Professional Documents
Culture Documents
4new Specifications
4new Specifications
4new Specifications
September 2015
INDEX
1. The guidelines
These guidelines are for the purpose of project formulation, appraisal, financing and
disbursal of long term loans by REC under the Transmission & Distribution (T&D)
category.
These guidelines provides the framework for funding the creation of infrastructure and
system improvement of transmission, sub-transmission and distribution systems and
also covers the Renovation & Modernisation of the system to improve its operational
efficiency. It also supersedes all guidelines issued earlier in this regard viz. guidelines
for System Improvement Schemes, Guidelines for Bulk Loan Schemes, Guidelines for
Intensive Electrification and Guidelines for Special Project Agriculture (SPA), Financing
norms for transmission EHV & Guidelines for cancellation, withdrawal and closure of
schemes.
Distribution Projects are those projects which pertain to the utility involved in distribution
business (Discoms) in case of unbundled utilities. For integrated utilities/power
departments, projects pertaining to system voltages upto 66 KV will be classified as
distribution projects.
Transmission Projects are those projects which pertain to the utility involved in
transmission business (Transcos) in case of unbundled utilities. For integrated
utilities/power departments, projects pertaining to system voltages above 66 KV will be
classified as transmission projects.
3. Objectives
All projects will be covered under the two major categories of Transmission or
Distribution. Sub categories under each category are as below:
a) Distribution:
(iv) Projects approved under various Central Govt. Schemes e.g. R-APDRP,
DDUGJY, IPDS etc
(vi) Works relating to Energy Audit e.g. consultancy assignment for energy Audit,
implementation of recommendation of Energy Audit etc.(EA)
(ix) Financial assistance against Regulatory Assets as per REC policy for financing of
Regulatory Assets (RA). Detailed policy of financing against Regulatory Assets is
enclosed as Annexure-I.
(x) Equipment required for Research laboratories, testing facilities including mobile
testing facilities, Training Centers, Customer Care Centers.(Labs/testing/training
centre/Customer care)
(xi) Office/Residential buildings, buildings for training centres, customer care centres,
testing labs, stores etc subject to (i) utility certifying that the expenditure is part of
capital expenditure filed/being filed with regulator and (ii) mortgage of concerned
land in favour of REC (Buildings)
(xii) Any other works not covered above but fulfilling the objectives of these guidelines
as per merits of the case (Misc).
Note 1: The existing SPA category of scheme is being merged under the category- Infrastructure for
providing electricity access to various categories of Consumers including Agriculture (Intensive
Electrification).
Note 2: The abbreviations in brackets are for denoting the class category or sub category in ERP and for
internal use of REC.
b) Transmission:
(vii) Schemes related to innovation & best practices in transmission sector (Inn/BP)
(viii) Any other works not covered above but fulfilling the objectives of these
guidelines as per merits of the case (Misc).
Note: The abbreviations in brackets are for denoting the class category or sub category in ERP and
for internal use of REC.
a) The Detailed project report (DPR) for each proposal shall include (but not limited
to) the need & justification of the projects, objectives, detailed works with cost
along with the basis, details of execution with time frame, mode of execution,
status of administrative approval, requirement and status of regulatory/ statutory
and non- statutory approvals, land availability, details about involvement of forest
land and financial analysis.
b) For system improvement schemes, the formulation of the scheme by the utility
shall be done justifying the load growth, improvement of voltage regulation,
reduction of technical losses and to provide quality and reliable power to the
existing and prospective consumers. The parameters based on which the
schemes have been formulated and benefits envisaged to be accrued from the
implementation of the scheme, viz. additional sale, loss reduction etc. needs to
be indicated in the DPR. For other categories of schemes also, the benefits
envisaged to be accrued shall be suitably quantified and indicated.
c) The processing note of the project / zonal office shall be as per the format
enclosed at Annexure II.
e) Spares and T&P shall be considered as part of the project cost for sanction,
subject to the ceiling of 3% of the project cost (or as per CERC/SERC norms).
However, the disbursement shall only be considered against the identified spares
within the overall ceiling sanctioned.
j) In case of turnkey projects, if award cost(s) exceeds the sanctioned loan amount,
the utility has the option to request for enhancement of loan to meet the
increased award cost, which will be considered by REC within its policies and
guidelines. Or else, the reimbursement from REC would be restricted to the
sanctioned loan amount.
a) State Sector / CPSU / Govt. Sector: The grading shall be as per latest entity
grading circular issued by REC for determining exposure limits and interest rates.
