roiter 2/20
- Kayu meranti, papan 0.004 M3 4,370,000.00 17,480.00
- Paku 0.050 Kg 17,500.00 875.00
1 2 3 4 5 6 7
- Upah Pekerjaan 1.000 Ls 10,000.00 10,000.00 28,355.00
55 1 m' Papan Kompres kayu Meranti (MA)
- Kayu Meranti, papan 0.003 M3 6,900,000.00 20,700.00
- Seng BJLS 30 0.250 m2 26,562.50 6,640.63
- Paku 0.100 Kg 23,000.00 2,300.00
- Upah Pekerjaan 1.000 Ls 12,500.00 12,500.00 42,140.63
56 1 m' Papan Kompres kayu Meranti (MC)
- Kayu Meranti, papan 0.003 M3 4,370,000.00 13,110.00
- Seng BJLS 30 0.250 m2 26,562.50 6,640.63
- Paku 0.100 Kg 23,000.00 2,300.00
- Upah Pekerjaan 1.000 Ls 12,500.00 12,500.00 34,550.63

VII PEKERJAAN BETON


1 1 M3 Membuat Beton Mutu f'c = 7,4 Mpa (K 100)
- Semen Portland 247.000 Kg 1,495.00 369,265.00
- Pasir Beton (Lumajang) 869.000 Kg 85.71 74,485.71
- Batu Pecah Mesin 2/3 999.000 Kg 191.67 191,475.00
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 55,000.00 90,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Kepala Tukang 0.028 Oh 85,000.00 2,380.00
~ Mandor 0.083 Oh 100,000.00 8,300.00 760,205.71
1 2 3 4 5 6 7
2 1 M3 Membuat Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K 100)
- Semen Portland 230.000 Kg 1,495.00 343,850.00
- Pasir Beton (Lumajang) 893.000 Kg 85.71 76,542.86
- Batu Pecah Mesin 2/3 1027.000 Kg 191.67 196,841.67
- Air 200.000 Ltr 20.00 4,000.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 55,000.00 66,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.060 Oh 100,000.00 6,000.00 708,934.52
3 1 M3 Membuat Beton Mutu f'c = 14,5 Mpa (K 175)
- Semen Portland 326.000 Kg 1,495.00 487,370.00
- Pasir Beton (Lumajang) 760.000 Kg 85.71 65,142.86
- Batu Pecah Mesin 2/3 1029.000 Kg 191.67 197,225.00
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 55,000.00 90,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Kepala Tukang 0.028 Oh 85,000.00 2,380.00
~ Mandor 0.083 Oh 100,000.00 8,300.00 874,717.86
4 1 M3 Membuat Beton Mutu f'c = 19,3 Mpa (K 225)
- Semen Portland 371.000 Kg 1,495.00 554,645.00
- Pasir Beton (Lumajang) 698.000 Kg 85.71 59,828.57
- Batu Pecah Mesin 2/3 1047.000 Kg 191.67 200,675.00
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 55,000.00 90,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Kepala Tukang 0.028 Oh 85,000.00 2,380.00
~ Mandor 0.083 Oh 100,000.00 8,300.00 940,128.57
5 1 M3 Membuat Beton Mutu f'c = 31,2 Mpa (K 350)
- Semen Portland 448.000 Kg 1,495.00 669,760.00
- Pasir Beton (Lumajang) 667.000 Kg 85.71 57,171.43
- Batu Pecah Mesin 2/3 1000.000 Kg 191.67 191,666.67
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 2.100 Oh 55,000.00 115,500.00
~ Tukang Batu 0.350 Oh 70,000.00 24,500.00
~ Kepala Tukang 0.035 Oh 85,000.00 2,975.00
~ Mandor 0.105 Oh 100,000.00 10,500.00 1,076,373.10
6 1 M3 Membuat Beton Kedap Air dengan Strotox - 100
- Semen Portland 400.000 Kg 1,495.00 598,000.00
- Pasir Beton (Lumajang) 0.480 M3 120,000.00 57,600.00
- Batu Pecah Mesin 2/3 0.800 M3 258,750.00 207,000.00
- Strotox - 100 1.200 Kg 82,500.00 99,000.00
- Upah Pekerjaan
~ Pekerja 2.100 Oh 55,000.00 115,500.00
~ Tukang Batu 0.350 Oh 70,000.00 24,500.00
~ Kepala Tukang 0.035 Oh 85,000.00 2,975.00
~ Mandor 0.105 Oh 100,000.00 10,500.00 1,115,075.00
7 1 Kg Pembesian dengan besi polos
- Besi beton (polos) 1.050 Kg 11,800.00 12,390.00
- Kawat beton 0.015 Kg 20,000.00 300.00
- Upah Pekerjaan
~ Pekerja 0.007 Oh 55,000.00 385.00
~ Tukang Besi 0.007 Oh 70,000.00 490.00
~ Kepala Tukang 0.0007 Oh 85,000.00 59.50
~ Mandor 0.0004 Oh 100,000.00 40.00 13,664.50
8 1 m2 Pasang Bekisting untuk pondasi
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.300 Kg 17,500.00 5,250.00
- Minyak Bekisting 0.100 Liter 3,200.00 320.00
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.520 Oh 55,000.00 28,600.00
~ Tukang Kayu 0.260 Oh 70,000.00 18,200.00
~ Kepala Tukang 0.026 Oh 85,000.00 2,210.00
~ Mandor 0.026 Oh 100,000.00 2,600.00 91,680.00
1 2 3 4 5 6 7
9 1 m2 Pasang Bekisting untuk sloof
- Kayu Cetakan 0.045 M3 862,500.00 38,812.50
- Paku Biasa 2 ' - 5' 0.300 Kg 17,500.00 5,250.00
- Minyak Bekisting 0.100 Liter 3,200.00 320.00
- Upah Pekerjaan
~ Pekerja 0.520 Oh 55,000.00 28,600.00
~ Tukang Kayu 0.260 Oh 70,000.00 18,200.00
~ Kepala Tukang 0.026 Oh 85,000.00 2,210.00
~ Mandor 0.026 Oh 100,000.00 2,600.00 95,992.50
10 1 m2 Pasang Bekisting untuk kolom bebas
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.015 M3 2,875,000.00 43,125.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 2.000 btg 17,250.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.006 Oh 100,000.00 600.00 232,882.50
11 1 m2 Pasang Bekisting untuk balok
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.018 M3 2,875,000.00 51,750.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 2.000 btg 17,250.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.006 Oh 100,000.00 600.00 241,507.50
12 1 m2 Pasang Bekisting untuk plat lantai
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.015 M3 2,875,000.00 43,125.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 6.000 btg 17,250.00 103,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.033 Oh 100,000.00 3,300.00 304,582.50
13 1 m2 Pasang Bekisting untuk tangga
- Kayu Cetakan 0.030 M3 862,500.00 25,875.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.015 M3 2,875,000.00 43,125.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 2.000 btg 17,250.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.033 Oh 100,000.00 3,300.00 226,957.50
14 1 m2 jembatan untuk pengecoran beton
- Kayu Cetakan 0.0264 M3 862,500.00 22,770.00
- Paku Biasa 2 ' - 5' 0.600 Kg 17,500.00 10,500.00
- Dolken Kayu galam 0.500 btg 17,250.00 8,625.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
1 2 3 4 5 6 7
~ Tukang Batu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.006 Oh 100,000.00 600.00 54,670.00
1 2 3 4 5 6 7
15 1 m3 Membuat pondasi beton bertulang (150 kg besi + bekisting)
- Kayu Cetakan 0.200 M3 862,500.00 172,500.00
- Paku Biasa 2 ' - 5' 1.500 Kg 17,500.00 26,250.00
- Minyak Bekisting 0.400 Liter 3,200.00 1,280.00
- Besi beton (polos) 157.500 Kg 11,800.00 1,858,500.00
- Kawat beton 2.250 Kg 20,000.00 45,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.262 Oh 85,000.00 22,270.00
~ Mandor 0.265 Oh 100,000.00 26,500.00 3,404,257.50
16 1 m3 Membuat sloof, ring balk, kolom praktis beton bertulang (200 kg besi + bekisting)
- Kayu Cetakan 0.270 M3 862,500.00 232,875.00
- Paku Biasa 2 ' - 5' 2.000 Kg 17,500.00 35,000.00
- Minyak Bekisting 0.600 Liter 3,200.00 1,920.00
- Besi beton (polos) 210.000 Kg 11,800.00 2,478,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Upah Pekerjaan
~ Pekerja 5.650 Oh 55,000.00 310,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.560 Oh 70,000.00 109,200.00
~ Tukang Besi 1.400 Oh 70,000.00 98,000.00
~ Kepala Tukang 0.323 Oh 85,000.00 27,455.00
~ Mandor 0.283 Oh 100,000.00 28,300.00 4,177,457.50
17 1 m3 Membuat balok beton bertulang (200 kg besi + bekisting)
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 210.000 Kg 11,800.00 2,478,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.140 M3 2,875,000.00 402,500.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 16.000 btg 17,250.00 276,000.00
- Upah Pekerjaan
~ Pekerja 6.350 Oh 55,000.00 349,250.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.650 Oh 70,000.00 115,500.00
~ Tukang Besi 1.400 Oh 70,000.00 98,000.00
~ Kepala Tukang 0.333 Oh 85,000.00 28,305.00
~ Mandor 0.318 Oh 100,000.00 31,800.00 5,374,932.50
18 1 m3 Membuat kolom beton bertulang (200 kg besi + bekisting)
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 210.000 Kg 11,800.00 2,478,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.120 M3 2,875,000.00 345,000.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 20.000 btg 17,250.00 345,000.00
1 2 3 4 5 6 7
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.265 Oh 85,000.00 22,525.00
~ Mandor 0.265 Oh 100,000.00 26,500.00 5,268,602.50
1 2 3 4 5 6 7
19 1 m3 Membuat kolom beton bertulang (300 kg besi + bekisting)
- Kayu Cetakan 0.400 M3 862,500.00 345,000.00
- Paku Biasa 2 ' - 5' 4.000 Kg 17,500.00 70,000.00
- Minyak Bekisting 2.000 Liter 3,200.00 6,400.00
- Besi beton (polos) 315.000 Kg 11,800.00 3,717,000.00
- Kawat beton 4.500 Kg 20,000.00 90,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.150 M3 2,875,000.00 431,250.00
- Plywood tebal 9 mm 3.500 Lbr 143,750.00 503,125.00
- Dolken Kayu galam 20.000 btg 17,250.00 345,000.00
- Upah Pekerjaan
~ Pekerja 7.050 Oh 55,000.00 387,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.650 Oh 70,000.00 115,500.00
~ Tukang Besi 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.403 Oh 85,000.00 34,255.00
~ Mandor 0.353 Oh 100,000.00 35,300.00 7,023,537.50
20 1 m3 Membuat kolom beton bertulang (150 kg besi + bekisting)
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 157.500 Kg 11,800.00 1,858,500.00
- Kawat beton 2.250 Kg 20,000.00 45,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.120 M3 2,875,000.00 345,000.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 32.000 btg 17,250.00 552,000.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.265 Oh 85,000.00 22,525.00
~ Mandor 0.265 Oh 100,000.00 26,500.00 4,841,102.50
21 1 m3 Membuat tangga beton bertulang (200 kg besi + bekisting)
- Kayu Cetakan 0.250 M3 862,500.00 215,625.00
- Paku Biasa 2 ' - 5' 3.000 Kg 17,500.00 52,500.00
- Minyak Bekisting 1.200 Liter 3,200.00 3,840.00
- Besi beton (polos) 200.000 Kg 11,800.00 2,360,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 323.000 Kg 1,495.00 482,885.00
- Pasir Beton (Lumajang) 0.520 M3 120,000.00 62,400.00
- Batu Pecah Mesin 2/3 0.780 M3 258,750.00 201,825.00
- Balok kayu 0.105 M3 2,875,000.00 301,875.00
- Plywood tebal 9 mm 2.500 Lbr 143,750.00 359,375.00
- Dolken Kayu galam 14.000 btg 17,250.00 241,500.00
- Upah Pekerjaan
~ Pekerja 5.600 Oh 55,000.00 308,000.00
~ Tukang Batu 0.350 Oh 70,000.00 24,500.00
~ Tukang Kayu 2.300 Oh 70,000.00 161,000.00
~ Tukang Besi 1.400 Oh 70,000.00 98,000.00
~ Kepala Tukang 0.405 Oh 85,000.00 34,425.00
~ Mandor 0.202 Oh 100,000.00 20,200.00 4,987,950.00
22 1 m3 Membuat plat lantai beton bertulang
- Beton Bertulang, K 175 1.000 M3 874,717.86 874,717.86
- Pembesian dengan besi polos 150.000 Kg 13,664.50 2,049,675.00
- Pasang Bekisting 8.500 M2 304,582.50 2,588,951.25 5,513,344.11
23 1 m3 Membuat plat beton bertulang tanpa bekisting
- Beton Bertulang, K 175 1.000 M3 874,717.86 874,717.86
1 2 3 4 5 6 7
- Pembesian dengan besi polos 150.000 Kg 13,664.50 2,049,675.00 2,924,392.86
24 1 m3 Membuat plat deker beton bertulang tebal s/d 10 cm
- Beton Bertulang, K 175 1.000 M3 874,717.86 874,717.86
- Pembesian dengan besi polos 150.000 Kg 13,664.50 2,049,675.00
- Pasang Bekisting 8.500 M2 95,992.50 815,936.25 3,740,329.11
25 1 m3 Membuat plat deker beton bertulang tebal > 10 cm
- Beton Bertulang, K 175 1.000 M3 874,717.86 874,717.86
- Pembesian dengan besi polos 300.000 Kg 13,664.50 4,099,350.00
- Pasang Bekisting 8.500 M2 95,992.50 815,936.25 5,790,004.11
1 2 3 4 5 6 7
VIII PEKERJAAN KUSEN
1 1 m3 Pasang Kusen Pintu dan Jendela Kayu Jati
- Kayu Jati, balok 1.100 M3 16,100,000.00 17,710,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 7.000 Oh 55,000.00 385,000.00
~ Tukang Kayu 21.000 Oh 70,000.00 1,470,000.00
~ Kepala Tukang 2.100 Oh 85,000.00 178,500.00
~ Mandor 0.350 Oh 100,000.00 35,000.00 19,812,875.00
2 1 m3 Pasang Kusen Pintu dan Jendela Kayu Kamper
- Kayu Kamper, balok 1.200 M3 10,200,000.00 12,240,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 55,000.00 330,000.00
~ Tukang Kayu 18.000 Oh 70,000.00 1,260,000.00
~ Kepala Tukang 1.800 Oh 85,000.00 153,000.00
~ Mandor 0.300 Oh 100,000.00 30,000.00 14,047,375.00
3 1 m3 Pasang Kusen Pintu dan Jendela Kayu Meranti (MA)
- Kayu Meranti, balok 1.200 M3 6,210,000.00 7,452,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 55,000.00 330,000.00
~ Tukang Kayu 18.000 Oh 70,000.00 1,260,000.00
~ Kepala Tukang 1.800 Oh 85,000.00 153,000.00
~ Mandor 0.300 Oh 100,000.00 30,000.00 9,259,375.00
4 1 m3 Pasang Kusen Pintu dan Jendela Kayu Meranti (MC)
- Kayu Meranti, balok 1.200 M3 4,025,000.00 4,830,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 55,000.00 330,000.00
~ Tukang Kayu 18.000 Oh 70,000.00 1,260,000.00
~ Kepala Tukang 1.800 Oh 85,000.00 153,000.00
~ Mandor 0.300 Oh 100,000.00 30,000.00 6,637,375.00
5 1 m2 Pasang Pintu Panel Kayu Jati lokal kelas 1
- Kayu Jati, Papan 0.040 M3 16,675,000.00 667,000.00
- Lem Kayu 0.500 kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 968,750.00
1 2 3 4 5 6 7
6 1 m2 Pasang Pintu Panel Kayu Kamper
- Kayu Kamper, papan 0.040 M3 10,200,000.00 408,000.00
- Lem Kayu 0.500 Kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 709,750.00
7 1 m2 Pasang Pintu dan Jendela Jalusi Kayu Kamper
- Kayu Kamper, Papan 0.064 M3 10,200,000.00 652,800.00
- Lem Kayu 0.500 Kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 954,550.00
8 1 m2 Pasang Pintu Plywood Rangkap, Rangka Kayu Meranti (MA)
- Kayu Meranti, Papan 0.025 M3 6,900,000.00 172,500.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 kg 12,500.00 6,250.00
- Plywood 90 x 210 x 4 mm 1.000 Lbr 54,700.00 54,700.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 55,000.00 38,500.00
~ Tukang Kayu 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.210 Oh 85,000.00 17,850.00
~ Mandor 0.035 Oh 100,000.00 3,500.00 440,825.00
9 1 m2 Pasang Pintu Plywood Rangkap, Rangka Kayu Meranti (MC)
- Kayu Meranti, Papan 0.0250 M3 4,370,000.00 109,250.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 Lt 12,500.00 6,250.00
- Plywood 90 x 210 x 4 mm 1.000 Lbr 54,700.00 54,700.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 55,000.00 38,500.00
~ Tukang Kayu 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.210 Oh 85,000.00 17,850.00
~ Mandor 0.035 Oh 100,000.00 3,500.00 377,575.00
10 1 m2 Pasang Pintu Doubel Teakwood, Rangka Kayu Meranti (MC)
- Kayu Meranti, Papan 0.025 M3 4,370,000.00 109,250.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 Lt 12,500.00 6,250.00
- Tekwood 90 x 210 x 4 mm 1.000 Lbr 97,750.00 97,750.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 55,000.00 38,500.00
~ Tukang Kayu 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.210 Oh 85,000.00 17,850.00
~ Mandor 0.035 Oh 100,000.00 3,500.00 420,625.00
11 1 m2 Pasang Pintu Doubel Teakwood Lapis Almunium, Rangka Kayu Meranti (MC)
- Kayu Meranti, Papan 0.025 M3 4,370,000.00 109,250.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 Lt 12,500.00 6,250.00
- Tekwood 90 x 210 x 4 mm 1.000 Lbr 97,750.00 97,750.00
- Almunium 3' x 7' x 4 mm 0.500 Lbr 196,000.00 98,000.00
- Upah Pekerjaan
~ Pekerja 0.850 Oh 55,000.00 46,750.00
~ Tukang Kayu 2.550 Oh 70,000.00 178,500.00
~ Kepala Tukang 0.255 Oh 85,000.00 21,675.00
~ Mandor 0.043 Oh 100,000.00 4,300.00 563,000.00
12 1 m2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Meranti (MA)
- Kayu Meranti, Balok (6 x 12) 0.0280 M3 6,210,000.00 173,880.00
- Paku Biasa 1/2" - 1 0.150 Kg 17,500.00 2,625.00
- Lem Kayu 0.560 Kg 12,500.00 7,000.00
- Tekwood 120 x 240 x 4 mm 0.860 Lbr 112,200.00 96,492.00
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.450 Oh 70,000.00 31,500.00
~ Kepala Tukang 0.045 Oh 85,000.00 3,825.00
~ Mandor 0.008 Oh 100,000.00 800.00 324,372.00
1 2 3 4 5 6 7
12 1 m2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Jati
- Kayu Jati, Papan 0.0240 M3 16,675,000.00 400,200.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00 640,350.00
13 1 m2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Kamper
- Kayu Kamper, Papan 0.0240 M3 10,200,000.00 244,800.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00 484,950.00
14 1 m2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Meranti ( MA )
- Kayu Meranti (MA), Papan 0.0240 M3 6,900,000.00 165,600.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00 405,750.00
15 1 m2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Meranti ( MC )
- Kayu Meranti ( MC ), Papan 0.0240 M3 4,370,000.00 104,880.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00 345,030.00
16 1 m2 Pasang jalusi Kusen Kayu Kamper
- Kayu kamper, papan 0.0600 M3 10,200,000.00 612,000.00
- Paku 1 cm - 2.5 cm 0.1500 kg 17,500.00 2,625.00
- Upah Pekerjaan
~ Pekerja 0.670 Oh 55,000.00 36,850.00
~ Tukang Kayu 2.000 Oh 70,000.00 140,000.00
~ Kepala Tukang 0.200 Oh 85,000.00 17,000.00
~ Mandor 0.335 Oh 100,000.00 33,500.00 841,975.00
17 1 m2 Pasang Kaca, Tebal 5 mm
- Kaca 1.1000 M2 69,000.00 75,900.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00 88,575.00
18 1 m2 Pasang Kaca, Tebal 8 mm
- Kaca 1.1000 M2 172,500.00 189,750.00
- Upah Pekerjaan
~ Pekerja 0.0165 Oh 55,000.00 907.50
~ Tukang Kayu 0.165 Oh 70,000.00 11,550.00
~ Kepala Tukang 0.0165 Oh 85,000.00 1,402.50
~ Mandor 0.00080 Oh 100,000.00 80.00 203,690.00
19 1 m2 Pasang Kaca Rayben, Tebal 5 mm
- Kaca Rayben 1.1000 M2 80,500.00 88,550.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00 101,225.00
20 Pasang 1 buah kunci pintu biasa
- Kunci Pintu Biasa 1.000 Bh 72,000.00 72,000.00
1 2 3 4 5 6 7
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.500 Oh 70,000.00 35,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 108,900.00
1 2 3 4 5 6 7
21 Pasang 1 buah kunci tanam hias
- Kunci Tanam Hias 1.000 Bh 195,500.00 195,500.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Kayu 0.600 Oh 70,000.00 42,000.00
~ Kepala Tukang 0.060 Oh 85,000.00 5,100.00
~ Mandor 0.003 Oh 100,000.00 300.00 246,200.00
22 Pasang 1 buah kunci tanam silinder + pegangan
- Kunci tanam Silinder 1.000 Bh 105,000.00 105,000.00
- Pegangan pintu (handle) 2.000 Bh 49,000.00 98,000.00
- Upah Pekerjaan
~ Pekerja 0.005 Oh 55,000.00 275.00
~ Tukang Kayu 0.500 Oh 70,000.00 35,000.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.00025 Oh 100,000.00 25.00 238,725.00
23 Pasang engsel pintu besar (Kuningan/sendok)
- Engsel pintu besar 1.000 Set 34,500.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00 47,175.00
24 Pasang engsel pintu kecil
- Engsel pintu kecil 1.000 Set 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00 25,175.00
25 Pasang engsel jendela
- Engsel jendela kecil 1.000 Set 11,100.00 11,100.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.00050 Oh 100,000.00 50.00 19,550.00
26 Pasang Kunci Selot
- Kunci Selot 1.000 bh 45,000.00 45,000.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.001 Oh 100,000.00 100.00 61,900.00
27 Pasang hak angin / Sikutan Kuningan
- Hak angin 1.000 Set 20,700.00 20,700.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00 33,375.00
28 Pasang hak angin 4 mm lurus
- Hak angin 4 mm lurus 1.000 Set 19,000.00 19,000.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00 31,675.00
29 Pasang Grendel
- Grendel pintu besar 1.000 Bh 13,400.00 13,400.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
1 2 3 4 5 6 7
~ Mandor 0.00050 Oh 100,000.00 50.00 21,850.00
30 Pasang Grendel Kecil
- Grendel jendela kecil 1.000 Bh 7,300.00 7,300.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.00050 Oh 100,000.00 50.00 15,750.00
1 2 3 4 5 6 7
31 Memasang kawat harmonika 1 M2
- Kawat Harmonika 1.000 M2 43,200.00 43,200.00
- Paku 0.020 Kg 17,500.00 350.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.00025 Oh 100,000.00 25.00 50,250.00
32 1 M2 Pasang Rolling Door Aluminium (silver)
- Rolling Door tebal 1,2 mm 1.000 M2 419,750.00 419,750.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Besi Konstruksi 1.000 Oh 70,000.00 70,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 8,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 558,250.00
33 1 m' Pasang Kusen Aluminium 3 " (Silver)
- Kusen Almunium 3" 1.100 M' 69,000.00 75,900.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00 85,464.50
34 1 m' Pasang Kusen Aluminium 3 " (Brown)
- Kusen Almunium 3" 1.100 M' 74,750.00 82,225.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00 91,789.50
35 1 m' Pasang Kusen Aluminium 4 " (Silver)
- Kusen Almunium 4" 1.100 M' 86,250.00 94,875.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00 104,439.50
36 1 m' Pasang Kusen Aluminium 4 " (Brown)
- Kusen Almunium 4" 1.100 M' 92,000.00 101,200.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00 110,764.50
37 1 m' Pasang Kusen Aluminium Curtain Wall 3" (Silver)
- Kusen Curtain Wall 1.100 M' 69,000.00 75,900.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00 85,429.00
38 1 m' Pasang Kusen Aluminium Curtain Wall 3" (brown)
- Kusen Curtain Wall brown 1.100 M' 74,750.00 82,225.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
1 2 3 4 5 6 7
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00 91,754.00
1 2 3 4 5 6 7
39 i1 m' Pasang Kusen Alumunium Curtain Wall 4" (Silver)
- Kusen Curtain Wall silver 1.100 M' 86,250.00 94,875.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00 104,404.00
40 1 m' Pasang Kusen Aluminium Curtain Wall 4" (brown)
- Kusen Curtain Wall brown 1.100 M' 92,000.00 101,200.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00 110,729.00
41 1 m' Pasang Daun jendela aluminium (silver)
- Daun jendela aluminium 1.100 M' 50,600.00 55,660.00
- Karet 2.000 M' 3,000.00 6,000.00
- Sponeng 1.100 M' 23,000.00 25,300.00
- Upah Pekerjaan
~ Pekerja 0.080 Oh 55,000.00 4,400.00
~ Tukang Besi 0.800 Oh 70,000.00 56,000.00
~ Kepala Tukang 0.080 Oh 85,000.00 6,800.00
~ Mandor 0.004 Oh 100,000.00 400.00 154,560.00
42 1 m' Pasang Daun jendela aluminium (brown)
- Daun jendela aluminium 1.100 M' 63,250.00 69,575.00
- Karet 2.000 M' 3,000.00 6,000.00
- Sponeng 1.100 M' 23,000.00 25,300.00
- Upah Pekerjaan
~ Pekerja 0.080 Oh 55,000.00 4,400.00
~ Tukang Besi 0.800 Oh 70,000.00 56,000.00
~ Kepala Tukang 0.080 Oh 85,000.00 6,800.00
~ Mandor 0.004 Oh 100,000.00 400.00 168,475.00
43 1 m2 Pasang Sunscreen Aluminium
- Sunscreen Aluminium 1.000 M2 1,115,500.00 1,115,500.00
- Upah Pekerjaan
~ Pekerja 0.080 Oh 55,000.00 4,400.00
~ Tukang Besi 0.800 Oh 70,000.00 56,000.00
~ Kepala Tukang 0.080 Oh 85,000.00 6,800.00
~ Mandor 0.004 Oh 100,000.00 400.00 1,183,100.00

IX PEKERJAAN LANGIT-LANGIT / RANGKA PLAFOND


1 1 m2 Pasang Rangka Plafond Hollow Partisi
- Besi Hollow partisi 4x4 3.000 M' 9,775.00 29,325.00
- Besi Hollow partisi 2x4 2.500 M' 8,337.50 20,843.75
- Accesories 0.150 Kg 25,300.00 3,795.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Las 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00 63,888.75
2 1 m2 Rangka Langit-langit Kayu Meranti (MA) 1 x 1 m
- Kayu Meranti (MA) 0.012 M3 6,210,000.00 74,520.00
- Paku 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.250 Oh 70,000.00 17,500.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00 111,645.00
3 1 m2 Rangka Langit-langit Kayu Meranti (MC) 1 x 1 m
1 2 3 4 5 6 7
- Kayu Meranti (MC) 0.012 M3 4,025,000.00 48,300.00
- Paku 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.250 Oh 70,000.00 17,500.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00 85,425.00
1 2 3 4 5 6 7
4 1 m2 Rangka Langit-langit Kayu Meranti (MA) 0,5 x 1 m
- Kayu Meranti (MA) 0.015 M3 6,210,000.00 95,634.00
- Paku 0.200 Kg 17,500.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00 138,434.00
5 1 m2 Rangka Langit-langit Kayu Meranti (MC) 0,5 x 1 m
- Kayu Meranti (MC) 0.015 M3 4,025,000.00 61,985.00
- Paku 0.200 Kg 17,500.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00 104,785.00
6 1 m2 Rangka Langit-langit Kayu Meranti (MA) (60x60)
- Kayu Meranti (MA) 0.016 M3 6,210,000.00 101,223.00
- Paku 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0100 Oh 100,000.00 1,000.00 141,148.00
7 1 m2 Rangka Langit-langit Kayu Meranti (MC) (60x60)
- Kayu Meranti (MC) 0.016 M3 4,025,000.00 64,400.00
- Paku 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0100 Oh 100,000.00 1,000.00 104,325.00
8 1 m2 Pasang Eternit, tebal 4 mm, 5 mm, dan 6 mm
- Eternit 1.100 M2 10,500.00 11,550.00
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.030 Oh 55,000.00 1,650.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.004 Oh 100,000.00 400.00 19,270.00
9 1 m2 Pasang Langit-langit Triplek (120x240) tebal 4 mm
- Tripleks 0.375 Lbr 74,750.00 28,031.25
- Paku 0.030 Kg 17,500.00 525.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 42,406.25
10 1 m2 Pasang langit-langit gypsum board, ( 120 X 240 X 9 ) mm
- Gypsum Board 0.364 lbr 69,000.00 25,116.00
- Paku Sekrup 0.110 Kg 28,750.00 3,162.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00 38,203.50
11 1 m2 Pasang langit-langit calsiboard, ( 120 X 240 ) mm
- Calsi Board 0.364 lbr 63,250.00 23,023.00
- Paku 0.110 Kg 17,500.00 1,925.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
1 2 3 4 5 6 7
~ Mandor 0.005 Oh 100,000.00 500.00 34,873.00
12 1 m2 Pasang langit-langit calsiboard, ( 120 X 240 ) mm pada metal furring
- Calsium Board tebal 4,5 mm 0.364 lbr 63,250.00 23,023.00
- Paku skrup 0.110 Kg 28,750.00 3,162.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00 36,110.50
1 2 3 4 5 6 7
13 1 m' Pasang list plafond - kayu profil
- Kayu profil 1.050 M' 12,350.00 12,967.50
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.003 Oh 100,000.00 300.00 20,117.50
14 1 m' Pasang list plafond gypsum lebar 15 cm
- Gypsum list profil lebar 15 cm 1.050 M' 10,350.00 10,867.50
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 19,352.50
15 1 m' Pasang list plafond gypsum lebar 8 cm
- Gypsum list profil lebar 8 cm 1.050 M' 8,050.00 8,452.50
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00 16,937.50

PEKERJAAN
X PENGECATAN
1 1 m2 mendempul dan menggosok kayu
- Plamir Kayu 0.080 Kg 31,600.00 2,528.00
- Minyak Cat 0.020 kg 26,450.00 529.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Cat 0.040 Oh 70,000.00 2,800.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.0025 Oh 100,000.00 250.00 8,682.00
2 1 m2 Pengecatan bidang kayu lama
- Cat Kayu 0.142 Kg 55,000.00 7,810.00
- Minyak cat 0.019 Lt 26,450.00 502.55
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 18,300.05
3 1 m2 Pengecatan bidang kayu baru
- Cat Kayu 0.260 Kg 55,000.00 14,300.00
- Plamir 0.150 Kg 31,600.00 4,740.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 35,402.50
4 1 m2 Pengecatan besi baru
- Cat besi Emco 0.260 Kg 55,000.00 14,300.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Plamir 0.150 Kg 31,600.00 4,740.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 35,402.50
1 2 3 4 5 6 7
5 1 m2 Pengecatan besi Finishing baru (Tanpa Cat dasar)
- Cat besi Emco Finishing ( 3 Lapis ) 0.260 Kg 55,000.00 14,300.00
- Upah Pekerjaan
~ Pekerja 0.035 Oh 55,000.00 1,925.00
~ Tukang Cat 0.053 Oh 70,000.00 3,710.00
~ Kepala Tukang 0.0020 Oh 85,000.00 170.00
~ Mandor 0.0013 Oh 100,000.00 130.00 20,235.00
1 2 3 4 5 6 7
6 1 m2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter
- Residu atau Ter 0.350 Ltr 16,350.00 5,722.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Mandor 0.006 Oh 100,000.00 600.00 11,822.50
7 1 m2 Pelaburan Bidang Kayu dengan Politur
- Politur 0.372 Ltr 66,700.00 24,812.40
- Ampelas 2.000 Lbr 3,500.00 7,000.00
- Upah Pekerjaan
~ Tukang Cat 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00 37,622.40
8 1 m2 Pelaburan Bidang Kayu dengan Vernis
- Vernis 0.150 Ltr 88,550.00 13,282.50
- Dempul 0.050 Kg 31,600.00 1,580.00
- Ampelas 0.100 Lbr 3,500.00 350.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.160 Oh 55,000.00 8,800.00
~ Tukang Cat 0.160 Oh 70,000.00 11,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00 36,995.00
9 1 m2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis cat Penutup)
- Plamir 0.100 Kg 17,250.00 1,725.00
- Cat Dasar 0.100 Kg 23,000.00 2,300.00
- Cat Penutup 2x 0.260 Kg 23,000.00 5,980.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.063 Oh 70,000.00 4,410.00
~ Kepala Tukang 0.0063 Oh 85,000.00 535.50
~ Mandor 0.0025 Oh 100,000.00 250.00 16,300.50
10 1 m2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar, 2 x pengecatan)
- Cat Dasar 0.120 Kg 23,000.00 2,760.00
- Cat Penutup 2x 0.180 Kg 23,000.00 4,140.00
- Upah Pekerjaan
~ Pekerja 0.028 Oh 55,000.00 1,540.00
~ Tukang Cat 0.042 Oh 70,000.00 2,940.00
~ Kepala Tukang 0.0042 Oh 85,000.00 357.00
~ Mandor 0.0025 Oh 100,000.00 250.00 11,987.00
11 1 m2 Pengecatan permukaan baja dengan meni besi
- Meni Besi 0.100 Kg 31,700.00 3,170.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 21,142.50
12 1 m2 Pengecatan Genteng Baru
- Cat 0.300 Kg 34,500.00 10,350.00
- Kuas 0.100 Bh 17,250.00 1,725.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 22,062.50
13 1 m2 Coating transparan (doff) untuk batu alam
- Coating 0.2000 Ltr 69,000.00 13,800.00
- Kuas 0.0100 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 23,960.00
1 2 3 4 5 6 7
14 1 m2 Coating Waterproffing
- Waterproffing 0.6000 Kg 46,000.00 27,600.00
- Serabut Kasa 1.0000 m2 69,000.00 69,000.00
- Upah Pekerjaan
~ Pekerja 0.1200 Oh 55,000.00 6,600.00
~ Tukang Cat 0.0800 Oh 70,000.00 5,600.00
~ Kepala Tukang 0.0070 Oh 85,000.00 595.00
~ Mandor 0.0800 Oh 100,000.00 8,000.00 117,395.00
15 1 m2 Coating Waterproffing tanpa serabut kasa
- Waterproffing 0.3000 Kg 46,000.00 13,800.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00 23,787.50
1 2 3 4 5 6 7
16 1 m2. Lapis melamin duco (2x lapis sampai rata)
- Cat Titan lux 0.500 kg 89,050.00 44,525.00
- Kertas gosok no. 150 1.000 lbr 3,500.00 3,500.00
- Clear 0.200 kg 65,000.00 13,000.00
- Thinner A 0.837 ltr 26,450.00 22,138.65
- Alat
- Sewa alat bantu @ 3 alat 1.00 set 10,000.00 10,000.00
- Sewa compresor 0.625 jam 134,900.00 84,312.50
- Upah Pekerjaan
- Pekerja Terampil 0.075 Oh 55,000.00 4,125.00
- Tukang cat 0.9 Oh 70,000.00 63,000.00
- Kepala tukang cat 0.09 Oh 85,000.00 7,650.00
- Mandor 0.0025 Oh 100,000.00 250.00 252,501.15
17 1 m2 Pengecatan Weathershield
- Plamir 0.100 Kg 17,250.00 1,725.00
- Cat Weathershield 0.100 Kg 90,000.00 9,000.00
- Cat Penutup 2x 0.260 Kg 90,000.00 23,400.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.063 Oh 70,000.00 4,410.00
~ Kepala Tukang 0.0063 Oh 85,000.00 535.50
~ Mandor 0.0025 Oh 100,000.00 250.00 40,420.50

