ITP Contoh

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

DOC. NO.

INSPECTION AND TEST PLAN MA6043-900-001


CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 1 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-1 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

A-2 Design

Calculations Reviewed & Checked AP


GA Drawings Approved by Client AP R AP
Detail Drawings & Equipment Specifications Approved by Engineers AP

A-3 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report

A-4 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 2 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-5 Material Receiving Inspection

Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Certification R R Mill Certs / Certs of
Compliance
Proprietary Items (if applicable)
Baltec/Client supplied items PO A1 R Mill Certs / Certs of
Compliance
Instrumentation
Instrumentation list Baltec specification R Test, calibration, compl
certs
Hydraulic power pack
Manufacturer’s tests Test, calibration, compl
Baltec specification R
certs

Air barrier fan units


Test, calibration, compl
Motor manufacturer’s tests Baltec specification R
certs
Fan manufacturer’s performance tests

Electrical Control Panel


Electrical requirements Baltec specification
Protection class IP 55
Conformity with electrical drawings Drawings
Painting Supplier standard A1 S R AP
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 3 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-6 Manufacture Diverter Shell

Mark, cut, form CS components Drawings A1 S


Assemble & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1
Dimensional inspection Drawings A1 W S Report
Dimensional inspection of HRSG flange Drawings A1 W W AP Report
NDE Visual 100% A1 W Report
Lifting lugs LP 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)
Butt welds (200mm from junction & flanges) LP 20% A1 S Report
Welds on sheet within 200mm of a bearing or lifting point LP 20%
Junction welds between perpendicular stiffeners LP10% Report
Flange butt welds LP 5%
Flanges to shell (2x400mm samples per flange) LP 20% Report

A-7 Fabricate Blanking Plate

Mark, cut, form components Drawings A1 S


Assemble frame & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)
Butt welds LP 20%

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 4 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-8 Diverter Shell & Blanking Plate Painting

Surface Preparation & Painting Client Spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
*: applied on site by erecting
sub-contractor
A-9 Fabricate Cladding sheets

Mark, cut, form SS sheets Drawings A1 S


Welding (if applicable) Drawings / AWS D1.1 A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100%
Butt welds LP 5%

A-10 Fabricate Blade shafts, arm and flanges

Mark, cut, machining Drawings A1 S


Assemble, tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W S Report
Pickling Pickling paste – manufacturer A1 S
instructions
NDE LP 100% / visual 100% A1 W Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 5 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-11 Fabricate Blade

Mark, cut, form Drawings A1 S


Assemble frame & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
pre &/or post weld heat treat
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Arm to blade welds LP 100% A1 S S Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)
Butt welds LP 20%

A-12 Fit Insulation / cladding

Install insulation to shell & blanking plate Drawings A1 S S


Install cladding sheets, washers & nuts Drawings A1 S
Torque nuts & tack weld Drawings A1 S

A-13 Install Diverter Blade and Drive

Install bearings, shafts & blade Drawings A1 S Report


Install landing bars & line up with blade Drawings A1 W
Install blade seals Drawings A1 S S
Install drive arms Drawings A1 S
Install hydraulic rams Drawings A1 S

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 6 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-14 Complete trial assembly and check function

Workshop operational test Baltec procedures A1 W W AP Report


Set blade stops A1 W Section A-13 to be
Check blade sealing A1 W W AP witnessed by Client. 3
days notice required to
Client.
A-15 Seal air pipework

Mark, cut, assemble & tack weld pipes Drawings A1 S


Welding Drawings A1 S
Dimensional inspection Drawings A1 W Report
Surface Preparation & Painting Client Spec
Surface preparation SP10 – Sa 2 ½ QCP S Report
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
Jotun-Jotaprime 15 (=Resist
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
*: applied on site by erecting
sub-contractor

A-16 Fabricate Walkways & ladders

Mark, cut, assemble, tack weld Drawings A1 S


Welding Drawings A1 S
Dimensional inspection Drawings A1 W Report
Surface treatment Hot-dip galvanize QCP S Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: DIVERTER DAMPER & BLANKING PLATE JOB SUB NO: A - 350 Issue Date: 22/07/03
DRAWINGS: MA-6043-350 & 550 & A – 550 Copy No: 001
PAGE 7 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

A-17 End of manufacturing inspections

Identification plate Baltec standard


Conformity to purchase order R
Packing list R
Verification of receipt of supplier quality documentation PO Documents, ITP’s R

A-18 Final inspection

Review Quality of Finished Goods Drawings, PO Documents H W AP Inspection Release


Good Engineering Practices Report

Final inspection to be
Review and Approval of the Manufacturer’s Data Report PO Documents, ITP R AP witnessed by Client. 3
days notice required to
Client.