If the utility is not covered in the circular, the grading shall be done on receipt of
proposal.
b) For identified CPSUs for which REC interest rate circular provides for special
grade and interest rate, entity grading shall not be required to be carried out
during approval of the projects.
c) Private Sector Distribution: The utility shall be reviewed and rated by Entity
Appraisal Division, on receipt of any proposal. The grading carried out shall be
valid for a period of one year.
d) State Governments/Power Departments- In case of loans to State
Governments and Power Departments directly under State Governments, interest
rates as applicable for A and B category would be applicable, even in case of
their grading being C. However, such borrowers who are graded as A+ will
continue to get the benefit of interest rate as applicable for A+ category.
However, for determining the maximum permissible exposure limit for such
borrowers, the actual grading would be applicable.
7. Cost data:
b) For partial turnkey projects (where works are awarded in different packages
and a portion of work is also executed departmentally): For the non-turnkey
portion of the project, the methodology as in departmental execution may be
used. For the turnkey portion, the actual award cost of the various packages may
be used. In case projects are not awarded at the time of posing the projects for
sanction, the last awarded rates or latest schedule of rates may be used for
formulation, with permitted escalation as per utility’s norms.
c) For total turnkey projects: The actual award cost of the various packages may
be used for formulation and sanction of the projects. In case projects are not
awarded at the time of posing the projects for sanction, the last awarded rates or
latest schedule of rates may be used for formulation, with permitted escalation as
per utility’s norms.
These guidelines shall be applicable for the private sector distribution projects in respect
of formulation of projects, appraisal, sanction, loan disbursement, documentation,
monitoring and closure etc. However, the private sector borrowers shall pay the
processing and upfront fees as applicable as per REC policy. Also, in case of private
sector borrowers, REC shall reserve the right to engage Lenders Legal Counsel,
Lenders Independent Engineers and Lenders Financial Advisors if found necessary, the
cost of which shall be borne by the borrower.
State and Central Sector borrowers are not required to pay any processing fees. Also,
they are not required to pay any upfront fees or commitment charges for loans
sanctioned up to Rs.500 crores. However, for loans sanctioned beyond Rs.500 crores,
the state/central sector borrowers have the option to pay either upfront fees (0.1% of
loan amount) or commitment charges at rates as per prevalent policies of REC in this
regard. The commitment charges would be applicable on the extent of under drawal
from the quarterly drawal schedule furnished by the borrower, initially at the time of
documentation and subsequently before the start of every FY.
Private sector borrowers are required to pay processing fee at the rate of 0.1% of the
loan amount (subject to a minimum of Rs.5 lakhs and maximum of Rs.30 lakhs). 50% of
the processing fee has to be paid at the time of submission of loan proposal. Balance
50% shall be paid before issue of sanction letter. Private sector borrowers shall also pay
upfront fee at the rates as below depending on their grading:
a) The projects shall invariably be formulated by the utilities on the basis of the
purchase orders placed for the equipment. The cost of the equipment considered
shall be the FOR stores rate (supply rate plus freight plus insurance). If there is a
variation in the cost adopted in the project compared to the rates as above,
borrowing utility shall give reasons for the same in the DPR. The eligible project
cost under these schemes is only the cost of the material/equipment, however,
the last 10% of material/equipment cost shall be released after the utility certifies
that the equipment has been installed.
b) Where the utilities have not yet placed the purchase order for the equipment at
the time of formulation, the cost as per the latest purchase orders can be
d) Utility shall provide a certificate that equipment proposed to be funded under this
category will not be financed under any other category of project financed from
REC/other lenders.
The annual ceiling for sanction under the category of Bulk procurement for each
utility shall be as follows:
In case of Single Discom like Maharashtra, West Bengal, Tamil Nadu etc. the limit for
Bulk loan shall be 150% of above applicable limits.
Execution of the project shall be completed within the project implementation period
agreed at the time of the sanction (maximum 3 years for all categories of Transmission
& Distribution projects). However, the project implementation period may be extended
beyond the agreed time if desired by the utility, by the competent authority as per latest
delegation of powers, amended from time to time. Project implementation period is
reckoned from the date of first release by REC and disbursements shall be made during
the implementation period (original or extended). However, for the works completed
during the implementation period, claims can be submitted by the utility up to three
months from the completion of the project.