XI PEKERJAAN SANITAIR
1 Memasang 1 buah kloset duduk / monoblok
- Kloset duduk / monoblok 1.000 Bh 1,207,500.00 1,207,500.00
- Perlengkapan 0.060 hrg 1,207,500.00 72,450.00
- Upah Pekerjaan
~ Pekerja 3.300 Oh 55,000.00 181,500.00
~ Tukang Batu 1.100 Oh 45,000.00 49,500.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.160 Oh 100,000.00 16,000.00 1,527,035.00
2 Memasang 1 buah kloset jongkok porselen
- Kloset jongkok porselen 1.000 Bh 126,500.00 126,500.00
- Semen portland 6.000 Kg 1,397.50 8,385.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.500 Oh 45,000.00 67,500.00
~ Kepala Tukang 1.500 Oh 85,000.00 127,500.00
~ Mandor 0.160 Oh 100,000.00 16,000.00 401,789.00
3 Memasang 1 buah urinoir
- Urinoir 1.000 Bh 980,000.00 980,000.00
- Perlengkapan 0.300 hrg 980,000.00 294,000.00
- Semen portland 6.000 Kg 1,397.50 8,385.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.000 Oh 45,000.00 45,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 8,500.00
~ Mandor 0.100 Oh 100,000.00 10,000.00 1,401,789.00
4 Memasang 1 buah wastafel
- Wastafel 1.000 Bh 300,000.00 300,000.00
- Perlengkapan 0.120 hrg 300,000.00 36,000.00
- Semen portland 6.000 Kg 1,397.50 8,385.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 55,000.00 66,000.00
~ Tukang Batu 1.450 Oh 45,000.00 65,250.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.010 Oh 100,000.00 1,000.00 490,289.00
5 Memasang 1 buah bak cuci stainless
- Bak cuci stainless 1.000 Bh 180,000.00 180,000.00
- Water drain dan accessories 1.000 set 30,000.00 30,000.00
1 2 3 4 5 6 7
- Upah Pekerjaan
~ Pekerja 0.030 Oh 55,000.00 1,650.00
~ Tukang Batu 0.300 Oh 45,000.00 13,500.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0015 Oh 100,000.00 150.00 227,850.00
6 Memasang 1 buah bak mandi fiber glass
- Bak fiberglass 1.000 Bh 316,250.00 316,250.00
- Perlengkapan 0.180 hrg 316,250.00 56,925.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 45,000.00 121,500.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00 650,575.00
1 2 3 4 5 6 7
7 Memasang 1 pintu KM PVC
- Pintu PVC 1.000 Bh 316,250.00 316,250.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 45,000.00 121,500.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00 593,650.00
8 Pasang Buis Beton U 20
- Buis Beton 1.000 M 21,000.00 21,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.0035 Oh 100,000.00 350.00 27,072.50
9 Pasang Buis Beton U 30
- Buis Beton 1.000 M 26,500.00 26,500.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00 32,572.50
10 Pasang Buis Beton O 20
- Buis Beton 1.000 M 35,000.00 35,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00 41,072.50
11 Pasang Buis Beton O 30
- Buis Beton 1.000 M 51,000.00 51,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 45,000.00 1,575.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00 57,072.50
12 Memasang 1 buah kran diameter 3/4" atau 1/2"
- Kran air 1.000 Bh 20,000.00 20,000.00
- Seal Tape 0.025 Bh 3,450.00 86.25
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Batu 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 26,486.25
13 Memasang 1 m' pipa PVC diameter 0,5" (AW)
- Pipa PVC 1.000 M' 6,475.00 6,475.00
- Perlengkapan 0.350 Hrg 6,475.00 2,266.25
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00 14,111.25
14 Memasang 1 m' pipa PVC diameter 3/4" (AW)
- Pipa PVC 1.000 M' 7,912.50 7,912.50
- Perlengkapan 0.350 Hrg 7,912.50 2,769.38
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00 16,051.88
15 Memasang 1 m' pipa PVC diameter 1" (AW)
- Pipa PVC 1.000 M' 10,062.50 10,062.50
- Perlengkapan 0.350 Hrg 10,062.50 3,521.88
- Upah Pekerjaan
1 2 3 4 5 6 7
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00 18,954.38
1 2 3 4 5 6 7
16 Memasang 1 m' pipa PVC diameter 2" (AW)
- Pipa PVC 1.000 M' 27,025.00 27,025.00
- Perlengkapan 0.350 Hrg 27,025.00 9,458.75
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0027 Oh 100,000.00 270.00 44,538.75
17 Memasang 1 m' pipa PVC diameter 3" (AW)
- Pipa PVC 1.000 M' 49,312.50 49,312.50
- Perlengkapan 0.350 Hrg 49,312.50 17,259.38
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 78,659.38
18 Memasang 1 m' pipa PVC diameter 4" (AW)
- Pipa PVC 1.000 M' 71,875.00 71,875.00
- Perlengkapan 0.350 Hrg 71,875.00 25,156.25
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 109,118.75
19 Memasang 1 m' pipa PVC diameter 2" (D)
- Pipa PVC 1.000 M' 15,000.00 15,000.00
- Perlengkapan 0.350 Hrg 15,000.00 5,250.00
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0027 Oh 100,000.00 270.00 28,305.00
20 Memasang 1 m' pipa PVC diameter 3" (D)
- Pipa PVC 1.000 M' 22,000.00 22,000.00
- Perlengkapan 0.350 Hrg 22,000.00 7,700.00
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 41,787.50
21 Memasang 1 m' pipa PVC diameter 4" (D)
- Pipa PVC 1.000 M' 33,750.00 33,750.00
- Perlengkapan 0.350 Hrg 33,750.00 11,812.50
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 45,000.00 6,075.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00 57,650.00
22 Memasang 1 m' pipa galvanis diameter 1/2"
- Pipa Galvanis 1.000 M' 23,958.33 23,958.33
- Perlengkapan 0.350 Hrg 23,958.33 8,385.42
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00 42,828.75
23 Memasang 1 m' pipa Galvanis diameter 3/4"
- Pipa Galvanis 1.000 M' 28,750.00 28,750.00
- Perlengkapan 0.350 Hrg 28,750.00 10,062.50
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
1 2 3 4 5 6 7
~ Mandor 0.0270 Oh 100,000.00 2,700.00 49,297.50
24 Memasang 1 m' pipa Galvanis diameter 1"
- Pipa Galvanis 1.000 M' 43,125.00 43,125.00
- Perlengkapan 0.350 Hrg 43,125.00 15,093.75
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 45,000.00 4,050.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00 68,703.75
1 2 3 4 5 6 7
25 Memasang 1 m' pipa Galvanis diameter 1 1/2"
- Pipa Galvanis medium 1.000 M' 64,700.00 64,700.00
- Perlengkapan 0.350 Hrg 64,700.00 22,645.00
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 103,455.00
26 Memasang 1 m' pipa Galvanis diameter 2"
- Pipa Galvanis Medium 1.000 M' 88,166.67 88,166.67
- Perlengkapan 0.350 Hrg 88,166.67 30,858.33
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 135,135.00
27 Memasang 1 m' pipa Galvanis diameter 2 1/2"
- Pipa Galvanis tebal 1.000 M' 110,208.33 110,208.33
- Perlengkapan 0.350 Hrg 110,208.33 38,572.92
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 164,891.25
28 Memasang 1 m' pipa Galvanis diameter 3"
- Pipa Galvanis tebal 1.000 M' 142,791.67 142,791.67
- Perlengkapan 0.350 Hrg 142,791.67 49,977.08
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 45,000.00 8,100.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00 208,878.75
29 Memasang 1 m' pipa Galvanis diameter 4"
- Pipa Galvanis tebal 1.000 M' 208,916.67 208,916.67
- Perlengkapan 0.350 Hrg 208,916.67 73,120.83
- Upah Pekerjaan
~ Pekerja 0.135 Oh 55,000.00 7,425.00
~ Tukang Batu 0.225 Oh 45,000.00 10,125.00
~ Kepala Tukang 0.0225 Oh 85,000.00 1,912.50
~ Mandor 0.0068 Oh 100,000.00 680.00 302,180.00
30 1 Unit Septictank ( h = 1,7 m , L = 1,3 m , P = 2,15 m )
- Galian Tanah 4.752 m3 54,000.00 256,608.00
- Pas. batu bata tebal 1/2 bata, 1 : 3 12.105 m2 92,949.15 1,125,149.46
- Plesteran t = 15 mm, 1Pc : 3Ps 14.005 m2 43,479.32 608,927.88
- Pas. Pipa Pembuangan gas PVC 2" 1.000 m1 44,538.75 44,538.75
- Pek. Beton Bertulang K 175 0.309 m3 2,924,392.86 903,637.39 2,938,861.48
31 1 Unit Resapan ( h = 2,1 m diameter 1,9 m)
- Galian Tanah 3.990 m3 54,000.00 215,460.00
- Pas. batu bata kosong tebal 1 bata 4.396 m2 109,850.00 482,900.60
- Pas. batu bata tebal 1 bata, 1 : 5 1.884 m2 178,109.80 335,558.86
- Plesteran t = 15 mm, 1Pc : 3Ps 1.884 m2 43,479.32 81,915.04
- Pas. Pipa Pembuangan gas PVC 2" 1.000 m1 44,538.75 44,538.75
- Pek. Beton Bertulang K 175 0.118 m3 2,924,392.86 345,078.36
- Kerikil Bulat 2 - 3 cm 0.200 m3 149,500.00 29,900.00
- Ijuk 5.000 kg 8,750.00 43,750.00 1,579,101.61
32 Memasang 1 bh Floor drain
- Floor drain 1.000 Bh 74,750.00 74,750.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Batu 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.0100 Oh 85,000.00 850.00
~ Mandor 0.0050 Oh 100,000.00 500.00 81,150.00
1 2 3 4 5 6 7
XII PEKERJAAN PAVING
1 1 m2 Pasang Paving K 300 abu-abu
- Paving stone K 300 abu-abu 1.000 M2 60,000.00 60,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 100,400.00
2 1 m2 Pasang Paving K 300 warna
- Paving stone K 300 warna 1.000 M2 72,000.00 72,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 112,400.00
1 2 3 4 5 6 7
3 1 m2 Pasang Paving K 200 abu-abu
- Paving stone K 200 abu-abu 1.000 M2 54,000.00 54,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 94,400.00
4 1 m2 Pasang Paving K 200 warna
- Paving stone K 200 warna 1.000 M2 66,000.00 66,000.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 106,400.00
5 1 m2 Pasang Paving K 100 abu-abu
- Paving stone K 100 abu-abu 1.000 M2 38,400.00 38,400.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 78,800.00
6 1 m2 Pasang Paving K 100 warna
- Paving stone K 100 warna 1.000 M2 44,400.00 44,400.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00 84,800.00
7 1 m1 Pasang Kanstin 10,20,50
- Kanstin 2.000 Bh #REF! #REF!
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 #REF!
8 1 m1 Pasang Kanstin 10,30,50
- Kanstin 2.000 Bh #REF! #REF!
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 #REF!
9 1 m1 Pasang Kanstin 15,20,50 (ex pandaan)
- Kanstin 2.000 Bh 31,500.00 63,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 85,044.71
10 1 m1 Pasang Kanstin 15,30,50 (ex pandaan)
- Kanstin 2.000 Bh 33,000.00 66,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
1 2 3 4 5 6 7
~ Mandor 0.0228 Oh 100,000.00 2,280.00 88,044.71
11 1 m1 Pasang Kanstin 15,25,40 (ex pandaan)
- Kanstin 2.500 Bh 16,800.00 42,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 45,000.00 2,700.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00 64,044.71
1 2 3 4 5 6 7
XIII PEKERJAAN PAGAR BESI
1 1 M1 Pasang Pagar BRC tinggi 90 cm
- Kawat BRC t=90 cm 1.000 M1 212,750.00 212,750.00
- Kawat Las RB 0.200 kg 28,750.00 5,750.00
- Upah Pekerjaan 1.000 Org 50,000.00 50,000.00 268,500.00
2 1 M1 Pasang Pagar BRC tinggi 120 cm
- Kawat BRC t=120 cm 1.000 M1 258,750.00 258,750.00
- Kawat Las RB 0.200 kg 28,750.00 5,750.00
- Upah Pekerjaan 1.000 Org 50,000.00 50,000.00 314,500.00
3 1 m2 Pasang pintu besi plat baja tebal 2 mm, rangka baja siku
- Besi siku L 30.30.3 15.000 Kg 12,000.00 180,000.00
- Besi plat baja 32.800 Kg 12,000.00 393,600.00
- Kawat las 0.050 Kg 28,750.00 1,437.50
- Upah Pekerjaan
~ Pekerja 1.050 Oh 55,000.00 57,750.00
~ Tukang besi konstruksi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.105 Oh 85,000.00 8,925.00
~ Mandor 0.052 Oh 100,000.00 5,200.00 720,412.50
4 1 m2 Pasang Pagar besi
- Pagar besi 1.000 M2 450,000.00 450,000.00
- Upah Pekerjaan
~ Pekerja 1.050 Oh 55,000.00 57,750.00
~ Tukang besi konstruksi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.105 Oh 85,000.00 8,925.00
~ Mandor 0.00525 Oh 100,000.00 525.00 590,700.00
5 1 m2 Pasang Pintu Harmonika
- Pintu harmonika 1.000 M2 1,124,125.00 1,124,125.00
- Upah Pekerjaan
~ Pekerja 1.050 Oh 55,000.00 57,750.00
~ Tukang besi konstruksi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.105 Oh 85,000.00 8,925.00
~ Mandor 0.00525 Oh 100,000.00 525.00 1,264,825.00
6 1 m2 Pasang Teralis besi strip (2 x 3) mm
- Besi Plat Strip 6.177 Kg 12,000.00 74,124.00
- Pengelasan 27.080 cm 2,500.10 67,702.71
- Upah Pekerjaan
~ Pekerja 1.670 Oh 55,000.00 91,850.00
~ Tukang besi konstruksi 1.670 Oh 70,000.00 116,900.00
~ Kepala Tukang 0.167 Oh 85,000.00 14,195.00
~ Mandor 0.08300 Oh 100,000.00 8,300.00 298,947.71
7 1 m2 Pasang kawat harmonika
- Kawat harmonika 1.100 M2 43,200.00 47,520.00
- Pengelasan 11.110 Cm 2,500.10 27,776.11
- Baja Strip (0,2x2) cm 1.7160 Kg 12,000.00 20,592.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang besi konstruksi 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.0005 Oh 100,000.00 50.00 106,788.11
8 1 m2 Pasang kawat nyamuk kassa
- Kawat nyamuk kassa alumunium 1.100 M2 28,750.00 31,625.00
- Pengelasan 11.110 Cm 2,500.10 27,776.11
- Baja Strip (0,2x2) cm 1.7160 Kg 12,000.00 20,592.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang besi konstruksi 0.100 Oh 45,000.00 4,500.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.0005 Oh 100,000.00 50.00 90,893.11
BIDANG PENGAIRAN
HARGA SATUAN JUMLAH HSPK 2011
NO JENIS PEKERJAAN KOEF. STN
(Rp) (Rp) (Rp)
1 2 3 4 5 6 7

I KEGIATAN PENGUKURAN
1 Pengukuran Bendung untuk MC. 1.000 bh
TENAGA
1. Juru ukur 1.500 Org/hr 60,000.00 90,000.00
2. Pekerja 4.500 Org/hr 37,000.00 166,500.00
BAHAN
1. Patok kayu uk. 4 x 6 x 50 cm 0.012 m3 2,400,000.00 28,800.00
2. Cat meni 0.120 kg 22,800.00 2,736.00
3. Paku payung 0.050 kg 23,000.00 1,150.00
ALAT
1. Pesawat ukur 1.000 unit 150,000.00 150,000.00
2. Meteran 0.030 bh 14,000.00 420.00
3. Palu 0.060 bh 35,000.00 2,100.00 441,706.00
2 Pengukuran Saluran Untuk MC. 1.000 bh
TENAGA
1. Juru ukur 2.000 Org/hr 60,000.00 120,000.00
2. Pekerja 6.000 Org/hr 37,000.00 222,000.00
BAHAN
1. Patok kayu uk. 4 x 6 x 50 cm 0.012 m3 2,400,000.00 28,800.00
2. Cat meni 0.120 kg 22,800.00 2,736.00
3. Paku payung 0.050 kg 23,000.00 1,150.00
ALAT
1. Pesawat ukur 2.000 unit 150,000.00 300,000.00
2. Meteran 0.045 bh 14,000.00 630.00
3. Palu 0.090 bh 35,000.00 3,150.00
678,466.00
3 Pengukuran Bangunan untuk MC. 1.000 bh
TENAGA
1. Juru ukur 0.250 Org/hr 60,000.00 15,000.00
2. Pekerja 0.750 Org/hr 37,000.00 27,750.00
BAHAN
1. Patok kayu uk. 4 x 6 x 50 cm 0.002 m3 2,400,000.00 4,800.00
2. Cat meni 0.020 kg 22,800.00 456.00
3. Paku payung 0.010 kg 23,000.00 230.00
ALAT
1. Pesawat ukur 0.250 unit 150,000.00 37,500.00
2. Meteran 0.020 bh 14,000.00 280.00
3. Palu 0.030 bh 35,000.00 1,050.00 87,066.00

II KEGIATAN PERSIAPAN
1 Pembuatan bouwplank Pertitik 1.000 m
TENAGA
1. Kep. Tukang Kayu 0.010 Org/hr 50,000.00 500.00
2. Tukang Kayu 0.100 Org/hr 70,000.00 7,000.00
3. Pekerja 0.100 Org/hr 37,000.00 3,700.00
4. Mandor 0.005 Org/hr 55,000.00 275.00
BAHAN
1. Kayu perancah 5/7 0.012 m3 2,200,000.00 26,400.00
3. Paku usuk 0.020 kg 15,000.00 300.00 38,175.00

III PEMBERSIHAN:
1 Pembersihan saluran 1.000 m2
TENAGA
1. Mandor 0.008 Org/hr 55,000.00 440.00
2. Pekerja 0.050 Org/hr 37,000.00 1,850.00 2,290.00
2 Angkutan Pembersihan Saluran 1.000 m3
TENAGA
1. Mandor 0.002 Org/hr 55,000.00 110.00
2. Pekerja Terampil 0.050 Org/hr 37,000.00 1,850.00
ALAT
1 2 3 4 5 6 7
1. Sewa Truck (min 5 jam) 0.020 Jam 151,646.00 3,032.92 4,992.92

IV KEGIATAN PENGGALIAN
1 Menggali Tanah Dengan Alat Berat 1.000 m3
TENAGA
1. Pekerja 0.226 Jam 37,000.00 8,362.00
2. Mandor 0.007 Jam 55,000.00 385.00
ALAT
1. Sewa Excavator 0.076 Jam 297,651.00 22,621.48
2. Sewa Truck (min 5 jam) 0.074 Jam 151,646.00 11,221.80 42,590.28
1 2 3 4 5 6 7
2 Bongkaran Pas. Batu Kali dan dibersihkan 1.000 m3
TENAGA
1. Mandor 0.205 Org/hr 55,000.00 11,275.00
2. Pekerja 2.048 Org/hr 37,000.00 75,776.00
ALAT
1. Bodem 0.010 unit 135,000.00 1,350.00
2. Keranjang 0.083 bh 11,500.00 954.50 89,355.50
3 Bongkaran beton bertulang (mesin) 1.000 m3
TENAGA
Pekerja 1.000 Org/hr 37,000.00 37,000.00
Mandor 0.050 Org/hr 55,000.00 2,750.00
BAHAN .
1. Solar 2.000 Ltr 4,500.00 9,000.00
ALAT
1. Jack hammer 4.000 Jam 25,800.00 103,200.00 151,950.00

V KEGIATAN PENDONGKELAN
1 Pendongkelan rumpun bambu dan menimbun kembali 1.000 m2 0.90
bekas dongkelan
TENAGA
1. Mandor 0.054 Org/hr 55,000.00 2,970.00
2. Pekerja 1.575 Org/hr 37,000.00 58,275.00
BAHAN
1. Tanah urug 0.900 m3 58,500.00 52,650.00
ALAT
1. Ganco 0.050 bh 60,000.00 3,000.00
2. Keranjang 0.225 bh 11,500.00 2,587.50
3. Kereta dorong / alat angkut 0.042 bh 200,000.00 8,400.00
4. Pemadat timbunan (Vibro roller/stamper) 0.900 Jam 33,900.00 30,510.00 158,392.50
2 Pendongkelan rumpun bambu 1.000 m2
TENAGA
1. Mandor 0.045 Org/hr 55,000.00 2,475.00
2. Pekerja 1.327 Org/hr 37,000.00 49,099.00
ALAT
1. Ganco 0.050 bh 60,000.00 3,000.00
2. Keranjang 0.225 bh 11,500.00 2,587.50 57,161.50
3 Pendongkelan pohon keliling >0.75 m 1.000 btg
TENAGA
1. Mandor 0.400 Org/hr 55,000.00 22,000.00
2. Pekerja 3.000 Org/hr 37,000.00 111,000.00
ALAT
1. Gergaji 0.034 bh 35,000.00 1,190.00
2. Ganco 0.050 bh 60,000.00 3,000.00
3. Sabit besar 0.040 bh 40,000.00 1,600.00 138,790.00
4 Pendongkelan pohon keliling >0.75 m dan menimbun 1.000 btg
kembali bekas dongkelan
TENAGA
1. Mandor 0.412 Org/hr 55,000.00 22,660.00
2. Pekerja 3.330 Org/hr 37,000.00 123,210.00
BAHAN
1. Tanah urug 1.200 m3 58,500.00 70,200.00
ALAT
1. Gergaji 0.034 bh 35,000.00 1,190.00
2. Ganco 0.050 bh 60,000.00 3,000.00
3. Sabit besar 0.040 bh 40,000.00 1,600.00
4. Pemadat timbunan (Vibro roller/stamper) 1.200 Jam 33,900.00 40,680.00
5. Kereta dorong / alat angkut 0.042 bh 200,000.00 8,400.00 270,940.00
5 Kosrekan tanah setebal 15 cm dan dibuang keluar 1.000 m2
TENAGA
1. Mandor 0.019 Org/hr 55,000.00 1,045.00
2. Pekerja 0.156 Org/hr 37,000.00 5,772.00
ALAT
1. Keranjang 0.083 bh 11,500.00 954.50 7,771.50
6 Pengeringan / Pompa Air 1.000 Jam
TENAGA
1 2 3 4 5 6 7
1. Operator 0.042 Org/hr 125,000.00 5,250.00
2. Mekanik 0.042 Org/hr 75,000.00 3,150.00
BAHAN
1. Solar 1.500 ltr 4,500.00 6,750.00
ALAT
1. Pompa Air 0.042 unit 40,000.00 1,680.00 16,830.00

VI KEGIATAN PENIMBUNAN & PERATAAN TANAH


1 Urugan Puddel 1 KP : 6 Ps 1.000 m3
BAHAN
1. Pasir urug 0.875 m3 70,000.00 61,250.00
2. Kapur pasang 0.145 m3 488,750.00 70,868.75
TENAGA
1. Mandor 0.150 Org/hr 55,000.00 8,250.00
2. Pekerja 1.500 Org/hr 37,000.00 55,500.00
1 2 3 4 5 6 7
VII KEGIATAN PEMASANGAN BATU
1 Pasangan batu kali bekas bongkaran1pc:4psr 1.000 m3
TENAGA
1. Mandor 0.075 Org/hr 55,000.00 4,125.00
2. Kepala tukang batu 0.075 Org/hr 85,000.00 6,375.00
3. Tukang batu 0.750 Org/hr 70,000.00 52,500.00
4. Pekerja 1.500 Org/hr 37,000.00 55,500.00
BAHAN
1. Pasir Lumajang 0.522 m3 120,000.00 62,640.00
2. Semen (Portland cement) 163.00 Kg 1,495.00 243,685.00 424,825.00
2 Pasangan batu kali dengan spesi 1pc:3psr 1.000 m3
TENAGA
1. Mandor 0.075 Org/hr 55,000.00 4,125.00
2. Kepala tukang batu 0.075 Org/hr 85,000.00 6,375.00
3. Tukang batu 0.750 Org/hr 70,000.00 52,500.00
4. Pekerja 1.500 Org/hr 37,000.00 55,500.00
BAHAN
1. Batu kali 1.200 m3 130,000.00 156,000.00
2. Pasir Lumajang 0.520 m3 120,000.00 62,400.00
3. Semen (Portland cement) 202.500 Kg 1,495.00 302,737.50 639,637.50
3 Pasangan batu raen dengan spesi 1pc:4psr 1.000 m3
TENAGA
1. Mandor 0.114 Org/hr 55,000.00 6,270.00
2. Kepala tukang batu 0.096 Org/hr 85,000.00 8,160.00
3. Tukang batu 0.960 Org/hr 70,000.00 67,200.00
4. Pekerja 2.880 Org/hr 37,000.00 106,560.00
5. Ongkos batu raen 75.000 bh 950.00 71,250.00
BAHAN
1. Batu kali 1.200 m3 130,000.00 156,000.00
2. Pasir Lumajang 0.456 m3 120,000.00 54,720.00
3. Semen (Portland cement) 162.000 Kg 1,495.00 242,190.00 712,350.00

VIII KEGIATAN PLESTERAN


1 Siaran dengan spesi 1pc:2psr 1.000 m2
TENAGA
1. Mandor 0.008 Org/hr 55,000.00 440.00
2. Kepala tukang batu 0.007 Org/hr 85,000.00 595.00
3. Tukang batu 0.075 Org/hr 70,000.00 5,250.00
4. Pekerja 0.150 Org/hr 37,000.00 5,550.00
BAHAN
1. Pasir Lumajang 0.012 m3 120,000.00 1,440.00
2. Semen (Portland cement) 6.340 Kg 1,495.00 9,478.30 22,753.30

IX KEGIATAN PERKAWATAN
1 Bronjong kawat galvanis d = 4mm 1.000 m3
TENAGA
1. Mandor pengisi 0.024 Org/hr 55,000.00 1,320.00
2. Penganyam 0.704 Org/hr 55,000.00 38,720.00
3. Mandor penganyam 0.026 Org/hr 55,000.00 1,430.00
4. Pekerja pengisi 1.382 Org/hr 37,000.00 51,134.00
5. Pekerja penganyam 0.567 Org/hr 37,000.00 20,979.00
BAHAN
1. Batu kali 1.100 m3 130,000.00 143,000.00
2. Kawat galvanize 15.000 kg 23,000.00 345,000.00
ALAT
1. Tang pemotong kawat 0.010 bh 25,000.00 250.00
2. Palu 0.010 bh 35,000.00 350.00 602,183.00

2 Bronjong kawat galvanis d =4mm dengan - 1.000 m3


batu lama
TENAGA
1. Mandor pengisi 0.024 Org/hr 55,000.00 1,320.00
2. Penganyam 0.704 Org/hr 55,000.00 38,720.00
3. Mandor penganyam 0.026 Org/hr 55,000.00 1,430.00
4. Pekerja pengisi 1.382 Org/hr 37,000.00 51,134.00
1 2 3 4 5 6 7
5. Pekerja penganyam 0.567 Org/hr 37,000.00 20,979.00
BAHAN
1. Kawat galvanize 15.000 kg 23,000.00 345,000.00
ALAT
1. Tang pemotong kawat 0.010 bh 25,000.00 250.00
2. Palu 0.010 bh 35,000.00 350.00 459,183.00
3 Pagar kawat berduri tinggi 2,50 m jarak tinggi < = 3 m 1.000 m'
TENAGA
1. Mandor 0.020 Org/hr 55,000.00 1,100.00
2. Tukang 0.110 Org/hr 70,000.00 7,700.00
3. Pekerja 0.110 Org/hr 37,000.00 4,070.00
BAHAN
1. Kawat Duri 1.000 m 4,600.00 4,600.00
2. Besi L 60.60.6 5.240 kg 12,000.00 62,880.00
ALAT
1. Tang 0.010 unit 25,000.00 250.00
2. Bor besi 0.440 bh 42,000.00 18,480.00 99,080.00
1 2 3 4 5 6 7
4 Pagar kawat harmonika jarak tiang < =3m 1.000 m'
TENAGA
1. Mandor 0.020 Org/hr 55,000.00 1,100.00
2. Tukang 0.110 Org/hr 70,000.00 7,700.00
3. Pekerja 0.110 Org/hr 37,000.00 4,070.00
BAHAN
1. Kawat harmonika 1.000 m 43,200.00 43,200.00
2. Besi L 60.60.6 2.340 kg 12,000.00 28,080.00
3. Besi L 30.30.3 4.520 kg 12,000.00 54,240.00
4. Baut 0.300 kg 28,750.00 8,625.00
ALAT
1. Tang 0.010 unit 25,000.00 250.00
2. Bor besi 0.440 bh 42,000.00 18,480.00
165,745.00

X KEGIATAN PASANGAN GORONG-GORONG


1 Pasang Gorong-2 buis beton O 30 1.000 m'
TENAGA
1. Mandor 0.0035 Org/hr 100,000.00 350.00
2. Kepala tukang batu 0.0035 Org/hr 85,000.00 297.50
3. Tukang batu 0.0350 Org/hr 70,000.00 2,450.00
4. Pekerja 0.0700 Org/hr 55,000.00 3,850.00
BAHAN
1. Buis beton 1.0000 M' 51,000.00 51,000.00 57,947.50
2 Pasang Gorong-2 buis beton O 40 1.0000 m'
TENAGA
1. Mandor 0.0040 Org/hr 100,000.00 400.00
2. Kepala tukang batu 0.0035 Org/hr 85,000.00 297.50
3. Tukang batu 0.0350 Org/hr 70,000.00 2,450.00
4. Pekerja 0.0700 Org/hr 55,000.00 3,850.00
BAHAN
1. Buis beton 1.0000 M' 70,000.00 70,000.00 76,997.50
3 Pasang Gorong-2 buis beton O 50 1.0000 m'
TENAGA
1. Mandor 0.0040 Org/hr 100,000.00 400.00
2. Kepala tukang batu 0.0035 Org/hr 85,000.00 297.50
3. Tukang batu 0.0350 Org/hr 70,000.00 2,450.00
4. Pekerja 0.1400 Org/hr 55,000.00 7,700.00
BAHAN
1. Buis beton 1.0000 M' 86,500.00 86,500.00
ALAT
1. Alat Bantu 1.0000 Ls 305.40 305.40 97,652.90
4 Pasang Gorong-2 buis beton O 60 1.0000 m'
TENAGA
1. Mandor 0.0120 Org/hr 100,000.00 1,200.00
2. Kepala tukang batu 0.0035 Org/hr 85,000.00 297.50
3. Tukang batu 0.0350 Org/hr 70,000.00 2,450.00
4. Pekerja 0.2100 Org/hr 55,000.00 11,550.00
BAHAN
1. Buis beton 1.0000 M' 140,000.00 140,000.00
ALAT
1. Alat Bantu 1.0000 Ls 305.40 305.40 155,802.90
5 Pasang Gorong-2 buis beton O 80 1.000 m'
TENAGA
1. Mandor 0.0120 Org/hr 100,000.00 1,200.00
2. Kepala tukang batu 0.0035 Org/hr 85,000.00 297.50
3. Tukang batu 0.0350 Org/hr 70,000.00 2,450.00
4. Pekerja 0.2100 Org/hr 55,000.00 11,550.00
BAHAN
1. Buis beton 1.0000 m' 230,000.00 230,000.00
ALAT
1. Alat Bantu 1.0000 Ls 305.40 305.40 245,802.90
6 Pasang Gorong-2 buis beton O 100 1.0000 m'
TENAGA
1. Mandor 0.1860 Org/hr 100,000.00 18,600.00
1 2 3 4 5 6 7
2. Kepala tukang batu 0.0750 Org/hr 85,000.00 6,375.00
3. Tukang batu 0.7460 Org/hr 70,000.00 52,220.00
4. Pekerja 3.7300 Org/hr 55,000.00 205,150.00
BAHAN
1. Buis beton 1.0000 m' 300,000.00 300,000.00
ALAT
1. Alat Bantu 1.0000 Ls 305.40 305.40 582,345.00
1 2 3 4 5 6 7
7 Pasang U - Ditch 600/600 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1. U - Ditch 600/600/1200 1.0000 bh 1,580,400.00 1,580,400.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 1,801,462.10
8 Pasang U - Ditch Crossing 600/600 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1. U - Ditch Crossing 600/600/1200 1.0000 bh 1,580,400.00 1,580,400.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 1,801,462.10
9 Pasang U - Ditch 600/700 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1. U - Ditch 600/700/1200 1.0000 bh 1,836,000.00 1,836,000.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 2,057,062.10
10 Pasang U - Ditch Crossing 600/700 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1. U - Ditch Crossing 600/700/1200 1.0000 bh 1,836,000.00 1,836,000.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 2,057,062.10
11 Pasang U - Ditch 800/800 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1. U - Ditch 800/800/1200 1.0000 bh 1,909,200.00 1,909,200.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 2,130,262.10
12 Pasang U - Ditch Crossing 800/800 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1. U - Ditch Crossing 800/800/1200 1.0000 bh 1,909,200.00 1,909,200.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 2,130,262.10
13 Pasang Cover U-Heavy 800/120 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1.Cover U - Heavy 800/120/600 1.0000 bh 870,000.00 870,000.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 1,091,062.10
14 Pasang Cover U-Heavy 800/150 Fabrikasi (termasuk Penurunan dan Pemasangan)
TENAGA
1 2 3 4 5 6 7
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1.Cover U - Heavy 800/150/600 1.0000 bh 1,000,000.00 1,000,000.00
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 1,221,062.10
15 Pasang box culvert type BC 1200 (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1.Box culvert type BC 1200 1.0000 bh #REF! #REF!
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 #REF!
1 2 3 4 5 6 7
16 Pasang box culvert type BC 1000 (termasuk Penurunan dan Pemasangan)
TENAGA
1. Mandor 0.0306 Org/hr 100,000.00 3,060.00
2. Operator 0.4340 Org/hr 125,000.00 54,250.00
3. Pekerja tak terampil 0.1571 Org/hr 55,000.00 8,640.50
BAHAN
1.Box culver type BC 1000 1.0000 bh #REF! #REF!
ALAT
1. Sewa Crane 30t - min 8 jam(termasuk mob/demob, BBM) 0.4340 jam 357,400.00 155,111.60 #REF!

XI PENGANGKUTAN TANAH:
1 Pengangkutan tanah sejauh 30m 1.000 m3
TENAGA
1. Pekerja 0.330 Org/hr 55,000.00 18,150.00
2. Mandor 0.010 Org/hr 100,000.00 1,000.00 19,150.00
2 Mengangkut tanah dari lubang galian dalamnya lebih 1.000 m3
dari 1 m
TENAGA
1. Pekerja 0.150 Org/hr 55,000.00 8,250.00
2. Mandor 0.008 Org/hr 100,000.00 800.00 9,050.00
3 Mengangkut lumpur dari lubang galian dalamnya lebih 1.000 m3
dari 1 m
TENAGA
1. Pekerja 0.250 Org/hr 55,000.00 13,750.00
2. Mandor 0.010 Org/hr 100,000.00 1,000.00 14,750.00
4 Mengangkut lumpur Pada lokasi yang sulit 1.000 m3
TENAGA
1. Pekerja 1.400 Org/hr 55,000.00 77,000.00
2. Mandor 0.024 Org/hr 100,000.00 2,400.00 79,400.00
5 Angkutan Tanah Keluar Proyek 1.000 m3
TENAGA
1. Pekerja 0.250 Org/hr 55,000.00 13,750.00
ALAT
1. Sewa Truck (min 5 jam) 0.250 Jam 196,800.00 49,200.00 62,950.00
6 Pengerukan lumpur Pada lokasi sulit (Gorong-2) 1.000 m3
TENAGA
1. Mandor 0.024 Org/hr 100,000.00 2,400.00
2. Pekerja 1.400 Org/hr 55,000.00 77,000.00 79,400.00
7 BIAYA LANGSIRAN >50 m' s/d 100 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.450 Org/hr 55,000.00 24,750.00 24,750.00
8 BIAYA LANGSIRAN s/d 200 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.545 Org/hr 55,000.00 29,975.00 29,975.00
1 2 3 4 5 6 7
9 BIAYA LANGSIRAN s/d 300 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.725 Org/hr 55,000.00 39,875.00 39,875.00
10 BIAYA LANGSIRAN s/d 400 m' 1.000 m3
Upah Pekerjaan
- Pekerja 0.909 Org/hr 55,000.00 49,995.00 49,995.00
11 BIAYA LANGSIRAN s/d 500 m' 1.000 m3
Upah Pekerjaan
- Pekerja 1.090 Org/hr 55,000.00 59,950.00 59,950.00
12 BIAYA LANGSIRAN >700 m' 1.000 m3
Upah Pekerjaan
- Pekerja 1.452 Org/hr 55,000.00 79,860.00 79,860.00
13 Gebalan rumput 1.000 m2
TENAGA
1. Mandor 0.010 Org/hr 100,000.00 1,000.00
2. Pekerja 0.144 Org/hr 55,000.00 7,920.00
BAHAN
1. Gebalan rumput 1.000 m2 15,650.00 15,650.00 24,570.00
14 Pasang Lubang Drainase 1.000 bh
TENAGA
1. Mandor 0.020 Org/hr 100,000.00 2,000.00
2. Kepala Tukang Batu 0.001 Org/hr 85,000.00 85.00
3. Tukang Batu 0.010 Org/hr 70,000.00 700.00
4. Pekerja 0.001 Org/hr 55,000.00 55.00
BAHAN
1. Pipa PVC diameter 1,25" 0.500 m' 8,625.00 4,312.50
2. Ijuk 0.050 kg 8,750.00 437.50 7,590.00

XII PEMASANGAN TRUCUK & PERANCAK:


1 Pemasangan Trucuk Bambu 8 s/d 12 - P.2.50 M' 1.000 btg
TENAGA
1. Mandor 0.003 Org/hr 100,000.00 300.00
2. Kepala Tukang 0.006 Org/hr 85,000.00 510.00
3. Pekerja 0.050 Org/hr 55,000.00 2,750.00
BAHAN
1. Bongkotan Bambu 10-12 cm panjang 3 m 0.667 Bt 17,250.00 11,505.75 15,065.75
2 1.000 btg
Pemasangan Trucuk Kayu Gelam 8 s/d 12 - P.2.50 M'
TENAGA
1. Mandor 0.004 Org/hr 100,000.00 400.00
2. Kepala Tukang 0.008 Org/hr 85,000.00 680.00
3. Pekerja 0.075 Org/hr 55,000.00 4,125.00
BAHAN
1. Kayu Gelam 10 -12 cm 1.000 Bt 17,250.00 17,250.00 22,455.00
3 Pemasangan Perancak Bambu 1.000 m2
TENAGA
1. Mandor 0.033 Org/hr 100,000.00 3,300.00
2. Kepala Tukang 0.067 Org/hr 85,000.00 5,695.00
3. Pekerja 0.600 Org/hr 55,000.00 33,000.00
BAHAN
1. Bambu Ori 10-12 cm panjang 3 m 8.000 Bt 17,250.00 138,000.00
2. Paku Usuk 0.300 Kg 17,500.00 5,250.00
3. Gedeg Guling 1.150 m2 34,500.00 39,675.00 224,920.00
4 Pemasangan Perancah Kayu Gelam 10-12 1.000 m2
TENAGA
1. Mandor 0.033 Hr 100,000.00 3,300.00
2. Kepala Tukang Kayu 0.067 Hr 85,000.00 5,695.00
3. Pekerja 0.600 Hr 55,000.00 33,000.00
BAHAN
1. Kayu Gelam 12 8.000 Hr 17,250.00 138,000.00
2. Paku Usuk 0.300 Kg 17,500.00 5,250.00
3. Gedeg Guling 1.150 m2 34,500.00 39,675.00 224,920.00

XIII PEMBUATAN KISDAM:


1 Pembuatan dan Pembongkaran kistdam 1.000 m
1 2 3 4 5 6 7
TENAGA
1. Mandor 0.038 Org/hr 100,000.00 3,800.00
2. Kepala Tukang Kayu 0.005 Org/hr 85,000.00 425.00
3. Tukang Kayu 0.046 Org/hr 45,000.00 2,070.00
4. Pekerja 1.037 Org/hr 55,000.00 57,035.00
BAHAN
1. Gedek 0.400 lbr 22,500.00 9,000.00
2. Bambu 1.600 btg 17,250.00 27,600.00
3. Kawat 0.370 kg 20,700.00 7,659.00
ALAT
1. Alat pelancip / pisau besar 0.080 bh 25,000.00 2,000.00
2. Bodem 0.030 bh 135,000.00 4,050.00
3. Keranjang 0.040 bh 11,500.00 460.00 114,099.00
1 2 3 4 5 6 7
2 Timbunan pasir dalam karung 1.000 m3
TENAGA
1. Mandor 0.010 Org/hr 100,000.00 1,000.00
2. Pekerja 0.288 Org/hr 55,000.00 15,840.00
BAHAN
1. Pasir urug 1.000 m3 70,000.00 70,000.00
2. Karung plastik 20.000 bh 3,900.00 78,000.00
ALAT
1. Keranjang 0.050 bh 11,500.00 575.00 165,415.00
3 Pembuatan dan pembongkaran Kistdam dengan tinggi 1.000 m
>1m
TENAGA
1. Mandor 0.038 Org/hr 100,000.00 3,800.00
2. Kepala Tukang kayu 0.005 Org/hr 85,000.00 425.00
3. Tukang Kayu 0.046 Org/hr 45,000.00 2,070.00
4. Pekerja 1.037 Org/hr 55,000.00 57,035.00
BAHAN
1. Gedek 0.400 lbr 22,500.00 9,000.00
2. Bongkotan Bambu dia. 10 - 12 cm panjang 3 m 1.600 btg 17,250.00 27,600.00
3. Kawat 0.370 kg 20,700.00 7,659.00
ALAT
1. Alat pelancip / pisau besar 0.080 bh 25,000.00 2,000.00
2. Bodem 0.003 bh 135,000.00 405.00
3. Keranjang 0.040 bh 11,500.00 460.00 110,454.00
4 Pembuatan Kisdam Tinggi 1.00 m tebal 0.60 m 1.000 m
TENAGA
1. Mandor 0.025 Org/hr 100,000.00 2,500.00
2. Kepala Tukang Batu 0.013 Org/hr 85,000.00 1,105.00
3. Tukang Batu 0.110 Org/hr 45,000.00 4,950.00
4. Pekerja 0.225 Org/hr 55,000.00 12,375.00
BAHAN
1. Kawat Ikat 2.400 Kg 20,700.00 49,680.00
2. Gedeg Guling 3.000 m2 34,500.00 103,500.00
3. Bongkotan Bambu dia. 10-12 cm panjang 3m 0.200 Btg 17,250.00 3,450.00 177,560.00
5 Pembuatan Kisdam Tinggi 1.50 m tebal 0,60 m 1.000 m
TENAGA
1. Mandor 0.025 Org/hr 100,000.00 2,500.00
2. Kepala Tukang Batu 0.033 Org/hr 85,000.00 2,805.00
3. Tukang Batu 0.110 Org/hr 45,000.00 4,950.00
4. Pekerja 0.225 Org/hr 55,000.00 12,375.00
BAHAN
1. Kawat Ikat Beton 3.300 m2 20,700.00 68,310.00
2. Gedeg Guling 4.000 m2 34,500.00 138,000.00
3. Bongkotan Bambu dia. 10-12 cm panjang 3m 0.300 Btg 17,250.00 5,175.00 234,115.00
6 Pembuatan Kistdam Tinggi 2.00 m tebal 0,60 m 1.000 m
TENAGA
1. Mandor 0.021 Org/hr 100,000.00 2,100.00
2. Kepala Tukang Batu 0.042 Org/hr 85,000.00 3,570.00
3. Tukang Batu 0.120 Org/hr 45,000.00 5,400.00
4. Pekerja 0.225 Org/hr 55,000.00 12,375.00
BAHAN
1. Kawat Ikat 4.400 m2 20,700.00 91,080.00
2. Gedeg Guling 5.000 m2 34,500.00 172,500.00
3. Bongkotan Bambu dia. 10-12 cm panjang 3m 0.400 Btg 17,250.00 6,900.00 293,925.00
7 Pembuatan Kisdam Tinggi 2.50 m tebal 0,60 m 1.000 m
TENAGA
1. Mandor 0.023 Org/hr 100,000.00 2,300.00
2. Kepala Tukang Batu 0.050 Org/hr 85,000.00 4,250.00
3. Tukang Batu 0.120 Org/hr 45,000.00 5,400.00
4. Pekerja 0.225 Org/hr 55,000.00 12,375.00
BAHAN
1. Kawat Ikat 5.500 m2 20,700.00 113,850.00
2. Gedeg Guling 6.000 m2 34,500.00 207,000.00
3. Bongkotan Bambu dia. 10-12 cm panjang 3m 0.500 Btg 17,250.00 8,625.00 353,800.00
1 2 3 4 5 6 7
XV PEMASANGAN TURAP :
1 Pemasangan Turap Bambu Tinggi 2,75 m' 1.000 m
TENAGA
1. Mandor 0.013 Org/hr 100,000.00 1,300.00
2. Kepala Tukang Kayu 0.004 Org/hr 85,000.00 340.00
3. Tukang Kayu 0.040 Org/hr 45,000.00 1,800.00
4. Pekerja 0.500 Org/hr 55,000.00 27,500.00
BAHAN
1. Kawat Ikat 3.000 m2 20,700.00 62,100.00
2. Gedeg Guling 1.000 m2 34,500.00 34,500.00
3. Bambu bongkotan 10-12 cm panjang 3m 0.200 Btg 17,250.00 3,450.00 130,990.00
1 2 3 4 5 6 7
2 Pemasangan Turap Bambu Tinggi 1,50 m' 1.000 m
TENAGA
1. Mandor 0.007 Org/hr 100,000.00 700.00
2. Kepala Tukang Kayu 0.002 Org/hr 85,000.00 170.00
3. Tukang Kayu 0.020 Org/hr 45,000.00 900.00
4. Pekerja 0.273 Org/hr 55,000.00 15,015.00
BAHAN
1. Kawat Ikat 1.635 m2 20,700.00 33,844.50
2. Gedeg Guling 0.545 m2 34,500.00 18,802.50
3. Bambu bongkotan 10-12 cm panjang 3m 0.109 Btg 17,250.00 1,880.25 71,312.25
3 Pemasangan Turap Papan Tebal ( 3cm ) 1.000 m
TENAGA
1. Mandor 0.080 Org/hr 55,000.00 4,400.00
2. Kepala Tukang Kayu 0.250 Org/hr 85,000.00 21,250.00
3. Tukang Kayu 1.000 Org/hr 70,000.00 70,000.00
4. Pekerja 0.080 Org/hr 37,000.00 2,960.00
BAHAN
1. Kayu Meranti 0.050 m3 6,900,000.00 345,000.00
2. Paku Usuk 0.300 Kg 17,500.00 5,250.00 448,860.00
4 Turap bambu 1.000 m'
TENAGA
1. Mandor 0.020 Org/hr 100,000.00 2,000.00
2. Kepala Tukang Kayu 0.002 Org/hr 85,000.00 170.00
3. Tukang Kayu 0.019 Org/hr 45,000.00 855.00
4. Pekerja 0.864 Org/hr 55,000.00 47,520.00
BAHAN
1. Bambu 1.000 bh 17,250.00 17,250.00
ALAT
1. Alat pelancip / pisau besar 0.040 bh 25,000.00 1,000.00
2. Bodem 0.010 bh 135,000.00 1,350.00 70,145.00

XVI PENGELASAN DAN PEMOTONGAN BAJA


1 Pasang Trektank (Jarum keras) 1.000 Bh
- Treaktank dia. 16 1.000 Bh 31,700.00 31,700.00
- perlengkapan 10.000 % 3,170.00 3,170.00
TENAGA
Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
Mandor 0.050 Oh 100,000.00 5,000.00 43,370.00
2 Pasang Trektank (Jarum keras)
- Treaktank dia. 22 1.000 Bh 74,750.00 74,750.00
- perlengkapan 10.000 % 7,475.00 7,475.00
TENAGA
Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
Mandor 0.050 Oh 100,000.00 5,000.00 90,725.00
3 Pasang Trektank (Jarum keras)
- Treaktank dia. 32 1.000 Bh 287,500.00 287,500.00
- perlengkapan 10.000 % 28,750.00 28,750.00
TENAGA
Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
Mandor 0.050 Oh 100,000.00 5,000.00 324,750.00
4 Gril Bak Kontrol Saluran (100/100) 1.000 m2
- Plat Siku L 50,50,5 33.000 kg 12,000.00 396,000.00
- Plat strip 30x3 27.873 kg 12,000.00 334,480.00
- Kawat Las RB 0.200 kg 28,750.00 5,750.00
- Engsel 1.000 set 28,750.00 28,750.00
- Beton Eyzer f 12 mm 1.200 m 4,260.00 5,112.00
- Upah Pekerjaan
- Tukang Las 0.770 Oh 70,000.00 53,900.00 823,992.00
5 Gril Saluran Air Hujan (20/40) 1.000 bh
- Plat Siku L 50,50,5 12.000 kg 12,000.00 144,000.00
- Plat strip 30x3 1.657 Kg 12,000.00 19,888.00
- Kawat Las RB 0.017 kg 28,750.00 483.00
- Engsel 1.000 set 28,750.00 28,750.00
- Beton Eyzer f 12 mm 0.600 m 7,850.00 4,710.00
1 2 3 4 5 6 7
- Upah Pekerjaan
- Tukang Las 0.062 Oh 70,000.00 4,312.00 202,143.00
6 Gril filter Saluran Air Hujan (20/40) 1.000 bh
- Plat strip 3x30 0.904 kg 12,000.00 10,848.00
- Kawat Las RB 0.017 kg 28,750.00 483.00
- Sekrup fixer 4.000 bh 7,500.00 30,000.00
- Beton Eyzer f 12 mm 1.470 m 7,850.00 11,539.50
- Upah Pekerjaan
- Tukang Las 0.062 Oh 70,000.00 4,312.00 57,182.50
ANALISA HARGA SATUAN PEKERJAAN
KOTA PROBOLINGGO
TAHUN ANGGARAN 2011

Koefisien/ HARGA SATUAN


NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)

Kelompok Pekerjaan Jalan : PEKERJAAN PONDASI JALAN


1 Penyiapan badan jalan 1 m2 #REF!
TENAGA
1 Pekerja 0.0064 Jam #REF! #REF!
2 Mandor 0.0016 Jam #REF! #REF!
PERALATAN
1 Motor Grader 0.0018 Jam #REF! #REF!
2 Vibro roller 0.0016 Jam #REF! #REF!
3 Water Tanker 0.0126 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!