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: STACK SUPPORT STRUCTURE (001) JOB SUB NO: B - 150 Issue Date: 22/07/03
DRAWINGS: MA-6043-150, 200 & 300 & STACK TRANSITIONS (101) B - 200 & B - 300 Copy No: 001
PAGE 8 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

B-001 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

B-002 Design

Calculations Reviewed & Checked AP


GA Drawing Approved by Client AP R AP
Detail Drawings & EquipmentSpecifications Approved by Engineers AP

B-003 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report

B-004 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec
B- Material Receiving Inspection
005
Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Certification R R Mill Certs / Certs of
Compliance
Proprietary Items (if applicable)
Baltec/Client supplied items PO A1 R Mill Certs / Certs of
Compliance

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: STACK SUPPORT STRUCTURE (001) JOB SUB NO: B - 150 Issue Date: 22/07/03
DRAWINGS: MA-6043-150, 200 & 300 & STACK TRANSITIONS (101) B - 200 & B - 300 Copy No: 001
PAGE 9 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

B-006 Stack support structure


Mark, cut CS pipes, beams, plate Drawings A1 S
Drill base plates & flanges Drawings A1 S
Fit, tack weld flanges Drawings A1 S
Trial assembly Drawings A1 S S
Welding Drawings / AWS D1.1 A1 S
Base plates AWS D1.1, NDE 10% UT A1 W Report
Dimensional inspection Drawings A1 W W AP Report
NDE Visual 100% A1
Lifting lugs (if applicable) LP 100% A1 S Report

Surface Preparation & Painting Client spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Penguard HB
RAL 9006 Silver DFT 50µ
* Topcoat: Jotun Hardtop AS
RAL 9006 Silver DFT 50µ
*: applied on site by erecting
sub-contractor
Final inspection Drawings H W AP Inspection Release
Report
Final inspection to be
witnessed by Client. 3
days notice required to
Client

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: STACK SUPPORT STRUCTURE (001) JOB SUB NO: B - 150 Issue Date: 22/07/03
DRAWINGS: MA-6043-150, 200 & 300 & STACK TRANSITIONS (101) B - 200 & B - 300 Copy No: 001
PAGE 10 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

B-101 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

B-102 Design

Calculations Reviewed & Checked AP


GA Drawing Approved by Client AP R AP
Detail Drawings & EquipmentSpecifications Approved by Engineers AP

B-103 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report
B-104 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec
B- Material Receiving Inspection
105
Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Certification R R Mill Certs / Certs of
Compliance
Proprietary Items (if applicable)
Baltec/Client supplied items PO A1 R Mill Certs / Certs of
Compliance

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: STACK SUPPORT STRUCTURE (001) JOB SUB NO: B - 150 Issue Date: 22/07/03
DRAWINGS: MA-6043-150, 200 & 300 & STACK TRANSITIONS (101) B - 200 & B - 300 Copy No: 001
PAGE 11 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

B-106 Stack transitions


Mark, cut CS steel Drawings A1 S
Match drill & match-mark flanges Drawings A1 S
Forming, fitting, weld preparation & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Lifting lugs (if applicable) LP 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)
Surface Preparation & Painting Client Spec
Surface preparation
SP10 – Sa 2 ½ QCP S Report
Internal painting
Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
*: applied on site by erecting
sub-contractor
Mark, cut SS liners Drawings A1 S
Form, punch SS liners Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W Report
Install insulation to shell Drawings A1 S Final inspection to be
Install cladding sheets, washers & nuts Drawings A1 S witnessed by Client. 3
Torque nuts & tack-weld A1 S days notice required to
Drawings
Final inspection Client
Drawings H W AP
Inspection Release
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: SILENCER, SPLITTERS (201) JOB SUB NO: D - 250 Issue Date: 22/07/03
DRAWINGS: MA-6043-250 & 400 & STACK SECTIONS (301) & D - 400 Copy No: 001
PAGE 12 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

D-201 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

D-202 Design

Calculations Reviewed & Checked AP


GA Drawing Approved by Client AP R AP
Detail Drawings & EquipmentSpecifications Approved by Engineers AP

D-203 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report

D-204 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec
D- Material Receiving Inspection
205
Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Certification R R Mill Certs / Certs of
Compliance
Proprietary Items (if applicable)
Baltec/Client supplied items PO A1 R Mill Certs / Certs of
Compliance

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: SILENCER, SPLITTERS (201) JOB SUB NO: D - 250 Issue Date: 22/07/03
DRAWINGS: MA-6043-250 & 400 & STACK SECTIONS (301) & D - 400 Copy No: 001
PAGE 13 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