The moratorium period for all T&D loans shall be three years from the date of first
disbursement, irrespective of the implementation period. However, higher moratorium
It is clarified that for (a) and (b) above, where the loan is already restricted to 90% of
the project cost, there may be no further reduction in case the security offered is
“Hypothecation of future assets”. Likewise, for (c), the loan will be restricted to 90%
if security is by way of hypothecation of future assets. In case of (d), as per
guidelines, the loan component is 30% of the project cost. However, if the utility
desires, the 10% of state/utility contribution can also given as REC loan.
Approval for deviation during the course of execution of the project shall be required
for change in scope of works, quantity and rate, within the overall sanctioned loan
amount and shall not be construed as approval for reduction in loan amount. All such
deviations needs to be technically justified, fulfilling the objectives of the project. The
project shall also continue to be viable as per stipulated norms, taking into account
the deviation.
Addition of new work not related to the project shall not be considered if it is with the
sole objective of compensating for the decrease in loan sanctioned due to deviations
as above.
Change in location of the sub stations & routes of lines, redistribution of works within
the Circle/ divisions/sub divisions and change in specification of material/equipment
used within the same item/class of work, if technically justified, and in line with the
In case the award cost of the project is less than the sanctioned project cost, only the
disbursement (in the same debt equity ratio) shall be restricted based on award and
further increase in cost due to Price Variation in award within the original sanction
shall not require any deviation approval. The changes shall be informed by P.O. /
Z.O. to the T&D Division and Claims Division.
Approval for deviation during the course of execution of the project shall be required
for change in quantity and/or rates of sanctioned equipment/material of a particular
specification beyond +/-25% of the original sanction, and for any addition of the
same equipment/material of new specification. The deviation shall be subject to loan
remaining within the overall sanctioned loan amount, and deviation approval shall
not be construed as approval for reduction in loan amount. Such deviations shall be
technically justified and required for fulfilling the objectives of the project. The
difference in sanctioned and invoice rate, as well as quantity within the limits of +/-
25% shall not be treated as deviation, subject to no increase in financial commitment
of REC.
c) Common for all schemes- Any increase in loan amount if required on account of
the deviations will be treated as request for additional loan and will be dealt with
accordingly.
The above tenure of loan shall also be applicable for Bulk Procurement and Installation
schemes under both categories.
b) If actual cost becomes higher than the sanctioned amount during execution, the
borrower will have the option to revise the project cost on the basis of actual
expenditure incurred and seek the approval of the corporation for revised project
cost, giving proper financial justification.
c) The undrawn portion of the loan including provision of cost escalation shall not be
considered for inclusion of additional works unrelated to the project.
Interest During Construction (IDC) shall be considered for sanction, irrespective of size
and quantum of loan of the project. The IDC shall be paid as per actuals and shall be
considered only if approval has been taken at the time of sanction.
The indicative methodology/format for calculating the benefits due to the project
and its financial viability is given in Annexure –III.
a) If no disbursement has been made against a scheme upto a period of one year
after documentation, the scheme shall be considered as non-starter, and ZO/PO
needs to follow up with the utility for either its cancellation, or for revival. In case
the ZO/PO is satisfied with the explanation/justification given by the utility that
progress will be made and reimbursement claims will be submitted by the
borrower, the scheme may be revived by ZM/CPM and reimbursement claims
admitted as and when received upto two years after documentation. However,
approval as per delegation of powers is required for revival of the scheme
wherein the first claim is not preferred even after a period of two years from
documentation.
c) In such schemes where utility has drawn mobilization advance, and has not
preferred any reimbursement claim for a period of one year after drawal of
mobilization advance, a notice shall be sent to the borrower by the ZO/PO to
refund the advance to REC, along with the applicable additional interest per
annum (as per latest REC circular in this regard), which will be applicable from
the date of drawal of first instalment. Alternatively, the utility needs to submit the
utilization of such advance against the project. If the utility wishes to continue the
scheme, the reasons with justification may be sent to competent authority as
defined in delegation of powers for not recalling the advance and permitting the
scheme to continue.
d) If the total mobilization advance (of all schemes of a utility) in which no progress
has been reported after a period of twelve months exceeds Rs.10 crore, the
same needs to be brought to the notice of the BOD, REC as per their directives.
