Professional Documents
Culture Documents
PMP Presentation PDF
PMP Presentation PDF
PMP Presentation PDF
trainings@windowslive.com
0548 582 754
Abu Bakar Ahsen
• Education / Qualification
– BCS , M.IT
– PMP , RMP
– MCTS , MCPD
– Lean Six Sigma Green Belt + Black Belt
Certified
• Work Experience
– 16+ Years of Working & Project Management
Experience
– 170+ Project Management Workshops
– Already trained 6500+ Industry Professionals
trainings@windowslive.com
0548 582 754
You can become PMP , if
Graduation or Above Diploma Holders
Ref : www.pmi.org
trainings@windowslive.com
0548 582 754
PMP Examination Information
• Computer-based exam at a Prometric Test Center
• 200 Multiple Choice Questions
• Total time is 4 Hours
• All questions have 4 Options
• Of the 200 questions, 25 are considered pretest
questions and are not scored.
• 61.0% passing score ( 106 / 175 ) But may vary
depending upon your luck on that day ( Best case
scenario and worst case scenario )
trainings@windowslive.com
0548 582 754
Frequently Asked Questions (FAQs)
What is the cost of the PMP Exam?
PMI member = $405 Non-PMI member = $555
If I fail the PMP, what is the cost to retake the PMP
Exam?
PMI member = $275 Non-PMI member = $375
How many times can I take the PMP Exam?
You are granted a one-year eligibility period in which
to pass the examination. During the eligibility period,
you may take the examination up to three times.
When do I learn if I passed the PMP Exam?
On the spot result
trainings@windowslive.com
0548 582 754
Prometric Centers
• Medina
• Jeddah
• Riyadh
• Dammam
trainings@windowslive.com
0548 582 754
Cartoons Time
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Project Management Training Sources
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
Which of the following is NOT true of obtaining project plan approval?
a. Until you obtain plan approval, you don’t need to put changes to it
through change control.
b. Change control makes sure that only approved changes can make it into
the approved plan.
c. Only one person needs to approve the Project Management Plan and
that’s the Project Manager.
d. It’s important for the entire team to buy into the Project Management
Plan for it to be successful.
Answer: C
It’s not enough that the Project Manager approves of the Project Management Plan; it needs to be
approved by all of the stakeholders in the project. Everyone on the team should feel comfortable with the
processes that are going to be used to do the work.
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
You are the project manager for a railroad construction project. Your
sponsor has asked you for a forecast for the cost of project
completion. The project has a total budget of $80,000 and CPI of
.95. The project has spent $25,000 of its budget so far. How much
more money do you plan to spend on the project?
a. $59,210
b. $80,000
c. $84,210
d. $109,210
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
You are the project manager for a railroad construction project. Your
sponsor has asked you for a forecast for the cost of project
completion. The project has a total budget of $80,000 and CPI of
.95. The project has spent $25,000 of its budget so far. How much
more money do you plan to spend on the project?
a. $59,210
b. $80,000
c. $84,210
d. $109,210
Answer: A
This question is asking you to create a forecast using Estimate To Complete (ETC), which uses CPI (Cost
Performance Index) to project how much money is likely to be spent for the rest of the project. The first
step is to plug the numbers into the formula EAC = BAC / CPI, which yields EAC = $80,000 / .95 =
$84,210. That’s how much money you’re likely to spend on the project. Now you can figure out ETC =
EAC - AC = $84,210 - $25,000 = $59,210.
[BAC = Budget at Completion, EAC = Estimate at Completion, AC = Actual Cost]
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
Answer: A
It’s just easy to calculate the late finish (LF) of an activity in a network diagram. Look at the following
activity, take its LS (late start), and subtract one. If there’s more than one following activity, use the one
with the lowest LS. So for activity F in the question, the following activities are G, with an LS of 17, and H,
with an LS of 11. So the LF of F is 11 - 1 = 10.
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
There have been several rounds of layoffs at your company. Now your
project team is worried about their job security, and you’ve noticed
that their performance has decreased significantly because of it.
This is predicted by which motivational theory?
a. McGregor’s Theory of X and Y
b. Maslow’s Hierarchy of Needs
c. McLellands Achievement Theory
d. Herzberg’s Motivation-Hygiene Theory
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
There have been several rounds of layoffs at your company. Now your
project team is worried about their job security, and you’ve noticed
that their performance has decreased significantly because of it.