D-206 Silencer

Mark, cut CS steel Drawings A1 S


Match drill & match-mark flanges Drawings A1 S
Forming, fitting, weld preparation & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Lifting lugs (if applicable) LP 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random A1
thereafter)
Surface Preparation & Painting Client spec
Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal Painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External Painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 DFT 40µ
* Topcoat: Jotun Solvalitt
RAL 9006 DFT 40µ
*: applied on site by erecting
sub-contractor
Mark, cut SS liners A1 S
Drawings
Form, punch SS liners A1 S
Drawings
Welding S
AWS D1.1 / WPS
Dimensional inspection A1 W Report
Drawings
Install insulation to shell A1 S S Final inspection to be
Drawings witnessed by Client. 3
Install cladding sheets, washers & nuts A1 S
Drawings days notice required to
Torque nuts & tack-weld A1 S
Drawings Client
Final inspection H W AP
Drawings Inspection Release
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: SILENCER, SPLITTERS (201) JOB SUB NO: D - 250 Issue Date: 22/07/03
DRAWINGS: MA-6043-250 & 400 & STACK SECTIONS (301) & D - 400 Copy No: 001
PAGE 14 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

D-207 Silencer splitters

Mark, cut SS frames Drawings A1 S


Form SS frames Drawings A1 S
Fit, weld preparation & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Lifting lugs LP 100% A1 W Report
Fit & weld perforated sheets (1 side only) Drawings A1 S

Install acoustic insulation Dwgs / install instructions A1 W S


Fit & weld perforated sheets (2nd side) Drawings A1 S

Final inspection Drawings H W AP Inspection Release


Report

Final inspection to be
witnessed by Client. 3
days notice required to
Client

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: SILENCER, SPLITTERS (201) JOB SUB NO: D - 250 Issue Date: 22/07/03
DRAWINGS: MA-6043-250 & 400 & STACK SECTIONS (301) & D - 400 Copy No: 001
PAGE 15 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

D-301 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

D-302 Design

Calculations Reviewed & Checked AP


GA Drawing Approved by Client AP R AP
Detail Drawings & EquipmentSpecifications Approved by Engineers AP

D-303 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report
Radiography 10% (if required) Report

D-304 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec
D-305 Material Receiving Inspection

Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Mill Certs / Certs of
Certification R R Compliance

Proprietary Items (if applicable)


Mill Certs / Certs of
Baltec/Client supplied items PO A1 R Compliance

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: SILENCER, SPLITTERS (201) JOB SUB NO: D - 250 Issue Date: 22/07/03
DRAWINGS: MA-6043-250 & 400 & STACK SECTIONS (301) & D - 400 Copy No: 001
PAGE 16 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

D-306 Bottom stack section

Mark, cut CS steel Drawings A1 S


Match drill & match-mark flanges Drawings A1 S
Forming, fitting, weld preparation & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Lifting lugs (if applicable) LP 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)

Surface Preparation & Painting Client spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
*: applied on site by erecting
sub-contractor
Mark, cut SS liners Drawings A1 S
Form, punch SS liners Drawings A1 S
Final inspection to be
Welding AWS D1.1 / WPS A1 S
witnessed by Client. 3
Dimensional inspection Drawings A1 W days notice required to
Install insulation to shell Drawings A1 S Client
Install cladding sheets, washers & nuts Drawings A1 S
Torque nuts & tack-weld Drawings A1 S Inspection Release
Final inspection H W AP Report
Drawings

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: SILENCER, SPLITTERS (201) JOB SUB NO: D - 250 Issue Date: 22/07/03
DRAWINGS: MA-6043-250 & 400 & STACK SECTIONS (301) & D - 400 Copy No: 001
PAGE 17 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

D-307 Top stack section

Mark, cut CS steel Drawings A1 S


Match drill & match-mark flanges Drawings A1 S
Forming, fitting, weld preparation & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Drawings A1 W S Report
Dimensional inspection
NDE Visual 100% A1 W Report
Lifting lugs (if applicable) LP 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)

Surface Preparation & Painting Client spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* Topcoat: Jotun Solvalitt
RAL 9006 Silver DFT 40µ
*: applied on site by erecting
sub-contractor
Mark, cut SS liners Drawings A1 S
Form, punch SS liners Drawings A1 S
Final inspection to be
Welding AWS D1.1 / WPS A1 S
witnessed by Client. 3
Dimensional inspection Drawings A1 W days notice required to
Install insulation to shell Drawings A1 S Client
Install cladding sheets, washers & nuts Drawings A1 S
Torque nuts & tack-weld Drawings A1 S Inspection Release
Final inspection H W AP Report
Drawings