19. Monitoring
The monitoring of T&D schemes (except Bulk Procurement) during implementation shall
be carried out in accordance with the approved Monitoring Guidelines for T&D schemes,
as amended from time to time. A copy of the same is enclosed as Annexure-IV.
The prepayment of term loan availed for projects under these guidelines shall be
governed by the prevalent policy of REC on prepayment.
All borrowers have various options/combinations of security defined in the REC loan
policy which can be chosen by them. However, loans to State Government and Power
Departments under State Governments are deemed to be Government Guaranteed,
and as such, no separate security is required to be given (hypothecation of assets, BG,
GG etc). However, the loan agreement shall contain a clause that the State Government
shall be responsible for the repayment of the loan, and the State Government needs to
make provision in the annual plan/budget of the Power Department towards loan
liabilities of REC, every year, till the entire loan is repaid.
The sanction terms and conditions shall be governed by Standard Sanction letter for
T&D schemes, in addition to any special conditions levied for the respective projects.
The loan documents shall be executed only if the utility is not in default.
(i) If the loan amount is more than Rs.100 crore, the mobilization advance shall
be limited to 10% of the loan amount.
(ii) In case of schemes where loan amount is more than Rs. 50 crore & up to
Rs.100 crore, the mobilization advance shall be limited to 15% of the loan
amount.
(iii) For schemes having a loan amount of less than Rs. 50 crore, the
mobilization advance shall be considered up to 20% of the loan amount.
d. In case of transmission projects with loan more than Rs.100 crores, and to be
implemented on partial turnkey/turnkey basis, and where there is no upfront
security available, REC shall consider to release loan for payment of
mobilization advance to the turnkey contractor by the borrower, governed by the
LoA/contract agreement with the turnkey contractor, subject to submission of
original invoice/proforma invoice or any other equivalent document for payment
of such advance to REC. The release of such advance by REC shall be made
directly to the contractor/supplier. Such mobilization advance shall be adjusted
against reimbursement claims of the respective supplier/contractor.
e. For GoI schemes where there is upfront release of loan/grant/subsidy from the
Govt of India, REC shall release the funds against the loan/counterpart funding,
based on the progress submitted by the utility, only after the expenditure against
the project has exceeded the amount disbursed by GoI for the project. The utility
shall certify that the amount disbursed by GOI has been utilized only for that
project for which it was given, at the time of submission of the first claim to REC.
g. In case of award cost(s) being less than the sanctioned cost, the reimbursement
from REC would be restricted to the invoice values raised by contractor and
reimbursed by the utility. There is no need to take any revised sanction or
reduce the loan amount from REC. IDC would be paid as per actuals over and
above the award cost if provided for in the sanction.
l. Physical progress made against the scheme within one year prior to actual
sanction, could be considered as permissible expenditure for reimbursement.
Also, for the works completed during the implementation period, claims can be
submitted by the utility upto three months from the completion of the project.
m.For bulk procurement and installation Schemes, the release would be up to 90%
of the invoice value of the equipment/material supplied, after pro-rata adjustment
of initial advance, if any. 10% of the retained individual invoice value, would be
released after the borrower certifies that equipment/material has actually been
installed in the field. Each claim shall also be supported by the following
documents:
i. The original invoice, along with a copy of the same, duly approved and
signed by the authorized officer of the Division/Circle of the Board/utility.
Invoice are to be certified by the authorized officer of the Division/ Circle of
the Utility/Board that the equipment/material have been duly received in
good order and have been issued or under issue to the field officer for
installation.
ii. A certificate from the authorized officer of the borrower that the
equipment/material, for which the claim is being lodged, have not been or
are not proposed to be financed from any other loan from REC or any
other funding agency, including the State Govt.
The original invoice will be returned to the borrower after the following certificate
is recorded prominently on each page of the same by the concerned CPM/ZM:
“All the material /equipment, under this invoice are being financed by the REC under scheme
code no.______."
d) The ZMs/CPMs have been delegated the powers for closure of all types of REC
schemes.
These guidelines stipulate the general guiding principles for REC and the borrowers.