This is predicted by which motivational theory?
a. McGregor’s Theory of X and Y
b. Maslow’s Hierarchy of Needs
c. McLellands Achievement Theory
d. Herzberg’s Motivation-Hygiene Theory
Answer: B
Maslow’s Hierarchy of Needs says that people have needs, and until the lower ones (like acceptance
on the team, job safety or job security) are satisfied they won’t even begin to think about the higher
ones (fulfilling their potential and making a contribution).
trainings@windowslive.com
0548 582 754
Project Definition (PMI)
trainings@windowslive.com
0548 582 754
PROJECT MANAGEMENT
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Project Characteristics
Temporary
Have some objectives to meet.
Progressive Elaboration ( Means more details
become available with the passage of time)
Are done to
grab some opportunity,
market demand,
capacity building,
technological advancement
regulatory requirements.
trainings@windowslive.com
0548 582 754
KNOWLEDGE AREAS
•Scope Management
•Time Management
•Cost Management
•Quality Management
•HR Management
•Communication Management
•Risk Management
•Procurement Management
•Stakeholder Management
•Integration Management trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Scope Management
Processes required to ensure that the project includes all
the work required, and only the work required, to
complete the project successfully.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Cost Management
Describes the processes required to ensure that the
project is completed within the approved budget.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Quality Management
Describes the processes required to ensure that the
project will satisfy the needs for which it was
undertaken.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Human Resource Management
Describes the processes required to make the most effective use
of the people involved with the project.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Communications Management
Describes the processes required to ensure timely and
appropriate generation, collection, dissemination, storage, and
ultimate disposition of project information.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Risk Management
Describes the processes concerned with identifying,
analyzing, and responding to project risk.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Procurement Management
Describes the processes required to acquire goods
and services from outside the performing organization.
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Stakeholder Management
.
1. Identify Stakeholders
2. Plan Stakeholder Management
3. Manage Stakeholder Engagement
4. Control Stakeholder Engagement
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
• Project Integration Management
Processes required to ensure that the various elements of
the project are properly coordinated.
• Below are the process in Integration Management
Knowledge Area
1. Develop Project Charter
2. Develop Project Management Plan
3. Direct and Manage Project Execution
4. Monitor and Control Project Work
5. Perform Integrated Change Control
6. Close Project or Phase
trainings@windowslive.com
0548 582 754
Process Groups
trainings@windowslive.com
0548 582 754
Process Groups
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Thank You
trainings@windowslive.com
0548 582 754
WHAT IS Work Break Down Structure
(WBS) ?
What is an activity ?
trainings@windowslive.com
0548 582 754
How to calculate the project duration?
Using Critical Path Method
trainings@windowslive.com
0548 582 754
Simple Example:
Lets say we have two activities
a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm
trainings@windowslive.com
0548 582 754
Simple Example:
Flaot is the amount / duration by which you can delay an activity without affecting
the project target completion date.
trainings@windowslive.com
0548 582 754
Simple Example:
60 Minutes is the project duration. The path containing “make Biryani” is the critical
path, longest path, and the shortest duration in which you can complete this project
trainings@windowslive.com
and is called as critical path. 0548 582 754
Example Project
Activity Name Duration ( days) Predecessor
A 5 None
B 6 None
C 4 A
D 3 A
E 1 A
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
trainings@windowslive.com
0548 582 754
Network Diagram
start
trainings@windowslive.com
