PMP Presentation PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 82

Project Management

Using PMI Approach

February 2016 – Khobar, KSA


PMP Training full Course - Schedule

– 1st Lecture 10th Feb Wed 7 – 10 pm


– 2nd Lecture 11th Feb Thu 7 – 10 pm
– 3rd Lecture 12th Feb Fri 3 – 9 pm
– 4th Lecture 13th Feb Sat 5 – 10 pm
– 5th Lecture 14th Feb Sun 7 - 10 pm
– 6th Lecture 15th Feb Mon 7 - 10 pm
– 7th Lecture 16th Feb Tue 7 - 10 pm
– 8th Lecture 17th Feb Wed 7 - 10 pm
– 9th Lecture 18th Feb Thu 7 – 10 pm

trainings@windowslive.com
0548 582 754
Abu Bakar Ahsen

• Education / Qualification
– BCS , M.IT
– PMP , RMP
– MCTS , MCPD
– Lean Six Sigma Green Belt + Black Belt
Certified

• Work Experience
– 16+ Years of Working & Project Management
Experience
– 170+ Project Management Workshops
– Already trained 6500+ Industry Professionals
trainings@windowslive.com
0548 582 754
You can become PMP , if
Graduation or Above Diploma Holders

Work 3+ Years Job Experience 5 + Years Job Experience


Experience Including 4,500 + Hours of Including 7,500 + Hours of
Project Experience. Project Experience
( Non Overlapping) (Non Overlapping)

Project 35 PDU’s of Project 35 PDU’s of Project Management


Management Management Training Training
Training

Exam One 4 hours Exam , One 4 hours Exam ,


200 MCQ’s 200 MCQ’s

Ref : www.pmi.org
trainings@windowslive.com
0548 582 754
PMP Examination Information
• Computer-based exam at a Prometric Test Center
• 200 Multiple Choice Questions
• Total time is 4 Hours
• All questions have 4 Options
• Of the 200 questions, 25 are considered pretest
questions and are not scored.
• 61.0% passing score ( 106 / 175 ) But may vary
depending upon your luck on that day ( Best case
scenario and worst case scenario )
trainings@windowslive.com
0548 582 754
Frequently Asked Questions (FAQs)
What is the cost of the PMP Exam?
PMI member = $405 Non-PMI member = $555
If I fail the PMP, what is the cost to retake the PMP
Exam?
PMI member = $275 Non-PMI member = $375
How many times can I take the PMP Exam?
You are granted a one-year eligibility period in which
to pass the examination. During the eligibility period,
you may take the examination up to three times.
When do I learn if I passed the PMP Exam?
On the spot result
trainings@windowslive.com
0548 582 754
Prometric Centers

• Medina
• Jeddah
• Riyadh
• Dammam

trainings@windowslive.com
0548 582 754
Cartoons Time


trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Project Management Training Sources

trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question

Which of the following is NOT true of obtaining project plan approval?


a. Until you obtain plan approval, you don’t need to put changes to it
through change control.
b. Change control makes sure that only approved changes can make it into
the approved plan.
c. Only one person needs to approve the Project Management Plan and
that’s the Project Manager.
d. It’s important for the entire team to buy into the Project Management
Plan for it to be successful.

trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
Which of the following is NOT true of obtaining project plan approval?
a. Until you obtain plan approval, you don’t need to put changes to it
through change control.
b. Change control makes sure that only approved changes can make it into
the approved plan.
c. Only one person needs to approve the Project Management Plan and
that’s the Project Manager.
d. It’s important for the entire team to buy into the Project Management
Plan for it to be successful.