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: GT OUTLET HORIZONTAL TRANSITION DUCT JOB SUB NO: H - 500 Issue Date: 22/07/03
DRAWINGS: MA-6043-500 Copy No: 001
PAGE 18 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

H-1 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

H-2 Design

Calculations Reviewed & Checked AP


GA Drawing Approved by Client AP R AP
Detail Drawings & Equipment Specifications Approved by Engineers AP

H-3 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report

H-4 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec
H-5 Material Receiving Inspection

Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Certification R R Mill Certs / Certs of
Compliance
Proprietary Items (if applicable)
Baltec/Client supplied items PO A1 R Mill Certs / Certs of
Compliance

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: GT OUTLET HORIZONTAL TRANSITION DUCT JOB SUB NO: H - 500 Issue Date: 22/07/03
DRAWINGS: MA-6043-500 Copy No: 001
PAGE 19 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

H-6 GT Outlet Horizontal Transition Duct


Mark, cut CS steel Drawings A1 S
Match drill & match-mark flanges Drawings A1 S
Forming, fitting, weld preparation & tack weld Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Lifting lugs (if applicable) LP 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)

Surface Preparation & Painting Client spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
*Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
* : applied on site by erecting
sub-contractor
Mark, cut SS liners Drawings A1 S
Form, punch SS liners Drawings A1 S
Welding AWS D1.1 / WPS A1 S
Final inspection to be
Dimensional inspection Drawings A1 W
witnessed by Client. 3
Install insulation to shell Drawings A1 S S days notice required to
Install cladding sheets, washers & nuts Drawings A1 S Client
Torque nuts & tack-weld Drawings A1 S
Final inspection Drawings H W AP Inspection Release
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: EXPANSION JOINTS JOB SUB NO: J - 450 Issue Date: 22/07/03
DRAWINGS: MA-6043-450 Copy No: 001
PAGE 20 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

J-1 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

J-2 Design

Calculations Reviewed & Checked AP


GA Drawing Approved by Client AP R AP
Detail Drawings & EquipmentSpecifications Approved by Engineers AP

J-3 Welding

Welding Procedure Specification AWS D1.1 AP H WPS


Welding Procedure Qualification Record AWS D1.1 AP H R WPQR
Welder Qualification AWS D1.1 AP H WQR
NDE (by qualified personnel) Visual 100% A1 R/S Report

J-4 Purchasing

Supplier Prequalification Baltec Procedures IN R


Order placement Baltec Procedures IN R Unpriced copy of PO to
Baltec
J-5 Material Receiving Inspection

Raw Material
Quantity, dimensions, damage PO / Material specifications A1/R R
Certification R R Mill Certs / Certs of
Compliance
Proprietary Items (if applicable)
Baltec/Client supplied items PO A1 R Mill Certs / Certs of
Compliance

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: EXPANSION JOINTS JOB SUB NO: J - 450 Issue Date: 22/07/03
DRAWINGS: MA-6043-450 Copy No: 001
PAGE 21 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

J-6 GT Outlet Upstream Expansion Joint

Mark, cut CS steel Drawings A1 S


Form, fit, weld prep & tack weld Drawings A1 S
Welding Drawings / AWS D1.1 A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of
every shift, 1% at random A1 S
thereafter)
Mark & drill flange holes Drawings A1 S
Dimensional inspection of interface flanges Drawings A1 W Report

Surface Preparation & Painting Client Spec


Surface preparation SP10 – Sa 2 ½ QCP S
Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S
Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S
Report
JTI) DFT 65µ
Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
(Int & Top coats of EJs to be
applied at workshop)
Mark, cut SS liner A1 S
Drawings
Fit liner A1 S
Drawings
Weld liner A1 S
Drawings / AWS D1.1
Dimensional inspection A1 W
Drawings
Install bolster & dome seal A1 S W AP Report
Drawings
Install shipping protection & preset bars A1 S
Drawings
Final inspection H W AP Inspection Release
Drawings
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: EXPANSION JOINTS JOB SUB NO: J - 450 Issue Date: 22/07/03
DRAWINGS: MA-6043-450 Copy No: 001
PAGE 22 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

J-7 Diverter HRSG Outlet Expansion Joint

Mark, cut CS steel Drawings A1 S


Form, fit, weld prep & tack weld Drawings A1 S
Welding Drawings / AWS D1.1 A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)
Mark & drill flange holes Drawings A1 S
Dimensional inspection of interface flanges Drawings A1 W Report