0548 582 754
Network Diagram
A D
start E
trainings@windowslive.com
0548 582 754
Network Diagram
C H
A D
G
start end
E F
trainings@windowslive.com
0548 582 754
Network Diagram
A E F
start end
C
H
B
trainings@windowslive.com
0548 582 754
Network Diagram
C H
A D
G
start end
E F
Path 1 A - D - G - I Path 3 A - C - H - I
Path 2 A – E - F - G - I Path 4 B - H - I
trainings@windowslive.com
0548 582 754
Network Diagram
C H
A D
G
start end
E F
trainings@windowslive.com
0548 582 754
Critical Path Method
Activity Duration
Name (Days) Predecessor ES EF LS LF Float
A 5 None
B 6 None
C 4 A
D 3 A
E 1 A
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
trainings@windowslive.com
0548 582 754
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5
B 6 None 1 6
C 4 A
D 3 A
E 1 A
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5
B 6 None 1 6
C 4 A 6
D 3 A 6
E 1 A 6
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5
B 6 None 1 6
C 4 A 6 9
D 3 A 6 8
E 1 A 6 6
F 4 E 7 10
G 14 D,F 11
H 12 B,C
I 2 G,H
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5
B 6 None 1 6
C 4 A 6 9
D 3 A 6 8
E 1 A 6 6
F 4 E 7 10
G 14 D,F 11 24
H 12 B,C 10 21
I 2 G,H 25 26
Backward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5
B 6 None 1 6
C 4 A 6 9
D 3 A 6 8
E 1 A 6 6
F 4 E 7 10
G 14 D,F 11 24
H 12 B,C 10 21
I 2 G,H 25 26 25 26
Backward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5 1 5
B 6 None 1 6 7 12
C 4 A 6 9 9 12
D 3 A 6 8 8 10
E 1 A 6 6 6 6
F 4 E 7 10 7 10
G 14 D,F 11 24 11 24
H 12 B,C 10 21 13 24
I 2 G,H 25 26 25 26
Backward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5 1 5
B 6 None 1 6 7 12
C 4 A 6 9 9 12
D 3 A 6 8 8 10
E 1 A 6 6 6 6
F 4 E 7 10 7 10
G 14 D,F 11 24 11 24
H 12 B,C 10 21 13 24
I 2 G,H 25 26 25 26
Float
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5 1 5 0
B 6 None 1 6 7 12 6
C 4 A 6 9 9 12 3
D 3 A 6 8 8 10 2
E 1 A 6 6 6 6 0
F 4 E 7 10 7 10 0
G 14 D,F 11 24 11 24 0
H 12 B,C 10 21 13 24 3
I 2 G,H 25 26 25 26 0
Zero Float Activities
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 5 None 1 5 1 5 0
E 1 A 6 6 6 6 0
F 4 E 7 10 7 10 0
G 14 D,F 11 24 11 24 0
I 2 G,H 25 26 25 26 0
Second Example
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 2 None
B 4 A
C 7 B
D 5 A
E 2 D
F 6 B,E
G 6 A
H 7 E,G
I 3 C,F,H
Second Example
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 2 None 1 2
B 4 A 3 6
C 7 B 7 13
D 5 A 3 7
E 2 D 8 9
F 6 B,E 10 15
G 6 A 3 8
H 7 E,G 10 16
I 3 C,F,H 17 19
Second Example
Activity Duration
Name ( WEEKS) Predecessor ES EF LS LF Float
A 2 None 1 2 1 2,3,5
B 4 A 3 6 6 10 , 9
C 7 B 7 13 10 16
D 5 A 3 7 3 7
E 2 D 8 9 8 9 , 10
F 6 B,E 10 15 11 16
G 6 A 3 8 4 9
H 7 E,G 10 16 10 16
I 3 C,F,H 17 19 17 19
Second Example
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 2 None 1 2 1 2 0
B 4 A 3 6 6 9 3
C 7 B 7 13 10 16 3
D 5 A 3 7 3 7 0
E 2 D 8 9 8 9 0
F 6 B,E 10 15 11 16 1
G 6 A 3 8 4 9 1
H 7 E,G 10 16 10 16 0
I 3 C,F,H 17 19 17 19 0
Earned Value Management
trainings@windowslive.com
0548 582 754
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
• Schedule Variance (SV)
• Cost Variance (CV)
• Schedule Performance Index (SPI)
• Cost Performance Index (CPI)
• BAC = Budget At Completion
• EAC = Estimate At Completion
• ETC = Estimate to Complete
• VAC = Variance At Completion
• TCPI = To Complete Performance Index
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
• PV = Planned Value = Budgeted cost of work
scheduled ) means we wanted to do )
At the end of 4th day ?? 40 %
Budget allocated for 40 % = 400
PV = 400
trainings@windowslive.com
0548 582 754
• AC = Actual Cost of the work so far done
• Schedule variance = SV = EV – PV
• Cost Variance = CV = EV – AC
trainings@windowslive.com
0548 582 754
• Schedule Performance Index= SPI = EV / PV
• Cost Performance Index = CPI = EV / AC
trainings@windowslive.com
0548 582 754
• How to remember the formulas
• SV = EV – PV
• CV = EV – AC
• SPI = EV / PV
• CPI = EV / AC
• EV is coming first
• For Variance its Minus
• For Index is division
• For Schedule other operand is PV
• For Cost other operand is AC
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
• Schedule Variance (SV)
• Cost Variance (CV)
• Schedule Performance Index (SPI)
• Cost Performance Index (CPI)
• BAC
• EAC
• ETC
• VAC
• TCPI
trainings@windowslive.com
0548 582 754
EVM – Calculations
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754