Time Frame for Delivery

For an analysis and development of “My Banking App Project”, our development Team has
estimated 3 months of time frame. The time frame stages and credit days are tabulated below.

First Month
Table 1: 1st Month’s Tasks

Task Time (Days)

Preliminary Investigation 5

Requirement Analysis and Gathering 6

Market Analysis and Scope 5

Finding Required function 4

Finding Non-Required function 4

Second Month

Table 2: 2nd Month’s Tasks

Task Time (Days)

Framework Design 5

User Interface/Design 4

Entity Relationship (ERD) and Data Flow 9


Diagram(DFD)

Data Dictionary 3

Offline Storage 4
Third Month

Table 3: 3rd Month’s Tasks

Task Time (Days)

Prototype Typing and Updating 3

Coding 8

Fixing Bugs 3

Deployment 3

Support, Training API integration 8