Surface Preparation & Painting Client Spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
(Int & Top coats of EJs to be
applied at workshop)
Mark, cut SS liner A1 S
Drawings
Fit liner A1 S
Drawings
Weld liner A1 S
Drawings / AWS D1.1
Dimensional inspection A1 W
Drawings
Install bolster & dome seal A1 S W AP Report
Drawings
Install shipping protection & preset bars A1 S
Drawings
Final inspection H W AP Inspection Release
Drawings
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO: 6043 Rev: D
CONTRACT NO: 6043 PORTION: EXPANSION JOINTS JOB SUB NO: J - 450 Issue Date: 22/07/03
DRAWINGS: MA-6043-450 Copy No: 001
PAGE 23 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

J-8 Diverter Stack Outlet Expansion Joint

Mark, cut CS steel Drawings A1 S


Form, fit, weld prep & tack weld Drawings A1 S
Welding Drawings / AWS D1.1 A1 S
Dimensional inspection Drawings A1 W S Report
NDE Visual 100% A1 W Report
Cladding pins (stud weld & then fillet weld) Bend test (3 pins at start of A1 S
every shift, 1% at random
thereafter)
Mark & drill flange holes Drawings A1 S
Dimensional inspection of interface flanges Drawings A1 W Report

Surface Preparation & Painting Client Spec


Surface preparation SP10 – Sa 2 ½ QCP S Report
Internal painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
External painting Jotun-Jotaprime 15 (=Resist QCP S Report
JTI) DFT 65µ
Int.coat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
Topcoat: Jotun Solvalitt RAL
9006 Silver DFT 40µ
(Int & Top coats of EJs to be
applied at workshop)
Mark, cut SS liner A1 S
Drawings
Fit liner A1 S
Drawings
Weld liner A1 S
Drawings / AWS D1.1
Dimensional inspection A1 W
Drawings
Install bolster & dome seal A1 S W AP Report
Drawings
Install shipping protection & preset bars A1 S
Drawings
Final inspection H W AP Inspection Release
Drawings
Report

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date
DOC. NO.
INSPECTION AND TEST PLAN MA6043-900-001
CLIENT: PT INDONESIA POWER PROJECT: RELOKASI PLTG Unit 4 & 5 Priok Ke Pemaron Bali ORDER NO:6043 Rev: D
Issue Date: 22/07/03
CONTRACT NO: 6043 PORTION: FINAL DOCUMENTATION AND DELIVERY JOB SUB NO: K - 900
Copy No: 001
DRAWINGS: MA-6043-900 PAGE 24 OF 24
STEP INSPECTION AND TEST FUNCTION APPLICABLE STANDARD/ SUBCONTRACTOR VENDOR WASA MITRA INDO POWER RECORDS / REMARKS
ACCEPTANCE CRITERIA SIGNATURE/STAMP SIGN DATE SIGN DATE SIGN DATE

K-1 Contract Review & Handover

Review Technical Documentation PO QCP


Review Commercial Terms PO QCP

K-2 Packing & Dispatch

Identify & tag all items against Packing List A1 W W,S AP Packing List
Pack S
Dispatch Client PO specification A1 W Inspection Release
Report
Final inspection to be
witnessed by Client. 3
days notice required to
Client
K-3 Manufacturers Data report

Review and approval Client PO specification AP H W,R AP

NB: 1) Paint specified is Jotun Paints. All paint for intermediate and topcoats (except for Expansion Joints) are in scope of supply of CUSTOMER erecting sub-contractors and to be
applied on site.
2) This document needs to be used in conjunction with Shop Inspection Procedure Document no = to be advised if applicable
3) All weld procedures and qualifications must be submitted and approved prior to starting welding and fabrication. Personnel must be qualified to AWS standards.
For poor workmanship and quality, CONSULTANT reserves the right to use third party inspectors at CONTRACTOR’s (fabricator’s) cost.
4) Shipping bracings and beams to be provided for all components to secure them during transport. These supports are required to be inspected and approved prior to shipping.
5) Paint for Expansion Joints is in scope of supply of FABRICATOR. Expansion Joints will be intermediate and final coated at the workshop.

INSPECTION SYMBOLS: A1 = 100% INSPECTION H = HOLD POINT QCP = QUALITY CONTROL PROCEDURE S = SURVEILLANCE ACTIVITY
AP = FORMAL APPROVAL REQD IN = FOR INFORMATION R = DOCUMENT REVIEW W = WITNESS

COMPILED BY: Paul Spence Sign: Date: APPROVED BY: Sinan Boratav Sign: Date

You might also like