2 Lapisan agregat pondasi kelas A tebal = 0.2 m 1 m3 #REF!


TENAGA
1 Pekerja 0.2201 Jam #REF! #REF!
2 Mandor 0.0314 Jam #REF! #REF!
BAHAN
1 Agregat Base Klas A 1.2000 M3 #REF! #REF!
PERALATAN
1 Wheel Loader 0.0314 Jam #REF! #REF!
2 Dump Truck 8-10 M3 0.1655 Jam #REF! #REF!
3 Motor Grader 0.0092 Jam #REF! #REF!
4 Vibro Roller 0.0080 Jam #REF! #REF!
5 P. Tyre Roller 0.0115 Jam #REF! #REF!
6 Water Tanker 0.0383 Jam #REF! #REF!
7 Alat Bantu 1.0000 Ls #REF! #REF!

3 Lapisan agregat pondasi kelas B 1 m3 #REF!


TENAGA
1 Pekerja 0.2201 Jam #REF! #REF!
2 Mandor 0.0314 Jam #REF! #REF!
BAHAN
1 Agregat Base Klas B 1.2000 M3 #REF! #REF!
PERALATAN
1 Wheel Loader 0.0314 Jam #REF! #REF!
2 Dump Truck 8-10M3 0.1655 Jam #REF! #REF!
3 Motor Grader 0.0092 Jam #REF! #REF!
4 Vibro Roller 0.0080 Jam #REF! #REF!
5 P. Tyre Roller 0.0115 #REF! #REF!
6 Water Tanker 0.0383 Jam #REF! #REF!
7 Alat Bantu 1.0000 Ls #REF! #REF!

4 Lapisan Agregat Pondasi Klas C 1 m3 #REF!


TENAGA
1 Pekerja 0.2800 Jam #REF! #REF!
2 Mandor 0.0400 Jam #REF! #REF!
BAHAN
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
1 Agregat Base kelas C 1.2000 M3 #REF! #REF!
PERALATAN
1 Whell loader 0.0405 Jam #REF! #REF!
2 Dump Truck 0.1570 Jam #REF! #REF!
3 Motor Grader 0.0080 Jam #REF! #REF!
4 Vibro roller 0.0080 Jam #REF! #REF!
5 P.Tyer roller 0.0115 Jam #REF! #REF!
6 Water Tanker 0.0211 Jam #REF! #REF!
7 Alat Bantu 1.0000 Ls #REF! #REF!

5 Macadam Telford ( Onderlaagh ) 1 m2 #REF!


TENAGA
1 Pekerja 1.1667 Jam #REF! #REF!
3 Mandor 0.0583 Jam #REF! #REF!
BAHAN
1 Batu Belah 15/20 0.2400 M3 #REF! #REF!
2 Batu Pecah 5/7 0.0733 M3 #REF! #REF!
3 Pasir 0.1575 M3 #REF! #REF!
PERALATAN
1 Three Wheel Roller 0.0039 Jam #REF! #REF!
2 Alat Bantu 1.0000 Ls #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)

Kelompok Pekerjaan Jalan : PEKERJAAN PENGASPALAN


1 Lapis Resap Pengikat (Prime Coat) 1 Lt #REF!
TENAGA
1 Pekerja 0.0211 Jam #REF! #REF!
2 Mandor 0.0030 Jam #REF! #REF!
BAHAN
1 Aspal Curah 0.6294 Kg #REF! #REF!
2 Kerosene 0.4889 Lt #REF! #REF!
PERALATAN
1 Asphal Sprayer 0.0030 Jam #REF! #REF!
2 Compressor 0.0029 Jam #REF! #REF!
3 Dump Truck 3 - 4 M3 0.0030 Jam #REF! #REF!

2 Lapis Perekat (Tack Coat) 1 Lt #REF!


TENAGA
1 Pekerja 0.0211 Jam #REF! #REF!
2 Mandor 0.0030 Jam #REF! #REF!
BAHAN
1 Aspal Curah 0.8715 Kg #REF! #REF!
2 Kerosene 0.2538 Lt #REF! #REF!
PERALATAN
1 Asphal Sprayer 0.0030 Jam #REF! #REF!
2 Compressor 0.0063 Jam #REF! #REF!
3 Dump Truck 3 - 4 M3 0.0030 Jam #REF! #REF!

3 Aspal untuk Pek.Pelaburan (0.8 Lt/M2) 1 Lt #REF!


TENAGA
1 Pekerja 0.0301 Jam #REF! #REF!
2 Mandor 0.0030 Jam #REF! #REF!
BAHAN
1 Aspal Curah 1.0790 Kg #REF! #REF!
2 Kerosene 0.0524 Lt #REF! #REF!
PERALATAN
1 Asphal Sprayer 0.0030 Jam #REF! #REF!
2 Compressor 0.0023 Jam #REF! #REF!
3 Dump Truck 3 - 4 M3 0.0030 Jam #REF! #REF!

4 Agregat penutup burtu 1 m2 #REF!


TENAGA
1 Pekerja 0.0459 Jam #REF! #REF!
2 Mandor 0.0023 Jam #REF! #REF!
BAHAN
1 Agregat burtu / Chipping 0.0151 m3 #REF! #REF!
PERALATAN
1 Wheel Loader 0.0002 Jam #REF! #REF!
2 Dump Truck 8-10 t 0.0042 Jam #REF! #REF!
3 P.Tyre Roller 0.0023 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!

5 Lataston (HRS) 1 ton #REF!


Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
TENAGA
1 Pekerja 0.1205 Jam #REF! #REF!
2 Mandor 0.0241 Jam #REF! #REF!
BAHAN
1 Agregat kasar 0.2750 M3 #REF! #REF!
2 Agregat halus 0.3968 M3 #REF! #REF!
3 Filler 77.0000 Kg #REF! #REF!
4 Aspal 78.7500 Kg #REF! #REF!
PERALATAN
1 Wheel loader 0.0160 Jam #REF! #REF!
2 AMP 0.0241 Jam #REF! #REF!
3 Dump Truck 0.0000 Jam #REF! #REF!
4 Asphalt Finisher 0.0000 Jam #REF! #REF!
5 Tandem Roller 0.0000 Jam #REF! #REF!
6 P.Tyre Roller 0.0000 Jam #REF! #REF!
7 Alat Bantu 1.0000 Ls #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
6 Aspal Treated Base (ATB) 1 ton #REF!
TENAGA
1 Pekerja 0.1205 Jam #REF! #REF!
2 Mandor 0.0241 Jam #REF! #REF!
BAHAN
1 Agregat kasar 0.3929 M3 #REF! #REF!
2 Agregat halus 0.3064 M3 #REF! #REF!
3 Filler 49.5000 Kg #REF! #REF!
4 Aspal 68.2500 Kg #REF! #REF!
PERALATAN
1 AMP 0.0241 Jam #REF! #REF!
2 Asphalt Finisher 0.0000 Jam #REF! #REF!
3 Tandem Roller 0.0000 Jam #REF! #REF!
4 P. Tyre Roller 0.0000 Jam #REF! #REF!
5 Wheel Loader 0.0161 Jam #REF! #REF!
6 Dump Truck 0.0000 Jam #REF! #REF!
7 Alat Bantu 1.0000 Ls #REF! #REF!

7 Laston (AC) 1 Ton #REF!


TENAGA
1 Pekerja 0.1205 Jam #REF! #REF!
2 Mandor 0.0241 Jam #REF! #REF!
BAHAN
1 Agregat kasar 0.3795 M3 #REF! #REF!
2 Agregat halus 0.3434 M3 #REF! #REF!
3 Filler 22.0000 Kg #REF! #REF!
4 Aspal Curah 63.0000 Kg #REF! #REF!
PERALATAN
1 Wheel loader 0.0162 Jam #REF! #REF!
2 AMP 0.0241 Jam #REF! #REF!
3 Dump Truck - Jam #REF! #REF!
4 Asphalt Finisher - Jam #REF! #REF!
5 Tandem Roller - Jam #REF! #REF!
6 P.Tyre Roller - Jam #REF! #REF!
7 Alat Bantu 1.0000 Ls #REF! #REF!

8 Penetrasi Makadam tebal 5 cm 1 m3 #REF!


TENAGA
1 Pekerja 1.5422 Jam #REF! #REF!
2 Mandor 0.1542 Jam #REF! #REF!
BAHAN
1 Aggregat Pokok (3/5) 0.9429 M3 #REF! #REF!
2 Agregat Pengunci (2/3 ; 1/2, 0,5/1) 0.3929 M3 #REF! #REF!
3 Agregat Penutup (pasir lumajang) 0.2200 M3 #REF! #REF!
4 Aspal Drum 105.0000 Kg #REF! #REF!
PERALATAN
1 Three Wheel Roller 0.0771 Jam #REF! #REF!
2 Alat Bantu 1.0000 Ls #REF! #REF!
3 #REF! 0.1891 Jam #REF! #REF!

9 Pelapisan Burda 1 m2 #REF!


Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
TENAGA
1 Pekerja 0.602 Jam #REF! #REF!
2 Tukang Masak Aspal 0.280 Jam #REF! #REF!
3 Mandor 0.033 Jam #REF! #REF!
BAHAN
1 Aspal AC 3.0000 Kg #REF! #REF!
2 Batu pecah mesin 1/2 0.0140 M3 #REF! #REF!
3 Batu Pecah mesin 0,5/0,5 0.0120 M3 #REF! #REF!
4 Pasir Lumajang 0.0040 M3 #REF! #REF!
5 Kayu Bakar 0.0027 M3 #REF! #REF!
ALAT
1 #REF! 0.0020 Jam #REF! #REF!
2 Alat Bantu 1.0000 Ls #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
KELOMPOK PEKERJAAN JALAN : PEKERJAAN PENUNJUK JALAN
1 Marka Jalan 1 m' #REF!
TENAGA
1 Pekerja 0.6000 Jam #REF! #REF!
2 Tukang 0.3000 Jam #REF! #REF!
3 Mandor 0.1000 Jam #REF! #REF!
BAHAN
1 Thermoplastic 2.6775 Kg #REF! #REF!
2 Glass Bead 0.4725 Kg #REF! #REF!
PERALATAN
1 Compresor 0.1000 Jam #REF! #REF!
2 Alat Bantu 1.0000 Ls #REF! #REF!

2 Patok Pengarah 1 buah #REF!


TENAGA
1 Pekerja 0.9653 Jam #REF! #REF!
2 Tukang 0.4827 Jam #REF! #REF!
3 Mandor 0.1207 Jam #REF! #REF!
BAHAN
1 Beton K-175 0.0338 m3 #REF! #REF!
2 Baja Tulangan 4.2188 Kg #REF! #REF!
3 Cat Dan Material lainnya 1.0000 Ltr #REF! #REF!
PERALATAN
1 Dump Truck 0.1207 Jam #REF! #REF!
2 Alat Bantu 1.0000 Jam #REF! #REF!

3 Patok Hektometer 1 buah #REF!


TENAGA
1 Pekerja 1.2900 Jam #REF! #REF!
2 Tukang 0.6450 Jam #REF! #REF!
3 Mandor 0.1290 Jam #REF! #REF!
BAHAN
1 Beton K-175 0.0281 m3 #REF! #REF!
2 Baja Tulangan 3.5156 Kg #REF! #REF!
3 Cat Dan Material lainnya 1.0000 Ls #REF! #REF!
PERALATAN
1 Dump Truck 0.1290 Jam #REF! #REF!
2 Alat Bantu 1.0000 Jam #REF! #REF!

4 Patok Kilometer 1 buah #REF!


TENAGA
1 Pekerja 1.5867 Jam #REF! #REF!
2 Tukang 0.7933 Jam #REF! #REF!
3 Mandor 0.1983 Jam #REF! #REF!
BAHAN
1 Beton K-175 0.1575 m3 #REF! #REF!
2 Baja Tulangan 19.6875 Kg #REF! #REF!
3 Cat Dan Material lainnya 1.0000 Ls #REF! #REF!
PERALATAN
1 Dump Truck 0.1983 Jam #REF! #REF!
2 Alat Bantu 1.0000 Jam #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)

KELOMPOK PEKERJAAN JALAN : PERBETONAN


1 BETON K-350 1 M3 #REF!
TENAGA
1 Pekerja 7.2289 Jam #REF! #REF!
2 Tukang 1.4458 Jam #REF! #REF!
3 Mandor 0.4819 Jam #REF! #REF!
BAHAN
1 Semen 446.2500 Kg #REF! #REF!
2 Pasir Cor 0.4752 M3 #REF! #REF!
3 Batu Pecah 1 - 2 1.0087 M3 #REF! #REF!
PERALATAN
1 Concrete Mixer 0.4819 Jam #REF! #REF!
2 Water Tanker 0.0576 Jam #REF! #REF!
3 Concrete Vibrator 0.4819 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
2 BETON K-300 1 M3 #REF!
TENAGA
1 Pekerja 7.2289 Jam #REF! #REF!
2 Tukang 1.4458 Jam #REF! #REF!
3 Mandor 0.4819 Jam #REF! #REF!
BAHAN
1 Semen 420.0000 Kg #REF! #REF!
2 Pasir Cor 0.4813 M3 #REF! #REF!
3 Batu Pecah 1.0214 M3 #REF! #REF!
PERALATAN
1 Concrete Mixer 0.4819 Jam #REF! #REF!
2 Water Tanker 0.0542 Jam #REF! #REF!
3 Concrete Vibrator 0.4819 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!

3 BETON K-275 1 M3 #REF!


TENAGA
1 Pekerja 7.2289 Jam #REF! #REF!
2 Tukang 1.4458 Jam #REF! #REF!
3 Mandor 0.4819 Jam #REF! #REF!
BAHAN
1 Semen 393.7500 Kg #REF! #REF!
2 Pasir Cor 0.4873 M3 #REF! #REF!
3 Batu Pecah 1.0342 M3 #REF! #REF!
PERALATAN
1 Concrete Mixer 0.4819 Jam #REF! #REF!
2 Water Tanker 0.0508 Jam #REF! #REF!
3 Concrete Vibrator 0.4819 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!

4 BETON K-225 1 M3 #REF!


TENAGA
1 Pekerja 7.2289 Jam #REF! #REF!
2 Tukang 1.4458 Jam #REF! #REF!
3 Mandor 0.4819 Jam #REF! #REF!
BAHAN
1 Semen 341.2500 Kg #REF! #REF!
2 Pasir Cor 0.4933 M3 #REF! #REF!
3 Batu Pecah 1.0597 M3 #REF! #REF!
PERALATAN
1 Concrete Mixer 0.4819 Jam #REF! #REF!
2 Water Tanker 0.0489 Jam #REF! #REF!
3 Concrete Vibrator 0.4819 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!

5123 BAJA
TENAGA
Besi
Kawat TULANG
Pekerja
Tukang
Mandor
BAHAN BetonPolosPOLOS
Beton
PERALATAN
Alat Bantu 1 Kg
0.1050
0.0350
1.1000
0.0100
1.0000 Jam
Kg
M3
Ls #REF! #REF!
#REF!
5 BAJA TULANG POLOS 1 Kg #REF!
BAHAN
1 Besi beton (polos) 1.0500 Kg #REF! #REF!
2 Kawat beton 0.0150 Kg #REF! #REF!
TENAGA
1 Pekerja 0.0070 Oh #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
2 Tukang Besi 0.0070 Oh #REF! #REF!
3 Kepala Tukang 0.0007 Oh #REF! #REF!
4 Mandor 0.0003 Oh #REF! #REF!

6 BETON K-175 1 M3 #REF!


TENAGA
1 Pekerja 7.2289 Jam #REF! #REF!
2 Tukang 1.4458 Jam #REF! #REF!
3 Mandor 0.4819 Jam #REF! #REF!
BAHAN
1 Semen 283.5000 Kg #REF! #REF!
2 Pasir Cor 0.5125 M3 #REF! #REF!
3 Batu Pecah 1.0878 M3 #REF! #REF!
PERALATAN
1 Concrete Mixer 0.4819 Jam #REF! #REF!
2 Water Tanker 0.0464 Jam #REF! #REF!
3 Concrete Vibrator 0.4819 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!

7 BETON K-125 1 M3 #REF!


TENAGA
1 Pekerja 7.2289 Jam #REF! #REF!
2 Tukang 1.4458 Jam #REF! #REF!
3 Mandor 0.4819 Jam #REF! #REF!
BAHAN
1 Semen 231.0000 Kg #REF! #REF!
2 Pasir Cor 0.5246 M3 #REF! #REF!
3 Batu Pecah 1.1134 M3 #REF! #REF!
PERALATAN
1 Concrete Mixer 0.4819 Jam #REF! #REF!
2 Water Tanker 0.0398 Jam #REF! #REF!
3 Concrete Vibrator 0.4819 Jam #REF! #REF!
4 Alat Bantu 1.0000 Ls #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
KELOMPOK PEKERJAAN JALAN : KANSTEEN (BETON K-175)
1 Kansteen Ukuran (0,4 x 0,15 x 0,5) m 1 M' #REF!
TENAGA
1 Tukang Batu 0.5000 OH #REF! #REF!
2 Mandor 0.0500 OH #REF! #REF!
BAHAN
1 Kansteen Ukuran (0,4 x 0,15 x 0,5) m 2.0000 Buah #REF! #REF!
2 Pasir Pasang 0.0150 M3 #REF! #REF!

2 Kansteen Ukuran (0,2 x 0,15 x 0,5) m 1 M' #REF!


TENAGA
1 Tukang Batu 0.5000 OH #REF! #REF!
2 Mandor 0.0500 OH #REF! #REF!
BAHAN
1 Kansteen Ukuran (0,2 x 0,15 x 0,5) m 2.5000 Buah #REF! #REF!
2 Pasir Pasang 0.0150 M3 #REF! #REF!

3 Pasang Buis Beton dia 60 cm 1.0000 m' #REF!


TENAGA
1 Mandor 0.0120 OH #REF! #REF!
2 Kepala Tukang Batu 0.0035 OH #REF! #REF!
3 Tukang Batu 0.0350 OH #REF! #REF!
4 Pekerja 0.2100 OH #REF! #REF!
BAHAN
1 Pasang Buis Beton dia 60 cm 1.0000 M' #REF! #REF!
ALAT
1 Alat Bantu 1.0000 Ls 305.40 305.40

4 Pasang Buis Beton dia 80 cm 1.0000 m' #REF!


TENAGA
1 Mandor 0.0120 OH #REF! #REF!
2 Kepala Tukang Batu 0.0035 OH #REF! #REF!
3 Tukang Batu 0.0350 OH #REF! #REF!
4 Pekerja 0.2100 OH #REF! #REF!
BAHAN
1 Pasang Buis Beton dia 80 cm 1.0000 M' #REF! #REF!
ALAT
1 Alat Bantu 1.0000 Ls 305.40 305.40

5 Wire Mesh 1.0000 lbr #REF!


TENAGA
1 Mandor 0.0120 OH #REF! #REF!
2 Kepala Tukang Batu 0.0670 OH #REF! #REF!
3 Pekerja 0.0010 OH #REF! #REF!
BAHAN
1 Wire Mesh dia 6 uk. 5,4 x 2,1 m 1.0000 Lbr #REF! #REF!
2 Kawat Beton 0.1400 Kg #REF! #REF!

6 Wire Mesh 1.0000 lbr #REF!


TENAGA
1 Mandor 0.0120 OH #REF! #REF!
Koefisien/ HARGA SATUAN
NO Uraian Kegiatan Satuan HSPK 2011
Volume (RP.)
(Rp.)
2 Kepala Tukang Batu 0.0670 OH #REF! #REF!
3 Pekerja 0.0010 OH #REF! #REF!
BAHAN
1 Wire Mesh dia 10 uk. 5,4 x 2,1 m 1.0000 Lbr #REF! #REF!
2 Kawat Beton 0.1400 Kg #REF! #REF!

7 Pemasangan Hardener Floor 1.0000 m2 #REF!


TENAGA
1 Mandor 0.0340 OH #REF! #REF!
2 Kepala Tukang Batu 0.0300 OH #REF! #REF!
3 Tukang 0.3000 OH #REF! #REF!
4 Pekerja 0.6000 OH #REF! #REF!
BAHAN
1 Semen 15.0500 Kg #REF! #REF!
2 Pasir pasang 0.0230 M3 #REF! #REF!
3 Pewarna/Pigmen 0.2500 Kg #REF! #REF!
4 Batu Ampyang 15.0000 Kg #REF! #REF!
DAFTAR HARGA SATUAN BAHAN BANGUNAN
TAHUN 2016

No. BAHAN Sat. Harga SatuanHarga Satuan


(Rp) 2013
1 2 3 4
I JENIS BAHAN BANGUNAN BAHAN
PENUTUP ATAP & PLAFON
1 Asbes datar tebal 2.7 mm (60 x 200) Lbr 20,700.00
2 Asbes gelombang besar tebal 5 mm (180x100) Lbr 79,100.00
3 Asbes gelombang kecil tebal 4 mm (180x80) Lbr 34,500.00
4 Asbes bubung gelombang kecil (105) M 1
32,800.00
5 Asbes bubung gelombang besar (102) M 1
57,000.00
6 Aluminium (0,90 x 2,10) Lbr 196,000.00
7 Genteng flam pres jawa / lokal Bj 1,500.00
8 Genteng Ambulu Model Karang Pilang Bj 2,550.00
9 Genteng Karang Pilang biasa Bj 2,800.00
10 Genteng Karang Pilang besar Bj 5,750.00
11 Genteng bubung karang pilang Bj 6,900.00
12 Genteng wuwung jawa / lokal Bj 4,050.00
13 Genteng wuwung model karang pilang Bj 5,750.00
14 Genteng wuwung pres beton Bj 8,650.00
15 Genteng wuwung nglayur Bj 5,750.00
16 Genteng Wuwung Keramik (Tengah) Bj 19,550.00
17 Genteng Wuwung Keramik (Tepi) Bj 11,500.00
18 Genteng Beton Bj 5,750.00
19 Genteng Nglayur Bj 2,200.00
20 Genteng Keramik Kilap Bj 15,000.00
21 Genteng kaca Bj 11,500.00
22 Nok genteng Beton Bj 11,500.00
23 Seng Datar BJLS 030 x 90 M 1
45,450.00
24 Seng Gelombang BJLS 030 3x6 Lbr 74,750.00
25 Teak wood tebal 3 mm (1.22 x 2.44) Lbr 112,200.00
26 Teak wood tebal 3 mm (0,9 x 2.10) Lbr 97,750.00
27 Plywood tebal 4 mm (1.22 x 2.44) Lbr 74,750.00
28 Plywood tebal 4 mm (0,9 x 2,1) Lbr 54,700.00
29 Plywood tebal 9 mm (1.22 x 2.44) Lbr 143,750.00
30 Triplek tebal 4 mm (1,20 x 2.40) Lbr 72,450.00
31 Triplek tebal 4 mm (0.90 x 2.10) Lbr 54,700.00
32 Triplek tebal 4 mm (1.22 x 2.44) Lbr 74,750.00
33 Multiplek 9 mm (1.22 x 2.44) Lbr 143,750.00
34 Multiplek 12 mm (1.22 x 2.44) Lbr 212,750.00
35 Multiplek 15 mm (1.22 x 2.44) Lbr 241,500.00
36 Calsiboard ex Gresik (4,5 mm) 1,2 x 2,4 Lbr 69,000.00
37 Calsiboard ex Gresik (3,5 mm) Lbr 57,500.00
38 Eternit kerang bh 13,800.00
39 Fiber Plastic datar M 2
40,250.00
40 Fiber Plastic gelombang M 2
86,250.00
41 Gypsum list profil 15 cm M 1
10,350.00
42 Gypsum list profil 6 cm M 1
8,050.00
43 Gypsum Board 9 (122x244) lbr 69,000.00
44 Polycarbonate (2.1 x 11.8 m) KW 1 M 2
115,000.00
45 Atap Zincalum / Galvalum M 2
86,250.00
46 Rangka Atap Baja Ringan M 2
165,000.00
47 Kalsium plank 30 M1 17,250.00
48 Kalsium plank 20 M1 14,400.00
1 2 3 4
II BAHAN MENGGUNAKAN KAYU
1 Kayu Jati balok (Nasional) Klas 1 M3 26,335,000.00
2 Kayu Jati Papan ( Nasional) Klas 1 M 3
27,830,000.00
3 Kayu Jati Balok (Lokal) Klas 1 M 3
16,100,000.00
4 Kayu Jati Papan ( Lokal ) Klas 1 M 3
16,675,000.00
5 Kayu Jati Balok (Lokal) Klas 2 M 3
12,880,000.00
6 Kayu Jati Papan (Lokal) Klas 2 M 3
13,225,000.00
9 Kayu meranti (balok) (MA) (klas awet 3; klas kuat 2) M 3
6,210,000.00
10 Kayu meranti (papan) (MA) (klas awet 3; klas kuat 2) M 3
6,900,000.00
11 Kayu meranti (balok) (MC) (klas awet 4; klas kuat 4) M 3
4,025,000.00
12 Kayu meranti (papan) - 4m (MC) M 3
4,370,000.00
13 List Kayu Profil - 3m M 1
12,350.00
14 Kayu Bekisting M 3
862,500.00
15 Kayu Perancah M3 2,875,000.00
16 Dolken/Gelam/Bongkot Bambu Ø>10, Pjng >3 m Ljr 17,250.00
17 Gedek / Sesek Bambu Lbr 22,500.00
18 Gedek Guling M 2
34,500.00
19 Kayu Bakar M 3
431,250.00
20 Bambu Ljr 17,250.00
21 Patok Kayu 5/7 M 3
2,530,000.00
22 Kayu Mahoni (klas awet 3, klas kuat 2,3) M 3
3,450,000.00
23 Kayu Mahoni Papan (klas awet 3, klas kuat 2,3) M 3
4,025,000.00
24 Kayu Gemalina M 3
3,450,000.00
25 Kayu kruing (balok) - 4m M 3
8,970,000.00
26 Kayu kruing (papan) - 4m M 3
9,775,000.00
27 Kayu kamper (balok) - 4m M 3
9,100,000.00
28 Kayu kamper (papan) - 4m M 3
11,500,000.00
29 Kayu Bayur M 3
3,335,000.00
30 Kayu Cemara M3 3,105,000.00
31 Kayu Sono Keling M3 3,450,000.00

III BAHAN MENGGUNAKAN BATU/PASIR & SEMEN


1 Agregat Base Klas A M3 177,350.00
2 Agregat Base Klas B M 3
166,750.00
3 Agregat Base Klas C M 3
81,650.00
4 Batu Bata merah kelas 1 Bj 600.00
5 Batu bata merah kelas 2 Bj 500.00
6 Batu kali/batu belah - lokal M 3
130,000.00
7 Batu belah 15/20 ( Lumajang ) M 3
103,500.00
8 Batu pecah 5/7 lokal M 3
155,000.00
9 Batu pecah lokal 0,5-3 (campuran) M 3
158,200.00
10 Batu kali pecah 3/5 M 3
158,200.00
11 Batu/cor koral pecah 2/3 M 3
158,200.00
12 Batu pecah 1/2 M3 158,200.00
13 Batu pecah mesin 0,5-1 cm/Abu batu M3 258,750.00
14 Batu pecah mesin 1-2 cm M3 258,750.00
15 Batu pecah mesin 2-3 cm M 3
258,750.00
16 Batu pecah mesin 3-5 cm M 3
258,750.00
17 Kerikil bulat 2-3 cm M 3
149,500.00
18 Pasir Beton (pasir Lumajang) M 3
120,000.00
19 Pasir Pasang Lokal M 3
90,400.00
20 Pasir urug M 3
70,000.00
21 Pasir grosok/garuk M3 70,000.00
1 2 3 4
22 Semen berwarna yiyitan kg 9,800.00
23 Semen PC ( 40 Kg) Zak 59,800.00
24 Strotox - 100 Kg 84,000.00
25 Semen Putih Kg 2,300.00
26 Kapur gamping Ton 1,150,000.00
27 Kapur Pasang M 3
488,750.00
28 Tanah Urug M 3
60,000.00
29 Tanah Urug untuk Taman M 3
75,000.00
30 Tanah Paras M 3
70,000.00
31 Sirtu biasa M 3
80,500.00
32 Roster terawang bakar Bj 4,600.00
33 Bataco 10,20,40 Bj 3,700.00
34 Pagar Panel Beton M 2
205,000.00

IV BAHAN MENGGUNAKAN BESI/LOGAM


1 Besi begel/ baut Kg 25,300.00
2 Besi beton ulir Kg 12,000.00
3 Besi beton polos Kg 11,800.00
4 Beton Eyzer Ø 12 mm M 1
7,850.00
5 Besi pipa galvanis medium 1/2, 6m Ljr 143,750.00
6 Besi pipa galvanis medium 3/4, 6m Ljr 172,500.00
7 Besi pipa galvanis medium 1, 6m Ljr 258,750.00
8 Besi pipa galvanis medium 1 1/4, 6m Ljr 339,250.00
9 Besi pipa galvanis medium 1 1/2, 6m Ljr 388,200.00
10 Besi pipa galvanis medium 2, 6m Ljr 529,000.00
11 Besi pipa galvanis medium 2 1/2, 6m Ljr 661,250.00
12 Besi pipa galvanis medium 3, 6m Ljr 856,750.00
13 Besi pipa galvanis tebal 4, 6m Ljr 1,253,500.00
5 Besi pipa gas medium 1/2, 6m Ljr 57,500.00
6 Besi pipa gas medium 3/4, 6m Ljr 74,750.00
7 Besi pipa gas medium 1, 6m Ljr 92,000.00
8 Besi pipa gas medium 1 1/4, 6m Ljr 109,250.00
9 Besi pipa gas medium 1 1/2, 6m Ljr 138,000.00
10 Besi pipa gas medium 2, 6m Ljr 172,500.00
11 Besi pipa gas medium 2 1/2, 6m Ljr 230,000.00
12 Besi pipa gas medium 3, 6m Ljr 258,750.00
13 Besi pipa gas tebal 4, 6m Ljr 437,000.00
14 Besi profil WF Kg 13,300.00
15 Besi profil canal C Kg 12,600.00
16 Besi siku L Kg 12,000.00
17 Besi plat strip Kg 12,000.00
18 Kawat Baja Sling Ø 26 RB M 1
276,000.00
19 Kawat ikat beton/bendrat Kg 20,000.00
20 Kawat nyamuk kasa alumunium M 2
28,750.00
21 Kawat harmonika M 2
43,200.00
22 Kawat las RB Kg 28,750.00
23 Kawat BRC Tinggi = 90 cm M1 212,750.00
24 Kawat BRC Tinggi = 120 cm M1 258,750.00
25 Kawat BRC Tinggi = 175 cm M 1
287,500.00
26 Kawat Galvanis Kg 23,000.00
27 Kawat Kg 20,700.00
28 Kawat Duri M 1
4,600.00
1 2 3 4
29 Trestank Ø 16 Bh 31,700.00
30 Trestank Ø 22 Bh 74,750.00
31 Trestank Ø 32 Bh 287,500.00
32 Anker Ø 16 mm Bh 46,000.00
33 Baut Ø 16 mm Bh 22,200.00
34 Baut Ø 12 mm Bh 20,900.00
35 Baut Ø 10 mm Bh 10,350.00
36 Pintu lipat harmonika M 2
977,500.00
37 Pintu KM Almunium t = 1mm lengkap kusen 3" unit 1,380,000.00
38 Rolling Door tebal 1,2 mm silver M 2
419,750.00
39 Rolling Door tebal 1,2 mm coklat M 2
488,750.00
40 Kusen Almunium 3" Silver M 1
69,000.00
41 Kusen Almunium 3" Brown M 1
74,750.00
42 Kusen Almunium 4" Silver M 1
86,250.00
43 Kusen Almunium 4" Brown M 1
92,000.00
44 Kusen Curtain Wall 3" silver M1 69,000.00
45 Kusen Curtain Wall 3" brown M1 74,750.00
46 Kusen Curtain Wall 4" silver M1 86,250.00
47 Kusen Curtain Wall 4" brown M 1
92,000.00
48 Daun jendela almunium silver M 1
50,600.00
49 Daun jendela almunium brown M 1
63,250.00
50 Sunscreen Almunium M 1
1,115,500.00
51 Sponeng/stopper almunium M 1
23,000.00
52 Skrup fixer bh 1,600.00
53 Wiremesh dia 4 ukuran 5,4 x 2,1 m lbr 204,600.00
54 Wiremesh dia 5 ukuran 5,4 x 2,1 m lbr 277,200.00
55 Wiremesh dia 6 ukuran 5,4 x 2,1 m lbr 382,800.00
56 Wiremesh dia 8 ukuran 5,4 x 2,1 m lbr 814,200.00
57 Wiremesh dia 10 ukuran 5,4 x 2,1 m lbr 1,188,000.00
58 Besi hollow 2x4 tebal 1,4 ljr 62,100.00
59 Besi hollow 2x4 tebal 1,6 ljr 72,450.00
60 Besi hollow 2x4 tebal 1,8 ljr 83,950.00
61 Besi hollow 4x4 tebal 1,2 ljr 69,000.00
62 Besi hollow 4x4 tebal 1,4 ljr 87,400.00
63 Besi hollow 4x4 tebal 1,6 ljr 98,900.00
64 Besi hollow 4x4 tebal 1,8 ljr 120,750.00
65 Besi hollow 5x5 tebal 1,2 ljr 89,700.00
66 Besi hollow 5x5 tebal 1,4 ljr 110,400.00
67 Besi hollow 5x5 tebal 1,6 ljr 128,800.00
68 Besi hollow 5x5 tebal 1,8 ljr 155,250.00
69 Besi hollow partisi 2x4 tebal 0,4 ljr 33,350.00
70 Besi hollow partisi 4x4 tebal 0,4 ljr 39,100.00

V BAHAN UNTUK LANTAI


1 Paving stone K 300 warna ex pandaan tebal 8 cm M2 86,500.00
2 Paving stone K 300 abu-abu ex pandaan tebal 8 cm M2 74,500.00
3 Paving stone K 400 warna ex pandaan tebal 6 cm M2 108,000.00
4 Paving stone K 400 abu-abu ex pandaan tebal 6 cm M2 102,000.00
5 Paving stone K 300 warna ex pandaan tebal 6 cm M 2
72,000.00
6 Paving stone K 300 abu-abu ex pandaan tebal 6 cm M 2
60,000.00
7 Paving stone K 200 warna tebal 6 cm M 2
66,000.00
8 Paving stone K 200 abu-abu tebal 6 cm M 2
54,000.00
1 2 3 4
9 Paving stone K 100 warna tebal 6 cm M2 44,400.00
10 Paving stone K 100 abu-abu tebal 6 cm M2 38,400.00
11 Paving Grass Block 30x30 M2 54,000.00
12 Uskup K 200 tebal 8 cm bh 3,600.00
13 Uskup K 300 tebal 8 cm bh 4,800.00
14 Uskup K 400 tebal 8 cm bh 7,000.00
15 Uskup K 200 tebal 6 cm bh 3,000.00
16 Uskup K 300 tebal 6 cm bh 3,600.00
17 Uskup K 400 tebal 6 cm bh 5,500.00
18 Kanstin 10.20.40 bh 14,400.00
19 Kanstin 15.25.40 K175 bh 16,800.00
20 Kanstin 15.20.50 K200 bh 31,500.00
21 Kanstin 15.30.50 K200 bh 33,000.00
22 Kanstin 15.30.50 lubang grill K200 bh 36,000.00
24 Kanstin 15.40.50 K200 bh 36,000.00
25 Kanstin 15.40.50 lubang grill bh 39,000.00
26 Kanstin Median 15.40.50 bh 40,500.00
27 Keramik granito warna motif 30x30 M2 170,000.00
28 Keramik granito warna motif 40x40 M 2
212,500.00
29 Keramik granito warna motif 60x60 M 2
300,000.00
30 Tegel Garis Abu-abu M 2
46,000.00
31 Keramik lantai 30/30 Putih KW I M 2
48,900.00
32 Keramik lantai 30/30 Warna KW I M 2
48,900.00
33 Keramik lantai 30/30 Kasar KW I M 2
52,900.00
34 Keramik lantai 40/40 Putih KW I M 2
87,000.00
35 Keramik lantai 40/40 Warna KW I M 2
57,500.00
36 Keramik lantai 40/40 Kasar KW I M 2
69,000.00
37 Keramik lantai 60/60 Warna KW I M 2
100,700.00
38 Keramik dinding 20/25 Putih KW I M 2
51,750.00
39 Keramik dinding 20/25 Warna KW I M 2
55,200.00
40 Keramik lantai 20/20 M2 51,750.00
41 List Keramik 5/20 bh 3,500.00
42 Batu Alam Candi M2 115,000.00
43 Batu Susun Sirih 2,5/40 M 2
115,000.00
44 Batu Alam Garis, Alur M 2
109,250.00
45 Batu Alam Lempeng M 2
28,750.00
46 Batu Alam Palimanan, Marmo M 2
103,500.00
47 Batu Alam Koral M 2
23,000.00
48 Batu Alam Andesit 15/15 M 2
109,250.00
49 Batu Alam Andesit 20/40 M 2
143,750.00
50 Batu Alam Andesit 30/60 M 2
155,250.00
51 Batu Alam Sukabumi/lempeng 10/10 M 2
74,750.00
52 Batu Alam Ampyang kg 4,600.00
53 Cetakan Semen M 2
46,000.00
54 Roster batu alam 20/20 bh 34,500.00
55 Roster batu alam 25/25 bh 40,250.00
56 Roster batu alam 30/30 bh 46,000.00
57 Roster batu alam 40/40 bh 51,750.00
58 Roster batu alam 30/60 bh 86,250.00
59 Roster batu alam 25/50 bh 80,500.00
60 Batu Alam Koral Taman Warna M 2
M
2
58,000.00
1 2 3 4
VI BAHAN UNTUK PENGECATAN
1 Cat besi Kg 55,000.00
2 Cat kayu Kg 55,000.00
3 Cat brown putih Kg 48,900.00
4 Cat Meni kayu Kg 31,700.00
5 Cat Meni besi Kg 31,700.00
6 Cat tembok warna Kg 23,000.00
7 Cat tembok putih Kg 21,300.00
8 Cat marka Kg 60,400.00
9 Cerlak Kg 89,700.00
10 Politur Lt 66,700.00
11 Vernis Lt 88,550.00
12 Dempul Kg 35,600.00
13 Minyak cat Lt 26,450.00
14 Teer Kg 16,350.00
15 Kertas gosok Lbr 3,500.00
16 Plamir tembok Kg 17,250.00
17 Plamir kayu Kg 31,600.00
18 Plamir Besi Kg 43,100.00
19 Spiritus Lt 20,100.00
20 Lem kayu Kg 12,500.00
21 Thinner B / minyak cat Lt 11,100.00
22 Soda api Kg 28,750.00
24 Cat Genteng Kg 34,500.00
25 Cat Taman / Tekstur Kg 79,350.00
26 Cat Coating Batu Alam Lt 69,000.00
27 Cat Waterproffing Kg 46,000.00
28 Cat Weathershield Kg 90,000.00
29 Serabut Kasa Waterproffing M 2
69,000.00
30 Kuas Bh 17,250.00
31 Termoplastic Kg 36,500.00
32 Glass Bead Kg 25,450.00
33 Wallpapper 50 cm m ### 20,000.00
34 Cat Titan kg ### 90,300.00
35 Clear kg ### 65,900.00

VII BAHAN PENGGANTUNG DAN PENGUNCI


1 Engsel H Stl 12,500.00
2 Engsel Kuningan arch asli Stl 25,000.00
3 Engsel jendela Stl 11,100.00
4 Engsel Pintu Besar Stl 34,500.00
5 Engsel Pintu Kecil Stl 12,500.00
6 Engsel Grill Bh 28,750.00
7 Sekrup fixer Bh 7,500.00
8 Grendel biasa (besar) Bh 13,400.00
9 Grendel biasa (kecil) Bh 7,300.00
10 Kunci tanam Bh 72,000.00
11 Kunci tanam hias Set 195,500.00
12 Kunci pintu Set 72,000.00
13 Kunci tanam silender Bh 105,000.00
14 Kunci Selot Bh 45,000.00
1 2 3 4
15 Hak angin (kuningan) Stl 20,700.00
16 Hak angin 4 mm (lurus) Stl 19,000.00
17 Pegangan Pintu Biasa Stl 49,000.00
18 Pegangan Pintu Hias Stl 149,500.00
19 Floor Hinge Set 977,500.00
20 Door Closer Bh 65,100.00
21 Door Stop Bh 71,000.00