Any specific policies of REC and terms and conditions of standard sanction letter shall
form a part of these guidelines and shall prevail over the stipulations in these guidelines
in case of any clarification. REC reserves the right to interpret any provisions of these
guidelines in consonance with its prevalent policies.
----------------------------
Board of Directors of REC approved the aforesaid policy in the 405 th meeting held on
15th July 2014. The salient features of the policy are as below:
1. Eligibility :
The funding against the regulatory assets shall be available only to
2. Purpose :
3. Basis of funding :
The funding shall be available only against the regulatory assets recognized
by the respective State Electricity Regulatory Commission (SERC) and
recovery schedule included in the tariff order.
Funding shall be available only against regulatory assets recognized in
previous three years' tariff orders.
A time bound recovery plan of the regulatory asset by SERC shall be in place.
A plan for recovery of carrying cost of the regulatory assets by SERC shall be
in place.
A business plan of the utility for turnaround of cash flow shall be in place and
made available to REC
The funding against regulatory assets shall be limited to the lowest of the
following amounts:
5. Rate of Interest :
The rate of interest shall be as per T&D rates applicable on the borrower
based on grade awarded in the State Grading Circular issued by REC time
to time. REC policy shall be applicable wherever grading is not available
for borrower.
For joint sector borrowers, a risk premium of 0.5% over and above the rate
applicable for T&D scheme shall be applicable.
The tenor of the loan for funding of Regulatory Assets shall not exceed the
amortization period allowed by the respective SERC subject to a maximum
tenor of 10 years.
7. Disbursement:
Disbursement shall be made within a period of not more than 3 months from the
date of the documentation.
9. Default Escrow:
The borrower shall create an Escrow account as per REC guidelines to facilitate
the repayment of payment obligations towards REC.
Additional Security
c) An undertaking will be given by the borrower that tariff petition for the
subsequent years i.e. after drawl of the loan will be filed before November 30,
every year during the tenor of the loan.
Sanctioning authority for Term Loan will be as per existing DoP with respect to
sanction of financial assistance for Term Loans.
In case of any query/clarification required with respect of the aforesaid Policy, the
same shall be decided by the CMD, REC and his decision shall be final.
4. Project Details:
5. Certification that no other agency is providing loan against this project and is not
covered under any govt scheme/ other projects sanctioned by REC or other FIs
6. For Bulk procurement projects: a certificate from utility that the equipments being
procured are not covered under financing from regular projects
7. Undertaking that the Cost estimates are acceptable to ZM/CPM and the project
has been prepared as per applicable T&D Guidelines.
8. The relaxations requested if any along with detailed justification may be outlined.
B. IRR Calculations
(Amount in Rs Lakhs)
Anticipated investment over 2/3 years(as per scheme Anticipated benefits
period) over 25 years
1 Year-I : 0%
2 Year-II : 40% Justified
3 Year-III : 60% Anticipated %
80%
100%
1. INTRODUCTION
REC is required to have an effective monitoring system for watching the progress of
Projects being financed by it. Monitoring is required to obtain feed back on the
physical and financial progress of the REC funded projects to take necessary steps
for taking timely action/remedial measures. Financing of REC projects is mainly
done on reimbursement basis and release of funds at different stages is also
required to be linked with the monitoring observations, as well as ensure creation of
assets which are offered as security for the projects.
2. OBJECTIVE
The main objectives of monitoring rural electrification schemes are to ensure the
following:
3. MONITORING
The sample size as above shall be maintained in totality over all the different types of
monitoring.
(ii) CPM shall carry out checks on at least 5% of the due schemes on random basis.
(iii) Final Monitoring of schemes where loan amount is more than Rs.500 crores would
preferably be done along with a representative of the Corporate Office. T&D Division at
CO may, however, monitor any of the sanctioned scheme at any stage for taking direct
feedback from the borrower.
FORMATS OF MONITORING
4. Category
5. Date of sanction
6. Date of Documentation
Period of scheme/ Scheduled date of
7.
completion
Extended date of completion, if
8.
applicable
9. Scheme cost (Rs. Lakh)
2. MONITORING DETAILS
2. Date of Monitoring
3-A Whether progress reported is higher than the progress as per last
claim. YES/ NO/ N.A.
5. DEFICIENCIES OBSERVED