Answer: C
It’s not enough that the Project Manager approves of the Project Management Plan; it needs to be
approved by all of the stakeholders in the project. Everyone on the team should feel comfortable with the
processes that are going to be used to do the work.

trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
You are the project manager for a railroad construction project. Your
sponsor has asked you for a forecast for the cost of project
completion. The project has a total budget of $80,000 and CPI of
.95. The project has spent $25,000 of its budget so far. How much
more money do you plan to spend on the project?
a. $59,210
b. $80,000
c. $84,210
d. $109,210

trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question
You are the project manager for a railroad construction project. Your
sponsor has asked you for a forecast for the cost of project
completion. The project has a total budget of $80,000 and CPI of
.95. The project has spent $25,000 of its budget so far. How much
more money do you plan to spend on the project?
a. $59,210
b. $80,000
c. $84,210
d. $109,210
Answer: A
This question is asking you to create a forecast using Estimate To Complete (ETC), which uses CPI (Cost
Performance Index) to project how much money is likely to be spent for the rest of the project. The first
step is to plug the numbers into the formula EAC = BAC / CPI, which yields EAC = $80,000 / .95 =
$84,210. That’s how much money you’re likely to spend on the project. Now you can figure out ETC =
EAC - AC = $84,210 - $25,000 = $59,210.
[BAC = Budget at Completion, EAC = Estimate at Completion, AC = Actual Cost]
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question

Given this portion of the network


diagram to the right, what’s the LF
of activity F?
a. 10
b. 11
c. 16
d. 17

trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question

Given this portion of the network


diagram to the right, what’s the LF
of activity F?
a. 10
b. 11
c. 16
d. 17

Answer: A
It’s just easy to calculate the late finish (LF) of an activity in a network diagram. Look at the following
activity, take its LS (late start), and subtract one. If there’s more than one following activity, use the one
with the lowest LS. So for activity F in the question, the following activities are G, with an LS of 17, and H,
with an LS of 11. So the LF of F is 11 - 1 = 10.
trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question

There have been several rounds of layoffs at your company. Now your
project team is worried about their job security, and you’ve noticed
that their performance has decreased significantly because of it.
This is predicted by which motivational theory?
a. McGregor’s Theory of X and Y
b. Maslow’s Hierarchy of Needs
c. McLellands Achievement Theory
d. Herzberg’s Motivation-Hygiene Theory

trainings@windowslive.com
0548 582 754
Sample PMP Exam
Question

There have been several rounds of layoffs at your company. Now your
project team is worried about their job security, and you’ve noticed
that their performance has decreased significantly because of it.
This is predicted by which motivational theory?
a. McGregor’s Theory of X and Y
b. Maslow’s Hierarchy of Needs
c. McLellands Achievement Theory
d. Herzberg’s Motivation-Hygiene Theory

Answer: B
Maslow’s Hierarchy of Needs says that people have needs, and until the lower ones (like acceptance
on the team, job safety or job security) are satisfied they won’t even begin to think about the higher
ones (fulfilling their potential and making a contribution).

trainings@windowslive.com
0548 582 754
Project Definition (PMI)

A project is a temporary endeavor undertaken


to create a unique product, service, or result.

Product : Road / Building / Software / New Car etc


Service: Mobile Network Coverage / Urgent Mail Service etc

Result : Elections / Surveys / Exploration of Petroleum etc

trainings@windowslive.com
0548 582 754
PROJECT MANAGEMENT

The application of skills and methodologies that


allow to deliver a project on time, within
budget and to the specifications.

trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Project Characteristics

Temporary
Have some objectives to meet.
Progressive Elaboration ( Means more details
become available with the passage of time)
Are done to
grab some opportunity,
market demand,
capacity building,
technological advancement
regulatory requirements.
trainings@windowslive.com
0548 582 754
KNOWLEDGE AREAS

•Scope Management
•Time Management
•Cost Management
•Quality Management
•HR Management
•Communication Management
•Risk Management
•Procurement Management
•Stakeholder Management
•Integration Management trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Scope Management
Processes required to ensure that the project includes all
the work required, and only the work required, to
complete the project successfully.