VIII BAHAN UNTUK KM/WC/URINOIR


1 Pipa / slang spiral saluran kran Bh 30,000.00
2 Closet duduk lengkap tangki Bh 1,207,500.00
3 Closet duduk biasa lengkap+tutup Set 488,750.00
4 Closet jongkok Bh 126,500.00
5 Closet jongkok teraso Bh 92,000.00
6 Bak cuci piring stainless steel 1 bak Bh 180,000.00
7 Bak cuci + meja beton teraso Bh 172,500.00
8 Bak mandi fiberglass Bh 316,250.00
9 Wastafel kecil Bh 300,000.00
10 Kran air washtafel Bh 74,750.00
11 Kran air biasa 1/2" Bh 20,000.00
12 Kran air plastik 1/2" Bh 15,000.00
13 Tempat sabun besar Bh 23,000.00
14 Tempat sabun kecil Bh 17,250.00
15 Urinoir lengkap asesoris Bh 980,000.00
16 Instalasi Kran Air Ttk 115,000.00
17 Avuur Lantai (Stainless) Bh 74,750.00
18 Avuur Bak (Stainless) Bh 19,550.00
19 Avuur Lantai (plastik) Bh 14,400.00
20 Avuur Bak (plastik) Bh 5,750.00
21 Pintu PVC Lengkap Kusen Set 316,250.00
22 Tandon Air Stainless Steel 1000 liter Bh 2,300,000.00
23 Tandon Air Fiber 1000 liter Bh 1,265,000.00

IX BAHAN JENIS KACA


1 Kaca polos tb. 3 mm M2 51,750.00
2 Kaca polos tb 5 mm M 2
69,000.00
3 Kaca rayban tb. 5mm M 2
80,500.00
4 Kaca es 3 mm M2 80,500.00
5 Kaca es 5 mm M2 109,250.00
6 Kaca tebal 8 tb.mm M2 172,500.00
7 Kaca Tempered tb.12 mm M 2
632,500.00
8 Glass block Bh 20,700.00

X BAHAN BETON CETAKAN


1 Buis beton O 20 cm M 35,000.00
2 Buis beton O 30 cm M 51,000.00
3 Buis beton O 40 cm M 70,000.00
4 Buis beton O 50 cm M 86,500.00
5 Buis beton U 20 mm M 21,000.00
6 Buis beton U 30 mm M 26,500.00
7 Buis beton U 40 mm M 35,000.00
8 Gorong-gorong beton D=60cm M 140,000.00
9 Gorong-gorong beton D=80cm M 230,000.00
10 Gorong-gorong beton D=100cm M 300,000.00
1 2 3 4
11 Box Culvert U Ditch 600x600x1200 t:150 mm bh 1,580,400.00
12 Box Culvert U Ditch 600x800x1200 t:150 mm bh 1,836,000.00
13 Box Culvert U Ditch 800x800x1200 t:150 mm bh 1,909,200.00
14 Box Culvert U Ditch 800x1000x1200 t:150 mm bh 2,160,000.00
15 Box Culvert U Ditch 1000x1000x1200 t:150 mm bh 2,688,000.00
16 Box Culvert U Ditch 1200x1200x1200 t:150 mm bh 3,060,000.00
17 Box Culvert Monolit 1500x1500x1200 mm bh 8,256,000.00
18 Box Culvert Monolit 2100x1500x1200 mm bh 8,737,200.00
19 Box Culvert Monolit 2400x2400x1200 mm bh 13,508,400.00
20 Box Culvert Monolit 3500x3500x1200 mm bh 18,480,000.00
21 Box Culvert Monolit 3500x4000x1200 mm bh 19,543,200.00
22 Cover U Heavy 600x120x1200 bh 487,200.00
23 Cover U Heavy 800x120x1200 bh 616,200.00
24 Cover U Heavy 1000x120x1200 bh 870,000.00
25 Cover U Heavy 1200x150x1200 bh 1,000,000.00

XI BAHAN PLASTIK
1 Keni PVC 1/2" Bh 2,500.00
2 Keni PVC 3/4" Bh 3,000.00
3 Keni PVC 1" Bh 4,000.00
4 Keni PVC 1 1/4" Bh 4,000.00
5 Keni PVC 1 1/2" Bh 4,000.00
6 Keni PVC 2" Bh 5,000.00
7 Keni PVC 2,5" Bh 6,000.00
8 Keni PVC 3" Bh 7,000.00
9 Keni PVC 4" Bh 9,000.00
10 Shock 1/2" Bh 1,500.00
11 Shock 3/4" Bh 1,500.00
12 Shock 1" Bh 2,000.00
13 Shock 1 1/4" Bh 3,000.00
14 Shock 1 1/2" Bh 3,000.00
15 Shock 2" Bh 3,000.00
16 Shock 2,5" Bh 4,500.00
17 Shock 3" Bh 7,000.00
18 Shock 4" Bh 8,000.00
19 Shock drat luar 1" Bh 3,450.00
20 Stop Kran 1" Bh 132,250.00
21 Stop Kran 3/4" Bh 100,650.00
22 Tee 1/2" Bh 2,900.00
23 Tee 3/4" Bh 3,450.00
24 Tee 1" Bh 4,600.00
25 Tee 1 1/4" Bh 5,200.00
26 Tee 1 1/2" Bh 7,500.00
27 Tee 2" Bh 9,800.00
28 Tee 4" Bh 43,150.00
29 Tee Verloop PVC 1" x 3/4" Bh 4,600.00
30 Keni Verloop PVC 1" x 3/4" Bh 7,500.00
31 Keni Drat 3/4" x 1/2" Bh 9,800.00
32 Keni Galvanis 1/2" Bh 5,750.00
33 Seal Tape Bh 3,450.00
34 Lem PVC /Sealent Bh 6,900.00
35 Pelampung Otomatis Bh 172,500.00
36 Klem Pipa Bh 5,200.00
37 Filter Pipa /kleb pipa Bh 7,500.00
1 2 3 4
38 Corong W Bh 20,700.00
39 Corong U Bh 23,000.00
40 Pipa paralon 5/8" panjang 4 Ljr 5,500.00
41 Pipa PVC 1/2" (AW) Ljr 25,900.00
42 Pipa PVC 3/4" (AW) Ljr 31,650.00
43 Pipa PVC 1" (AW) Ljr 40,250.00
44 Pipa PVC 1 1/4" (AW) Ljr 55,800.00
45 Pipa PVC 1 1/2" (AW) Ljr 73,600.00
46 Pipa PVC 2" (AW) Ljr 108,100.00
47 Pipa PVC 2,5" (AW) Ljr 138,600.00
48 Pipa PVC 3" (AW) Ljr 197,250.00
49 Pipa PVC 4" (AW) Ljr 287,500.00
50 Pipa PVC 6" (AW) Ljr 598,000.00
51 Pipa PVC 8" (AW) Ljr 931,500.00
52 Pipa PVC 10" (AW) Ljr 1,322,500.00
53 PVC 1" D Ljr 32,200.00
54 PVC 1,25" D Ljr 34,500.00
55 PVC 1,5" D Ljr 40,250.00
56 PVC 2" D Ljr 60,000.00
57 PVC 3" D Ljr 88,000.00
58 PVC 4" D Ljr 135,000.00
59 PVC 5" D Ljr 165,000.00
60 PVC 6" D Ljr 201,500.00
61 PVC U 15 Ljr 106,250.00

XII BAHAN JENIS PAKU


1 Paku Kg 17,500.00
2 Paku asbes bh 1,750.00
3 Mur, Baut Kg 28,750.00
4 Paku Payung Kg 23,000.00

XIII BAHAN PERALATAN LISTRIK


1 Stop kontak Bh 14,400.00
2 Stop kontak AC Bh 75,000.00
3 Skakelar Tunggal Bh 12,650.00
4 Skakelar Ganda Bh 17,500.00
5 Arde 12 mm Ljr 17,500.00
6 Bola Armateur Bh 120,750.00
7 Box Sekering Unit 52,000.00
8 Instalasi listrik Ttk 165,000.00
9 Kabel NYA 1 1/2 m 3,000.00
10 Kabel NYA 2 ,5mm m 4,100.00
11 Kabel NYY 3 X 2 1/2 m 19,000.00
12 Kabel NYA 4 X 2 1/2 m 21,850.00
Isolator bh 1,500.00
T dos PVC bh 6,000.00
Pipa Listrik 5/8 Ljr 13,000.00
Stater Lampu TL bh 8,500.00
Last Doof bh 550.00
Fitting plafound bh 22,000.00
13 Kap Down Light Besar Bh 63,500.00
14 Kap Down Light Kecil Bh 51,750.00
15 Lampu pijar 25 watt Bh 5,750.00
16 Lampu pijar 5 watt Bh 4,100.00
1 2 3 4
17 Lampu TL 1x20 W komplit+reflektor (TKI) Bh 190,000.00
18 Lampu TL 1x40 W komplit+reflektor (TKI) Bh 283,000.00
19 Lampu TL 2x20 W komplit+reflektor (TKI) Bh 236,000.00
20 Lampu TL 2x40 W komplit+reflektor (TKI) Bh 402,500.00
21 Lampu TL 1x20 W komplit+reflektor (biasa) Bh 72,500.00
22 Lampu TL 1x40 W komplit+reflektor (biasa) Bh 108,100.00
23 Lampu TL 2x20 W komplit+reflektor (biasa) Bh 87,400.00
24 Lampu TL 2x40 W komplit+reflektor (biasa) Bh 168,000.00
25 Lampu TL tanam 2x20 W stainless steel Bh 400,000.00
26 Lampu XL 18 watt Bh 31,100.00
27 Lampu TL 20 Watt Bh 43,700.00
Sekring Cast bh 65,000.00
28 MCB 2 A Bh 46,000.00
29 MCB 16 A Bh 51,750.00
30 Panel MACB Bh 195,500.00
31 Panel box Bh 178,250.00
32 Penangkal petir ( Radius 5 M ) Set 730,250.00
33 Pitingan Putih Bh 10,350.00
34 Pasang Daya Listrik 450 Watt Unit 2,100,000.00
35 Pasang Daya Listrik 900 Watt Unit 2,570,000.00
36 Pasang Daya Listrik 1300 Watt Unit 3,280,000.00
37 Pasang Daya Listrik 2200 Watt Unit 3,995,000.00
38 Pasang Daya Listrik 3500 Watt Unit 5,278,500.00
39 Pasang Daya Listrik 4400 Watt Unit 7,132,000.00
40 Pasang Daya Listrik 5500 Watt Unit 8,558,200.00

XIV BAHAN BBM


1 Aspal Drum Kg 10,600.00
2 Aspal Curah Kg 9,800.00
3 Bensin Ltr 4,500.00
4 Solar Ltr 4,500.00
5 Filler Kg 500.00
6 Minyak Tanah Ltr 11,000.00
7 Minyak Pelumas Ltr 42,600.00
8 Minyak bekisting Liter 3,200.00

XV LAIN-LAIN
1 Karung Plastik Bh 3,900.00
2 Ijuk Kg 8,750.00
3 Gabalan Rumput M 2
15,650.00
DAFTAR HARGA UPAH PEKERJA

NO TENAGA KERJA Sat. Harga Satuan


(Rp)

1 Mandor Org/hari 100,000.00


2 Kepala Tukang Kayu Org/hari 85,000.00
3 Kepala Tukang Batu Org/hari 85,000.00
4 Kepala Tukang Cat Org/hari 85,000.00
5 Kepala Tukang Las Org/hari 85,000.00
6 Kepala Tukang Besi Org/hari 85,000.00
Kepala Tukang listrik Org/hari 85,000.00
7 Tukang Kayu Org/hari 70,000.00
8 Tukang Batu Org/hari 70,000.00
9 Tukang Cat Org/hari 70,000.00
10 Tukang Besi Org/hari 70,000.00
11 Tukang Las Org/hari 70,000.00
Tukang listrik Org/hari 70,000.00
12 Pembantu Tukang / Pekerja Org/hari 55,000.00
13 Tukang Ukur Org/hari 55,000.00
14 Penjaga Org/hari 50,000.00
15 Juru Ukur Org/hari 70,000.00
16 Operator Org/hari 125,000.00
17 Operator Pompa Org/hari 75,000.00
18 Mekanik Pompa Org/hari 75,000.00
19 Operator Alat Berat Org/hari 125,000.00
20 Pembantu Operator Alat Berat Org/hari 75,000.00
RENCANA ANGGARAN BIAYA ( RAB )
OE

PEKERJAAN :
TAHUN ANGGARAN : 2018

HARGA JUMLAH JUMLAH


NO URAIAN PEKERJAAN VOLUME SATUAN HARGA PERPOS
Rp Rp Rp

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 1.00 ls Rp 200,000.00 Rp 200,000.00
Sub Jumlah Rp 200,000.00
II PEKERJAAN TANAH DAN URUGAN
1 Galian tanah 39.50 m3 Rp 62,750.00 Rp 2,478,625.00
2 Urugan tanah kembali 11.85 m3 Rp 20,916.67 Rp 247,862.50
3 Urugan pasir 1.38 m3 Rp 160,100.00 Rp 221,338.25
4 Urugan tanah - m3 Rp 220,400.00 Rp -
Sub Jumlah Rp 2,947,825.75
III PEKERJAAN BETON BERTULANG
1 Rabatan 2.95 m3 Rp 945,726.80 Rp 2,789,894.06
4 Sloof 15/30 1.78 m3 Rp 3,899,868.50 Rp 6,932,016.26
5 Kolom 15/15 1.46 m3 Rp 6,289,072.00 Rp 9,197,767.80
7 Balok latai teras 20/30 - m3 Rp 6,340,358.00 Rp -
8 Balok latai 15/15 - m3 Rp 6,340,358.00 Rp -
9 Plaat leufell 5 cm - m3 Rp 7,687,542.00 Rp -
10 Ring balok 15/20 0.89 m3 Rp 6,340,358.00 Rp 5,634,993.17
Sub Jumlah Rp 24,554,671.29
IV PEKERJAAN PONDASI
1 Aanstamping 5.53 m3 Rp 334,290.00 Rp 1,848,623.70
2 Pondasi bt kali 8.89 m3 Rp 686,250.00 Rp 6,099,046.88
Sub Jumlah Rp 7,947,670.58
V PEK. PASANGAN & PLESTERAN
1 Pas. Batu bata tembok 1pc : 4ps m2 Rp 104,232.50 Rp -
2 Plesteran 1pc : 4 ps m2 Rp 51,351.00 Rp -
3 Acian m2 Rp 31,975.00 Rp -
4 Benangan sudut m' Rp 17,201.00 Rp -
5 Pas keramik 40/40 m2 Rp 252,177.50 Rp -
6 Pas batu alur m2 Rp 324,768.00 Rp -
7 Pas. Batu bobos m2 Rp 324,768.00 Rp -
Sub Jumlah Rp -
VI PEKERJAAN ATAP
1 Pasang Kuda-kuda moorplat ky kruing 8/12 m3 Rp 7,566,280.00 Rp -
2 Pasang Kuda-kuda moorplat ky lama m3 Rp 2,425,980.00 Rp -
3 Gording kayu kruing 8/12 m3 Rp 7,566,280.00 Rp -
4 Gording kayu bongkaran m3 Rp 2,425,980.00 Rp -
5 Pas.usuk kruing/reng kamper kayu 5/7, 3/6 m3 Rp 179,056.25 Rp -
6 Pas.usuk lama /reng baru kayu kamper 5/7, 3/5 m2 Rp 109,056.25 Rp -
7 Genteng model karangpilang m2 Rp 170,430.00 Rp -
8 Genteng bubungan m' Rp 102,820.00 Rp -
9 Pasang Lisplank ukuran 30 cm tebal 8 mm m' Rp 79,332.50 Rp -
10 Pas. Plafond rangka hollow gypsumboard m2 Rp 166,425.00 Rp -
11 Pas. List Gypsum m' Rp 32,084.25 Rp -
Sub Jumlah Rp -
VII PEKERJAAN KUSEN
1 Kusen pintu dan jendela kamper 0.47 m3 Rp 17,373,531.25 Rp 8,177,721.16
2 Daun pintu kamper 5.13 m2 Rp 1,029,622.00 Rp 5,276,812.75
3 Daun jendela 1.00 m2 Rp 575,850.00 Rp 575,850.00
4 Kaca 5 mm rayben 3.92 m2 Rp 236,282.50 Rp 927,290.67
5 Pasang 1 buah kunci tanam silinder + pegangan 2.00 unit Rp 432,732.60 Rp 865,465.20
6 Engsel jendela 4.00 bh Rp 40,665.00 Rp 162,660.00
7 Engsel pintu 12.00 bh Rp 66,662.50 Rp 799,950.00
8 Grendel jendela 2.00 bh Rp 26,025.10 Rp 52,050.20
9 Grendel pintu 2.00 bh Rp 41,194.10 Rp 82,388.20
10 Hak angin 2.00 bh Rp 49,282.50 Rp 98,565.00
Sub Jumlah Rp 17,018,753.18
VIII PEKERJAAN CAT
1 Cat tembok baru - m2 Rp 32,805.00 Rp -
2 Cat kayu m2 Rp 48,890.80 Rp -
3 Cat plafond - m2 Rp 29,085.00 Rp -
Sub Jumlah Rp -
IX PEKERJAAN LAMPU
1 Pasang Instalasi listrik + lampu XL 10 watt 13.00 ttk Rp 278,600.00 Rp 3,621,800.00
2 Pasang Instalasi listrik + lampu XL 18 watt 3.00 ttk Rp 295,020.00 Rp 885,060.00
3 Pasang Instalasi listrik + Pas. Stop kontak 8.00 ttk Rp 246,420.00 Rp 1,971,360.00
4 Pasang Instalasi listrik + Pas. Saklar ganda 4.00 ttk Rp 240,365.00 Rp 961,460.00
5 Pasang Instalasi listrik + Pas. Saklar tunggal 6.00 ttk Rp 302,580.00 Rp 1,815,480.00
Sub Jumlah Rp 9,255,160.00
ANALISA HARGA SATUAN BAHAN DAN UPAH TENAGA
BERDASARKAN SNI
TAHUN ANGGARAN 2018

HARGA HSPK
JUMLAH
NO JENIS PEKERJAAN KOEF. SAT. SATUAN 2013
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
2 1 m Pengukuran & Pemasangan Bouwplank 109,096.54
- Patok Kayu 0.012 M3 4,715,370.00 56,584.44
- Paku 0.020 Kg 16,425.00 328.50
- Kayu Papan 3/20 0.007 M3 4,804,800.00 33,633.60
- Upah Pekerjaan
~ Pekerja 0.100 Oh 80,000.00 8,000.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.005 Oh 110,000.00 550.00
II PEKERJAAN TANAH
1 1 m 3 Galian Tanah biasa sedalam 1 meter 62,750.00
- Pekerja 0.750 Oh 80,000.00 60,000.00
- Mandor 0.025 Oh 110,000.00 2,750.00
2 1 m 3 Galian Tanah biasa 2 meter 76,950.00
- Pekerja 0.900 Oh 80,000.00 72,000.00
- Mandor 0.045 Oh 110,000.00 4,950.00

3 1 m 3 Urugan kembali 20,916.67


- Pekerja 0.250 Oh 80,000.00 20,000.00
- Mandor 0.008 Oh 110,000.00 916.67
4 1 m 3 Pemadatan tanah ( per 20 cm ) 45,500.00
- Pekerja 0.500 Oh 80,000.00 40,000.00
- Mandor 0.050 Oh 110,000.00 5,500.00
5 1 m Urugan Pasir Padat
3
160,100.00
- Pasir Urug 1.200 M3 112,500.00 135,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Mandor 0.010 Oh 110,000.00 1,100.00
6 1 m 3 Urugan Sirtu Padat 297,284.00
- Sirtu 1.200 M 3
226,820.00 272,184.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Mandor 0.010 Oh 110,000.00 1,100.00
7 1 m 3 Urugan Sirtu Padat untuk peninggian lantai bangunan 294,934.00
- Sirtu 1.200 M 3
226,820.00 272,184.00
- Upah Pekerjaan
~ Pekerja 0.250 Oh 80,000.00 20,000.00
~ Mandor 0.025 Oh 110,000.00 2,750.00
8 1 m 3 Urugan Tanah Padat 267,716.00
- Tanah urug 1.200 M 3
202,180.00 242,616.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Mandor 0.010 Oh 110,000.00 1,100.00
9 1 m³ Cut & Fill
Gali tanah dengan alat berat ( m3 ) 114,416.75
~ Mandor 0.007 Org 110,000.00 770.00
~ Pekerja tak terampil 0.226 Org 80,000.00 18,080.00
~ Sewa dump truck 0.070 hr 373,800.00 26,166.00
~ Sewa escavator 0.067 jam 150,000.00 10,050.00
10 Pengurugan tanah dengan pemadatan ( m3 )
~ Mandor 0.050 Org 110,000.00 5,500.00
~ Pekerja tak terampil 0.500 Org 80,000.00 40,000.00
~ Sewa alat bantu 0.021 hr 651,800.00 13,850.75
III PEKERJAAN PASANGAN & PLESTERAN
1 1 m 3 Pasang Aanstampeng Batu Kali termasuk urugan pasir (lokal) 334,290.00
- Batu Kali 1.200 M3 150,000.00 180,000.00
- Pasir Urug 0.432 M3 112,500.00 48,600.00
- Upah Pekerjaan
~ Pekerja 0.780 Oh 80,000.00 62,400.00
~ Tukang Batu 0.390 Oh 90,000.00 35,100.00
~ Kepala Tukang 0.039 Oh 100,000.00 3,900.00
~ Mandor 0.039 Oh 110,000.00 4,290.00
2 1 m Pasang Pondasi Batu Kali, 1 Pc : 4 Ps (lumajang)
3
686,250.00
- Batu Kali 1.200 M3 150,000.00 180,000.00
- Semen Portland 163.000 Kg 1,500.00 244,500.00
- Pasir pasang 0.520 M3 112,500.00 58,500.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 80,000.00 120,000.00
~ Tukang Batu 0.750 Oh 90,000.00 67,500.00
~ Kepala Tukang 0.075 Oh 100,000.00 7,500.00
~ Mandor 0.075 Oh 110,000.00 8,250.00
3 1 m Pasang Pondasi Batu Kali, 1 Pc : 5 Ps
3
648,450.00
- Batu Kali 1.200 M3 150,000.00 180,000.00
- Semen Portland 136.000 Kg 1,500.00 204,000.00
- Pasir pasang 0.544 M3 112,500.00 61,200.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 80,000.00 120,000.00
~ Tukang Batu 0.750 Oh 90,000.00 67,500.00
~ Kepala Tukang 0.075 Oh 100,000.00 7,500.00
~ Mandor 0.075 Oh 110,000.00 8,250.00
4 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 3 Ps 110,705.00
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 700.00 49,000.00
- Semen Portland 14.370 Kg 1,500.00 21,555.00
- Pasir Pasang 0.040 M3 112,500.00 4,500.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
5 1 m Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 5 Ps
2
104,232.50
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 700.00 49,000.00
- Semen Portland 9.680 Kg 1,500.00 14,520.00
- Pasir Pasang 0.045 M3 112,500.00 5,062.50
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
6 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 6Ps 102,642.50
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 700.00 49,000.00
- Semen Portland 8.320 Kg 1,500.00 12,480.00
- Pasir Pasang 0.049 M3 112,500.00 5,512.50
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
7 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 8Ps 100,025.00
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 700.00 49,000.00
- Semen Portland 6.500 Kg 1,500.00 9,750.00
- Pasir Pasang 0.050 M3 112,500.00 5,625.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
9 1 m 2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 3 Ps 228,962.50
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 700.00 98,000.00
- Semen Portland 32.950 Kg 1,500.00 49,425.00
- Pasir Pasang 0.091 M3 112,500.00 10,237.50
- Upah Pekerjaan
~ Pekerja 0.600 Oh 80,000.00 48,000.00
~ Tukang Batu 0.200 Oh 90,000.00 18,000.00
~ Kepala Tukang 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.030 Oh 110,000.00 3,300.00
10 1 m 2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 4 Ps 219,587.50
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 700.00 98,000.00
- Semen Portland 26.550 Kg 1,500.00 39,825.00
- Pasir Pasang 0.093 M3 112,500.00 10,462.50
- Upah Pekerjaan
~ Pekerja 0.600 Oh 80,000.00 48,000.00
~ Tukang Batu 0.200 Oh 90,000.00 18,000.00
~ Kepala Tukang 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.030 Oh 110,000.00 3,300.00
11 1 m 2 Pasangan Platelaag ( 1 Lapis ) 46,563.75
- Bata Merah 5 x 11 x 22 cm 35.000 Bh 700.00 24,500.00
- Semen Portland 0.605 kg 1,500.00 907.50
- Pasir Pasang 0.023 M3 112,500.00 2,531.25
- Upah Pekerjaan
~ Pekerja 0.160 Oh 80,000.00 12,800.00
~ Tukang Batu 0.050 Oh 90,000.00 4,500.00
~ Kepala Tukang 0.005 Oh 100,000.00 500.00
~ Mandor 0.008 Oh 110,000.00 825.00
12 1 m Plesteran 1 Pc : 2 Ps, tebal 15 mm
2
58,236.00
- Semen Portland 10.224 Kg 1,500.00 15,336.00
- Pasir Pasang 0.020 M3 112,500.00 2,250.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.150 Oh 90,000.00 13,500.00
~ Kepala Tukang 0.015 Oh 100,000.00 1,500.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
13 1 m 2 Plesteran 1 Pc : 5 Ps, tebal 15 mm 51,351.00
- Semen Portland 5.184 Kg 1,500.00 7,776.00
- Pasir Pasang 0.026 M3 112,500.00 2,925.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.150 Oh 90,000.00 13,500.00
~ Kepala Tukang 0.015 Oh 100,000.00 1,500.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
14 1 m Plesteran 1 Pc : 6 Ps, tebal 15 mm
2
50,311.50
- Semen Portland 4.416 Kg 1,500.00 6,624.00
- Pasir Pasang 0.027 M3 112,500.00 3,037.50
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.150 Oh 90,000.00 13,500.00
~ Kepala Tukang 0.015 Oh 100,000.00 1,500.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
15 1 m Plesteran Ciprat 1 Pc : 2 Ps
2
42,805.00
- Semen Portland 4.320 Kg 1,500.00 6,480.00
- Pasir Pasang 0.006 M3 112,500.00 675.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 80,000.00 24,000.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
18 1 m Acian
2
31,975.00
- Semen Portland 3.250 Kg 1,500.00 4,875.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 80,000.00 16,000.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.010 Oh 110,000.00 1,100.00

19 1 m 1 Benangan 17,201.00
- Semen Portland 1.440 Kg 1,500.00 2,160.00
- Pasir Pasang 0.010 M3 112,500.00 1,125.00
- Upah Pekerjaan
~ Pekerja 0.105 Oh 80,000.00 8,400.00
~ Tukang Batu 0.049 Oh 90,000.00 4,410.00
~ Kepala Tukang 0.005 Oh 100,000.00 490.00
~ Mandor 0.006 Oh 110,000.00 616.00
20 1 m 1 Tali air 10,177.33
- Semen Portland 0.600 Kg 1,500.00 900.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 80,000.00 5,600.00
~ Tukang Batu 0.033 Oh 90,000.00 2,940.00
~ Kepala Tukang 0.003 Oh 100,000.00 326.67
~ Mandor 0.004 Oh 110,000.00 410.67

IV PEKERJAAN LANTAI
1 1 m 2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm 192,137.50
- Keramik 20 x 20 cm 1.060 M2 60,000.00 63,600.00
- Semen Portland 10.400 Kg 1,500.00 15,600.00
- Pasir Pasang 0.045 M3 112,500.00 5,062.50
- Semen Warna 1.500 Kg 40,300.00 60,450.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.018 Oh 110,000.00 1,925.00
2 1 m 2 Pasang Lantai Keramik 40 x 40 cm warna KW I 252,177.50
- Keramik 40 x 40 cm 1.105 M2
120,000.00 132,600.00
- Semen Portland 9.800 Kg 1,500.00 14,700.00
- Pasir Pasang 0.045 M3 112,500.00 5,062.50
- Semen Warna 1.300 Kg 40,300.00 52,390.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.018 Oh 110,000.00 1,925.00
3 1 m 2 Pasang Keramik Dinding 20 x 25 cm KW I 238,100.00
- Keramik 20 x 25 cm 1.060 M2 95,000.00 100,700.00
- Semen Portland 9.300 Kg 1,500.00 13,950.00
- Pasir Pasang 0.018 M3 112,500.00 2,025.00
- Semen Warna 1.500 Kg 40,300.00 60,450.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 80,000.00 36,000.00
~ Tukang Batu 0.225 Oh 90,000.00 20,250.00
~ Kepala Tukang 0.023 Oh 100,000.00 2,250.00
~ Mandor 0.023 Oh 110,000.00 2,475.00
4 1 m Pasang List Keramik Dinding 5 x 20 cm warna KW I
1
44,532.65
- List Keramik 5 x 20 cm 5.300 bh 4,950.00 26,235.00
- Semen Portland 0.570 Kg 1,500.00 855.00
- Pasir Pasang 0.0015 M3 112,500.00 168.75
- Semen Warna 0.013 Kg 40,300.00 523.90
- Upah Pekerjaan
~ Pekerja 0.090 Oh 80,000.00 7,200.00
~ Tukang Batu 0.090 Oh 90,000.00 8,100.00
~ Kepala Tukang 0.009 Oh 100,000.00 900.00
~ Mandor 0.005 Oh 110,000.00 550.00
5 1 m Pasang Batu Alam Candi
2
259,562.50
- Batu Alam Candi 1.100 M2 173,250.00 190,575.00
- Semen Portland 11.750 kg 1,500.00 17,625.00
- Pasir Pasang 0.035 M3 112,500.00 3,937.50
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.0175 Oh 110,000.00 1,925.00

6 1 m 2 Pasang Batu Alam Garis 196,037.50


- Batu Alam Garis 1.100 M2 115,500.00 127,050.00
- Semen Portland 11.750 kg 1,500.00 17,625.00
- Pasir Pasang 0.035 M3 112,500.00 3,937.50
- Upah Pekerjaan
~ Pekerja 0.350 Oh 80,000.00 28,000.00
~ Tukang Batu 0.175 Oh 90,000.00 15,750.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,750.00
~ Mandor 0.0175 Oh 110,000.00 1,925.00
V PEKERJAAN BETON
1 1 M 3 Membuat Beton Mutu f'c = 14,5 Mpa (K 175) 885,748.62
- Semen Portland 326.000 Kg 1,500.00 489,000.00
- Pasir Beton (Lumajang) 760.000 Kg 151.79 115,357.14
- Batu Pecah Mesin 2/3 1029.000 Kg 104.94 107,981.48
- Air 215.000 Ltr 22.00 4,730.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 80,000.00 132,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Kepala Tukang 0.028 Oh 100,000.00 2,800.00
~ Mandor 0.083 Oh 110,000.00 9,130.00
2 1 M 3 Membuat Beton Mutu f'c = 19,3 Mpa (K 225) 945,726.80
- Semen Portland 371.000 Kg 1,500.00 556,500.00
- Pasir Beton (Lumajang) 698.000 Kg 151.79 105,946.43
- Batu Pecah Mesin 2/3 1047.000 Kg 104.94 109,870.37
- Air 215.000 Ltr 22.00 4,730.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 80,000.00 132,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Kepala Tukang 0.028 Oh 100,000.00 2,800.00
~ Mandor 0.083 Oh 110,000.00 9,130.00
3 1 M Membuat Beton Mutu f'c = 31,2 Mpa (K 350)
3
1,097,459.34
- Semen Portland 448.000 Kg 1,500.00 672,000.00
- Pasir Beton (Lumajang) 667.000 Kg 151.79 101,241.07
- Batu Pecah Mesin 2/3 1000.000 Kg 104.94 104,938.27
- Air 215.000 Ltr 22.00 4,730.00
- Upah Pekerjaan
~ Pekerja 2.100 Oh 80,000.00 168,000.00
~ Tukang Batu 0.350 Oh 90,000.00 31,500.00
~ Kepala Tukang 0.035 Oh 100,000.00 3,500.00
~ Mandor 0.105 Oh 110,000.00 11,550.00
4 1 M Membuat Beton Kedap Air dengan Strotox - 100
3
1,130,683.33
- Semen Portland 400.000 Kg 1,500.00 600,000.00
- Pasir Beton (Lumajang) 0.480 M3 212,500.00 102,000.00
- Batu Pecah Mesin 2/3 0.800 M3 141,666.67 113,333.33
- Strotox - 100 1.200 Kg 84,000.00 100,800.00
- Upah Pekerjaan
~ Pekerja 2.100 Oh 80,000.00 168,000.00
~ Tukang Batu 0.350 Oh 90,000.00 31,500.00
~ Kepala Tukang 0.035 Oh 100,000.00 3,500.00
~ Mandor 0.105 Oh 110,000.00 11,550.00
5 1 Kg Pembesian dengan besi polos 15,221.00
- Besi beton (polos) 1.050 Kg 13,000.00 13,650.00
- Kawat beton 0.015 Kg 17,800.00 267.00
- Upah Pekerjaan
~ Pekerja 0.007 Oh 80,000.00 560.00
~ Tukang Besi 0.007 Oh 90,000.00 630.00
~ Kepala Tukang 0.0007 Oh 100,000.00 70.00
~ Mandor 0.0004 Oh 110,000.00 44.00
6 1 m 3 Membuat pondasi beton bertulang (145 kg besi + bekisting) 3,590,121.50
- Kayu Cetakan 0.200 M3 948,750.00 189,750.00
- Paku Biasa 2 ' - 5' 1.500 Kg 16,425.00 24,637.50
- Minyak Bekisting 0.400 Liter 3,960.00 1,584.00
- Besi beton (polos) 145.000 Kg 13,000.00 1,885,000.00
- Kawat beton 2.250 Kg 17,800.00 40,050.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00

- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00


- Upah Pekerjaan
~ Pekerja 5.300 Oh 80,000.00 424,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.300 Oh 90,000.00 117,000.00
~ Tukang Besi 1.050 Oh 90,000.00 94,500.00
~ Kepala Tukang 0.262 Oh 100,000.00 26,200.00
~ Mandor 0.265 Oh 110,000.00 29,150.00
7 1 m 3 Membuat sloof BETON BERTULANG (155 kg besi + bekisting) 3,899,868.50
- Kayu Cetakan 0.270 M3 948,750.00 256,162.50
- Paku Biasa 2 ' - 5' 2.000 Kg 16,425.00 32,850.00
- Minyak Bekisting 0.600 Liter 3,960.00 2,376.00
- Besi beton (polos) 155.000 Kg 13,000.00 2,015,000.00
- Kawat beton 3.000 Kg 17,800.00 53,400.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Upah Pekerjaan
~ Pekerja 5.650 Oh 80,000.00 452,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.560 Oh 90,000.00 140,400.00
~ Tukang Besi 1.400 Oh 90,000.00 126,000.00
~ Kepala Tukang 0.323 Oh 100,000.00 32,300.00
~ Mandor 0.283 Oh 110,000.00 31,130.00
8 1 m 3 Membuat balok beton bertulang (135 kg besi + bekisting) 6,340,358.00
- Kayu Cetakan 0.320 M3 948,750.00 303,600.00
- Paku Biasa 2 ' - 5' 3.200 Kg 16,425.00 52,560.00
- Minyak Bekisting 1.600 Liter 3,960.00 6,336.00
- Besi beton (polos) 135.000 Kg 13,000.00 1,755,000.00
- Kawat beton 3.000 Kg 17,800.00 53,400.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Balok kayu 0.140 M3 4,804,800.00 672,672.00
- Plywood tebal 9 mm 2.800 Lbr 155,000.00 434,000.00
- Dolken Kayu galam 16.000 btg 90,860.00 1,453,760.00
- Upah Pekerjaan
~ Pekerja 6.350 Oh 80,000.00 508,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.650 Oh 90,000.00 148,500.00
~ Tukang Besi 1.400 Oh 90,000.00 126,000.00
~ Kepala Tukang 0.333 Oh 100,000.00 33,300.00
~ Mandor 0.318 Oh 110,000.00 34,980.00
9 1 m Membuat kolom beton bertulang (150 kg besi + bekisting)
3
6,289,072.00
- Kayu Cetakan 0.320 M3 948,750.00 303,600.00
- Paku Biasa 2 ' - 5' 3.200 Kg 16,425.00 52,560.00
- Minyak Bekisting 1.600 Liter 3,960.00 6,336.00
- Besi beton (polos) 150.000 Kg 13,000.00 1,950,000.00
- Kawat beton 3.000 Kg 17,800.00 53,400.00
- Semen Portland 100.000 Kg 1,500.00 150,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Balok kayu 0.120 M3 4,804,800.00 576,576.00
- Plywood tebal 9 mm 2.800 Lbr 155,000.00 434,000.00
- Dolken Kayu galam 20.000 btg 90,860.00 1,817,200.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 80,000.00 424,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.300 Oh 90,000.00 117,000.00
~ Tukang Besi 1.050 Oh 90,000.00 94,500.00
~ Kepala Tukang 0.265 Oh 100,000.00 26,500.00
~ Mandor 0.265 Oh 110,000.00 29,150.00

10 1 m 3 Membuat kolom beton bertulang (300 kg besi + bekisting) 9,447,520.00


- Kayu Cetakan 0.400 M3 948,750.00 379,500.00
- Paku Biasa 2 ' - 5' 4.000 Kg 16,425.00 65,700.00
- Minyak Bekisting 2.000 Liter 3,960.00 7,920.00
- Besi beton (polos) 315.000 Kg 13,000.00 4,095,000.00
- Kawat beton 4.500 Kg 17,800.00 80,100.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Balok kayu 0.150 M3 4,804,800.00 720,720.00
- Plywood tebal 9 mm 3.500 Lbr 155,000.00 542,500.00
- Dolken Kayu galam 20.000 btg 90,860.00 1,817,200.00
- Upah Pekerjaan
~ Pekerja 7.050 Oh 80,000.00 564,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.650 Oh 90,000.00 148,500.00
~ Tukang Besi 2.100 Oh 90,000.00 189,000.00
~ Kepala Tukang 0.403 Oh 100,000.00 40,300.00
~ Mandor 0.353 Oh 110,000.00 38,830.00
11 1 m 3 Membuat kolom beton bertulang (150 kg besi + bekisting) 7,817,542.00
- Kayu Cetakan 0.320 M3 948,750.00 303,600.00
- Paku Biasa 2 ' - 5' 3.200 Kg 16,425.00 52,560.00
- Minyak Bekisting 1.600 Liter 3,960.00 6,336.00
- Besi beton (polos) 157.500 Kg 13,000.00 2,047,500.00
- Kawat beton 2.250 Kg 17,800.00 40,050.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Balok kayu 0.120 M3 4,804,800.00 576,576.00
- Plywood tebal 9 mm 2.800 Lbr 155,000.00 434,000.00
- Dolken Kayu galam 32.000 btg 90,860.00 2,907,520.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 80,000.00 424,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.300 Oh 90,000.00 117,000.00
~ Tukang Besi 1.050 Oh 90,000.00 94,500.00
~ Kepala Tukang 0.265 Oh 100,000.00 26,500.00
~ Mandor 0.265 Oh 110,000.00 29,150.00
12 1 m 3 Membuat tangga beton bertulang (200 kg besi + bekisting) 6,689,378.50
- Kayu Cetakan 0.250 M3 948,750.00 237,187.50
- Paku Biasa 2 ' - 5' 3.000 Kg 16,425.00 49,275.00
- Minyak Bekisting 1.200 Liter 3,960.00 4,752.00
- Besi beton (polos) 200.000 Kg 13,000.00 2,600,000.00
- Kawat beton 3.000 Kg 17,800.00 53,400.00
- Semen Portland 323.000 Kg 1,500.00 484,500.00
- Pasir Beton (Lumajang) 0.520 M3 212,500.00 110,500.00
- Batu Pecah Mesin 2/3 0.780 M3 141,666.67 110,500.00
- Balok kayu 0.105 M3 4,804,800.00 504,504.00
- Plywood tebal 9 mm 2.500 Lbr 155,000.00 387,500.00
- Dolken Kayu galam 14.000 btg 90,860.00 1,272,040.00
- Upah Pekerjaan
~ Pekerja 5.600 Oh 80,000.00 448,000.00
~ Tukang Batu 0.350 Oh 90,000.00 31,500.00
~ Tukang Kayu 2.300 Oh 90,000.00 207,000.00
~ Tukang Besi 1.400 Oh 90,000.00 126,000.00
~ Kepala Tukang 0.405 Oh 100,000.00 40,500.00
~ Mandor 0.202 Oh 110,000.00 22,220.00
13 1 m ' Membuat kolom praktis beton bertulang (11 x 11) cm 79,011.75
- Kayu Cetakan 0.002 M3 948,750.00 1,897.50
- Paku Biasa 2 ' - 5' 0.010 Kg 16,425.00 164.25
- Besi beton (polos) 3.000 Kg 13,000.00 39,000.00
- Kawat beton 0.450 Kg 17,800.00 8,010.00
- Semen Portland 4.000 Kg 1,500.00 6,000.00
- Pasir Beton (Lumajang) 0.006 M3 212,500.00 1,275.00
- Batu Pecah Mesin 2/3 0.009 M3 141,666.67 1,275.00