1. Plan Scope Management


2. Collect Requirements
3. Define Scope
4. Create WBS
5. Validate Scope
6. Control Scope
trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Time Management
Describes the processes required to ensure timely completion
of the project.

1. Plan Schedule Management


2. Define Activities
3. Sequence Activities
4. Estimate Activity Resource
5. Estimate Activity Durations
6. Develop Schedule
7. Control Schedule

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Cost Management
Describes the processes required to ensure that the
project is completed within the approved budget.

1. Plan Cost Management


2. Estimate Cost
3. Determine Budget
4. Control Costs

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Quality Management
Describes the processes required to ensure that the
project will satisfy the needs for which it was
undertaken.

1. Plan Quality Management


2. Perform Quality Assurance
3. Control Quality
( What is the difference between QA and QC )

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Human Resource Management
Describes the processes required to make the most effective use
of the people involved with the project.

1. Plan Human Resource Management


2. Acquire Project Team
3. Develop Project Team
4. Manage Project Team

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Communications Management
Describes the processes required to ensure timely and
appropriate generation, collection, dissemination, storage, and
ultimate disposition of project information.

1.Plan Communications Management


2.Manage Communications
3.Control Communications

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Risk Management
Describes the processes concerned with identifying,
analyzing, and responding to project risk.

1. Plan Risk Management


2. Identify Risks
3. Perform Qualitative Risk Analysis
4. Perform Quantitative Risk Analysis
5. Plan Risk Responses
6. Monitor and Control Risks

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Procurement Management
Describes the processes required to acquire goods
and services from outside the performing organization.

1. Plan Procurement Management


2. Conduct Procurements
3. Control Procurements
4. Close Procurements

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
Project Stakeholder Management
.

1. Identify Stakeholders
2. Plan Stakeholder Management
3. Manage Stakeholder Engagement
4. Control Stakeholder Engagement

trainings@windowslive.com
0548 582 754
Project management
Knowledge Areas
• Project Integration Management
Processes required to ensure that the various elements of
the project are properly coordinated.
• Below are the process in Integration Management
Knowledge Area
1. Develop Project Charter
2. Develop Project Management Plan
3. Direct and Manage Project Execution
4. Monitor and Control Project Work
5. Perform Integrated Change Control
6. Close Project or Phase
trainings@windowslive.com
0548 582 754
Process Groups

Project management processes can be organized into five groups:

• Initiating processes: recognizing that a project or phase should begin


and committing to do so.
• Planning processes: devising and maintaining a workable scheme to
accomplish the business need that the project was undertaken to
address.
• Executing processes: coordinating people and other resources to carry
out the plan.
• Controlling processes: ensuring that project objectives are met by
monitoring and measuring progress and taking corrective action when
necessary.
• Closing processes: formalizing acceptance of the project or phase and
bringing it to an orderly end.

trainings@windowslive.com
0548 582 754
Process Groups

trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
Thank You

trainings@windowslive.com
0548 582 754
WHAT IS Work Break Down Structure
(WBS) ?

What is an activity ?

What is activity Dependancy ?

trainings@windowslive.com
0548 582 754
How to calculate the project duration?
Using Critical Path Method

trainings@windowslive.com
0548 582 754
Simple Example:
Lets say we have two activities
a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm

trainings@windowslive.com
0548 582 754
Simple Example:

Lets say we have two activities


a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm
Activity Duration
Name ( Mins) ES EF LS LF Float

Biryani 60 08:00 09:00 08:00 09:00 0

Raita 10 08:00 08:10 08:50 09:00 50

Flaot is the amount / duration by which you can delay an activity without affecting
the project target completion date.
trainings@windowslive.com
0548 582 754
Simple Example:

Lets say we have two activities


a) Make Biryani ( Duration = 60 Min)
b) Make Raita ( Duration = 10 Mins)
Project Start time = 08:00 pm
Activity Duration
Name ( Mins) ES EF LS LF Float

Biryani 60 08:00 09:00 08:00 09:00 0

Raita 10 08:00 08:10 08:50 09:00 50

60 Minutes is the project duration. The path containing “make Biryani” is the critical
path, longest path, and the shortest duration in which you can complete this project
trainings@windowslive.com
and is called as critical path. 0548 582 754
Example Project
Activity Name Duration ( days) Predecessor

A 5 None
B 6 None
C 4 A
D 3 A
E 1 A
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
trainings@windowslive.com
0548 582 754
Network Diagram

start

trainings@windowslive.com
0548 582 754
Network Diagram

A D

start E

trainings@windowslive.com
0548 582 754
Network Diagram

C H

A D
G

start end

E F

trainings@windowslive.com
0548 582 754
Network Diagram

A E F

start end
C
H
B

trainings@windowslive.com
0548 582 754
Network Diagram
C H

A D
G

start end

E F

Path 1 A - D - G - I Path 3 A - C - H - I

Path 2 A – E - F - G - I Path 4 B - H - I

trainings@windowslive.com
0548 582 754
Network Diagram
C H

A D
G

start end

E F

Path 1 A - D - G - I = 24 days Path 3 A - C - H - I 23 days

Path 2 A – E - F - G - I = 26 days Path 4 B - H - I 20 days

trainings@windowslive.com
0548 582 754
Critical Path Method
Activity Duration
Name (Days) Predecessor ES EF LS LF Float

A 5 None
B 6 None
C 4 A
D 3 A
E 1 A
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
trainings@windowslive.com
0548 582 754
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5
B 6 None 1 6
C 4 A
D 3 A
E 1 A
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5
B 6 None 1 6
C 4 A 6
D 3 A 6
E 1 A 6
F 4 E
G 14 D,F
H 12 B,C
I 2 G,H
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5
B 6 None 1 6
C 4 A 6 9
D 3 A 6 8
E 1 A 6 6
F 4 E 7 10
G 14 D,F 11
H 12 B,C
I 2 G,H
Forward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5
B 6 None 1 6
C 4 A 6 9
D 3 A 6 8
E 1 A 6 6
F 4 E 7 10
G 14 D,F 11 24
H 12 B,C 10 21
I 2 G,H 25 26
Backward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5
B 6 None 1 6
C 4 A 6 9
D 3 A 6 8
E 1 A 6 6
F 4 E 7 10
G 14 D,F 11 24
H 12 B,C 10 21
I 2 G,H 25 26 25 26
Backward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5 1 5
B 6 None 1 6 7 12
C 4 A 6 9 9 12
D 3 A 6 8 8 10
E 1 A 6 6 6 6
F 4 E 7 10 7 10
G 14 D,F 11 24 11 24
H 12 B,C 10 21 13 24
I 2 G,H 25 26 25 26
Backward Pass
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5 1 5
B 6 None 1 6 7 12
C 4 A 6 9 9 12
D 3 A 6 8 8 10
E 1 A 6 6 6 6
F 4 E 7 10 7 10
G 14 D,F 11 24 11 24
H 12 B,C 10 21 13 24
I 2 G,H 25 26 25 26
Float
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5 1 5 0
B 6 None 1 6 7 12 6
C 4 A 6 9 9 12 3
D 3 A 6 8 8 10 2
E 1 A 6 6 6 6 0
F 4 E 7 10 7 10 0
G 14 D,F 11 24 11 24 0
H 12 B,C 10 21 13 24 3
I 2 G,H 25 26 25 26 0
Zero Float Activities

Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float

A 5 None 1 5 1 5 0

E 1 A 6 6 6 6 0

F 4 E 7 10 7 10 0

G 14 D,F 11 24 11 24 0

I 2 G,H 25 26 25 26 0
Second Example
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 2 None
B 4 A
C 7 B
D 5 A
E 2 D
F 6 B,E
G 6 A
H 7 E,G
I 3 C,F,H
Second Example
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 2 None 1 2
B 4 A 3 6
C 7 B 7 13
D 5 A 3 7
E 2 D 8 9
F 6 B,E 10 15
G 6 A 3 8
H 7 E,G 10 16
I 3 C,F,H 17 19
Second Example
Activity Duration
Name ( WEEKS) Predecessor ES EF LS LF Float
A 2 None 1 2 1 2,3,5