- Upah Pekerjaan
~ Pekerja 0.180 Oh 80,000.00 14,400.00
~ Tukang Batu 0.020 Oh 90,000.00 1,800.00
~ Tukang Kayu 0.020 Oh 90,000.00 1,800.00
~ Tukang Besi 0.020 Oh 90,000.00 1,800.00
~ Kepala Tukang 0.006 Oh 100,000.00 600.00
~ Mandor 0.009 Oh 110,000.00 990.00
14 1 m ' Membuat ring balok beton bertulang (10 x 15) cm 98,472.25
- Kayu Cetakan 0.003 M 3
948,750.00 2,846.25
- Paku Biasa 2 ' - 5' 0.020 Kg 16,425.00 328.50
- Besi beton (polos) 3.600 Kg 13,000.00 46,800.00
- Kawat beton 0.050 Kg 17,800.00 890.00
- Semen Portland 5.500 Kg 1,500.00 8,250.00
- Pasir Beton (Lumajang) 0.009 M3 212,500.00 1,912.50
- Batu Pecah Mesin 2/3 0.015 M3 141,666.67 2,125.00
- Upah Pekerjaan
~ Pekerja 0.297 Oh 80,000.00 23,760.00
~ Tukang Batu 0.033 Oh 90,000.00 2,970.00
~ Tukang Kayu 0.033 Oh 90,000.00 2,970.00
~ Tukang Besi 0.033 Oh 90,000.00 2,970.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.015 Oh 110,000.00 1,650.00
15 1 m 3 Membuat plat beton bertulang (150 kg besi + bekisting) 7,687,542.00
- Kayu Cetakan 0.320 M3 948,750.00 303,600.00
- Paku Biasa 2 ' - 5' 3.200 Kg 16,425.00 52,560.00
- Minyak Bekisting 1.600 Liter 3,960.00 6,336.00
- Besi beton (polos) 147.500 Kg 13,000.00 1,917,500.00
- Kawat beton 2.250 Kg 17,800.00 40,050.00
- Semen Portland 336.000 Kg 1,500.00 504,000.00
- Pasir Beton (Lumajang) 0.540 M3 212,500.00 114,750.00
- Batu Pecah Mesin 2/3 0.810 M3 141,666.67 114,750.00
- Balok kayu 0.120 M3 4,804,800.00 576,576.00
- Plywood tebal 9 mm 2.800 Lbr 155,000.00 434,000.00
- Dolken Kayu galam 32.000 btg 90,860.00 2,907,520.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 80,000.00 424,000.00
~ Tukang Batu 0.275 Oh 90,000.00 24,750.00
~ Tukang Kayu 1.300 Oh 90,000.00 117,000.00
~ Tukang Besi 1.050 Oh 90,000.00 94,500.00
~ Kepala Tukang 0.265 Oh 100,000.00 26,500.00
~ Mandor 0.265 Oh 110,000.00 29,150.00
VI PEKERJAAN KUSEN PINTU DAN JENDELA
1 1 M3 Pasang Kusen Pintu/jendela Kayu kamper 17,373,531.25
- kayu kamper kwalitas baik 1.200 M3 12,500,000.00 15,000,000.00
- Paku 10cm 1.250 kg 16,425.00 20,531.25
- Lem Kayu 1.000 kg 20,000.00 20,000.00
Upah Pekerjaan 0.00
~ Pekerja 6.000 Oh 80,000.00 480,000.00
~ Tukang Kayu 18.000 Oh 90,000.00 1,620,000.00
~ Kepala Tukang 2.000 Oh 100,000.00 200,000.00
~ Mandor 0.300 Oh 110,000.00 33,000.00
2 1 M2 Pasang pintu dan jendela kaca kayu kamper 575,850.00
- kayu kamper kwalitas baik 0.024 m³ 12,500,000.00 300,000.00
- Lem Kayu 0.300 kg 20,000.00 6,000.00
Upah Pekerjaan
~ Pekerja 0.700 Oh 80,000.00 56,000.00
~ Tukang Kayu 2.100 Oh 90,000.00 189,000.00
~ Kepala Tukang 0.210 Oh 100,000.00 21,000.00
~ Mandor 0.035 Oh 110,000.00 3,850.00
3 1 M2 Pasang Pintu Panil Kayu kamper 1,029,622.00
- Kayu Kamper papan 0.040 m³ 17,353,050.00 694,122.00
Upah Pekerjaan
~ Pekerja 1.000 Oh 80,000.00 80,000.00
~ Tukang Kayu 2.500 Oh 90,000.00 225,000.00
~ Kepala Tukang 0.250 Oh 100,000.00 25,000.00
~ Mandor 0.050 Oh 110,000.00 5,500.00

4 1 m 2 Pasang Pintu Doubel Teakwood, Rangka Kayu Meranti (MC) 504,047.75


- Kayu Meranti, Papan 0.025 M3 4,550,000.00 113,750.00
- Paku Biasa 1/2" - 1 0.030 Kg 16,425.00 492.75
- Lem Kayu 0.500 Lt 18,150.00 9,075.00
- Tekwood 90 x 210 x 3 mm 1.000 Lbr 110,880.00 110,880.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 80,000.00 56,000.00
~ Tukang Kayu 2.100 Oh 90,000.00 189,000.00
~ Kepala Tukang 0.210 Oh 100,000.00 21,000.00
~ Mandor 0.035 Oh 110,000.00 3,850.00
5 1 m Pasang Pintu Doubel Teakwood Lapis Almunium, Rangka Kayu Meranti (MC)
2
669,727.75
- Kayu Meranti, Papan 0.025 M3 4,550,000.00 113,750.00
- Paku Biasa 1/2" - 1 0.030 Kg 16,425.00 492.75
- Lem Kayu 0.500 Lt 18,150.00 9,075.00
- Tekwood 90 x 210 x 4 mm 1.000 Lbr 110,880.00 110,880.00
- Almunium 3' x 7' x 4 mm 0.500 Lbr 215,600.00 107,800.00
- Upah Pekerjaan
~ Pekerja 0.850 Oh 80,000.00 68,000.00
~ Tukang Kayu 2.550 Oh 90,000.00 229,500.00
~ Kepala Tukang 0.255 Oh 100,000.00 25,500.00
~ Mandor 0.043 Oh 110,000.00 4,730.00
VII PEKERJAAN ATAP DAN KUDA-KUDA
6 1 m3 Pasang Konstruksi Kuda-kuda Kayu kruing 7,566,280.00
- Kayu kruing 1.100 M3 5,000,000.00 5,500,000.00
- Besi Strip 15.000 Kg 28,820.00 432,300.00
- Paku Biasa 2" - 5" 5.600 Kg 16,425.00 91,980.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 80,000.00 320,000.00
~ Tukang Kayu 12.000 Oh 90,000.00 1,080,000.00
~ Kepala Tukang 1.200 Oh 100,000.00 120,000.00
~ Mandor 0.200 Oh 110,000.00 22,000.00
7 1 m3 Pasang Konstruksi Kuda-kuda lama Kayu Kelas II, III 2,425,980.00
- Kayu kruing 1.100 M3 -
- Besi Strip 15.000 Kg 52,800.00 792,000.00
- Paku Biasa 2" - 5" 5.600 Kg 16,425.00 91,980.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 80,000.00 320,000.00
~ Tukang Kayu 12.000 Oh 90,000.00 1,080,000.00
~ Kepala Tukang 1.200 Oh 100,000.00 120,000.00
~ Mandor 0.200 Oh 110,000.00 22,000.00
8 Pas.usuk lama/reng kayu kamper 5/7, 3/5 109,056.25
- Usuk kruing 5/7 0.014 M3 5,000,000.00
- Paku Kayu Segala Ukuran 0.250 Kg 16,425.00 4,106.25
- Reng kamper 2/3, 3/5 0.007 M3 12,000,000.00 86,400.00
Upah Pekerjaan - -
~ Pekerja Biasa 0.100 Oh 80,000.00 8,000.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang Kayu 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.005 Oh 110,000.00 550.00
9 Pas.usuk kruing/reng kamper kayu 5/7, 3/5 179,056.25
- Usuk kruing 5/7 0.014 M3 5,000,000.00 70,000.00
- Paku Kayu Segala Ukuran 0.250 M3 16,425.00 4,106.25
- Reng kamper 2/3, 3/5 0.007 Kg 12,000,000.00 86,400.00
Upah Pekerjaan - -
~ Pekerja Biasa 0.100 Oh 80,000.00 8,000.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang Kayu 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.005 Oh 110,000.00 550.00
10 1 m2 Pasangan Genting model kr pilang 170,430.00
~ Pekerja Biasa 0.150 Oh 80,000.00 12,000.00
~ Tukang Kayu 0.075 Oh 90,000.00 6,750.00
~ Kepala Tukang Kayu 0.008 Oh 100,000.00 800.00
~ Mandor 0.008 Oh 110,000.00 880.00
material
~ Genting Jawa / lokal
~ Gt.Lyr model kr.pilang 25.000 m2 6,000.00 150,000.00
~ Genting bambe

11 1 m' Menutup Bubungan genteng kodok dan sejenis Camp. 1PC : 3 Ps 102,820.00
~ P C ( 40 kg ) 0.200 zak 60,000.00 12,000.00
~ Pasir pasang 0.032 M3 112,500.00 3,600.00
~ bubung Gt.model kr.pilang 5.000 bh 7,000.00 35,000.00
Kepala Tukang Kayu -
~ Pekerja Biasa 0.400 Kg 80,000.00 32,000.00
~ Tukang Kayu 0.200 0 90,000.00 18,000.00
~ Kepala Tukang Kayu 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.002 Oh 110,000.00 220.00
12 1 m' Pasang listplang kayu meranti baik/waru tahun kwalitas bagus 3/20 79,332.50

- Papan (3x20) cm 0.011 m3 4,550,000.00 49,140.00


- Paku Kayu Segala Ukuran 0.100 kg 16,425.00 1,642.50
Upah Pekerjaan
~ Pekerja Biasa 0.100 Oh 80,000.00 8,000.00
~ Tukang Kayu 0.200 Oh 90,000.00 18,000.00
~ Kepala Tukang Kayu 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.005 Oh 110,000.00 550.00
VIII PEKERJAAN PLAFOND
1 Rangka plafound Hollow 2x4 + Gypsum board t=9mm 166,425.00
~ Pekerja Biasa 0.180 Oh 80,000.00 14,400.00
~ Tukang Kayu 0.320 Oh 90,000.00 28,800.00
~ Kepala Tukang Kayu 0.032 Oh 100,000.00 3,200.00
~ Mandor 0.009 Oh 110,000.00 990.00
material
~ Gypsum board 120 x 240 cm t=9mm 0.364 Lbr 100,000.00 36,400.00
~ Rangka Hollow 2 x 4 cm t=0,35mm 1.025 Btg 60,000.00 61,500.00
~ Stifenner 3.000 bh 6,000.00 18,000.00
~ Paku keling/sekrup 0.110 Kg 28,500.00 3,135.00
2 1 m' Pasang list plafond gypsum lebar 15 cm 32,084.25
- Gypsum list profil lebar 15 cm 1.050 M' 19,800.00 20,790.00
- Paku 0.010 Kg 16,425.00 164.25
- Upah Pekerjaan
~ Pekerja 0.060 Oh 80,000.00 4,800.00
~ Tukang Kayu 0.060 Oh 90,000.00 5,400.00
~ Kepala Tukang 0.006 Oh 100,000.00 600.00
~ Mandor 0.003 Oh 110,000.00 330.00
IX PEKERJAAN KUNCI
1 1 m 2 Pasang Kaca polos, Tebal 5 mm 236,282.50
- Kaca 1.1000 M2 200,000.00 220,000.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 80,000.00 1,200.00
~ Tukang Kayu 0.150 Oh 90,000.00 13,500.00
~ Kepala Tukang 0.015 Oh 100,000.00 1,500.00
~ Mandor 0.00075 Oh 110,000.00 82.50
2 1 m 2 Pasang Kaca Tempered polos, Tebal 12 mm 1,406,383.00
- Kaca 1.1000 M 2
935,000.00 1,028,500.00
- Aksesories 0.3500 m2 1,028,500.00 359,975.00
- Upah Pekerjaan
~ Pekerja 0.0165 Oh 80,000.00 1,320.00
~ Tukang Kayu 0.165 Oh 90,000.00 14,850.00
~ Kepala Tukang 0.0165 Oh 100,000.00 1,650.00
~ Mandor 0.00080 Oh 110,000.00 88.00
3 Pasang 1 buah kunci tanam silinder + pegangan 432,732.60
- Kunci tanam Silinder 1.000 Bh 177,805.10 177,805.10
- Pegangan pintu (handle) 1.000 Stl 209,000.00 209,000.00
-Upah Pekerjaan
~ Pekerja 0.005 Oh 80,000.00 400.00
~ Tukang Kayu 0.500 Oh 90,000.00 45,000.00
~ Kepala Tukang 0.005 Oh 100,000.00 500.00
~ Mandor 0.00025 Oh 110,000.00 27.50
4 Pasang engsel pintu 66,662.50
- Engsel pintu besar 1.000 Set 50,380.00 50,380.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 80,000.00 1,200.00
~ Tukang Kayu 0.150 Oh 90,000.00 13,500.00

~ Kepala Tukang 0.015 Oh 100,000.00 1,500.00


~ Mandor 0.00075 Oh 110,000.00 82.50
5 Pasang engsel jendela 40,665.00
- Engsel jendela kecil 1.000 Set 29,810.00 29,810.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 80,000.00 800.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.00050 Oh 110,000.00 55.00
6 Pasang Kunci Selot 235,110.00
- Kunci Selot 1.000 bh 213,400.00 213,400.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 80,000.00 1,600.00
~ Tukang Kayu 0.200 Oh 90,000.00 18,000.00
~ Kepala Tukang 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.001 Oh 110,000.00 110.00
7 Pasang hak angin / Sikutan Kuningan 49,282.50
- Hak angin 1.000 Set 33,000.00 33,000.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 80,000.00 1,200.00
~ Tukang Kayu 0.150 Oh 90,000.00 13,500.00
~ Kepala Tukang 0.015 Oh 100,000.00 1,500.00
~ Mandor 0.00075 Oh 110,000.00 82.50
8 Pasang Grendel pintu 41,194.10
- Grendel pintu 1.000 Bh 30,339.10 30,339.10
- Upah Pekerjaan
~ Pekerja 0.010 Oh 80,000.00 800.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.00050 Oh 110,000.00 55.00
9 Pasang Grendel jendela 26,025.10
- Grendel jendela 1.000 Bh 15,170.10 15,170.10
- Upah Pekerjaan
~ Pekerja 0.010 Oh 80,000.00 800.00
~ Tukang Kayu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.00050 Oh 110,000.00 55.00
X PEKERJAAN PENGECATAN
1 1 m 2 Pengecatan bidang kayu lama 25,295.12
- Cat Kayu 0.142 Kg 80,000.00 11,360.00
- Minyak cat 0.019 Lt 29,480.00 560.12
- Upah Pekerjaan
~ Pekerja 0.070 Oh 80,000.00 5,600.00
~ Tukang Cat 0.075 Oh 90,000.00 6,750.00
~ Kepala Tukang 0.0075 Oh 100,000.00 750.00
~ Mandor 0.0025 Oh 110,000.00 275.00
2 1 m 2 Pengecatan bidang kayu baru 48,890.80
- Cat Kayu 0.260 Kg 80,000.00 20,800.00
- Plamir 0.150 Kg 38,610.00 5,791.50
- Cat Meni 0.200 Kg 44,330.00 8,866.00
- Kertas gosok 0.010 Lbr 5,830.00 58.30
- Upah Pekerjaan
~ Pekerja 0.070 Oh 80,000.00 5,600.00
~ Tukang Cat 0.075 Oh 90,000.00 6,750.00
~ Kepala Tukang 0.0075 Oh 100,000.00 750.00
~ Mandor 0.0025 Oh 110,000.00 275.00
3 1 m 2 Pengecatan besi baru 50,854.30
- Cat besi Emco 0.260 Kg 80,000.00 20,800.00
- Cat Meni 0.200 Kg 44,330.00 8,866.00
- Kertas gosok 0.010 Lbr 5,830.00 58.30
- Plamir 0.150 Kg 51,700.00 7,755.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 80,000.00 5,600.00
~ Tukang Cat 0.075 Oh 90,000.00 6,750.00
~ Kepala Tukang 0.0075 Oh 100,000.00 750.00
~ Mandor 0.0025 Oh 110,000.00 275.00

4 1 m 2 Pengecatan besi Finishing baru (Tanpa Cat dasar) 28,713.00


- Cat besi Emco Finishing ( 3 Lapis ) 0.260 Kg 80,000.00 20,800.00
- Upah Pekerjaan
~ Pekerja 0.035 Oh 80,000.00 2,800.00
~ Tukang Cat 0.053 Oh 90,000.00 4,770.00
~ Kepala Tukang 0.0020 Oh 100,000.00 200.00
~ Mandor 0.0013 Oh 110,000.00 143.00
5 1 m Coating Waterproffing
2
122,900.00
- Waterproffing 0.6000 Kg 46,000.00 27,600.00
- Serabut Kasa 1.0000 m2 69,000.00 69,000.00
- Upah Pekerjaan
~ Pekerja 0.1200 Oh 80,000.00 9,600.00
~ Tukang Cat 0.0800 Oh 90,000.00 7,200.00
~ Kepala Tukang 0.0070 Oh 100,000.00 700.00
~ Mandor 0.0800 Oh 110,000.00 8,800.00
6 1 m Pengecatan Dinding Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis cat Penutup)
2
32,805.00
- Plamir 0.100 Kg 23,100.00 2,310.00
- Cat Dasar 0.100 Kg 62,000.00 6,200.00
- Cat Penutup 2x 0.260 Kg 62,000.00 16,120.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 80,000.00 1,600.00
~ Tukang Cat 0.063 Oh 90,000.00 5,670.00
~ Kepala Tukang 0.0063 Oh 100,000.00 630.00
~ Mandor 0.0025 Oh 110,000.00 275.00
7 1 m 2 Coating transparan (doff) untuk batu alam 28,730.00
- Coating 0.2000 Ltr 75,900.00 15,180.00
- Kuas 0.0100 Bh 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 80,000.00 5,600.00
~ Tukang Cat 0.075 Oh 90,000.00 6,750.00
~ Kepala Tukang 0.0075 Oh 100,000.00 750.00
~ Mandor 0.0025 Oh 110,000.00 275.00
8 1 m2 Pengecatan plafon (1 lapis plamir, 1 lapis cat dasar, 29,085.00
- Plamir 0.10 Kg 23,100.00 2,310.00
- Cat dasar 0.12 Kg 62,000.00 7,440.00
- Cat plafound 2x 0.18 Kg 62,000.00 11,160.00
- Upah Pekerjaan
~ Pekerja Biasa 0.02 Oh 80,000.00 1,600.00
~ Tukang Cat 0.06 Oh 90,000.00 5,670.00
~ Kepala Tukang Cat 0.01 Oh 100,000.00 630.00
~ Mandor 0.00 Oh 110,000.00 275.00
XI PEKERJAAN SANITAIR
1 Memasang 1 buah kloset jongkok porselen 605,100.90
- Kloset jongkok porselen 1.000 Bh 212,375.90 212,375.90
- Semen portland 6.000 Kg 1,500.00 9,000.00
- Pasir pasang 0.010 M 3
112,500.00 1,125.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 80,000.00 80,000.00
~ Tukang Batu 1.500 Oh 90,000.00 135,000.00
~ Kepala Tukang 1.500 Oh 100,000.00 150,000.00
~ Mandor 0.160 Oh 110,000.00 17,600.00
2 Memasang 1 buah wastafel 947,773.48
- Wastafel 1.000 Bh 620,579.00 620,579.00
- Perlengkapan 0.120 hrg 620,579.00 74,469.48
- Semen portland 6.000 Kg 1,500.00 9,000.00
-
Pasir pasang 0.010 M3 112,500.00 1,125.00
-
Upah Pekerjaan
~ Pekerja 1.200 Oh 80,000.00 96,000.00
~ Tukang Batu 1.450 Oh 90,000.00 130,500.00
~ Kepala Tukang 0.150 Oh 100,000.00 15,000.00
~ Mandor 0.010 Oh 110,000.00 1,100.00
3 Memasang 1 buah bak cuci stainless 578,150.50
- Bak cuci stainless 1.000 Bh 350,000.00 350,000.00
- Water drain dan accessories 1.000 set 195,585.50 195,585.50
- Upah Pekerjaan
~ Pekerja 0.030 Oh 80,000.00 2,400.00
~ Tukang Batu 0.300 Oh 90,000.00 27,000.00

~ Kepala Tukang 0.030 Oh 100,000.00 3,000.00


~ Mandor 0.0015 Oh 110,000.00 165.00
4 Memasang 1 buah bak mandi fiber glass 1,397,100.00
- Bak fiberglass 1.000 Bh 800,000.00 800,000.00
- Perlengkapan 0.180 hrg 800,000.00 144,000.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 80,000.00 144,000.00
~ Tukang Batu 2.700 Oh 90,000.00 243,000.00
~ Kepala Tukang 0.540 Oh 100,000.00 54,000.00
~ Mandor 0.1100 Oh 110,000.00 12,100.00
5 Pasang pipa galvanis, diameter 2" 229,734.00
- Pipa Galvanis Ø 2 ", tebal 1.8 mm 0.300 ljr 500,000.00 150,000.00
Perlengkapan 0.350 500,000.00 52,500.00
- Upah Pekerjaan
~ Pekerja 0.108 Oh 80,000.00 8,640.00
~ Tukang Batu 0.180 Oh 90,000.00 16,200.00
~ Kepala Tukang 0.018 Oh 100,000.00 1,800.00
~ Mandor 0.005 Oh 110,000.00 594.00
6 Memasang 1 buah kran diameter 3/4" atau 1/2" 60,960.00
- Kran air 1.000 Bh 49,500.00 49,500.00
- Seal Tape 0.025 Bh 4,400.00 110.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 80,000.00 800.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.010 Oh 100,000.00 1,000.00
~ Mandor 0.005 Oh 110,000.00 550.00
7 Memasang 1 m' pipa PVC diameter 0,5" (AW) 17,515.50
- Pipa PVC 1.000 M' 6,250.00 6,250.00
- Perlengkapan 0.350 Hrg 6,250.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.036 Oh 80,000.00 2,880.00
~ Tukang Batu 0.060 Oh 90,000.00 5,400.00
~ Kepala Tukang 0.006 Oh 100,000.00 600.00
~ Mandor 0.0018 Oh 110,000.00 198.00
8 Memasang 1 m' pipa PVC diameter 1/2" (AW) 25,116.00
- Pipa PVC 1.000 M' 11,880.00 11,880.00
- Perlengkapan 0.350 Hrg 11,880.00 4,158.00
- Upah Pekerjaan
~ Pekerja 0.036 Oh 80,000.00 2,880.00
~ Tukang Batu 0.060 Oh 90,000.00 5,400.00
~ Kepala Tukang 0.006 Oh 100,000.00 600.00
~ Mandor 0.0018 Oh 110,000.00 198.00
9 Memasang 1 m' pipa PVC diameter 2" (AW) 43,992.00
- Pipa PVC 1.000 M' 22,500.00 22,500.00
- Perlengkapan 0.350 Hrg 22,500.00 7,875.00
- Upah Pekerjaan
~ Pekerja 0.054 Oh 80,000.00 4,320.00
~ Tukang Batu 0.090 Oh 90,000.00 8,100.00
~ Kepala Tukang 0.0090 Oh 100,000.00 900.00
~ Mandor 0.0027 Oh 110,000.00 297.00
10 Memasang 1 m' pipa PVC diameter 3" (AW) 61,293.25
- Pipa PVC 1.000 M' 30,268.33 30,268.33
- Perlengkapan 0.350 Hrg 30,268.33 10,593.92
- Upah Pekerjaan
~ Pekerja 0.081 Oh 80,000.00 6,480.00
~ Tukang Batu 0.135 Oh 90,000.00 12,150.00
~ Kepala Tukang 0.0135 Oh 100,000.00 1,350.00
~ Mandor 0.0041 Oh 110,000.00 451.00
11 Memasang 1 m' pipa PVC diameter 4" (AW) 77,554.00
- Pipa PVC 1.000 M' 42,313.33 42,313.33
- Perlengkapan 0.350 Hrg 42,313.33 14,809.67
- Upah Pekerjaan
~ Pekerja 0.081 Oh 80,000.00 6,480.00
~ Tukang Batu 0.135 Oh 90,000.00 12,150.00
~ Kepala Tukang 0.0135 Oh 100,000.00 1,350.00
~ Mandor 0.0041 Oh 110,000.00 451.00

12 Memasang 1 bh Floor drain


- Floor drain 1.000 Bh 40,150.00 40,150.00 51,500.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 80,000.00 800.00
~ Tukang Batu 0.100 Oh 90,000.00 9,000.00
~ Kepala Tukang 0.0100 Oh 100,000.00 1,000.00
~ Mandor 0.0050 Oh 110,000.00 550.00
XII PEKERJAAN PAVING
1 1 m2 Pasang Paving K 300 abu-abu 151,100.00
- Paving stone K 300 abu-abu 1.000 M2 88,000.00 88,000.00
- Pasir Garuk 0.100 M3 176,000.00 17,600.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 80,000.00 40,000.00
~ Mandor 0.050 Oh 110,000.00 5,500.00
2 1 m1 Pasang Kanstin 15,25,40 87,023.75
- Kanstin K175 2.500 Bh 22,110.00 55,275.00
- Semen Portland 0.154 kg 1,500.00 231.00
- Pasir Pasang 0.0387 M3 112,500.00 4,353.75
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 80,000.00 18,656.00
~ Tukang Batu 0.06 Oh 90,000.00 5,400.00
~ Kepala Tukang 0.006 Oh 100,000.00 600.00
~ Mandor 0.0228 Oh 110,000.00 2,508.00
3 1 m1 Pasang Paving Pengunci (Uskup) 26,842.00
- Paving Pengunci K300 3.200 Bh 5,060.00 16,192.00
- Pasir Garuk 0.020 M3 176,000.00 3,520.00
- Upah Pekerjaan
~ Pekerja 0.06 Oh 80,000.00 4,800.00
~ Tukang Batu 0.02 Oh 90,000.00 1,800.00
~ Kepala Tukang 0.002 Oh 100,000.00 200.00
~ Mandor 0.003 Oh 110,000.00 330.00
XIII PEKERJAAN INSTALASI LISTRIK
1 1 ttk Pasang Instalasi listrik + lampu XL 10 watt 278,600.00
Bahan
~ Lampu XL 10 watt 1.000 bh 50,000.00 50,000.00
~ Kabel NYA 2x2,5mm 10.000 m' 6,050.00 60,500.00
~ Isolator 15.000 bh 1,870.00 28,050.00
~ T doos PVC 2.000 bh 6,820.00 13,640.00
~ Pipa 5/8" 1.000 ljr 17,710.00 17,710.00
~ Stater lampu TL 1.000 bh 8,580.00 8,580.00
~ last doof 6.000 bh 770.00 4,620.00
Upah Pekerjaan
~ Pekerja 0.500 Oh 80,000.00 40,000.00
~ Tukang Listrik 0.500 Oh 90,000.00 45,000.00
~ Kepala Tukang listrik 0.0500 Oh 100,000.00 5,000.00
~ Mandor 0.0500 Oh 110,000.00 5,500.00
2 1 ttk Pasang Instalasi listrik + lampu XL 18 Watt 295,020.00
Bahan
~ Lampu XL 18 watt 1.000 bh 75,000.00 75,000.00
~ Kabel NYA2x 2,5mm 10.000 m' 6,050.00 60,500.00
~ Isolator 15.000 bh 1,870.00 28,050.00
~ T doos PVC 2.000 bh 6,820.00 13,640.00
~ Pipa 5/8" 1.000 ljr 17,710.00 17,710.00
~ last doof 6.000 bh 770.00 4,620.00
Upah Pekerjaan
~ Pekerja 0.500 Oh 80,000.00 40,000.00
~ Tukang Listrik 0.500 Oh 90,000.00 45,000.00
~ Kepala Tukang listrik 0.0500 Oh 100,000.00 5,000.00
~ Mandor 0.0500 Oh 110,000.00 5,500.00
3 1 ttk Pasang Instalasi listrik + saklar tunggal 302,580.00
Bahan 0.00
~ saklar tunggal 1.000 bh 50,000.00 50,000.00
~ Kabel NYA 2x2,5mm 10.000 m' 6,050.00 60,500.00
~ Isolator 15.000 bh 1,870.00 28,050.00
~ T doos PVC 2.000 bh 6,820.00 13,640.00
~ Pipa 5/8" 1.000 ljr 17,710.00 17,710.00
~ Fitting plafond 1.000 bh 32,560.00 32,560.00

~ last doof 6.000 bh 770.00 4,620.00


Upah Pekerjaan
~ Pekerja 0.500 Oh 80,000.00 40,000.00
~ Tukang Listrik 0.500 Oh 90,000.00 45,000.00
~ Kepala Tukang listrik 0.0500 Oh 100,000.00 5,000.00
~ Mandor 0.0500 Oh 110,000.00 5,500.00
4 1 ttk Pasang Instalasi listrik + lampu DL 18 Watt 340,745.00
Bahan
~ Lampu XL 18 watt 1.000 bh 63,800.00 63,800.00
~ Kabel NYA 2x2,5mm 10.000 m' 6,050.00 60,500.00
~ Isolator 15.000 bh 1,870.00 28,050.00
~ T doos PVC 2.000 bh 6,820.00 13,640.00
~ Pipa 5/8" 1.000 ljr 17,710.00 17,710.00
~ Kap Down Light Kecil 1.000 bh 56,925.00 56,925.00
~ last doof 6.000 bh 770.00 4,620.00
Upah Pekerjaan
~ Pekerja 0.500 Oh 80,000.00 40,000.00
~ Tukang Listrik 0.500 Oh 90,000.00 45,000.00
~ Kepala Tukang listrik 0.0500 Oh 100,000.00 5,000.00
~ Mandor 0.0500 Oh 110,000.00 5,500.00
5 1 ttk Pasang Stop Kontak 246,420.00
Bahan 0.00
~ Stop Kontak 1.000 bh 48,180.00 48,180.00
~ Kabel NYA 2x 2,5mm 10.000 m' 6,050.00 60,500.00
~ T doos PVC 1.000 bh 6,820.00 6,820.00
~ Pipa 5/8" 2.000 ljr 17,710.00 35,420.00
Upah Pekerjaan 0.00
~ Pekerja 0.500 Oh 80,000.00 40,000.00
~ Tukang Listrik 0.500 Oh 90,000.00 45,000.00
~ Kepala Tukang listrik 0.0500 Oh 100,000.00 5,000.00
~ Mandor 0.0500 Oh 110,000.00 5,500.00
6 1 unit Pasang Seklar ganda 240,365.00
Bahan 0.00
~ Sekering Seklar ganda 1.000 Unit 70,000.00 70,000.00
~ Kabel NYA 2 x 2,5mm 8.000 m' 6,050.00 48,400.00
~ Pipa 5/8" 2.000 ljr 17,710.00 35,420.00
Upah Pekerjaan
~ Pekerja 0.950 Oh 80,000.00 76,000.00
~ Tukang Listrik 0.095 Oh 90,000.00 8,550.00
~ Kepala Tukang listrik 0.0095 Oh 100,000.00 950.00
~ Mandor 0.0095 Oh 110,000.00 1,045.00
XIV PEKERJAAN PAPAN NAMA
2 1 unit Papan Nama ukuran 80x120 445,235.98
- Kayu 5/7 0.019 M3 4,550,000.00 86,950.50
- Multiplek 9 mm 0.350 Lbr 155,000.00 54,250.00
- Tulisan 1.000 Unit 100,000.00 100,000.00
- Paku 0.100 Kg 16,425.00 1,642.50
- Rabat Beton 20x20x40 0.032 M3 885,748.62 28,343.96
- Cat Kayu Baru 2.976 M2 48,890.80 145,499.02
- Upah Pekerjaan
~ Pekerja 0.100 Oh 80,000.00 8,000.00
~ Tukang Kayu 0.200 Oh 90,000.00 18,000.00
~ Kepala Tukang 0.020 Oh 100,000.00 2,000.00
~ Mandor 0.005 Oh 110,000.00 550.00

( 1 M2 Pasang Pintu Panil Kayu )

( 1 m2 Pasangan Genting kodok dan sejenis )


- Gt.Lyr model kr.pilang 26 bh 3,500.00 91,000.00

- Upah Pekerjaan
~ Pekerja 0.000 Oh 80,000.00 -
~ Tukang Batu 0.000 Oh 90,000.00 -
~ Kepala Tukang 0.000 Oh 100,000.00 -
~ Mandor 0.000 Oh 110,000.00 -
A. TENAGA

1 Pekerja Biasa Org/hr 0.1000 80,000.00


2 Tukang Batu Org/hr 0.1000 110,000.00
3 Kepala Tukang Batu Org/hr 0.0100 100,000.00
4 Mandor Org/hr 0.0050 90,000.00

JUMLAH HARGA TENAGA

B BAHAN

1 Kawat Nyamuk m² 1.1000 52,250.00


2 Pengelasan dengan las listrik cm 11.1100 5,000.00
3 Besi Strip / Plat Plendes kg 1.7160 10,400.00

1 Pekerja Biasa Org/hr 4.00 80,000.00


2 Tukang Kayu Org/hr 12.00 90,000.00
3 Kepala Tukang Kayu Org/hr 1.20 100,000.00
4 Mandor Org/hr 0.20 110,000.00

JUMLAH HARGA TENAGA

B BAHAN

1 Balok m³ 1.10 4,550,000.00


2 Besi Strip / Plat Plendes kg 15.00
3 Paku Kayu Segala Ukuran kg 5.60 23,000.00

m' Kawat Harmonika @.Rp. 1.1000 52,250 57,475


kg Paku 1/2" - 1" @.Rp. 0.0200 19,400 388
m3Kayu meranti Papan @.Rp. 0.0018 6,795,700 12,232

Tenaga -
hariMandor @.Rp. 0.0005 110,000 55
hariKepala Tukang @.Rp. 0.0100 100,000 1,000
hariTukang Kayu @.Rp. 0.1000 90,000 9,000
hariPekerja @.Rp. 0.1000 80,000 8,000

Jumlah

6.12 ( 1 m2 Pas. Atap Asbes Gelombang kecil )


Asbes Gelombang kecil m2 1.1000 56,000 61,600
Paku hak kait bh 6.0000 3,200 19,200

Mandor hari 0.0070 110,000 770


Kepala Tukang hari 0.0070 100,000 700
Tukang Kayu hari 0.0670 90,000 6,030
Pekerja hari 0.1400 80,000 11,200

Jumlah

6.17 ( 1 m2 Pas. Atap Asbes Gelombang Besar )


m2Asbes Gelombang besar @.Rp. - 1.1000 59,312 65,243
bh Paku hak kait @.Rp. - 6.0000 3,200 19,200
-
hariMandor @.Rp. - 0.0070 110,000 770
hariKepala Tukang @.Rp. - 0.0070 100,000 700
hariTukang Kayu @.Rp. - 0.0670 90,000 6,030
hariPekerja @.Rp. - 0.1400 80,000 11,200

Jumlah

m' Bubungan Asbes @.Rp. 1.1000 69,100 76,010


bh Paku skrup @.Rp. 6.0000 3,200 19,200

hariMandor @.Rp. 0.0040 110,000 440


hariKepala Tukang @.Rp. 0.0130 100,000 1,300
hariTukang Kayu @.Rp. 0.1250 90,000 11,250
hariPekerja @.Rp. 0.0840 80,000 6,720

Jumlah
( 1 m' Menutup Bubungan Asbes gel.kecil ) 6.24
m' Bubungan Asbes @.Rp. 1.1000 68,454 75,299
bh Paku skrup @.Rp. 4.0000 3,200 12,800

hariMandor @.Rp. 0.0040 110,000 440


hariKepala Tukang @.Rp. 0.0130 100,000 1,300
hariTukang Kayu @.Rp. 0.1250 90,000 11,250
hariPekerja @.Rp. 0.0840 80,000 6,720

Jumlah

1 m 3 Pemadatan tanah ( per 20 cm ) 45,500.00


- Pekerja 0.500 Oh 80,000.00 40,000.00
- Mandor 0.050 Oh 110,000.00 5,500.00

1 m 3 Urugan Tanah Padat -


- Tanah urug 1.200 M3 0.00 -
- Upah Pekerjaan
~ Pekerja 0.300 Oh - -
~ Mandor 0.010 Oh - -

1 m3 Pasang Konstruksi Kuda-kuda Kayu Kelas II, III 7,048,640.00


- Kayu meranti 1.100 M3
4,550,000.00 5,005,000.00
- Besi Strip 15.00 Kg 26,200.00 393,000.00
- Paku Biasa 2" - 5" 5.60 Kg 19,400.00 108,640.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 80,000.00 320,000.00
~ Tukang Kayu 12.000 Oh 90,000.00 1,080,000.00
~ Kepala Tukang 1.200 Oh 100,000.00 120,000.00
~ Mandor 0.200 Oh 110,000.00 22,000.00

JENIS PEKERJAAN
SATUAN PEMBAYARAN
PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1 Pekerja Biasa Org/hr 0.38 80,000.00


2 Tukang Batu Org/hr 0.19 90,000.00
3 Kepala Tukang Batu Org/hr 0.019 100,000.00
4 Mandor Org/hr 0.019 110,000.00

JUMLAH HARGA TENAGA

B BAHAN

1 Buis Beton Ø 0.50 m m¹ 1.1 #REF!


2 Bata Merah bh 123.75 700.00
3 Portland Cement (PC) kg 5.15 1,500.00
4 Pasir Pasang m³ 0.0305 112,500.00
5 Pasir Urug m³ 0.0345 202,180.00

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

KODE ANALISA
JENIS PEKERJAAN
SATUAN PEMBAYARAN

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1 Pekerja Biasa Org/hr 0.1080 80,000.00


2 Tukang Batu Org/hr 0.1800 90,000.00
3 Kepala Tukang Batu Org/hr 0.0180 100,000.00
4 Mandor Org/hr 0.0054 110,000.00

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa Galvanis Ø 3 ", tebal 1.8 Ljr 0.3000 800,000.00


2 Perlengkapan 0.3500 280,000.00

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


KODE ANALISA
JENIS PEKERJAAN
SATUAN PEMBAYARAN

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1 Pekerja Biasa Org/hr 0.1080 80,000.00


2 Tukang Batu Org/hr 0.1800 90,000.00
3 Kepala Tukang Batu Org/hr 0.0180 100,000.00
4 Mandor Org/hr 0.0054 110,000.00

JUMLAH HARGA TENAGA

B BAHAN

1 Pipa Galvanis Ø 3 ", tebal 1.8 Ljr 0.3000 550,000.00


2 Perlengkapan 0.3500 192,500.00

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

Memasang 1 m' pipa Galvanis diameter 1 1/2"


- Pipa Galvanis medium 1.000 1.000 M' 64,700.00 64,700.00
- Perlengkapan 0.350 0.350 Hrg 64,700.00 22,645.00
- Upah Pekerjaan 0.00
Pekerja 0.108 0.108 Oh 80,000.00 8,640.00
Tukang Batu 0.180 0.180 Oh 90,000.00 16,200.00
Kepala Tukang 0.0180 0.0180 Oh 100,000.00 1,800.00
Mandor 0.0054 0.0054 Oh 110,000.00 594.00

Memasang 1 m' pipa Galvanis diameter 3"


- Pipa Galvanis tebal 1 1 M' 142,791.67 142,791.67
- Perlengkapan 0.35 0.35 Hrg 142,791.67 49,977.08
- Upah Pekerjaan 0.00
Pekerja 0.108 0.108 Oh 80,000.00 8,640.00
Tukang Batu 0.18 0.18 Oh 90,000.00 16,200.00
Kepala Tukang 0.018 0.018 Oh 100,000.00 1,800.00
Mandor 0.0054 0.0054 Oh 110,000.00 594.00

JENIS :
SATUAN :

PERKIRAAN HARGA
NO.
KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1 Pekerja Biasa Org/hr 4.0000 80,000.00 320,000.00


2 Tukang Kayu Org/hr 12.0000 90,000.00 1,080,000.00
3 Kepala Tukang Kayu Org/hr 1.2000 100,000.00 120,000.00
4 Mandor Org/hr 0.2000 110,000.00 22,000.00

JUMLAH HARGA TENAGA 1,542,000.00

B BAHAN

1 Balok m³ 1.1 4,550,000.0000 5,005,000.00


2 Besi Strip / Plat Plendes kg 15 28,820.0000 432,300.00
3 Paku Kayu Segala Ukuran kg 5.6 16,425.0000 91,980.00

JUMLAH HARGA BAHAN 5,529,280.00

7,071,280.00
1 m 3 Pasang Kusen Pintu dan Jendela Kayu Kelas Awet III 7,811,681.25
- Kayu Meranti balok 1.200 M3 4,550,000.00 5,460,000.00
- Paku 10cm 1.250 kg 16,425.00 20,531.25
- Lem Kayu 1.000 kg 18,150.00 18,150.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 80,000.00 480,000.00
~ Tukang Kayu 18.000 Oh 90,000.00 1,620,000.00
~ Kepala Tukang 1.800 Oh 100,000.00 180,000.00
~ Mandor 0.300 Oh 110,000.00 33,000.00

6.7 ( 1 M2 Pasang Pintu Panil Kayu )

0.05 harMandor @.Rp. ### Rp. 5,500.00


0.25 harKepala Tukang @.Rp. ### Rp. 25,000.00
2.5 harTukang Kayu @.Rp. ### Rp. 225,000.00
1 harPekerja @.Rp. ### Rp. 80,000.00

0.04 m3 Kayu Kamper papan @.Rp. ### Rp. 694,122.00

1 M2 Pasang Pintu panil kayu kamper Jumlah

6.10 ( 1 M2 Pasang Daun Jendela Kaca Rangka Kayu Kamper )

1 M2 Pasang Jendela panil Kayu Kamper


###hariMandor @.Rp. 110,000 Rp. 4,400
###hariKepala Tukang @.Rp. 100,000 Rp. 20,000
###hariTukang Kayu @.Rp. 90,000 Rp. 180,000
###hariPekerja @.Rp. 80,000 Rp. 64,000

### m3Kayu Kamper papan @.Rp. 17,353,050 Rp. 607,357

###m2Jendela panil kayu kamper @.Rp. 875,757 Rp. 350,303


###m2Kaca 5 mm polos @.Rp. 60,500 Rp. 66,550

1 M2 Pasang Jendela Kaca Slimar Kayu Kamper Jumlah

6.2 ( 1 m2 Pasangan Genting kodok dan sejenis )

###hariMandor @.Rp. 110,000 Rp. 880


###hariKepala Tukang @.Rp. 100,000 Rp. 800
###hariTukang Kayu @.Rp. 90,000 Rp. 6,750
###hariPekerja @.Rp. 80,000 Rp. 12,000

###m2Genting Jawa / lokal = Rp. - Rp. 20,430


###m2Gt.Lyr model kr.pilang = Rp. 83,200 Rp. 20,430
###m2Genting bambe = Rp. - Rp. 20,430

6.18 I m' Pasang Talang Datar, seng BJLS 28


1 m' Seng Plat BJLS 28 l=90 cm @.Rp. 40,000 Rp. 40,000
### kg Paku 1/2" - 1" @.Rp. 16,425 Rp. 246
###m3Kayu papan kamper 2 cm @.Rp. 17,353,050 Rp. 166,589
### kg Meni besi / Flincote @.Rp. 47,300 Rp. 11,825

Tenaga
###hariMandor @.Rp. 110,000 Rp. 138
###hariKepala Tukang @.Rp. 100,000 Rp. 2,500
###hariTukang Kayu @.Rp. 90,000 Rp. 36,000
###hariPekerja @.Rp. 80,000 Rp. 12,000

Jumlah

6.47 ( 1 M2 Pasangan Lantai Keramik)


Bahan Spesi+Penutup :
###zakP C ( 40 kg ) @.Rp. 60,000 Rp. 17,070
### kg Semen warna @.Rp. 19,140 Rp. 28,710
###m3Pasir pasang @.Rp. 112,500 Rp. 4,725
Jumlah Spesi
Upah :
###hariMandor @.Rp. 110,000 Rp. 3,300
###hariKepala Tukang @.Rp. 100,000 Rp. 3,500
###hariTukang Batu @.Rp. 90,000 Rp. 31,500
###hariPekerja @.Rp. 80,000 Rp. 49,600
Jumlah upah
Jumlah Upah + Bahan

###m2Keramik 20/20 polos KM dop = Rp. - Rp. 138,405


###m2Keramik 30/30 putih motif = Rp. - Rp. 138,405
###m2Keramik 40/40 putihmotif = Rp. - Rp. 138,405
(HERCULES) KW I
###m2Keramik 40/40 gelap/tua = Rp. 120,000 Rp. 138,405
(HERCULES) KW I

6.32 ( 1 M2 Pas. Usuk/reng genteng kodok)

###hariMandor @.Rp. 110,000 Rp. 550


###hariKepala Tukang @.Rp. 100,000 Rp. 1,000
###hariTukang Kayu @.Rp. 90,000 Rp. 9,000
###hariPekerja @.Rp. 80,000 Rp. 8,000

###m3Kayu Meranti usuk 5/7 @.Rp. 4,550,000 Rp. 31,200


###m3Kayu Meranti 2/3 @.Rp. 4,550,000 Rp. 23,400
### kg Paku balok / papan @.Rp. 16,425 Rp. 2,464

Jumlah

6.5 ( 1 m' Menutup Bubungan genteng kodok dan sejenis Camp. 1PC : 3 Ps )

###zakP C ( 40 kg ) @.Rp. 60,000 Rp. 12,000


###m3Pasir pasang @.Rp. 112,500 Rp. 3,600

###hariMandor @.Rp. 110,000 Rp. 220


###hariKepala Tukang @.Rp. 100,000 Rp. 2,000
###hariTukang Batu @.Rp. 90,000 Rp. 18,000
###hariPekerja @.Rp. 80,000 Rp. 32,000

Jumlah

### m' Gt.model kr.pilang = Rp. 260,000 Rp. 67,820


### m' Genting bambe = Rp. - Rp. 67,820

6.4 ( 1 m2 Pasang langit2 asbes (1,00x1,00)

###hariMandor @.Rp. 110,000 Rp. 165


###hariKepala Tukang @.Rp. 100,000 Rp. 700
###hariTukang Kayu @.Rp. 90,000 Rp. 6,300
###hariPekerja @.Rp. 80,000 Rp. 2,400

###m2Eternit cap kerang @.Rp. - Rp. -


### kg Paku eternit @.Rp. - Rp. -

KODE AN:
JENIS P :
SATUAN :

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1 Pekerja Biasa Org/hr 0.1 80,000


2 Tukang Kayu Org/hr 0.1 90,000
3 Kepala Tukang Kayu Org/hr 0.01 100,000
4 Mandor Org/hr 0.005 110,000

JUMLAH HARGA TENAGA

B BAHAN

1 Usuk 5/7 m³ 0.014 4,550,000.00


2 Paku Kayu Segala Ukuran kg 0.25 16,425.00
3 Reng 2/3, 3/5 m³ 0.0072 4,550,000.00

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)

6.2 ( 1 M3 Pasang Kusen Pintu/jendela Kayu )


1 m3 Pasang Kusen Pintu dan Jendela Kayu Kelas Awet III 9448406 Rp.
-Kayu mer 1.2 6083000 7E+06 Rp.
-Paku 10 1.25 17500 21875 Rp.
-Lem Kay 1 14931 14931 Rp.
-Upah Pekerjaan
~ Pekerj 6 65000 4E+05
~ Tukan 18 85000 2E+06 Rp.
~ Kepal 1.8 90000 2E+05
~ Mandor 0 ### ###
### haMandor @.Rp. 110,000 Rp. 33,000
### haKepala Tukang @.Rp. 100,000 Rp. 200,000
### haTukang Kayu @.Rp. 90,000 Rp. 1,620,000
### haPekerja @.Rp. 80,000 Rp. 480,000

###M3Kayu Kamper balok @.Rp. 12,500,000 Rp. 15,000,000

Jumlah

0.05 harMandor @.Rp. 0.00 Rp. 0.00


0.25 harKepala Tukang @.Rp. 0.00 Rp. 0.00
2.5 harTukang Kayu @.Rp. 0.00 Rp. 0.00
1 harPekerja @.Rp. 0.00 Rp. 0.00

0.04 m3 Kayu Kamper papan @.Rp. #REF! Rp. #REF!

1 M2 Pasang Pintu panil kayu kamper Jumlah

JENIS PE :
SATUAN :

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1 PekL17 Org/hr 0.18 70000


2 Tu L08 Org/hr 0.32 85000
3 KepL03 Org/hr 0.032 95000
4 Ma L01 Org/hr 0.009 100000

JUMLAH HARGA TENAGA

B BAHAN

1 GypM079 Lbr 0.364 68000


2 RanM140 Btg 1.025 29000
3 Sti M206 bh 3 6000
4 Paku keling/sekrup Kg 0.11 28500

JUMLAH HARGA BAHAN

C PERALATAN

JUMLAH HARGA PERALATAN

D JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C)


Besi Hollow partisi 4 0.023 3.5 M'
Besi Hollow partisi 2 0.023 2.5 M'
Accesories 0.15 0.15 Kg
Upah Pekerjaan
~ Pekerja 0.2 0.1 Oh
~ Tukang 0.3 0.05 Oh
~ Kepala 0.03 0.005 Oh
~ Mandor 0.01 0.005 Oh

Calsium Board tebal 0.364 0.364 lbr


Paku 0.11 0.11 Kg
Upah Pekerjaan
~ Pekerja 0.1 0.1 Oh
~ Tukang 0.05 0.05 Oh
~ Kepala 0.005 0.005 Oh
~ Mandor 0.005 0.005 Oh

6.5 ( 1 m' Menutup Bubungan genteng kodok dan sejenis Camp. 1PC : 3 Ps )

0.2 zak P C ( 40 kg ) @.Rp.


0.032 m3 Pasir pasang @.Rp.

0.002 hari Mandor @.Rp.


0.02 hari Kepala Tukang @.Rp.
0.2 hari Tukang Batu @.Rp.
0.4 hari Pekerja @.Rp.

1.0000 m' Gt.model kr.pil 0 = Rp.


1 m' Gt.model kr.pilang #REF! = Rp.
1 m' Genting bambe #REF! = Rp.
0.045
1
22.2222222222
0.95 84.4444444
0.65 112.111111
72.8722222
157.316667
L17
L10
L05
0

365477
8,000.00
11,000.00
1,000.00
450.00

20,450.00

57,475.00
55,550.00
17,846.40

320000 1 Pekerja Biasa Org/hr 4 80000


1080000 2 Tukang Kayu Org/hr 12 90000
120000 3 Kepala Tukang Kayu Org/hr 1.2 100000
22000 4 Mandor Org/hr 0.2 110000

JUMLAH HARGA TENAGA


1,672,871.40
B BAHAN

5005000 1 Balok m³ 1.1


2 Besi Strip / Plat Plende kg 15
128800 3 Paku Kayu Segala Ukukg 5.6 23000

8348671.4

Rp. 70095.26

Rp. 18055
Rp. 88150.26
Rp. 80800

Rp. 18700
Rp. 99500

Rp. 84443.3862433863

Rp. 18700
Rp. 103143.386243386

Rp. 95210

Rp. 19710
Rp. 114920

Rp. 88099.4

Rp. 19710
Rp. 107809.4
JUMLAH
HARGA
(Rp.)

30400
17100
1900
2090

#REF!
86625
7725
3431.25
6975.21

#REF!

232389.16

JUMLAH
HARGA
(Rp.)

8,640.00
16,200.00
1,800.00
594.00

27,234.00

240,000.00
98,000.00

338,000.00

365,234.00
JUMLAH
HARGA
(Rp.)

8,640.00
16,200.00
1,800.00
594.00

27,234.00

165,000.00
67,375.00

232,375.00

259,609.00

114,579.00

220,002.75
856,750.00

JUMLAH
HARGA
(Rp.)
Rp. 335500

Rp. 694122
Rp. 1,029,622

Rp. 268,400

Rp. 607,357
Rp. 875,757

Rp. 416,853
Rp. 20,430

= Rp. 20,430
= Rp. 103,630
= Rp. 20,430

Rp. 218,661

Rp. 50,638
Rp. 269,298

Rp. 50,505

Rp. 87,900
Rp. 138,405

= Rp. 138,405
= Rp. 138,405
= Rp. 138,405

= Rp. 258,405

Rp. 18,550

Rp. 57,064
Rp. 75,614

Rp. 15,600
Rp. 52,220
Rp. 67,820

= Rp. 327,820
= Rp.

Rp. 9,565

Rp. -
Rp. 9,565

JUMLAH
HARGA
(Rp.)

8000
9000
1000
550

18550

63700
4106.25
32760

100566.25

119,116

31500
190000
1620000
435000
Rp. 2276500

19878540
Rp. 19878540
22155040
Rp. 2,333,000

Rp. 15,000,000
Rp. 17,333,000

Rp. 0

Rp. #REF!
Rp. #REF!

JUMLAH
HARGA
(Rp.)

12600
27200
3040
900

43740

24752
29725
18000
3135

75612

119352
137920
22500 78750
16600 41500
25300 3795

80000 8000
95000 4750
105000 525
120000 600
43629.1
75000 27300
22310 2454.1

80000 8000
95000 4750
105000 525
120000 600

1PC : 3 Ps )

77000 Rp. ###


250000 Rp. ###
Rp. ###
105000 Rp. ###
95000 Rp. ###
90000 Rp. ###
72500 Rp. ###
Rp. ###
Ju Rp. ###

260,000 Rp. ### = Rp. ###


260000 + Rp. ### = Rp. ###
#REF! + Rp. ### = Rp.
320000
1080000
120000
22000

1542000

128800

3212800
ANALISA HARGA SATUAN BAHAN DAN UPAH TENAGA
BERDASARKAN SNI
TAHUN ANGGARAN 2016

HARGA HSPK
JUMLAH
NO JENIS PEKERJAAN KOEF. STN SATUAN 2013
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 1 m' Pagar sementara dari seng gelombang tinggi 2 m
Dolken kayu dia.8-10/400 1.250 Btg 17,250.00 21,562.50 220,778.75
Semen Portland 2.500 Kg 1,495.00 3,737.50
Seng Gelombang BJLS 30 1.200 Lbr 74,750.00 89,700.00
Pasir beton 0.005 M3 120,000.00 600.00
Koral Beton 0.009 M3 258,750.00 2,328.75
Kayu 5/7 0.072 M3 862,500.00 62,100.00
Paku 0.060 Kg 17,500.00 1,050.00
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.020 Oh 100,000.00 2,000.00
2 1 m Pengukuran dan Pemasangan Bouwplank 50,597.50
- Patok Kayu 0.012 M3 2,530,000.00 30,360.00
- Paku 0.020 Kg 17,500.00 350.00
- Kayu Papan 3/20 0.007 M3 862,500.00 6,037.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00
3 1 m2 Pembuatan gudang semen dan alat-alat 577,060.00
- Dolken kayu dia.8-10/400 1.700 Btg 17,250.00 29,325.00
- Kayu 0.210 M3 862,500.00 181,125.00
- Paku 0.300 Kg 17,500.00 5,250.00
- Semen Portland 10.500 Kg 1,495.00 15,697.50
- Pasir beton 0.030 M3 120,000.00 3,600.00
- Koral Beton 0.050 M3 258,750.00 12,937.50
- Seng Gelombang BJLS 30 1.500 Lbr 74,750.00 112,125.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 2.000 Oh 70,000.00 140,000.00
~ Kepala Tukang 0.200 Oh 85,000.00 17,000.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
4 1 m2 Pembuatan rumah jaga/konstruksi kayu 591,925.00
- Dolken kayu dia.8-10/400 3.000 Btg 17,250.00 51,750.00
- Kayu 0.276 M3 862,500.00 238,050.00
- Paku 0.700 Kg 17,500.00 12,250.00
- Seng Gelombang BJLS 30 1.500 Lbr 74,750.00 112,125.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 1.500 Oh 70,000.00 105,000.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
5 1 m2 Pembuatan Stegger dari bambu, ukuran (40x50x20) cm 35,847.50
- Bambu Ø 6-8 / 600 cm 1.000 Btg 17,250.00 17,250.00
- Tali ijuk 0.250 Kg 8,750.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.250 Oh 55,000.00 13,750.00
~ Tukang Kayu 0.017 Oh 70,000.00 1,190.00
~ Kepala Tukang 0.002 Oh 85,000.00 170.00
~ Mandor 0.013 Oh 100,000.00 1,300.00
6 1 m 3 Bongkaran Beton Bertulang 407,190.00
- Pekerja 6.667 Oh 55,000.00 366,685.00
- Mandor 0.333 Oh 100,000.00 33,300.00
Alat
- Bodem 0.025 unit 135,000.00 3,375.00
- Keranjang 0.050 unit 11,500.00 575.00
- Gergaji Besi 0.068 unit 35,000.00 2,380.00
- Betel 0.025 unit 35,000.00 875.00

HSPK 2013 Kota Probolinggo 148


1 2 3 4 5 6 7
7 1 m 3 Bongkaran Dinding tembok bata merah 370,015.00
- Pekerja 6.667 Oh 55,000.00 366,685.00
- Mandor 0.033 Oh 100,000.00 3,330.00
8 1 m 2 Membersihkan lapangan dan perataan 10,500.00
- Pekerja 0.100 Oh 55,000.00 5,500.00
- Mandor 0.050 Oh 100,000.00 5,000.00

II PEKERJAAN TANAH
1 1 m 3 Galian Tanah biasa sedalam 1 meter 43,750.00
- Pekerja 0.750 Oh 55,000.00 41,250.00
- Mandor 0.025 Oh 100,000.00 2,500.00
2 1 m 3 Galian Tanah biasa 2 meter 54,000.00
- Pekerja 0.900 Oh 55,000.00 49,500.00
- Mandor 0.045 Oh 100,000.00 4,500.00
3 1 m 3 Galian Tanah biasa 3 meter 64,450.00
- Pekerja 1.050 Oh 55,000.00 57,750.00
- Mandor 0.067 Oh 100,000.00 6,700.00
4 1 m 3 Galian Tanah keras 1 meter 58,200.00
- Pekerja 1.000 Oh 55,000.00 55,000.00
- Mandor 0.032 Oh 100,000.00 3,200.00
5 1 m 3 Galian cadas Keras 1 meter 88,500.00
- Pekerja 1.500 Oh 55,000.00 82,500.00
- Mandor 0.060 Oh 100,000.00 6,000.00
6 1 m 3 Galian Lumpur sedalam 1 meter 70,500.00
- Pekerja 1.200 Oh 55,000.00 66,000.00
- Mandor 0.045 Oh 100,000.00 4,500.00
7 1 m ' Galian bor Strouze (Dia =30 cm ) 69,725.00
- Pekerja 0.735 Oh 55,000.00 40,425.00
- Mandor 0.073 Oh 100,000.00 7,300.00
- Sewa Peralatan bor 1.000 ls 22,000.00 22,000.00
8 1 m ' Pengeboran air tanah (sumur pompa) 54,950.00
- Pekerja 0.750 Oh 55,000.00 41,250.00
- Mandor 0.072 Oh 100,000.00 7,200.00
- Sewa Peralatan bor / tradisionil 1.000 ls 6,500.00 6,500.00
9 1 m 3 Urugan kembali 14,583.33
- Pekerja 0.250 Oh 55,000.00 13,750.00
- Mandor 0.008 Oh 100,000.00 833.33
10 1 m 3 Pemadatan tanah ( per 20 cm ) 32,500.00
- Pekerja 0.500 Oh 55,000.00 27,500.00
- Mandor 0.050 Oh 100,000.00 5,000.00
11 1 m 3 Urugan Pasir Padat 101,500.00
- Pasir Urug 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
12 1 m 3 Urugan Sirtu Padat 114,100.00
- Sirtu 1.200 M3 80,500.00 96,600.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
13 1 m 3 Urugan Sirtu Padat untuk peninggian lantai bangunan 112,850.00
- Sirtu 1.200 M3 80,500.00 96,600.00
- Upah Pekerjaan
~ Pekerja 0.250 Oh 55,000.00 13,750.00
~ Mandor 0.025 Oh 100,000.00 2,500.00
14 1 m 3 Urugan Tanah Padat 89,500.00
- Tanah urug 1.200 M3 60,000.00 72,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
15 1 m 3 Urugan Paras Padat 101,500.00
- Tanah Paras 1.200 M3 70,000.00 84,000.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Mandor 0.010 Oh 100,000.00 1,000.00

HSPK 2013 Kota Probolinggo 149


1 2 3 4 5 6 7
III PEKERJAAN PASANGAN
1 1 m 3 Pasang Pondasi Batu Kali, 1 Pc : 4 Ps (lokal) 595,568.00
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 163.000 Kg 1,495.00 243,685.00
- Pasir Pasang 0.520 M3 90,400.00 47,008.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
2 1 m 3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps (lokal) 557,372.60
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 136.000 Kg 1,495.00 203,320.00
- Pasir Pasang 0.544 M3 90,400.00 49,177.60
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
3 1 m 3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps (lokal) 493,713.60
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 91.000 Kg 1,495.00 136,045.00
- Pasir Pasang 0.584 M3 90,400.00 52,793.60
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
4 1 m 3 Pasang Pondasi Batu Kali, 1 : 3 : 10 (lokal) 512,393.05
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 61.000 Kg 1,495.00 91,195.00
- Pasir Pasang 0.492 M3 90,400.00 44,476.80
- Kapur pasang 0.147 M3 488,750.00 71,846.25
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
5 1 m 3 Pasang Aanstampeng Batu Kali termasuk urugan pasir (lokal) 263,655.00
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Pasir Urug 0.432 M3 70,000.00 30,240.00
- Upah Pekerjaan
~ Pekerja 0.780 Oh 55,000.00 42,900.00
~ Tukang Batu 0.390 Oh 70,000.00 27,300.00
~ Kepala Tukang 0.039 Oh 85,000.00 3,315.00
~ Mandor 0.039 Oh 100,000.00 3,900.00
6 1 m 3 Pasang Pondasi Batu Kali, 1 Pc : 4 Ps (lumajang) 611,775.00
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 163.000 Kg 1,500.00 244,500.00
- Pasir Lumajang 0.520 M3 120,000.00 62,400.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
7 1 m 3 Pasang Pondasi Batu Kali, 1 Pc : 5 Ps (lumajang) 574,155.00
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 136.000 Kg 1,500.00 204,000.00
- Pasir Lumajang 0.544 M3 120,000.00 65,280.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
8 1 m 3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps (lumajang) 511,455.00
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 91.000 Kg 1,500.00 136,500.00
- Pasir Lumajang 0.584 M3 120,000.00 70,080.00
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00

HSPK 2013 Kota Probolinggo 150


1 2 3 4 5 6 7
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00

HSPK 2013 Kota Probolinggo 151


1 2 3 4 5 6 7
9 1 m 3 Pasang Pondasi Batu Kali, 1 : 3 : 10 (lumajang) 527,261.25
- Batu Kali 1.200 M3 130,000.00 156,000.00
- Semen Portland 61.000 Kg 1,500.00 91,500.00
- Pasir Lumajang 0.492 M3 120,000.00 59,040.00
- Kapur pasang 0.147 M3 488,750.00 71,846.25
- Upah Pekerjaan
~ Pekerja 1.500 Oh 55,000.00 82,500.00
~ Tukang Batu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.075 Oh 85,000.00 6,375.00
~ Mandor 0.075 Oh 100,000.00 7,500.00
10 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 3 Ps 93,021.00
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 14.370 Kg 1,500.00 21,555.00
- Pasir Pasang 0.040 M3 90,400.00 3,616.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
11 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 5 Ps 86,438.00
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 9.680 Kg 1,500.00 14,520.00
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
12 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 6Ps 84,759.60
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 8.320 Kg 1,500.00 12,480.00
- Pasir Pasang 0.049 M3 90,400.00 4,429.60
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
13 1 m 2 Pasangan Bata Merah tebal 1/2 Bata, 1 Pc : 8Ps 82,120.00
- Bata Merah 5 x 11 x 22 cm 70.000 Bh 600.00 42,000.00
- Semen Portland 6.500 Kg 1,500.00 9,750.00
- Pasir Pasang 0.050 M3 90,400.00 4,520.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
14 1 m 2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 2 Ps 208,182.00
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 43.500 Kg 1,500.00 65,250.00
- Pasir Pasang 0.080 M3 90,400.00 7,232.00
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00
15 1 m 2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 3 Ps 193,351.40
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 32.950 Kg 1,500.00 49,425.00
- Pasir Pasang 0.091 M3 90,400.00 8,226.40
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00
16 1 m Pasangan Bata Merah tebal 1 Bata, 1 Pc : 4 Ps
2
183,932.20
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 26.550 Kg 1,500.00 39,825.00
- Pasir Pasang 0.093 M3 90,400.00 8,407.20
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00

HSPK 2013 Kota Probolinggo 152


1 2 3 4 5 6 7
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00

HSPK 2013 Kota Probolinggo 153


1 2 3 4 5 6 7
17 1 m 2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 5 Ps 178,220.80
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 22.200 Kg 1,500.00 33,300.00
- Pasir Pasang 0.102 M3 90,400.00 9,220.80
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00
18 1 m 2 Pasangan Bata Merah tebal 1 Bata, 1 Pc : 6 Ps 174,478.80
- Bata Merah 5 x 11 x 22 cm 140.000 Bh 600.00 84,000.00
- Semen Portland 18.500 Kg 1,500.00 27,750.00
- Pasir Pasang 0.122 M3 90,400.00 11,028.80
- Upah Pekerjaan
~ Pekerja 0.600 Oh 55,000.00 33,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.030 Oh 100,000.00 3,000.00
19 1 m 2 Pasang dinding pemisah plywood rangkap, rangka kayu meranti 306,890.00
- Kayu Meranti, balok 0.0280 M3 6,210,000.00 173,880.00
- Paku biasa 2" - 5" 0.150 Kg 17,500.00 2,625.00
- Lem kayu 0.560 Lt 12,500.00 7,000.00
- Plywood 120 cm x 240 mm x 4 mm 0.860 Lbr 74,750.00 64,285.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.600 Oh 70,000.00 42,000.00
~ Kepala Tukang 0.060 Oh 85,000.00 5,100.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
20 1 m 2 Pasangan dinding roster terawang bakar (12x11x24), 1 Pc : 4 Pp #REF!
- Roster/terawang 30.000 Bh 4,600.00 138,000.00
- Semen Portland 11.000 Kg #REF! #REF!
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.0100 Oh 85,000.00 850.00
~ Mandor 0.0150 Oh 100,000.00 1,500.00
21 1 m 2 Pasangan Platelaag ( 1 Lapis ) #REF!
- Bata Merah 5 x 11 x 22 cm 35.000 Bh 600.00 21,000.00
- Semen Portland 0.605 kg #REF! #REF!
- Pasir Pasang 0.023 M3 90,400.00 2,034.00
- Upah Pekerjaan
~ Pekerja 0.160 Oh 55,000.00 8,800.00
~ Tukang Batu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.008 Oh 100,000.00 750.00

IV PEKERJAAN PLESTERAN
1 1 m 2 Plesteran 1 Pc : 2 Ps, tebal 15 mm #REF!
- Semen Portland 10.224 Kg #REF! #REF!
- Pasir Pasang 0.020 M3 90,400.00 1,808.00
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
2 1 m 2 Plesteran 1 Pc : 3 Ps, tebal 15 mm #REF!
- Semen Portland 7.776 Kg #REF! #REF!
- Pasir Pasang 0.023 M3 90,400.00 2,079.20
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
3 1 m 2 Plesteran 1 Pc : 5 Ps, tebal 15 mm #REF!
- Semen Portland 5.184 Kg #REF! #REF!
- Pasir Pasang 0.026 M3 90,400.00 2,350.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00

HSPK 2013 Kota Probolinggo 154


1 2 3 4 5 6 7
~ Mandor 0.015 Oh 100,000.00 1,500.00

HSPK 2013 Kota Probolinggo 155


1 2 3 4 5 6 7
4 1 m 2 Plesteran 1 Pc : 6 Ps, tebal 15 mm #REF!
- Semen Portland 4.416 Kg #REF! #REF!
- Pasir Pasang 0.027 M3 90,400.00 2,440.80
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
5 1 m 2 Plesteran 1 Pc : 8 Ps, tebal 15 mm #REF!
- Semen Portland 3.456 Kg #REF! #REF!
- Pasir Pasang 0.029 M3 90,400.00 2,621.60
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
6 1 m 2 Plesteran 1 Pc : 2 Ps, tebal 20 mm #REF!
- Semen Portland 13.632 Kg #REF! #REF!
- Pasir Pasang 0.027 M3 90,400.00 2,440.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.0220 Oh 100,000.00 2,200.00
7 1 m 2 Plesteran 1 Pc : 3 Ps, tebal 20 mm #REF!
- Semen Portland 10.368 Kg #REF! #REF!
- Pasir Pasang 0.031 M3 90,400.00 2,802.40
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.0220 Oh 100,000.00 2,200.00
8 1 m 2 Plesteran 1 Pc : 5 Ps, tebal 20 mm #REF!
- Semen Portland 6.912 Kg #REF! #REF!
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.022 Oh 100,000.00 2,200.00
9 1 m 2 Plesteran Ciprat 1 Pc : 2 Ps #REF!
- Semen Portland 4.320 Kg #REF! #REF!
- Pasir Pasang 0.006 M3 90,400.00 542.40
- Upah Pekerjaan
~ Pekerja 0.300 Oh 55,000.00 16,500.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00
10 1 m 2 Finishing Siar Pas. Dinding #REF!
- Semen Portland 3.108 Kg #REF! #REF!
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Batu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00
11 1 m 2 Finishing Siar 1 Pc : 2 Ps, Pas. Batu Kali #REF!
- Semen Portland 6.340 Kg #REF! #REF!
- Pasir Pasang 0.012 M3 90,400.00 1,084.80
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Batu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.008 Oh 100,000.00 800.00
12 1 m 2 Acian #REF!
- Semen Portland 3.250 Kg #REF! #REF!
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.010 Oh 100,000.00 1,000.00

HSPK 2013 Kota Probolinggo 156


1 2 3 4 5 6 7
13 1 m 1 Benangan #REF!
- Semen Portland 1.440 Kg #REF! #REF!
- Pasir Pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 0.105 Oh 55,000.00 5,775.00
~ Tukang Batu 0.049 Oh 70,000.00 3,430.00
~ Kepala Tukang 0.005 Oh 85,000.00 416.50
~ Mandor 0.006 Oh 100,000.00 560.00
14 1 m 1 Tali air #REF!
- Semen Portland 0.600 Kg #REF! #REF!
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.033 Oh 70,000.00 2,286.67
~ Kepala Tukang 0.003 Oh 85,000.00 277.67
~ Mandor 0.004 Oh 100,000.00 373.33

V PEKERJAAN LANTAI
1 1 m 2 Pasang Lantai Keramik 30 X 30 cm Putih KW I #REF!
- Keramik 30 x 30 cm 1.080 M2 48,900.00 52,812.00
- Semen Portland 10.000 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
2 1 m 2 Pasang Lantai Keramik 40 x 40 cm putih KW I #REF!
- Keramik 40 x 40 cm 1.105 M2 #REF! #REF!
- Semen Portland 9.800 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
3 1 m 2 Pasang Lantai Keramik Warna KM/WC 20 x 20 cm #REF!
- Keramik 20 x 20 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 10.400 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
3 1 m 2 Pasang Lantai Keramik Warna KM/WC 25 x 25 cm #REF!
- Keramik 20 x 20 cm 1.060 M2 #REF! #REF!
- Semen Portland 10.400 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 85,000.00 29,750.00
~ Tukang Batu 0.175 Oh 100,000.00 17,500.00
~ Kepala Tukang 0.018 Oh 0.00 -
~ Mandor 0.018 Oh #REF! #REF!
4 1 m 2 Pasang Lantai Keramik 30 x 30 cm Warna KW I #REF!
- Keramik 30 x 30 cm 1.080 M2 48,900.00 52,812.00
- Semen Portland 10.000 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
5 1 m 2 Pasang Lantai Keramik 30 x 30 cm Motif Kasar KW1 #REF!
- Keramik 30 x 30 cm Kasar 1.080 M2 52,900.00 57,132.00
- Semen Portland 10.000 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00

HSPK 2013 Kota Probolinggo 157


1 2 3 4 5 6 7
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00

HSPK 2013 Kota Probolinggo 158


1 2 3 4 5 6 7
6 1 m 2 Pasang Lantai Keramik 40 x 40 cm warna KW I #REF!
- Keramik 40 x 40 cm 1.105 M2 57,500.00 63,537.50
- Semen Portland 9.800 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Semen Warna 1.300 Kg 9,800.00 12,740.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.018 Oh 100,000.00 1,750.00
7 1 m 2 Pasang Keramik Dinding 20 x 25 cm putih KW I #REF!
- Keramik 20 x 25 cm 1.060 M2 51,750.00 54,855.00
- Semen Portland 9.300 Kg #REF! #REF!
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00
8 1 m 2 Pasang Keramik Dinding 20 x 25 cm warna KW I #REF!
- Keramik 20 x 25 cm 1.060 M2 55,200.00 58,512.00
- Semen Portland 9.300 Kg #REF! #REF!
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00
7 1 m 2 Pasang Keramik Dinding 25 x 40 cm putih KW I #REF!
- Keramik 25 x 40 cm 1.060 M2 0.00 -
- Semen Portland 9.300 Kg #REF! #REF!
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00
8 1 m 2 Pasang Keramik Dinding 25 x 40 cm warna KW I #REF!
- Keramik 25 x 40 cm 1.060 M2 80,500.00 85,330.00
- Semen Portland 9.300 Kg #REF! #REF!
- Pasir Pasang 0.018 M3 90,400.00 1,627.20
- Semen Warna 1.500 Kg 9,800.00 14,700.00
- Upah Pekerjaan
~ Pekerja 0.450 Oh 55,000.00 24,750.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.023 Oh 85,000.00 1,912.50
~ Mandor 0.023 Oh 100,000.00 2,250.00
9 1 m 1 Pasang List Keramik Dinding 5 x 20 cm warna KW I #REF!
- List Keramik 5 x 20 cm 5.300 bh 3,500.00 18,550.00
- Semen Portland 0.570 Kg #REF! #REF!
- Pasir Pasang 0.0015 M3 90,400.00 135.60
- Semen Warna 0.013 Kg 9,800.00 127.40
- Upah Pekerjaan
~ Pekerja 0.090 Oh 55,000.00 4,950.00
~ Tukang Batu 0.090 Oh 70,000.00 6,300.00
~ Kepala Tukang 0.009 Oh 85,000.00 765.00
~ Mandor 0.005 Oh 100,000.00 500.00
10 1 m Pasang Lantai Tegel Abu-abu
2
#REF!
- Tegel Abu-abu 1.060 M 2
46,000.00 48,760.00
- Semen Portland 10.400 Kg #REF! #REF!
- Pasir Pasang 0.045 M3 90,400.00 4,068.00
- Upah Pekerjaan
~ Pekerja 0.270 Oh 55,000.00 14,850.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.014 Oh 85,000.00 1,190.00
~ Mandor 0.0140 Oh 100,000.00 1,400.00
11 1 m 2 Pasang Batu Alam Candi #REF!
- Batu Alam Candi 1.100 M2 115,000.00 126,500.00

HSPK 2013 Kota Probolinggo 159


1 2 3 4 5 6 7
- Semen Portland 11.750 kg #REF! #REF!
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00
12 1 m 2 Pasang Batu Alam Garis #REF!
- Batu Alam Garis 1.100 M2 109,250.00 120,175.00
- Semen Portland 11.750 kg #REF! #REF!
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00

HSPK 2013 Kota Probolinggo 160


1 2 3 4 5 6 7
13 1 m 2 Pasang Batu Alam Koral/Ampyang #REF!
- Batu Alam Koral/Ampyang 1.100 M2 23,000.00 25,300.00
- Semen Portland 11.750 kg #REF! #REF!
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00
15 1 m 2 Pasang Batu Alam Lempeng/Piring #REF!
- Batu Alam Lempeng 1.100 M2 28,750.00 31,625.00
- Semen Portland 11.750 kg #REF! #REF!
- Pasir Pasang 0.035 M3 90,400.00 3,164.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Tukang Batu 0.175 Oh 70,000.00 12,250.00
~ Kepala Tukang 0.018 Oh 85,000.00 1,487.50
~ Mandor 0.0175 Oh 100,000.00 1,750.00
16 1 Bh Pasang Glass Block #REF!
- Glass Block 1.000 Bh 20,700.00 20,700.00
- Semen Portland 0.150 kg #REF! #REF!
- Upah Pekerjaan 1.000 ls 3,000.00 3,000.00
17 1 m 2 Pasang Wall paper lebar 50 cm 95,075.00
- Wall paper, lebar 50 cm 2.200 M 20,000.00 44,000.00
- Lem 0.250 Kg 12,500.00 3,125.00
- Upah Pekerjaan
~ Pekerja 0.350 Oh 55,000.00 19,250.00
~ Mandor 0.0060 Oh 100,000.00 600.00 16,620.00

VI PEKERJAAN ATAP
1 1 m3 Pasang Konstruksi Kuda-kuda Ekspose Kayu Kelas Kuat I 21,577,850.00
- Kayu Jati, balok 1.200 M3 16,100,000.00 19,320,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 6.700 Oh 55,000.00 368,500.00
~ Tukang Kayu 20.100 Oh 70,000.00 1,407,000.00
~ Kepala Tukang 2.010 Oh 85,000.00 170,850.00
~ Mandor 0.335 Oh 100,000.00 33,500.00
2 1 m3 Pasang Konstruksi Kuda-kuda konvensional kayu kelas I 19,170,000.00
- Kayu Jati, balok 1.100 M3 16,100,000.00 17,710,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00
3 1 m3 Pasang Konstruksi Kuda-kuda Kayu Kamper
- Kayu Kamper, balok 1.100 M3 -
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00 1,460,000.00
3 1 m3 Pasang Konstruksi Kuda-kuda Kayu kelas II 8,291,000.00
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00

HSPK 2013 Kota Probolinggo 161


1 2 3 4 5 6 7
4 1 m3 Pasang Konstruksi Kuda-kuda Kayu Kelas II, III 5,255,000.00
- Kayu Mahoni, balok 1.100 M3 3,450,000.00 3,795,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 5.60 Kg 17,500.00 98,000.00
- Upah Pekerjaan
~ Pekerja 4.000 Oh 55,000.00 220,000.00
~ Tukang Kayu 12.000 Oh 70,000.00 840,000.00
~ Kepala Tukang 1.200 Oh 85,000.00 102,000.00
~ Mandor 0.200 Oh 100,000.00 20,000.00
5 1 m3 Pasang Konstruksi Gording Kayu Kelas II 7,772,700.00
- Kayu Meranti Asli, balok 1.100 M3 6,210,000.00 6,831,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 3.00 Kg 17,500.00 52,500.00
- Upah Pekerjaan
~ Pekerja 2.400 Oh 55,000.00 132,000.00
~ Tukang Kayu 7.200 Oh 70,000.00 504,000.00
~ Kepala Tukang 0.720 Oh 85,000.00 61,200.00
~ Mandor 0.120 Oh 100,000.00 12,000.00
6 1 m3 Pasang Konstruksi Gording Kayu Kelas II, III 4,736,700.00
- Kayu Mahoni,gemalina balok 1.100 M3 3,450,000.00 3,795,000.00
- Besi Strip 15.00 Kg 12,000.00 180,000.00
- Paku Biasa 2" - 5" 3.00 Kg 17,500.00 52,500.00
- Upah Pekerjaan
~ Pekerja 2.400 Oh 55,000.00 132,000.00
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00 100,565.00
9 1 m2 Pasang Kaso (5/7) + Reng (3/5) Kayu Meranti MA untuk genteng beton
- Kaso-kaso (5 X 7 ) cm 0.014 M3 6,210,000.00 86,940.00
- Reng ( 3 X 4 ) cm 0.036 M3 -
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Paku 5cm dan 10 cm 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.005 Oh 100,000.00 500.00
11 1 m2 Pasang Kaso (5/7) Kayu Kruing
- Kayu Kruing, balok 0.0100 M3 5,750,000.00 57,500.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 66,612.50
10 1 m2 Pasang Kaso (5/7) Kayu Kelas II,III 57,412.50
- Kaso-kaso (5 X 7 ) cm mahoni,gemalina 0.0140 M3 3,450,000.00 48,300.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00
12 1 m2 Pasang Kaso (5/7) Kayu Meranti MC
- Kayu Meranti, balok MC 0.0080 M3 4,025,000.00 32,200.00
- Paku Biasa 2" - 5" 0.075 Kg 17,500.00 1,312.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00 40,437.50
11 1 m2 Reng (2/3) Kayu Kelas II,III 21,532.50
- Reng ( 2 X 3 ) cm 0.004 M3 3,450,000.00 12,420.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00

HSPK 2013 Kota Probolinggo 162


1 2 3 4 5 6 7
12 1 m2 Reng (3/5) Kayu Kelas II,III 33,952.50
- Reng ( 3 X 5 ) cm 0.007 M3 3,450,000.00 24,840.00
- Paku Biasa 2" - 5" 0.125 Kg 17,500.00 2,187.50
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.0025 Oh 100,000.00 250.00
13 1 m 2 Pasang Atap Genteng Karang Pilang besar 91,385.00
- Genteng Karang Pilang 13.500 Bh 5,750.00 77,625.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.008 Oh 100,000.00 800.00
14 1 m 2 Pasang Atap Genteng Model Karang Pilang (ex Ambulu) 78,730.00
- Genteng model Karang Pilang 25.000 Bh 2,550.00 63,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00
15 1 m 2 Pasang Atap Genteng Pres Kedung Bajul (biasa) 52,480.00
- Genteng Pres Kedung Bajul 25.000 Bh 1,500.00 37,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.008 Oh 100,000.00 800.00
16 1 m 2 Pasang Atap Genteng Beton 77,535.00
- Genteng Beton 11.000 Bh 5,750.00 63,250.00
- Paku 0.030 Kg 17,500.00 525.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.008 Oh 100,000.00 800.00
17 1 m Pasang Bubung Genteng Karang Pilang 87,252.80
- Genteng bubung karang pilang 5.000 Bh 6,900.00 34,500.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00
18 1 m Pasang Bubung Genteng Model Karang Pilang 81,502.80
- Genteng bubung model karang pilang 5.000 Bh 5,750.00 28,750.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00
19 1 m Pasang Bubung Pres Kedung Bajul 73,002.80
- Genteng Bubung pres kedung bajul 5.000 Bh 4,050.00 20,250.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00
20 1 m Pasang Bubung Pres Beton 87,352.80
- Genteng Bubung beton 4.000 Bh 8,650.00 34,600.00
- Semen Portland 8.000 Kg 1,495.00 11,960.00
- Pasir Pasang 0.032 M3 90,400.00 2,892.80
- Upah Pekerjaan
~ Pekerja 0.400 Oh 55,000.00 22,000.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00

HSPK 2013 Kota Probolinggo 163


1 2 3 4 5 6 7
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.002 Oh 100,000.00 200.00

HSPK 2013 Kota Probolinggo 164


1 2 3 4 5 6 7
21 1 m Pasang Bubung Asbes Gelombang kecil 51,175.00
- Asbes Bubung Gelombang 1.000 m 32,800.00 32,800.00
- Paku Sekrup 2.000 bj 1,750.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.084 Oh 55,000.00 4,620.00
~ Tukang Kayu 0.125 Oh 70,000.00 8,750.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,105.00
~ Mandor 0.004 Oh 100,000.00 400.00
22 1 m Pasang Bubung Asbes Gelombang besar 75,375.00
- Asbes Bubung Gelombang 1.000 m 57,000.00 57,000.00
- Paku Sekrup 2.000 bj 1,750.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.084 Oh 55,000.00 4,620.00
~ Tukang Kayu 0.125 Oh 70,000.00 8,750.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,105.00
~ Mandor 0.004 Oh 100,000.00 400.00
23 1 m 2 Pasang Atap Asbes Gelombang 4 mm (Kecil) 43,013.00
- Asbes Gelombang kecil 0.764 Lbr 34,500.00 26,358.00
- Paku Pancing 0.120 Kg 23,000.00 2,760.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00
24 1 m 2 Pasang Atap Asbes Gelombang 5 mm (Besar) 61,532.00
- Asbes Gelombang besar 0.570 Lbr 79,100.00 45,087.00
- Paku Pancing 0.120 Kg 23,000.00 2,760.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00
25 1 m 2 Pasang Atap Seng Gelombang BJLS 30 64,585.00
- Seng Gelombang 0.700 Lbr 74,750.00 52,325.00
- Paku Biasa 0.020 Kg 17,500.00 350.00
- Upah Pekerjaan
~ Pekerja 0.120 Oh 55,000.00 6,600.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.006 Oh 100,000.00 600.00
26 1 m 2 Pasang Atap Nok Seng 28,765.00
- Seng Plat BJLS 30 3x6 0.300 Lbr 45,450.00 13,635.00
- Paku Biasa 0.040 Kg 17,500.00 700.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.006 Oh 100,000.00 600.00
27 1 m 2 Pasang Atap Galvalum 235,630.00
- Galvalum 1.050 m2 165,000.00 173,250.00
- Paku Biasa 0.020 Kg 17,500.00 350.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.750 Oh 70,000.00 52,500.00
~ Kepala Tukang 0.008 Oh 85,000.00 680.00
~ Mandor 0.006 Oh 100,000.00 600.00
28 1 m 2 Pasang Fiberglass Gelombang 109,435.00
- Fiberglass Gelombang 1.100 M2 86,250.00 94,875.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.007 Oh 100,000.00 700.00
29 1 m Pasang Fiberglass datar
2
58,835.00
- Fiberglass datar 1.100 M2 40,250.00 44,275.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.140 Oh 55,000.00 7,700.00
~ Tukang Kayu 0.067 Oh 70,000.00 4,690.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00