B 4 A 3 6 6 10 , 9
C 7 B 7 13 10 16
D 5 A 3 7 3 7
E 2 D 8 9 8 9 , 10
F 6 B,E 10 15 11 16
G 6 A 3 8 4 9
H 7 E,G 10 16 10 16
I 3 C,F,H 17 19 17 19
Second Example
Activity Duration (
Name WEEKS) Predecessor ES EF LS LF Float
A 2 None 1 2 1 2 0
B 4 A 3 6 6 9 3
C 7 B 7 13 10 16 3
D 5 A 3 7 3 7 0
E 2 D 8 9 8 9 0
F 6 B,E 10 15 11 16 1
G 6 A 3 8 4 9 1
H 7 E,G 10 16 10 16 0
I 3 C,F,H 17 19 17 19 0
Earned Value Management

• A method to assess the project’s performance.


• Where we are standing ?
• How is it going ?
• Is it going good or Bad ?
– In Terms of Time
– In Terms of Cost

• If it continues like this ? What are the forecasts /


Projections / Estimations ?
trainings@windowslive.com
0548 582 754
Example
We have to construct a wall , in 10
days, and 1000 SAR budget. At the
end of 4 days, we have completed
20 % and spent 300 SAR. Assuming
linear planning ( 10 % daily
achievement and spending) ..
Calculate the following

trainings@windowslive.com
0548 582 754
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
• Schedule Variance (SV)
• Cost Variance (CV)
• Schedule Performance Index (SPI)
• Cost Performance Index (CPI)
• BAC = Budget At Completion
• EAC = Estimate At Completion
• ETC = Estimate to Complete
• VAC = Variance At Completion
• TCPI = To Complete Performance Index
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
• PV = Planned Value = Budgeted cost of work
scheduled ) means we wanted to do )
At the end of 4th day ?? 40 %
Budget allocated for 40 % = 400
PV = 400

• EV = Earned Value = Budgeted cost of work


performed ) means we have done )
At the end of 4th day ?? 20 %
Budget allocated for 20 % = 200
EV = 200

trainings@windowslive.com
0548 582 754
• AC = Actual Cost of the work so far done

• Which is given in the statement itself i.e. 300 SAR

• Schedule variance = SV = EV – PV
• Cost Variance = CV = EV – AC

• If SV or CV is negative shows a bad situation


• If SV or CV is positive shows a good situation
• If SV or CV is Zero shows an OK situation

trainings@windowslive.com
0548 582 754
• Schedule Performance Index= SPI = EV / PV
• Cost Performance Index = CPI = EV / AC

• If SPI or CPI is < 1 shows a bad situation


• If SPI or CPI is > 1 shows a good situation
• If SPI or CPI is 1 shows an OK situation

trainings@windowslive.com
0548 582 754
• How to remember the formulas

• SV = EV – PV
• CV = EV – AC
• SPI = EV / PV
• CPI = EV / AC

• EV is coming first
• For Variance its Minus
• For Index is division
• For Schedule other operand is PV
• For Cost other operand is AC
trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754
• Planned Value (PV)
• Earned Value (EV)
• Actual Cost (AC)
• Schedule Variance (SV)
• Cost Variance (CV)
• Schedule Performance Index (SPI)
• Cost Performance Index (CPI)
• BAC
• EAC
• ETC
• VAC
• TCPI
trainings@windowslive.com
0548 582 754
EVM – Calculations

trainings@windowslive.com
0548 582 754
trainings@windowslive.com
0548 582 754

You might also like