HSPK 2013 Kota Probolinggo 165


1 2 3 4 5 6 7
~ Mandor 0.007 Oh 100,000.00 700.00

HSPK 2013 Kota Probolinggo 166


1 2 3 4 5 6 7
30 1 Kg Pasang rangka atap baja WF 23,605.00
- Besi Profil WF 1.150 Kg 13,300.00 15,295.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00
31 1 Kg Pasang Cannal C baja 22,800.00
- Besi Profil Cannal C 1.150 Kg 12,600.00 14,490.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00
32 1 Kg Pasang Siku L baja 22,110.00
- Besi Profil Siku L 1.150 Kg 12,000.00 13,800.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Las 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00
33 100 Kg Pekerjaan Perakitan 52,325.00
- Solar 1.000 Ltr 4,500.00 4,500.00
- Minyak Pelumas 0.100 Ltr 42,600.00 4,260.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Las 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.005 Oh 100,000.00 500.00
- Alat
~ Mesin Las 0.8 Jam 38,100.00 30,480.00
34 10 cm Pekerjaan Pengelasan 25,001.00
- Kawat Las Listrik 0.400 Kg 28,750.00 11,500.00
- Solar 0.300 Ltr 4,500.00 1,350.00
- Minyak Pelumas 0.040 Ltr 42,600.00 1,704.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Las 0.020 Oh 70,000.00 1,400.00
~ Kepala Tukang 0.002 Oh 85,000.00 170.00
~ Mandor 0.002 Oh 100,000.00 200.00
- Alat
~ Mesin Las 0.170 Jam 38,100.00 6,477.00
35 1 Kg Pasang Plat Ezyer baja Tebal 8 s/d 22 mm 23,516.00
- Besi Plat Ezyer 1.000 Kg 12,000.00 12,000.00
- Kawat las/Electroda (Perlengkapan) 0.020 Kg 28,750.00 575.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Tukang Las / welder 0.050 Oh 70,000.00 3,500.00
- Alat
~ Mesin Las 0.01 Jam 38,100.00 381.00
~ Genset 0.01 Jam 81,000.00 810.00
36 1 Bh Pasang Trektank (Jarum keras) 71,900.00
- Treaktank 1.000 Bh 31,700.00 31,700.00
- Perlengkapan 10.000 % 3,170.00 31,700.00
- Upah Pekerjaan
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
37 1 Kg Pasang Beton Ezyer Regel 25,616.00
- Besi Beton Ezyer 1.000 Kg 11,800.00 11,800.00
- Kawat las/Electroda (Perlengkapan) 0.100 Kg 28,750.00 2,875.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Fitter/Tukang Stel 0.050 Oh 70,000.00 3,500.00
~ Tukang Las / welder 0.050 Oh 70,000.00 3,500.00
- Alat
~ Mesin Las 0.01 Jam 38,100.00 381.00
~ Genset 0.01 Jam 81,000.00 810.00

HSPK 2013 Kota Probolinggo 167


1 2 3 4 5 6 7
38 1 m' Pasang Lisplank ukuran (3x20) cm, Kayu Kelas Awet II 166,280.00
- Kayu Jati, Papan 0.0108 M3 13,225,000.00 142,830.00
- Paku Biasa 2" - 5" 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00
39 1 m' Pasang Lisplank ukuran (3x20) cm, Kayu Kelas Awet III 97,970.00
- Kayu Meranti A, Papan 0.0108 M3 6,900,000.00 74,520.00
- Paku Biasa 2" - 5" 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00
40 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Kelas Awet II 168,050.00
- Kayu Jati, Papan 0.011 M3 13,225,000.00 145,475.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00
41 1 m' Pasang Lisplank ukuran (3x30) cm, Kayu Kelas Awet III 98,475.00
- Kayu Meranti A, Papan 0.011 M3 6,900,000.00 75,900.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.005 Oh 100,000.00 500.00
40 1 m' Pasang Lisplank ukuran (2x20) cm, Kayu Kelas II 75,900.00
- Kayu Jati, Papan 0.0040 M3 13,225,000.00 52,900.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.005 Oh 100,000.00 500.00
41 1 m' Pasang Lisplank ukuran (2x20) cm, Kayu Kelas III 50,600.00
- Kayu Meranti A, Papan 0.0040 M3 6,900,000.00 27,600.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.005 Oh 100,000.00 500.00
42 1 m' Pasang Lisplank Kalsium ukuran 20 cm tebal 8 mm 43,380.50
- Kalsium Plank 1.000 M1 14,400.00 14,400.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Kayu Meranti C 3/5 0.004 M3 4,370,000.00 17,043.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,062.50
~ Mandor 0.003 Oh 100,000.00 250.00
43 1 m' Pasang Lisplank Kalsium ukuran 30 cm tebal 8 mm 48,852.50
- Kalsium Plank 1.000 M1 17,250.00 17,250.00
- Paku Biasa 2" - 5" 0.050 Kg 17,500.00 875.00
- Kayu Meranti C 3/5 0.005 M3 4,370,000.00 19,665.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.013 Oh 85,000.00 1,062.50
~ Mandor 0.003 Oh 100,000.00 250.00

HSPK 2013 Kota Probolinggo 168


1 2 3 4 5 6 7
44 1 M' Pasang talang datar, seng BJLS 30 132,062.00
- Seng Plat BJLS 30 (90 cm) 1.050 M1 45,450.00 47,722.50
- Paku biasa 0.015 Kg 17,500.00 262.50
- Kayu Meranti C, papan 0.0096 M3 4,370,000.00 41,952.00
45 1 M' Pasang talang U PVC 15 x 15 72,032.05
- Talang U PVC 15 1.050 M1 26,562.50 27,890.63
- Plat Strip 0.146 kg 12,000.00 1,753.92
- Paku 0.015 Kg 17,500.00 262.50
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Besi 0.400 Oh 70,000.00 28,000.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.01 Oh 100,000.00 1,000.00
46 1 m 2 Pasang Atap Polycarbonat 162,650.00
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Perlengkapan 0.100 Harga 11,500.00 1,150.00
- Upah Pekerjaan 1.000 ls 35,000.00 35,000.00
47 1 m 2 Pasang Atap Polycarbonat rangka pipa gas/besi kotak 426,500.00
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Gas + Pengecatan 1.000 ls 200,000.00 200,000.00
- Upah Pekerjaan 1.000 ls 100,000.00 100,000.00
48 1 m 2 Pasang Atap Polycarbonat rangka pipa stainless 481,500.00
- Polycarbonat KW 1 1.100 m2 115,000.00 126,500.00
- Rangka Pipa Stainless 1.000 ls 270,000.00 270,000.00
- Upah Pekerjaan 1.000 ls 85,000.00 85,000.00
49 1 m' Papan Roiter 2/20 28,355.00
- Kayu meranti C, papan 0.004 M3 4,370,000.00 17,480.00
- Paku 0.050 Kg 17,500.00 875.00
- Upah Pekerjaan 1.000 Ls 10,000.00 10,000.00
43 1 m' Papan Kompres Kayu Kamper
- Kayu Kamper, papan 0.003 M3 #REF! #REF!
- Seng BJLS 30 0.250 m1 26,562.50 6,640.63
- Paku Payung 0.100 Kg 23,000.00 2,300.00
- Upah Pekerjaan 1.000 Ls 12,500.00 12,500.00 #REF!
50 1 m' Papan Kompres kayu Meranti 39,272.50
- Kayu Meranti C, papan 0.003 M3 4,370,000.00 13,110.00
- Seng BJLS 30 0.250 m1 45,450.00 11,362.50
- Paku Payung 0.100 Kg 23,000.00 2,300.00
- Upah Pekerjaan 1.000 Ls 12,500.00 12,500.00
VII PEKERJAAN BETON
1 1 M 3 Membuat Beton Mutu f'c = 7,4 Mpa (K 100) 390,940.71
- Semen Portland 247.000 Kg 0.00
- Pasir Beton (Lumajang) 869.000 Kg 85.71 74,485.71
- Batu Pecah Mesin 2/3 999.000 Kg 191.67 191,475.00
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 55,000.00 90,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Kepala Tukang 0.028 Oh 85,000.00 2,380.00
~ Mandor 0.083 Oh 100,000.00 8,300.00
2 1 M 3 Membuat Lantai Kerja Beton Mutu f'c = 7,4 Mpa (K 100) 365,084.52
- Semen Portland 230.000 Kg 0.00 0.00
- Pasir Beton (Lumajang) 893.000 Kg 85.71 76,542.86
- Batu Pecah Mesin 2/3 1027.000 Kg 191.67 196,841.67
- Air 200.000 Ltr 20.00 4,000.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 55,000.00 66,000.00
~ Tukang Batu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.060 Oh 100,000.00 6,000.00
3 1 M Membuat Beton Mutu f'c = 14,5 Mpa (K 175)
3
387,347.86
- Semen Portland 326.000 Kg 0.00 0.00
- Pasir Beton (Lumajang) 760.000 Kg 85.71 65,142.86
- Batu Pecah Mesin 2/3 1029.000 Kg 191.67 197,225.00
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 55,000.00 90,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Kepala Tukang 0.028 Oh 85,000.00 2,380.00
~ Mandor 0.083 Oh 100,000.00 8,300.00

HSPK 2013 Kota Probolinggo 169


1 2 3 4 5 6 7
4 1 M 3 Membuat Beton Mutu f'c = 19,3 Mpa (K 225) 385,483.57
- Semen Portland 371.000 Kg 0.00 0.00
- Pasir Beton (Lumajang) 698.000 Kg 85.71 59,828.57
- Batu Pecah Mesin 2/3 1047.000 Kg 191.67 200,675.00
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 1.650 Oh 55,000.00 90,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Kepala Tukang 0.028 Oh 85,000.00 2,380.00
~ Mandor 0.083 Oh 100,000.00 8,300.00
5 1 M 3 Membuat Beton Mutu f'c = 31,2 Mpa (K 350) 406,613.10
- Semen Portland 448.000 Kg 0.00 0.00
- Pasir Beton (Lumajang) 667.000 Kg 85.71 57,171.43
- Batu Pecah Mesin 2/3 1000.000 Kg 191.67 191,666.67
- Air 215.000 Ltr 20.00 4,300.00
- Upah Pekerjaan
~ Pekerja 2.100 Oh 55,000.00 115,500.00
~ Tukang Batu 0.350 Oh 70,000.00 24,500.00
~ Kepala Tukang 0.035 Oh 85,000.00 2,975.00
~ Mandor 0.105 Oh 100,000.00 10,500.00
6 1 M 3 Membuat Beton Kedap Air dengan Strotox - 100 518,875.00
- Semen Portland 400.000 Kg 0.00 0.00
- Pasir Beton (Lumajang) 0.480 M3 120,000.00 57,600.00
- Batu Pecah Mesin 2/3 0.800 M3 258,750.00 207,000.00
- Strotox - 100 1.200 Kg 84,000.00 100,800.00
- Upah Pekerjaan
~ Pekerja 2.100 Oh 55,000.00 115,500.00
~ Tukang Batu 0.350 Oh 70,000.00 24,500.00
~ Kepala Tukang 0.035 Oh 85,000.00 2,975.00
~ Mandor 0.105 Oh 100,000.00 10,500.00
7 1 Kg Pembesian dengan besi polos 13,664.50
- Besi beton (polos) 1.050 Kg 11,800.00 12,390.00
- Kawat beton 0.015 Kg 20,000.00 300.00
- Upah Pekerjaan
~ Pekerja 0.007 Oh 55,000.00 385.00
~ Tukang Besi 0.007 Oh 70,000.00 490.00
~ Kepala Tukang 0.0007 Oh 85,000.00 59.50
~ Mandor 0.0004 Oh 100,000.00 40.00
8 1 m 2 Pasang Bekisting untuk pondasi 91,680.00
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.300 Kg 17,500.00 5,250.00
- Minyak Bekisting 0.100 Liter 3,200.00 320.00
- Upah Pekerjaan
~ Pekerja 0.520 Oh 55,000.00 28,600.00
~ Tukang Kayu 0.260 Oh 70,000.00 18,200.00
~ Kepala Tukang 0.026 Oh 85,000.00 2,210.00
~ Mandor 0.026 Oh 100,000.00 2,600.00
9 1 m 2 Pasang Bekisting untuk sloof 95,992.50
- Kayu Cetakan 0.045 M3 862,500.00 38,812.50
- Paku Biasa 2 ' - 5' 0.300 Kg 17,500.00 5,250.00
- Minyak Bekisting 0.100 Liter 3,200.00 320.00
- Upah Pekerjaan
~ Pekerja 0.520 Oh 55,000.00 28,600.00
~ Tukang Kayu 0.260 Oh 70,000.00 18,200.00
~ Kepala Tukang 0.026 Oh 85,000.00 2,210.00
~ Mandor 0.026 Oh 100,000.00 2,600.00
10 1 m 2 Pasang Bekisting untuk kolom bebas 232,882.50
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.015 M3 2,875,000.00 43,125.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 2.000 btg 17,250.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.006 Oh 100,000.00 600.00

HSPK 2013 Kota Probolinggo 170


1 2 3 4 5 6 7
11 1 m 2 Pasang Bekisting untuk balok 241,507.50
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.018 M3 2,875,000.00 51,750.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 2.000 btg 17,250.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.006 Oh 100,000.00 600.00
12 1 m 2 Pasang Bekisting untuk plat lantai 304,582.50
- Kayu Cetakan 0.040 M3 862,500.00 34,500.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.015 M3 2,875,000.00 43,125.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 6.000 btg 17,250.00 103,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.033 Oh 100,000.00 3,300.00
13 1 m 2 Pasang Bekisting untuk tangga 226,957.50
- Kayu Cetakan 0.030 M3 862,500.00 25,875.00
- Paku Biasa 2 ' - 5' 0.400 Kg 17,500.00 7,000.00
- Minyak Bekisting 0.200 Liter 3,200.00 640.00
- Balok kayu 0.015 M3 2,875,000.00 43,125.00
- Plywood tebal 9 mm 0.350 Lbr 143,750.00 50,312.50
- Dolken Kayu galam 2.000 btg 17,250.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.660 Oh 55,000.00 36,300.00
~ Tukang Kayu 0.330 Oh 70,000.00 23,100.00
~ Kepala Tukang 0.033 Oh 85,000.00 2,805.00
~ Mandor 0.033 Oh 100,000.00 3,300.00
14 1 m 3 Membuat pondasi beton bertulang (150 kg besi + bekisting) 3,404,257.50
- Kayu Cetakan 0.200 M3 862,500.00 172,500.00
- Paku Biasa 2 ' - 5' 1.500 Kg 17,500.00 26,250.00
- Minyak Bekisting 0.400 Liter 3,200.00 1,280.00
- Besi beton (polos) 157.500 Kg 11,800.00 1,858,500.00
- Kawat beton 2.250 Kg 20,000.00 45,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.262 Oh 85,000.00 22,270.00
~ Mandor 0.265 Oh 100,000.00 26,500.00
15 1 m 3 Membuat sloof BETON BERTULANG (200 kg besi + bekisting) 4,177,457.50
- Kayu Cetakan 0.270 M3 862,500.00 232,875.00
- Paku Biasa 2 ' - 5' 2.000 Kg 17,500.00 35,000.00
- Minyak Bekisting 0.600 Liter 3,200.00 1,920.00
- Besi beton (polos) 210.000 Kg 11,800.00 2,478,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Upah Pekerjaan
~ Pekerja 5.650 Oh 55,000.00 310,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.560 Oh 70,000.00 109,200.00
~ Tukang Besi 1.400 Oh 70,000.00 98,000.00
~ Kepala Tukang 0.323 Oh 85,000.00 27,455.00
~ Mandor 0.283 Oh 100,000.00 28,300.00

HSPK 2013 Kota Probolinggo 171


1 2 3 4 5 6 7
16 1 m 3 Membuat balok beton bertulang (200 kg besi + bekisting) 5,374,932.50
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 210.000 Kg 11,800.00 2,478,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.140 M3 2,875,000.00 402,500.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 16.000 btg 17,250.00 276,000.00
- Upah Pekerjaan
~ Pekerja 6.350 Oh 55,000.00 349,250.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.650 Oh 70,000.00 115,500.00
~ Tukang Besi 1.400 Oh 70,000.00 98,000.00
~ Kepala Tukang 0.333 Oh 85,000.00 28,305.00
~ Mandor 0.318 Oh 100,000.00 31,800.00
17 1 m 3 Membuat kolom beton bertulang (200 kg besi + bekisting) 5,268,602.50
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 210.000 Kg 11,800.00 2,478,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.120 M3 2,875,000.00 345,000.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 20.000 btg 17,250.00 345,000.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.265 Oh 85,000.00 22,525.00
~ Mandor 0.265 Oh 100,000.00 26,500.00
18 1 m 3 Membuat kolom beton bertulang (300 kg besi + bekisting) 7,023,537.50
- Kayu Cetakan 0.400 M3 862,500.00 345,000.00
- Paku Biasa 2 ' - 5' 4.000 Kg 17,500.00 70,000.00
- Minyak Bekisting 2.000 Liter 3,200.00 6,400.00
- Besi beton (polos) 315.000 Kg 11,800.00 3,717,000.00
- Kawat beton 4.500 Kg 20,000.00 90,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.150 M3 2,875,000.00 431,250.00
- Plywood tebal 9 mm 3.500 Lbr 143,750.00 503,125.00
- Dolken Kayu galam 20.000 btg 17,250.00 345,000.00
- Upah Pekerjaan
~ Pekerja 7.050 Oh 55,000.00 387,750.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.650 Oh 70,000.00 115,500.00
~ Tukang Besi 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.403 Oh 85,000.00 34,255.00
~ Mandor 0.353 Oh 100,000.00 35,300.00

HSPK 2013 Kota Probolinggo 172


1 2 3 4 5 6 7
19 1 m 3 Membuat kolom beton bertulang (150 kg besi + bekisting) 4,841,102.50
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 157.500 Kg 11,800.00 1,858,500.00
- Kawat beton 2.250 Kg 20,000.00 45,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.120 M3 2,875,000.00 345,000.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 32.000 btg 17,250.00 552,000.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.265 Oh 85,000.00 22,525.00
~ Mandor 0.265 Oh 100,000.00 26,500.00
20 1 m 3 Membuat tangga beton bertulang (200 kg besi + bekisting) 4,987,950.00
- Kayu Cetakan 0.250 M3 862,500.00 215,625.00
- Paku Biasa 2 ' - 5' 3.000 Kg 17,500.00 52,500.00
- Minyak Bekisting 1.200 Liter 3,200.00 3,840.00
- Besi beton (polos) 200.000 Kg 11,800.00 2,360,000.00
- Kawat beton 3.000 Kg 20,000.00 60,000.00
- Semen Portland 323.000 Kg 1,495.00 482,885.00
- Pasir Beton (Lumajang) 0.520 M3 120,000.00 62,400.00
- Batu Pecah Mesin 2/3 0.780 M3 258,750.00 201,825.00
- Balok kayu 0.105 M3 2,875,000.00 301,875.00
- Plywood tebal 9 mm 2.500 Lbr 143,750.00 359,375.00
- Dolken Kayu galam 14.000 btg 17,250.00 241,500.00
- Upah Pekerjaan
~ Pekerja 5.600 Oh 55,000.00 308,000.00
~ Tukang Batu 0.350 Oh 70,000.00 24,500.00
~ Tukang Kayu 2.300 Oh 70,000.00 161,000.00
~ Tukang Besi 1.400 Oh 70,000.00 98,000.00
~ Kepala Tukang 0.405 Oh 85,000.00 34,425.00
~ Mandor 0.202 Oh 100,000.00 20,200.00
22 1 m ' Membuat kolom praktis beton bertulang (11 x 11) cm 70,838.75
- Kayu Cetakan 0.002 M3 862,500.00 1,725.00
- Paku Biasa 2 ' - 5' 0.010 Kg 17,500.00 175.00
- Besi beton (polos) 3.000 Kg 11,800.00 35,400.00
- Kawat beton 0.450 Kg 20,000.00 9,000.00
- Semen Portland 4.000 Kg 1,495.00 5,980.00
- Pasir Beton (Lumajang) 0.006 M3 120,000.00 720.00
- Batu Pecah Mesin 2/3 0.009 M3 258,750.00 2,328.75
- Upah Pekerjaan
~ Pekerja 0.180 Oh 55,000.00 9,900.00
~ Tukang Batu 0.020 Oh 70,000.00 1,400.00
~ Tukang Kayu 0.020 Oh 70,000.00 1,400.00
~ Tukang Besi 0.020 Oh 70,000.00 1,400.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.009 Oh 100,000.00 900.00
23 1 m ' Membuat ring balok beton bertulang (10 x 15) cm 85,216.25
- Kayu Cetakan 0.003 M3 862,500.00 2,587.50
- Paku Biasa 2 ' - 5' 0.020 Kg 17,500.00 350.00
- Besi beton (polos) 3.600 Kg 11,800.00 42,480.00
- Kawat beton 0.050 Kg 20,000.00 1,000.00
- Semen Portland 5.500 Kg 1,495.00 8,222.50
- Pasir Beton (Lumajang) 0.009 M3 120,000.00 1,080.00
- Batu Pecah Mesin 2/3 0.015 M3 258,750.00 3,881.25
- Upah Pekerjaan
~ Pekerja 0.297 Oh 55,000.00 16,335.00
~ Tukang Batu 0.033 Oh 70,000.00 2,310.00
~ Tukang Kayu 0.033 Oh 70,000.00 2,310.00
~ Tukang Besi 0.033 Oh 70,000.00 2,310.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.015 Oh 100,000.00 1,500.00

HSPK 2013 Kota Probolinggo 173


1 2 3 4 5 6 7
21 1 m 3 Membuat plat beton bertulang (150 kg besi + bekisting) 4,841,102.50
- Kayu Cetakan 0.320 M3 862,500.00 276,000.00
- Paku Biasa 2 ' - 5' 3.200 Kg 17,500.00 56,000.00
- Minyak Bekisting 1.600 Liter 3,200.00 5,120.00
- Besi beton (polos) 157.500 Kg 11,800.00 1,858,500.00
- Kawat beton 2.250 Kg 20,000.00 45,000.00
- Semen Portland 336.000 Kg 1,495.00 502,320.00
- Pasir Beton (Lumajang) 0.540 M3 120,000.00 64,800.00
- Batu Pecah Mesin 2/3 0.810 M3 258,750.00 209,587.50
- Balok kayu 0.120 M3 2,875,000.00 345,000.00
- Plywood tebal 9 mm 2.800 Lbr 143,750.00 402,500.00
- Dolken Kayu galam 32.000 btg 17,250.00 552,000.00
- Upah Pekerjaan
~ Pekerja 5.300 Oh 55,000.00 291,500.00
~ Tukang Batu 0.275 Oh 70,000.00 19,250.00
~ Tukang Kayu 1.300 Oh 70,000.00 91,000.00
~ Tukang Besi 1.050 Oh 70,000.00 73,500.00
~ Kepala Tukang 0.265 Oh 85,000.00 22,525.00
~ Mandor 0.265 Oh 100,000.00 26,500.00
22 1 m 3 Membuat plat deker beton bertulang tebal s/d 10 cm 3,252,959.11
- Beton Bertulang, K 175 1.000 M3 387,347.86 387,347.86
- Pembesian dengan besi polos 150.000 Kg 13,664.50 2,049,675.00
- Pasang Bekisting 8.500 M2 95,992.50 815,936.25
23 1 m 3 Membuat plat deker beton bertulang tebal > 10 cm 3,936,184.11
- Beton Bertulang, K 175 1.000 M3 387,347.86 387,347.86
- Pembesian dengan besi polos 200.000 Kg 13,664.50 2,732,900.00
- Pasang Bekisting 8.500 M2 95,992.50 815,936.25
24 1 m 3 Membuat plat jembatan beton bertulang tebal > 10 cm 5,302,634.11
- Beton Bertulang, K 175 1.000 M3 387,347.86 387,347.86
- Pembesian dengan besi polos 300.000 Kg 13,664.50 4,099,350.00
- Pasang Bekisting 8.500 M2 95,992.50 815,936.25

HSPK 2013 Kota Probolinggo 174


1 2 3 4 5 6 7
VIII PEKERJAAN KUSEN
1 1 m 3 Pasang Kusen Pintu dan Jendela Kayu Jati Kelas Awet I 19,812,875.00
- Kayu Jati, balok 1.100 M3 16,100,000.00 17,710,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 7.000 Oh 55,000.00 385,000.00
~ Tukang Kayu 21.000 Oh 70,000.00 1,470,000.00
~ Kepala Tukang 2.100 Oh 85,000.00 178,500.00
~ Mandor 0.350 Oh 100,000.00 35,000.00
2 1 m 3 Pasang Kusen Pintu dan Jendela Kayu Jati Kelas Awet II 17,263,375.00
- Kayu Jati, balok 1.200 M3 12,880,000.00 15,456,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 55,000.00 330,000.00
~ Tukang Kayu 18.000 Oh 70,000.00 1,260,000.00
~ Kepala Tukang 1.800 Oh 85,000.00 153,000.00
~ Mandor 0.300 Oh 100,000.00 30,000.00
3 1 m 3 Pasang Kusen Pintu dan Jendela Kayu Kelas Awet III 5,947,375.00
- Kayu Mahoni balok 1.200 M3 3,450,000.00 4,140,000.00
- Paku 10cm 1.250 kg 17,500.00 21,875.00
- Lem Kayu 1.000 kg 12,500.00 12,500.00
- Upah Pekerjaan
~ Pekerja 6.000 Oh 55,000.00 330,000.00
~ Tukang Kayu 18.000 Oh 70,000.00 1,260,000.00
~ Kepala Tukang 1.800 Oh 85,000.00 153,000.00
~ Mandor 0.300 Oh 100,000.00 30,000.00
4 1 m 2 Pasang Pintu Panel Kayu kelas I #REF!
- Kayu Jati, Papan 0.040 M3 #REF! #REF!
- Lem Kayu 0.500 kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
5 1 m 2 Pasang Pintu Panel Kayu Kelas Awet II 830,750.00
- Kayu Jati, papan 0.040 M3 13,225,000.00 529,000.00
- Lem Kayu 0.500 Kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
6 1 m 2 Pasang Pintu Panel Kayu Kelas Awet III 462,750.00
- Kayu Mahoni papan 0.040 M3 4,025,000.00 161,000.00
- Lem Kayu 0.500 Kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
7 1 m 2 Pasang Pintu dan Jendela Jalusi Kayu Kelas II 1,148,150.00
- Kayu Jati, Papan 0.064 M3 13,225,000.00 846,400.00
- Lem Kayu 0.500 Kg 12,500.00 6,250.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Kayu 3.000 Oh 70,000.00 210,000.00
~ Kepala Tukang 0.300 Oh 85,000.00 25,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
8 1 m 2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kelas III 368,950.00
- Kayu Mahoni, Papan 0.025 M3 4,025,000.00 100,625.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 kg 12,500.00 6,250.00
- Plywood 90 x 220 x 4 mm 1.000 Lbr 54,700.00 54,700.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 55,000.00 38,500.00
~ Tukang Kayu 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.210 Oh 85,000.00 17,850.00
~ Mandor 0.035 Oh 100,000.00 3,500.00

HSPK 2013 Kota Probolinggo 175


1 2 3 4 5 6 7
9 1 m 2 Pasang Pintu Plywood Rangkap, Rangka Kayu Kelas IV 377,575.00
- Kayu Meranti C, Papan 0.0250 M3 4,370,000.00 109,250.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 Lt 12,500.00 6,250.00
- Plywood 90 x 220 x 4 mm 1.000 Lbr 54,700.00 54,700.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 55,000.00 38,500.00
~ Tukang Kayu 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.210 Oh 85,000.00 17,850.00
~ Mandor 0.035 Oh 100,000.00 3,500.00
10 1 m 2 Pasang Pintu Doubel Teakwood, Rangka Kayu Meranti (MC) 420,625.00
- Kayu Meranti, Papan 0.025 M3 4,370,000.00 109,250.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 Lt 12,500.00 6,250.00
- Tekwood 90 x 210 x 3 mm 1.000 Lbr 97,750.00 97,750.00
- Upah Pekerjaan
~ Pekerja 0.700 Oh 55,000.00 38,500.00
~ Tukang Kayu 2.100 Oh 70,000.00 147,000.00
~ Kepala Tukang 0.210 Oh 85,000.00 17,850.00
~ Mandor 0.035 Oh 100,000.00 3,500.00
11 1 m 2 Pasang Pintu Doubel Teakwood Lapis Almunium, Rangka Kayu Meranti (MC) 563,000.00
- Kayu Meranti, Papan 0.025 M3 4,370,000.00 109,250.00
- Paku Biasa 1/2" - 1 0.030 Kg 17,500.00 525.00
- Lem Kayu 0.500 Lt 12,500.00 6,250.00
- Tekwood 90 x 210 x 4 mm 1.000 Lbr 97,750.00 97,750.00
- Almunium 3' x 7' x 4 mm 0.500 Lbr 196,000.00 98,000.00
- Upah Pekerjaan
~ Pekerja 0.850 Oh 55,000.00 46,750.00
~ Tukang Kayu 2.550 Oh 70,000.00 178,500.00
~ Kepala Tukang 0.255 Oh 85,000.00 21,675.00
~ Mandor 0.043 Oh 100,000.00 4,300.00
12 1 m 2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Meranti (MA) 324,372.00
- Kayu Meranti, Balok (6 x 12) 0.0280 M3 6,210,000.00 173,880.00
- Paku Biasa 1/2" - 1 0.150 Kg 17,500.00 2,625.00
- Lem Kayu 0.560 Kg 12,500.00 7,000.00
- Tekwood 120 x 240 x 4 mm 0.860 Lbr 112,200.00 96,492.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.450 Oh 70,000.00 31,500.00
~ Kepala Tukang 0.045 Oh 85,000.00 3,825.00
~ Mandor 0.008 Oh 100,000.00 800.00
13 1 m 2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Kelas I 640,350.00
- Kayu Jati, Papan 0.0240 M3 16,675,000.00 400,200.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00
14 1 m2 Pasang Rangka Pintu / jendela Tanpa Kaca aluminium 324,950.00
- almunium 4/10 0.5000 lbr 109,780.00 54,890.00
- Lem Kayu 0.300 kg 112,200.00 33,660.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00
14 1 m 2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Kelas II 557,550.00
- Kayu Jati, Papan 0.0240 M3 13,225,000.00 317,400.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00
15 1 m 2 Pasang Rangka Pintu / jendela Tanpa Kaca Kayu Kelas III 336,750.00
- Kayu Mahoni, Papan 0.0240 M3 4,025,000.00 96,600.00
- Lem Kayu 0.300 kg 12,500.00 3,750.00
- Upah Pekerjaan
~ Pekerja 0.800 Oh 55,000.00 44,000.00
~ Tukang Kayu 2.400 Oh 70,000.00 168,000.00

HSPK 2013 Kota Probolinggo 176


1 2 3 4 5 6 7
~ Kepala Tukang 0.240 Oh 85,000.00 20,400.00
~ Mandor 0.040 Oh 100,000.00 4,000.00
16 1 m2 Pasang jalusi Kusen Kayu Kelas I 1,230,475.00
- Kayu Jati, papan 0.0600 M3 16,675,000.00 1,000,500.00
- Paku 1 cm - 2.5 cm 0.1500 kg 17,500.00 2,625.00
- Upah Pekerjaan
~ Pekerja 0.670 Oh 55,000.00 36,850.00
~ Tukang Kayu 2.000 Oh 70,000.00 140,000.00
~ Kepala Tukang 0.200 Oh 85,000.00 17,000.00
~ Mandor 0.335 Oh 100,000.00 33,500.00
17 1 m 2 Pasang jalusi Kusen Kayu Kelas II 1,023,475.00
- Kayu Jati, papan 0.0600 M3 13,225,000.00 793,500.00
- Paku 1 cm - 2.5 cm 0.1500 kg 17,500.00 2,625.00
- Upah Pekerjaan
~ Pekerja 0.670 Oh 55,000.00 36,850.00
~ Tukang Kayu 2.000 Oh 70,000.00 140,000.00
~ Kepala Tukang 0.200 Oh 85,000.00 17,000.00
~ Mandor 0.335 Oh 100,000.00 33,500.00
18 1 m 2 Pasang Kaca, Tebal 5 mm 88,575.00
- Kaca 1.1000 M2 69,000.00 75,900.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00
19 1 m 2 Pasang Kaca, Tebal 8 mm 203,690.00
- Kaca 1.1000 M2 172,500.00 189,750.00
- Upah Pekerjaan
~ Pekerja 0.0165 Oh 55,000.00 907.50
~ Tukang Kayu 0.165 Oh 70,000.00 11,550.00
~ Kepala Tukang 0.0165 Oh 85,000.00 1,402.50
~ Mandor 0.00080 Oh 100,000.00 80.00
20 1 m 2 Pasang Kaca Rayben, Tebal 5 mm 1,041,175.00
- Kaca Rayben 1.1000 M2 935,000.00 1,028,500.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00
21 Pasang 1 buah kunci pintu biasa 108,900.00
- Kunci Pintu Biasa 1.000 Bh 72,000.00 72,000.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.500 Oh 70,000.00 35,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00
22 Pasang 1 buah kunci tanam hias 246,200.00
- Kunci Tanam Hias 1.000 Bh 195,500.00 195,500.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Kayu 0.600 Oh 70,000.00 42,000.00
~ Kepala Tukang 0.060 Oh 85,000.00 5,100.00
~ Mandor 0.003 Oh 100,000.00 300.00
23 Pasang 1 buah kunci tanam silinder + pegangan 189,725.00
- Kunci tanam Silinder 1.000 Bh 105,000.00 105,000.00
- Pegangan pintu (handle) 1.000 Stl 49,000.00 49,000.00
- Upah Pekerjaan
~ Pekerja 0.005 Oh 55,000.00 275.00
~ Tukang Kayu 0.500 Oh 70,000.00 35,000.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.00025 Oh 100,000.00 25.00
24 Pasang engsel pintu besar (Kuningan/sendok) 47,175.00
- Engsel pintu besar 1.000 Set 34,500.00 34,500.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00
25 Pasang engsel pintu kecil 25,175.00
- Engsel pintu kecil 1.000 Set 12,500.00 12,500.00
- Upah Pekerjaan

HSPK 2013 Kota Probolinggo 177


1 2 3 4 5 6 7
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00
26 Pasang engsel jendela 19,550.00
- Engsel jendela kecil 1.000 Set 11,100.00 11,100.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.00050 Oh 100,000.00 50.00

HSPK 2013 Kota Probolinggo 178


1 2 3 4 5 6 7
27 Pasang Kunci Selot 61,900.00
- Kunci Selot 1.000 bh 45,000.00 45,000.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Kayu 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.001 Oh 100,000.00 100.00
28 Pasang hak angin / Sikutan Kuningan 33,375.00
- Hak angin 1.000 Set 20,700.00 20,700.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00
29 Pasang hak angin 4 mm lurus 31,675.00
- Hak angin 4 mm lurus 1.000 Set 19,000.00 19,000.00
- Upah Pekerjaan
~ Pekerja 0.015 Oh 55,000.00 825.00
~ Tukang Kayu 0.150 Oh 70,000.00 10,500.00
~ Kepala Tukang 0.015 Oh 85,000.00 1,275.00
~ Mandor 0.00075 Oh 100,000.00 75.00
30 Pasang Grendel 21,850.00
- Grendel pintu besar 1.000 Bh 13,400.00 13,400.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.00050 Oh 100,000.00 50.00
31 Pasang Grendel Kecil 23,620.10
- Grendel jendela kecil 1.000 Bh 15,170.10 15,170.10
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.00050 Oh 100,000.00 50.00
32 Memasang kawat harmonika 1 M 2 50,250.00
- Kawat Harmonika 1.000 M2 43,200.00 43,200.00
- Paku 0.020 Kg 17,500.00 350.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.00025 Oh 100,000.00 25.00
33 1 M 2 Pasang tralis 248,820.00
- besi stainlissteel 1.000 M2 28,820.00 28,820.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55000 55000
~ Tukang Besi Konstruksi 1.000 Oh 70,000.00 70,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 85,000.00
~ Mandor 0.050 Oh 100,000.00 10,000.00
33 1 M 2 Pasang Rolling Door Aluminium (silver) 558,250.00
- Rolling Door tebal 1,2 mm 1.000 M2 419,750.00 419,750.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Besi Konstruksi 1.000 Oh 70,000.00 70,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 8,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
34 1 m ' Pasang Kusen Aluminium 3 " (Silver) 85,464.50
- Kusen Almunium 3" 1.100 M' 69,000.00 75,900.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00
35 1 m ' Pasang Kusen Aluminium 3 " (Brown) 91,789.50
- Kusen Almunium 3" 1.100 M' 74,750.00 82,225.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan

HSPK 2013 Kota Probolinggo 179


1 2 3 4 5 6 7
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00

HSPK 2013 Kota Probolinggo 180


1 2 3 4 5 6 7
36 1 m ' Pasang Kusen Aluminium 4 " (Silver) 104,439.50
- Kusen Almunium 4" 1.100 M' 86,250.00 94,875.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00
37 1 m ' Pasang Kusen Aluminium 4 " (Brown) 189,612.50
- Kusen Almunium 4" 1.100 M' 163,680.00 180,048.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.0043 Oh 85,000.00 365.50
~ Mandor 0.0021 Oh 100,000.00 210.00
38 1 m ' Pasang Kusen Aluminium Curtain Wall 3" (Silver) 85,429.00
- Kusen Curtain Wall 1.100 M' 69,000.00 75,900.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00
39 1 m ' Pasang Kusen Aluminium Curtain Wall 3" (brown) 91,754.00
- Kusen Curtain Wall brown 1.100 M' 74,750.00 82,225.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00
40 1 m ' Pasang Kusen Alumunium Curtain Wall 4" (Silver) 104,404.00
- Kusen Curtain Wall silver 1.100 M' 86,250.00 94,875.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00
41 1 m ' Pasang Kusen Aluminium Curtain Wall 4" (brown) 110,729.00
- Kusen Curtain Wall brown 1.100 M' 92,000.00 101,200.00
- Skrup fixer 2.000 Buah 1,600.00 3,200.00
- Sealant 0.060 Tube 6,900.00 414.00
- Upah Pekerjaan
~ Pekerja 0.043 Oh 55,000.00 2,365.00
~ Tukang Besi Konstruksi 0.043 Oh 70,000.00 3,010.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.002 Oh 100,000.00 200.00
42 1 m ' Pasang Daun jendela aluminium (silver) 154,126.00
- Daun jendela aluminium 1.100 M' 50,600.00 55,660.00
- Accesories 0.100 Hrg 55,660.00 5,566.00
- Sponeng 1.100 M' 23,000.00 25,300.00
- Upah Pekerjaan
~ Pekerja 0.080 Oh 55,000.00 4,400.00
~ Tukang Besi 0.800 Oh 70,000.00 56,000.00
~ Kepala Tukang 0.080 Oh 85,000.00 6,800.00
~ Mandor 0.004 Oh 100,000.00 400.00
43 1 m Pasang Daun jendela aluminium (brown)
'
225,733.80
- Daun jendela aluminium 1.100 M '
109,780.00 120,758.00
- Accesories 0.100 Hrg 120,758.00 12,075.80
- Sponeng 1.100 M' 23,000.00 25,300.00
- Upah Pekerjaan
~ Pekerja 0.080 Oh 55,000.00 4,400.00
~ Tukang Besi 0.800 Oh 70,000.00 56,000.00
~ Kepala Tukang 0.080 Oh 85,000.00 6,800.00

HSPK 2013 Kota Probolinggo 181


1 2 3 4 5 6 7
~ Mandor 0.004 Oh 100,000.00 400.00

HSPK 2013 Kota Probolinggo 182


1 2 3 4 5 6 7
44 1 m 2 Pasang Sunscreen Aluminium 1,183,100.00
- Sunscreen Aluminium 1.000 M2 1,115,500.00 1,115,500.00
- Upah Pekerjaan
~ Pekerja 0.080 Oh 55,000.00 4,400.00
~ Tukang Besi 0.800 Oh 70,000.00 56,000.00
~ Kepala Tukang 0.080 Oh 85,000.00 6,800.00
~ Mandor 0.004 Oh 100,000.00 400.00
45 1 bh Pasang Door Closer 107,350.00
- Door Closer 1.000 Bh 65,100.00 65,100.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Besi 0.500 Oh 70,000.00 35,000.00
~ Kepala Tukang 0.050 Oh 85,000.00 4,250.00
~ Mandor 0.003 Oh 100,000.00 250.00
46 1 bh Pasang Door Holder/ Pegangan Pintu 191,750.00
- Door Holder hias 1.000 Set 149,500.00 149,500.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Besi 0.500 Oh 70,000.00 35,000.00
~ Kepala Tukang 0.050 Oh 85,000.00 4,250.00
~ Mandor 0.003 Oh 100,000.00 250.00

IX PEKERJAAN LANGIT-LANGIT / RANGKA PLAFOND


1 1 m 2 Pasang Rangka Plafond Hollow Partisi 63,888.75
- Besi Hollow partisi 4x4 3.000 M' 9,775.00 29,325.00
- Besi Hollow partisi 2x4 2.500 M' 8,337.50 20,843.75
- Accesories 0.150 Kg 25,300.00 3,795.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Besi 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00
2 1 m 2 Rangka Langit-langit Kayu Meranti (MA) 1 x 1 m 91,725.00
- Kayu Meranti (MA) 0.012 M3 4,550,000.00 54,600.00
- Paku 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.250 Oh 70,000.00 17,500.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00
3 1 m 2 Rangka Langit-langit Kayu Meranti (MC) 1 x 1 m 85,425.00
- Kayu Meranti (MC) 0.012 M3 4,025,000.00 48,300.00
- Paku 0.100 Kg 17,500.00 1,750.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.250 Oh 70,000.00 17,500.00
~ Kepala Tukang 0.025 Oh 85,000.00 2,125.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00
4 1 m 2 Rangka Langit-langit Kayu Meranti (MA) 0,5 x 1 m 112,870.00
- Kayu Meranti (MA) 0.015 M3 4,550,000.00 70,070.00
- Paku 0.200 Kg 17,500.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00
5 1 m 2 Rangka Langit-langit Kayu Meranti (MC) 0,5 x 1 m 104,785.00
- Kayu Meranti (MC) 0.015 M3 4,025,000.00 61,985.00
- Paku 0.200 Kg 17,500.00 3,500.00
- Upah Pekerjaan
~ Pekerja 0.150 Oh 55,000.00 8,250.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0750 Oh 100,000.00 7,500.00
6 1 m 2 Rangka Langit-langit Kayu Meranti (MA) (60x60) 114,090.00
- Kayu Meranti (MA) 0.016 M 3
4,550,000.00 74,165.00
- Paku 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00

HSPK 2013 Kota Probolinggo 183


1 2 3 4 5 6 7
~ Mandor 0.0100 Oh 100,000.00 1,000.00

HSPK 2013 Kota Probolinggo 184


1 2 3 4 5 6 7
7 1 m 2 Rangka Langit-langit Kayu Meranti (MC) (60x60) 104,325.00
- Kayu Meranti (MC) 0.016 M3 4,025,000.00 64,400.00
- Paku 0.250 Kg 17,500.00 4,375.00
- Upah Pekerjaan
~ Pekerja 0.200 Oh 55,000.00 11,000.00
~ Tukang Kayu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0100 Oh 100,000.00 1,000.00
8 1 m 2 Pasang Eternit, tebal 4 mm, 5 mm, dan 6 mm 22,900.00
- Eternit 1.100 M2 13,800.00 15,180.00
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.030 Oh 55,000.00 1,650.00
~ Tukang Kayu 0.070 Oh 70,000.00 4,900.00
~ Kepala Tukang 0.007 Oh 85,000.00 595.00
~ Mandor 0.004 Oh 100,000.00 400.00
9 1 m 2 Pasang Langit-langit Triplek (120x240) tebal 4 mm 41,543.75
- Tripleks 0.375 Lbr 72,450.00 27,168.75
- Paku 0.030 Kg 17,500.00 525.00
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00
10 1 m2 Pasang langit-langit gypsum board, ( 120 X 240 X 9 ) mm #REF!
- Gypsum Board 0.364 lbr #REF! #REF!
- Paku Sekrup 0.110 Kg 28,750.00 3,162.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00
11 1 m2 Pasang langit-langit calsiboard, ( 120 X 240 ) mm 49,487.50
- Calsium Board tebal 3,5 mm 0.364 lbr 100,000.00 36,400.00
- Paku 0.110 Kg 28,750.00 3,162.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00
12 1 m2 Pasang langit-langit calsiboard, ( 120 X 240 ) mm pada metal furring atau hollow 49,487.50
- Calsium Board tebal 3,5 mm 0.364 lbr 100,000.00 36,400.00
- Paku skrup 0.110 Kg 28,750.00 3,162.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.005 Oh 100,000.00 500.00
13 1 m' Pasang list plafond - kayu profil 20,117.50
- Kayu profil 1.050 M' 12,350.00 12,967.50
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.050 Oh 55,000.00 2,750.00
~ Tukang Kayu 0.050 Oh 70,000.00 3,500.00
~ Kepala Tukang 0.005 Oh 85,000.00 425.00
~ Mandor 0.003 Oh 100,000.00 300.00
14 1 m' Pasang list plafond gypsum lebar 15 cm 19,352.50
- Gypsum list profil lebar 15 cm 1.050 M' 10,350.00 10,867.50
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.003 Oh 100,000.00 300.00
15 1 m' Pasang list plafond gypsum lebar 8 cm 16,937.50
- Gypsum list profil lebar 8 cm 1.050 M' 8,050.00 8,452.50
- Paku 0.010 Kg 17,500.00 175.00
- Upah Pekerjaan
~ Pekerja 0.060 Oh 55,000.00 3,300.00
~ Tukang Kayu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00

HSPK 2013 Kota Probolinggo 185


1 2 3 4 5 6 7
~ Mandor 0.003 Oh 100,000.00 300.00

PEKERJAAN
X PENGECATAN
1 1 m 2 mendempul dan menggosok kayu 8,682.00
- Plamir Kayu 0.080 Kg 31,600.00 2,528.00
- Minyak Cat 0.020 kg 26,450.00 529.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.040 Oh 55,000.00 2,200.00
~ Tukang Cat 0.040 Oh 70,000.00 2,800.00
~ Kepala Tukang 0.004 Oh 85,000.00 340.00
~ Mandor 0.0025 Oh 100,000.00 250.00
2 1 m 2 Pengecatan bidang kayu lama 18,300.05
- Cat Kayu 0.142 Kg 55,000.00 7,810.00
- Minyak cat 0.019 Lt 26,450.00 502.55
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
3 1 m 2 Pengecatan bidang kayu baru 35,402.50
- Cat Kayu 0.260 Kg 55,000.00 14,300.00
- Plamir 0.150 Kg 31,600.00 4,740.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
4 1 m 2 Pengecatan besi baru 37,127.50
- Cat besi Emco 0.260 Kg 55,000.00 14,300.00
- Cat Meni 0.200 Kg 31,700.00 6,340.00
- Kertas gosok 0.010 Lbr 3,500.00 35.00
- Plamir 0.150 Kg 43,100.00 6,465.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
5 1 m 2 Pengecatan besi Finishing baru (Tanpa Cat dasar) 20,235.00
- Cat besi Emco Finishing ( 3 Lapis ) 0.260 Kg 55,000.00 14,300.00
- Upah Pekerjaan
~ Pekerja 0.035 Oh 55,000.00 1,925.00
~ Tukang Cat 0.053 Oh 70,000.00 3,710.00
~ Kepala Tukang 0.0020 Oh 85,000.00 170.00
~ Mandor 0.0013 Oh 100,000.00 130.00
6 1 m 2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter 11,822.50
- Residu atau Ter 0.350 Ltr 16,350.00 5,722.50
- Upah Pekerjaan
~ Pekerja 0.100 Oh 55,000.00 5,500.00
~ Mandor 0.006 Oh 100,000.00 600.00
7 1 m 2 Pelaburan Bidang Kayu dengan Politur 37,622.40
- Politur 0.372 Ltr 66,700.00 24,812.40
- Ampelas 2.000 Lbr 3,500.00 7,000.00
- Upah Pekerjaan
~ Tukang Cat 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00
8 1 m 2 Pelaburan Bidang Kayu dengan Vernis 37,195.00
- Vernis 0.150 Ltr 88,550.00 13,282.50
- Dempul 0.050 Kg 35,600.00 1,780.00
- Ampelas 0.100 Lbr 3,500.00 350.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.160 Oh 55,000.00 8,800.00
~ Tukang Cat 0.160 Oh 70,000.00 11,200.00
~ Kepala Tukang 0.016 Oh 85,000.00 1,360.00
~ Mandor 0.0025 Oh 100,000.00 250.00

HSPK 2013 Kota Probolinggo 186


1 2 3 4 5 6 7
9 1 m 2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis cat Penutup) 30,925.50
- Plamir 0.100 Kg 23,100.00 2,310.00
- Cat Dasar 0.100 Kg 62,000.00 6,200.00
- Cat Penutup 2x 0.260 Kg 62,000.00 16,120.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.063 Oh 70,000.00 4,410.00
~ Kepala Tukang 0.0063 Oh 85,000.00 535.50
~ Mandor 0.0025 Oh 100,000.00 250.00
10 1 m 2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar, 2 x pengecatan) 23,687.00
- Cat Dasar 0.120 Kg 62,000.00 7,440.00
- Cat Penutup 2x 0.180 Kg 62,000.00 11,160.00
- Upah Pekerjaan
~ Pekerja 0.028 Oh 55,000.00 1,540.00
~ Tukang Cat 0.042 Oh 70,000.00 2,940.00
~ Kepala Tukang 0.0042 Oh 85,000.00 357.00
~ Mandor 0.0025 Oh 100,000.00 250.00
11 1 m 2 Pengecatan permukaan baja dengan meni besi 21,142.50
- Meni Besi 0.100 Kg 31,700.00 3,170.00
- Kuas 0.010 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.200 Oh 70,000.00 14,000.00
~ Kepala Tukang 0.020 Oh 85,000.00 1,700.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
12 1 m 2 Pengecatan Genteng Baru 22,062.50
- Cat 0.300 Kg 34,500.00 10,350.00
- Kuas 0.100 Bh 17,250.00 1,725.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
13 1 m 2 Coating transparan (doff) untuk batu alam 23,960.00
- Coating 0.2000 Ltr 69,000.00 13,800.00
- Kuas 0.0100 Bh 17,250.00 172.50
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
14 1 m 2 Coating Waterproffing 117,395.00
- Waterproffing 0.6000 Kg 46,000.00 27,600.00
- Serabut Kasa 1.0000 m2 69,000.00 69,000.00
- Upah Pekerjaan
~ Pekerja 0.1200 Oh 55,000.00 6,600.00
~ Tukang Cat 0.0800 Oh 70,000.00 5,600.00
~ Kepala Tukang 0.0070 Oh 85,000.00 595.00
~ Mandor 0.0800 Oh 100,000.00 8,000.00
15 1 m 2 Coating Waterproffing tanpa serabut kasa 23,787.50
- Waterproffing 0.3000 Kg 46,000.00 13,800.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Cat 0.075 Oh 70,000.00 5,250.00
~ Kepala Tukang 0.0075 Oh 85,000.00 637.50
~ Mandor 0.0025 Oh 100,000.00 250.00
16 1 m2. Lapis melamin duco (2x lapis sampai rata) 253,306.15
- Cat Titan lux 0.500 kg 90,300.00 45,150.00
- Kertas gosok no. 150 1.000 lbr 3,500.00 3,500.00
- Clear 0.200 kg 65,900.00 13,180.00
- Thinner A 0.837 ltr 26,450.00 22,138.65
- Alat
- Sewa alat bantu @ 3 alat 1.00 set 10,000.00 10,000.00
- Sewa compresor 0.625 jam 134,900.00 84,312.50
- Upah Pekerjaan
- Pekerja Terampil 0.075 Oh 55,000.00 4,125.00
- Tukang cat 0.9 Oh 70,000.00 63,000.00
- Kepala tukang cat 0.09 Oh 85,000.00 7,650.00
- Mandor 0.0025 Oh 100,000.00 250.00

HSPK 2013 Kota Probolinggo 187


1 2 3 4 5 6 7
17 1 m 2 Pengecatan Weathershield 40,420.50
- Plamir 0.100 Kg 17,250.00 1,725.00
- Cat Weathershield 0.100 Kg 90,000.00 9,000.00
- Cat Penutup 2x 0.260 Kg 90,000.00 23,400.00
- Upah Pekerjaan
~ Pekerja 0.020 Oh 55,000.00 1,100.00
~ Tukang Cat 0.063 Oh 70,000.00 4,410.00
~ Kepala Tukang 0.0063 Oh 85,000.00 535.50
~ Mandor 0.0025 Oh 100,000.00 250.00

XI PEKERJAAN SANITAIR
1 Memasang 1 buah kloset duduk / monoblok 2,336,285.00
- Kloset duduk / monoblok 1.000 Bh 1,945,000.00 1,945,000.00
- Perlengkapan 0.060 hrg 1,945,000.00 116,700.00
- Upah Pekerjaan
~ Pekerja 3.300 Oh 55,000.00 181,500.00
~ Tukang Batu 1.100 Oh 70,000.00 77,000.00
~ Kepala Tukang 0.001 Oh 85,000.00 85.00
~ Mandor 0.160 Oh 100,000.00 16,000.00
2 Memasang 1 buah kloset jongkok porselen 439,874.00
- Kloset jongkok porselen 1.000 Bh 126,500.00 126,500.00
- Semen portland 6.000 Kg 1,495.00 8,970.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.500 Oh 70,000.00 105,000.00
~ Kepala Tukang 1.500 Oh 85,000.00 127,500.00
~ Mandor 0.160 Oh 100,000.00 16,000.00
3 Memasang 1 buah urinoir 1,427,374.00
- Urinoir 1.000 Bh 980,000.00 980,000.00
- Perlengkapan 0.300 hrg 980,000.00 294,000.00
- Semen portland 6.000 Kg 1,495.00 8,970.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.000 Oh 55,000.00 55,000.00
~ Tukang Batu 1.000 Oh 70,000.00 70,000.00
~ Kepala Tukang 0.100 Oh 85,000.00 8,500.00
~ Mandor 0.100 Oh 100,000.00 10,000.00
4 Memasang 1 buah wastafel 527,124.00
- Wastafel 1.000 Bh 300,000.00 300,000.00
- Perlengkapan 0.120 hrg 300,000.00 36,000.00
- Semen portland 6.000 Kg 1,495.00 8,970.00
- Pasir pasang 0.010 M3 90,400.00 904.00
- Upah Pekerjaan
~ Pekerja 1.200 Oh 55,000.00 66,000.00
~ Tukang Batu 1.450 Oh 70,000.00 101,500.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.010 Oh 100,000.00 1,000.00
5 Memasang 1 buah bak cuci stainless 455,350.00
- Bak cuci stainless 1.000 Bh 400,000.00 400,000.00
- Water drain dan accessories 1.000 set 30,000.00 30,000.00
- Upah Pekerjaan
~ Pekerja 0.030 Oh 55,000.00 1,650.00
~ Tukang Batu 0.300 Oh 70,000.00 21,000.00
~ Kepala Tukang 0.030 Oh 85,000.00 2,550.00
~ Mandor 0.0015 Oh 100,000.00 150.00
6 Memasang 1 buah bak mandi fiber glass 1,617,718.80
- Bak fiberglass 1.000 Bh 1,078,660.00 1,078,660.00
- Perlengkapan 0.180 hrg 1,078,660.00 194,158.80
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 70,000.00 189,000.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00
7 Memasang 1 pintu KM PVC 661,150.00
- Pintu PVC 1.000 Bh 316,250.00 316,250.00
- Upah Pekerjaan
~ Pekerja 1.800 Oh 55,000.00 99,000.00
~ Tukang Batu 2.700 Oh 70,000.00 189,000.00
~ Kepala Tukang 0.540 Oh 85,000.00 45,900.00
~ Mandor 0.1100 Oh 100,000.00 11,000.00

HSPK 2013 Kota Probolinggo 188


1 2 3 4 5 6 7
8 Pasang Buis Beton U 20 49,517.50
- Buis Beton 1.000 M 42,570.00 42,570.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 70,000.00 2,450.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.0035 Oh 100,000.00 350.00
9 Pasang Buis Beton U 30 58,757.50
- Buis Beton 1.000 M 51,810.00 51,810.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 70,000.00 2,450.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00
10 Pasang Buis Beton O 20 41,947.50
- Buis Beton 1.000 M 35,000.00 35,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 70,000.00 2,450.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00
11 Pasang Buis Beton O 30 57,947.50
- Buis Beton 1.000 M 51,000.00 51,000.00
- Upah Pekerjaan
~ Pekerja 0.070 Oh 55,000.00 3,850.00
~ Tukang Batu 0.035 Oh 70,000.00 2,450.00
~ Kepala Tukang 0.0035 Oh 85,000.00 297.50
~ Mandor 0.004 Oh 100,000.00 350.00
12 Memasang 1 buah kran diameter 3/4" atau 1/2" 58,486.25
- Kran air 1.000 Bh 49,500.00 49,500.00
- Seal Tape 0.025 Bh 3,450.00 86.25
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.010 Oh 85,000.00 850.00
~ Mandor 0.005 Oh 100,000.00 500.00
13 Memasang 1 m' pipa PVC diameter 0,5" (AW) 15,611.25
- Pipa PVC 1.000 M' 6,475.00 6,475.00
- Perlengkapan 0.350 Hrg 6,475.00 2,266.25
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00
14 Memasang 1 m' pipa PVC diameter 3/4" (AW) 17,551.88
- Pipa PVC 1.000 M' 7,912.50 7,912.50
- Perlengkapan 0.350 Hrg 7,912.50 2,769.38
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00
15 Memasang 1 m' pipa PVC diameter 1" (AW) 20,454.38
- Pipa PVC 1.000 M' 10,062.50 10,062.50
- Perlengkapan 0.350 Hrg 10,062.50 3,521.88
- Upah Pekerjaan
~ Pekerja 0.036 Oh 55,000.00 1,980.00
~ Tukang Batu 0.060 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0018 Oh 100,000.00 180.00
16 Memasang 1 m' pipa PVC diameter 2" (AW) 46,788.75
- Pipa PVC 1.000 M' 27,025.00 27,025.00
- Perlengkapan 0.350 Hrg 27,025.00 9,458.75
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 70,000.00 6,300.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0027 Oh 100,000.00 270.00

HSPK 2013 Kota Probolinggo 189


1 2 3 4 5 6 7
17 Memasang 1 m' pipa PVC diameter 3" (AW) 82,034.38
- Pipa PVC 1.000 M' 49,312.50 49,312.50
- Perlengkapan 0.350 Hrg 49,312.50 17,259.38
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00
18 Memasang 1 m' pipa PVC diameter 4" (AW) 112,493.75
- Pipa PVC 1.000 M' 71,875.00 71,875.00
- Perlengkapan 0.350 Hrg 71,875.00 25,156.25
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00
19 Memasang 1 m' pipa PVC diameter 2" (D) 30,555.00
- Pipa PVC 1.000 M' 15,000.00 15,000.00
- Perlengkapan 0.350 Hrg 15,000.00 5,250.00
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 70,000.00 6,300.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0027 Oh 100,000.00 270.00
20 Memasang 1 m' pipa PVC diameter 3" (D) 45,162.50
- Pipa PVC 1.000 M' 22,000.00 22,000.00
- Perlengkapan 0.350 Hrg 22,000.00 7,700.00
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00
21 Memasang 1 m' pipa PVC diameter 4" (D) 61,025.00
- Pipa PVC 1.000 M' 33,750.00 33,750.00
- Perlengkapan 0.350 Hrg 33,750.00 11,812.50
- Upah Pekerjaan
~ Pekerja 0.081 Oh 55,000.00 4,455.00
~ Tukang Batu 0.135 Oh 70,000.00 9,450.00
~ Kepala Tukang 0.0135 Oh 85,000.00 1,147.50
~ Mandor 0.0041 Oh 100,000.00 410.00
22 Memasang 1 m' pipa galvanis diameter 1/2" 45,078.75
- Pipa Galvanis 1.000 M' 23,958.33 23,958.33
- Perlengkapan 0.350 Hrg 23,958.33 8,385.42
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 70,000.00 6,300.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00
23 Memasang 1 m' pipa Galvanis diameter 3/4" 51,547.50
- Pipa Galvanis 1.000 M' 28,750.00 28,750.00
- Perlengkapan 0.350 Hrg 28,750.00 10,062.50
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 70,000.00 6,300.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00
24 Memasang 1 m' pipa Galvanis diameter 1" 70,953.75
- Pipa Galvanis 1.000 M' 43,125.00 43,125.00
- Perlengkapan 0.350 Hrg 43,125.00 15,093.75
- Upah Pekerjaan
~ Pekerja 0.054 Oh 55,000.00 2,970.00
~ Tukang Batu 0.090 Oh 70,000.00 6,300.00
~ Kepala Tukang 0.0090 Oh 85,000.00 765.00
~ Mandor 0.0270 Oh 100,000.00 2,700.00
25 Memasang 1 m' pipa Galvanis diameter 1 1/2" 107,955.00
- Pipa Galvanis medium 1.000 M' 64,700.00 64,700.00
- Perlengkapan 0.350 Hrg 64,700.00 22,645.00
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 70,000.00 12,600.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00

HSPK 2013 Kota Probolinggo 190


1 2 3 4 5 6 7
~ Mandor 0.0054 Oh 100,000.00 540.00

HSPK 2013 Kota Probolinggo 191


1 2 3 4 5 6 7
26 Memasang 1 m' pipa Galvanis diameter 2" 139,635.00
- Pipa Galvanis Medium 1.000 M' 88,166.67 88,166.67
- Perlengkapan 0.350 Hrg 88,166.67 30,858.33
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 70,000.00 12,600.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00
27 Memasang 1 m' pipa Galvanis diameter 2 1/2" 169,391.25
- Pipa Galvanis tebal 1.000 M' 110,208.33 110,208.33
- Perlengkapan 0.350 Hrg 110,208.33 38,572.92
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 70,000.00 12,600.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00
28 Memasang 1 m' pipa Galvanis diameter 3" 213,378.75
- Pipa Galvanis tebal 1.000 M' 142,791.67 142,791.67
- Perlengkapan 0.350 Hrg 142,791.67 49,977.08
- Upah Pekerjaan
~ Pekerja 0.108 Oh 55,000.00 5,940.00
~ Tukang Batu 0.180 Oh 70,000.00 12,600.00
~ Kepala Tukang 0.0180 Oh 85,000.00 1,530.00
~ Mandor 0.0054 Oh 100,000.00 540.00
29 Memasang 1 m' pipa Galvanis diameter 4" 307,805.00
- Pipa Galvanis tebal 1.000 M' 208,916.67 208,916.67
- Perlengkapan 0.350 Hrg 208,916.67 73,120.83
- Upah Pekerjaan
~ Pekerja 0.135 Oh 55,000.00 7,425.00
~ Tukang Batu 0.225 Oh 70,000.00 15,750.00
~ Kepala Tukang 0.0225 Oh 85,000.00 1,912.50
~ Mandor 0.0068 Oh 100,000.00 680.00
30 1 Unit Septictank ( h = 1,7 m , L = 1,3 m , P = 2,15 m ) 3,539,448.75
- Galian Tanah 5.752 m3 80,000.00 460,160.00
- Pas. batu bata tebal 1/2 bata, 1 : 3 16.105 m2 100,000.00 1,610,500.00
- Plesteran t = 15 mm, 1Pc : 3Ps 17.005 m2 60,000.00 1,020,300.00
- Pas. Pipa Pembuangan gas PVC 2" 1.000 m1 46,788.75 46,788.75
- Pek. Beton Bertulang K 175 0.309 m3 1,300,000.00 401,700.00
31 1 Unit Resapan ( h = 2,1 m diameter 1,9 m) 2,527,190.00
- Galian Tanah 5.990 m3 80,000.00 479,200.00
- Pas. batu bata kosong tebal 1 bata 6.396 m2 - -
- Pas. batu bata tebal 1 bata, 1 : 5 4.884 m2 200,000.00 976,800.00
- Plesteran t = 15 mm, 1Pc : 3Ps 4.884 m2 60,000.00 293,040.00
- Pas. Pipa Pembuangan gas PVC 2" 2.000 m1 50,000.00 100,000.00
- Pek. Beton Bertulang K 175 0.418 m3 1,300,000.00 543,400.00
- Kerikil Bulat 2 - 3 cm 0.500 m3 149,500.00 74,750.00
- Ijuk 6.000 kg 10,000.00 60,000.00
32 Memasang 1 bh Floor drain
- Floor drain stainless 1.000 Bh 74,750.00 74,750.00 83,650.00
- Upah Pekerjaan
~ Pekerja 0.010 Oh 55,000.00 550.00
~ Tukang Batu 0.100 Oh 70,000.00 7,000.00
~ Kepala Tukang 0.0100 Oh 85,000.00 850.00
~ Mandor 0.0050 Oh 100,000.00 500.00

Bata merah 1,176.00 bh 550.00 646,800.00


Pasir pasang 1.410 m3 100,000.00 141,000.00
Pasir Lumajang 0.170 m3 130,000.00 22,100.00
Semen / PC 567.200 kg 1,397.50 792,662.00
Pipa PVC Ø 4 " 6.000 m1 25,312.50 151,875.00
Pipa PVC Ø 1 " 2.250 m1 6,500.00 14,625.00
Besi beton 37.400 kg 9,500.00 355,300.00
Bendrat 0.560 kg 17,500.00 9,800.00
Batu pecah lokal 2/3 0.280 m3 144,400.00 40,432.00
Kayu hutan papan 0.042 m3 850,000.00 35,700.00
Paku 0.416 kg 15,000.00 6,240.00
Triplek 0.671 lbr 75,600.00 50,727.60
Kayu hutan balok 0.044 m3 850,000.00 37,400.00
- Upah Pekerjaan
~ Pekerja 26.891 Oh 55,000.00 1,479,005.00
~ Tukang Batu 7.490 Oh 70,000.00 524,300.00
~ Kepala Tukang 0.750 Oh 85,000.00 63,750.00

HSPK 2013 Kota Probolinggo 192


1 2 3 4 5 6 7
~ Mandor 1.840 Oh 100,000.00 184,000.00

31 1 UNIT RESAPAN ( h = 2 m , L = 1 m ) 4,555,716.60


Bata merah 784.00 bh 550.00 431,200.00
Pasir pasang 0.352 m3 100,000.00 35,200.00 1,580,581.75
Pasir beton 0.072 m3 130,000.00 9,360.00
Kerikil bulat 2-3 cm 0.200 m3 124,000.00 24,800.00
Semen / PC (40 kg) 162.000 kg 1,397.50 226,395.00
Pipa PVC Ø 4 " 1.500 m1 25,312.50 37,968.75
Besi beton 12.500 m1 9,500.00 118,750.00
Bendrat 0.160 kg 17,500.00 2,800.00
Batu pecah lokal 2/3 0.070 kg 144,400.00 10,108.00
Kayu hutan papan 0.0104 m3 850,000.00 8,840.00
Paku 0.104 m3 15,000.00 1,560.00
Triplek 0.3472 lbr 75,600.00 26,250.00
Kayu hutan balok 0.016 m3 850,000.00 13,600.00
Ijuk 5.000 kg 7,500.00 37,500.00
- Upah Pekerjaan
~ Pekerja 7.700 Oh 55,000.00 423,500.00
~ Tukang Batu 1.500 Oh 70,000.00 105,000.00
~ Kepala Tukang 0.150 Oh 85,000.00 12,750.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
5 1 m2 Pasang Paving K 100 abu-abu
- Paving stone K 100 abu-abu 1.000 M2 38,400.00 38,400.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00 78,800.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
6 1 m2 Pasang Paving K 100 warna
- Paving stone K 100 warna 1.000 M2 44,400.00 44,400.00
- Pasir Garuk 0.100 M3 70,000.00 7,000.00
- Pasir Lumajang 0.0075 M3 120,000.00 900.00 84,800.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
7 1 m2 Pasang Uskup K 300 abu-abu 151,940.00
- Uskup 23.000 Bh 4,800.00 110,400.00
- Pasir Pasang 0.100 M3 90,400.00 9,040.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
8 1 m2 Pasang Uskup abu-abu lokal 124,340.00
- Uskup 23.000 Bh 3,600.00 82,800.00
- Pasir Pasang 0.100 M3 90,400.00 9,040.00
- Upah Pekerjaan
~ Pekerja 0.500 Oh 55,000.00 27,500.00
~ Mandor 0.050 Oh 100,000.00 5,000.00
7 1 m1 Pasang Kanstin 10,20,50 89,334.71
- Kanstin 2.000 Bh 33,000.00 66,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 50,000.00 300.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00
8 1 m1 Pasang Kanstin 10,30,50 89,334.71
- Kanstin 2.000 Bh 33,000.00 66,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
~ Tukang Batu 0.06 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 50,000.00 300.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00
9 1 m1 Pasang Kanstin 15,20,50 86,544.71
- Kanstin K200 2.000 Bh 31,500.00 63,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
- Upah Pekerjaan
~ Pekerja 0.2332 Oh 55,000.00 12,826.00
HSPK 2013 Kota Probolinggo 193
~ Tukang Batu 0.06 Oh 70,000.00 4,200.00
~ Kepala Tukang 0.006 Oh 85,000.00 510.00
~ Mandor 0.0228 Oh 100,000.00 2,280.00
10 1 m1 Pasang Kanstin 15,30,50 89,544.71
- Kanstin K200 2.000 Bh 33,000.00 66,000.00
- Semen Portland 0.154 kg 1,495.00 230.23
- Pasir Pasang 0.0387 M3 90,400.00 3,498.48
REKAP RENCANA ANGGARAN BIAYA (OE)

PEKERJAAN : PERENCANAAN GEDUNG KANTOR KP. SUMBEREJO - BOJONEGORO


TAHUN ANGGAR : 2018

JUMLAH
NO URAIAN - PEKERJAAN (RP)

I PEKERJAAN PERSIAPAN Rp 200,000


II PEKERJAAN TANAH DAN URUGAN Rp 2,947,826
III PEKERJAAN BETON BERTULANG Rp 24,554,671
IV PEKERJAAN PONDASI Rp 7,947,671
V PEK. PASANGAN & PLESTERAN Rp -
VI PEKERJAAN ATAP Rp -
VII PEKERJAAN KUSEN Rp 17,018,753
VIII PEKERJAAN CAT Rp -
IX PEKERJAAN LAMPU Rp 9,255,160

JUMLAH Rp 61,924,080.79
PPN 10 % Rp 6,192,408

Rp 68,116,489
STANDART SATUAN HARGA BAHAN 2018

HARGA
NO JENIS BAHAN SATUAN (Rp.)

1 2 3 4

I Jenis Bahan Bangunan Penutup Atap dan Plafond


1 Teakwood 122x244x4mm Lbr 159,390.00
2 Teakwood 110x210x4mm Lbr 110,880.00
3 Kalsi Board 120 x 240 x 4 mm Lbr 75,000.00
4 Gypsum board 120 x 240 cm t=9mm Lbr 100,000.00
5 Playwood tebal 9mm Lbr 155,000.00
6 Gypsum list profil lebar 15 cm Ljr 49,500.00

II Jenis Bahan Bangunan Menggunakan Kayu


1 Kayu kamper (balok) M³ 12,500,000.00
2 Kayu kamper (papan) M³ 17,353,050.00
3 Kayu kamper (usuk) M³ 13,642,200.00
4 Kayu kamper (reng) M³ 12,000,000.00
5 Kayu meranti (balok) M³ 4,550,000.00
6 Kayu meranti (papan) M³ 4,550,000.00
7 Kayu meranti (usuk) M³ 4,550,000.00
8 Kayu Papan (begesting) M³ 4,804,800.00
9 Kayu bengkirai balok M³ 12,824,900.00
10 Kayu bengkirai papan M³ 14,114,100.00
11 Kayu bengkirai usuk M³ 12,824,900.00
12 Dolken ayu O 8-10 cm/400 cm Bt 90,860.00
13 Kayu cetakan m3 948,750.00
14 Kayu Kruing (Balok) M³ 5,000,000.00
15 Kayu Kruing (Papan) M³ 5,000,000.00
16 Kayu Kruing (Usuk) M³ 5,000,000.00
17 List Kayu 2/4 Kamper Ljr 9,680.00
18 Kalsium Plank Uk.30 tbl 8mm m' 20,075.00
19 List Kayu Propil M' 40,700.00
20 Kayu Begesting M³ 3,850,000.00
29 Multipltks 0,9 mm 1.22 x 2.44 Lbr 110,000.00
30 HVL Lbr 999,020.00
31 Kayu Terentang M3 4,715,370.00
32 Kayu Acuan M3 3,753,750.00
33 Air Ltr 22.00

III Bahan Menggunakan Batu/Pasir & Semen


1 Batu bata merah bh 700.00
2 Batu Kali M3 150,000.00
3 Batu bobos uk. 10 x 20 x 1.5 cm M2 12,320.00
4 Pasir cor / beton M3 212,500.00
5 Batu pecah mesin 2-3 cm m3 ###
141,666.67
6 Pasir halus M3 ###
112,500.00
7 Pasir pasang M3 ###
112,500.00
8 Pasir urug M3 112,500.00
9 Gt.Lyr model kr.pilang bh 6,000.00
10 Bubung gt.Lyr model kr.pilang bh 7,000.00
11 Rangka Hollow 2 x 4 cm t=0,35mm Btg 60,000.00
12 Stifenner bh 6,000.00
13 Paku keling/sekrup Kg 28,500.00
15 Semen berwarna yiyitan Kg 40,300.00
17 Semen PC (Portland Cemen)/semen gresik ( 40 kg ) Zak ###
60,000.00
19 Semen putih Kg 3,960.00
20 Semen Nat Kg 19,140.00
22 Tanah uruk M3 202,180.00
24 Bahan Tanah Timbunan M3 17,100.00
25 Kerikil Bulat 2 - 3 cm M3 164,450.00

IV Bahan Menggunakan Besi / Logam


1 Besi begel / baut Kg 38,500.00
2 Besi beton polos Kg 13,000.00
3 Besi plat 4 x 8 tebal 2 mm Lbr 1,741,740.00
4 Almunium 3' x 7' x 4 mm Lbr 215,600.00
5 Besi plat bordes 4" x 8" tb. 3 mm Lbr 24,090.00
6 Besi plat strip 2.5" pj.8mm Lonjor 174,130.00
7 Besi siku L. 70 . 70 . 7 Kg 19,250.00
8 Besi siku L. 40 . 40 .4 Kg 19,250.00
9 Besi steinliss steel Kg 28,820.00
10 Besi Strip Kg 28,820.00
11 Canal C. Kg 19,250.00
12 Kawat baja hitam 10 mm Kg 41,910.00
13 Kawat harmonika M2 52,250.00
14 Kawat ikat beton Kg 17,800.00
15 Kawat nyamuk kasa alumunium M2 44,770.00
16 Kawat duri pagar Kg 36,960.00
17 Kawat nyamuk kasa plastik M2 25,850.00
18 Elektroda stainless Kg 407,880.00
19 Elektrode baja Kg 52,800.00
20 Kusen aluminium Coklat 4" M1 163,680.00
21 Kusen aluminium Coklat 2.5" M1 137,500.00
22 Sealent Tube 7,590.00
23 Pintu + Kusen PVC Unit 548,680.00
24 Jarum keras Ø 8 mm Bh 65,780.00
25 Daun jendela Casmen non kaca M2 1,475,760.00
26 daun jendela Aluminium Warna Silver 4/10 M1 103,950.00
27 daun jendela Aluminium Warna Coklat 4/10 M1 109,780.00
28 Mur baut 1/2", 5/8", 7/5" Kg 39,380.00
29 Kawat Beton Kg 17,000.00

V Bahan untuk lantai


2 Kanstin 14 x 25 x 40 cm Bh 22,110.00
3 Paving Uskup ( Pengunci) Bh 5,060.00
4 Keramik 30 x 30 cm Warna KW 1 m2 66,000.00
6 Tegel keramik 40 x 40 (motif / warna) m2 120,000.00
8 Tegel list dinding 5x20 Bh 4,950.00
9 Tegel keramik 20 x 25 (dinding) Bh 95,000.00
10 Batu lempeng jember acak M2 81,070.00
15 Batu Alur Cetak M2 115,500.00
16 Kolplint Lantai 8 / 40 Bh 5,720.00
VI Bahan untuk pengecatan
1 Cat besi emco Kg 80,000.00
2 Cat kayu emco Kg 80,000.00
3 Cat meni (besi/kayu) cap pedang Kg 44,330.00
4 Cat Coating Kg 75,900.00
5 Meni A Kg 47,300.00
6 Meni B Kg 29,480.00
7 Cat tembok (Catilax) Kg 62,000.00
8 Cat tembok (mowilex) Kg 101,200.00
9 Cerelak Kg 534,270.00
13 Minyak Begesting Ltr 3,960.00
16 Kertas gosok Lmbr 5,830.00
17 Plamur tembok Galon 115,500.00
18 Plamur kayu Kg 38,610.00
19 Plamur Besi Kg ###
51,700.00
22 Lem Kg 18,150.00
23 Thinner B / minyak cat Ltr 29,700.00
24 Soda Api Kg 59,070.00
25 Sabun Kg 40,480.00
26 Teak Oil Ltr 32,340.00
27 Residu Ltr 23,320.00
28 Kuas Bh 17,500.00
30 Serabut Kasa M2 69,000.00

VII Bahan Penggantung Dan Pengunci


1 Engsel H Setel 31,460.00
2 Engsel kuningan ARCH asli Setel 105,105.00
3 Engsel Jendela Setel 29,810.00
4 Hak Angin Setel 37,950.00
5 Engsel Pintu Setel 50,380.00
6 Grendel Bh 19,800.00
7 Grendel biasa (besar) Bh 30,339.10
8 Grendel biasa (kecil) Bh 15,170.10
9 Grendel kuningan / cromm (kecil) Bh 22,754.60
10 Grendel tanam Bh 124,391.30
11 Kunci gembok besar Bh 75,848.30
12 Kunci gembok sedang Bh 53,093.70
13 Kunci tanam -808 Bh 154,097.90
14 Kunci tanam besar kupu tarung Bh 177,805.10
15 Kunci tanam antik Bh 414,877.10
16 Kunci tanam kamar mandi Bh 91,850.00
17 Kunci silinder Bh 177,805.10
18 Kunci selot (Cap Kuda terbang 2 x putaran) Bh 213,400.00
19 Sponeng m' 25,300.00
20 Kunci lemari Bh 37,070.00
21 Hak angin 4 mm (lurus) Bh 7,112.60
22 Hak angin (sikutan) Setel 25,300.00
23 Hak angin lurus (bisa disetel maju/mundur) Setel 110,014.30
24 Kait angin Bh 35,200.00
25 Dor closer Bh 466,840.00
26 Dor stop Bh 50,380.00
27 Rel pintu dorong Bh 529,760.00
28 Door Holder hias Unit 209,000.00
VIII Bahan untuk KM / WC / Urinoir
1 Pipa / slang spiral saluran kran Set 127,600.00
2 Closet duduk putih porselin komplit Bh 1,945,000.00
3 Closet jongkok porselin warna putih Bh 212,375.90
4 Closet jongkok teraso Bh 214,500.00
5 Closet jongkok INA Bh 262,900.00
6 Kran air Bh 49,500.00
7 Watermur Bh 67,540.00
8 Westafel besar warna Bh 620,579.00
9 Rol TBA Roll 11,377.30
10 Sifon wasser Set 196,240.00
11 Water drain + Assesoris Set 195,585.50
12 Bak fiberglass Bh 1,078,660.00
13 Bak cuci stainless steel Bh 400,000.00
14 Urinoir Bh 2,964,280.00
15 Tempat sabun Bh 38,500.00
16 Floor drain Bh 40,150.00
17 Avour Stenlless Bh 50,930.00
18 Seal Tape bh 4,400.00

IX Bahan Jenis Kaca


1 Kaca polos tb. 3 mm M2 153,340.00
2 Kaca polos tb. 5 mm rayben M2 200,000.00
3 Kaca polos tb. 8 mm M2 265,469.60
4 Kaca Tempered polos tb. 12 mm M2 935,000.00

X Bahan Beton Cetakan


1 Bahan roster klingker warna merah Bh 10,450.00
2 Buis beton diameter 20 cm Bh 44,330.00
3 Buis beton diameter 30 cm Bh 63,470.00
4 Buis Beton U 20 cm Bh 42,570.00
5 Buis Beton U 30 cm Bh 51,810.00
6 Tandon air feber Glas kapasitas 700 L Bh 1,271,270.00
7 Tandon air feber Glas kapasitas 1000 L Bh 1,733,490.00
8 Roster/Krawang 12 x 11 x 24 cm Bh 8,030.00

XI Bahan plastik Pipa PVC


1 Keni PVC 2" Bh 17,380.00
2 Klem PVC Bh 10,340.00
3 Pipa paralon 5/8" Lonjor 17,710.00
4 Pipa PVC 1/2" panjang 4.00 mt (maspion) M1 25,000.00
5 Pipa PVC 2" panjang 4.00 mt (maspion) M1 90,000.00
6 Pipa PVC 3" panjang 4.00 mt (maspion) M1 181,610.00
7 Pipa PVC 3/4" panjang 4.00 mt (maspion) M1 71,280.00
8 Pipa PVC 4" panjang 4.00 mt (maspion) M1 275,000.00
9 Pipa PVC 5" panjang 4.00 mt (maspion) M1 253,880.00

XII Bahan Jenis Paku


1 Paku Usuk/reng Kg 16,425.00
2 Paku seng payung Kg 36,960.00
3 Paku skrup 2'' Dos 55,440.00
4 Paku triplek Kg 33,770.00
5 Sekerup fixer Bh 1,760.00
6 Paku Pancing Bh 3,520.00
7 Paku Sekrup 3.5'' Dos 110,880.00
8 Paku Keling 3/4''.5/8''.7/8'' Kg 32,340.00

XIII Bahan-Bahan Peralatan Listrik


1 Capasito Sx 135 W 20 MF/250 V Bh 176,220.00
2 Capasito Sx 90 W 10 MF/250 V Bh 82,940.00
3 Faiting Flapon Bh 32,560.00
4 T Doos PVC Bh 6,820.00
5 Isolator Bh 1,870.00
6 Stop Kontak (Broco) Bh 48,180.00
7 Skakelar tunggal (broco) Bh 58,190.00
8 Skakelar ganda (broco) Bh 58,960.00
9 Skakelar / Handel Bh 51,700.00
10 sekering Lengkap Bh 141,570.00
11 Sekering SPA 60 Amp Bh 206,360.00
12 Las Doof Bh 770.00
13 Panel Box Bh 454,300.00
14 Main Swith Bh 358,820.00
15 Sekering MCB thermix 10-16 Amp Bh 37,070.00
16 Sekering MCB thermix 10 Amp Bh 37,070.00
17 Stater lampu TL Bh 8,580.00
18 Lampu Pijar 25/220 V Bh 80,850.00
19 Lampu XL 18 Watt/220 V bh 63,800.00
20 Lampu TL 20 W/220V Komplet balas Kaca (Philip) Bh 96,470.00
21 Lampu TL 40 W/220V Komplet balas Kaca (Philip) Bh 116,160.00
22 Kabel NYY 2x2,5 mm M1 6,050.00
23 Kap Down Light Kecil Bh 56,925.00

HARGA UPAH KERJA


1 Mandor Org/hr 110000
2 Kepala Tukang Kayu Org/hr 100000
3 Kepala Tukang Batu Org/hr 100000
4 Kepala Tukang Cat Org/hr 100000
5 Kepala Tukang Las Org/hr 100000
6 Kepala Tukang Besi Org/hr 100000
7 Kepala Tukang listrik Org/hr 100000
8 Tukang Kayu Org/hr 90000
9 Tukang Batu Org/hr 90000
10 Tukang Cat Org/hr 90000
11 Tukang Besi Org/hr 90000
12 Tukang Las Org/hr 90000
13 Tukang listrik Org/hr 90000
14 Pembantu Tukang / Pekerja Org/hr 80000