Client Logo

Inspection Report
Checklist for Excavation
Project
Client Inspection Report No

PMC CBRE South Asia Pvt. Ltd. Date

Vendor
Package Civil structure (Earth work)
Description of Work Excavation Quantity
Inspection Request
Location Level Inspected by
By Time
Grid

Sl. Description YES NO NA Remarks


No

Before Excavation
1 Method statement submitted
2 Availability of required drqwings and details checked
3 All statutory approvals are in place
4 Location for dumping of excavated soil identified

List of machinery along with fitness certificate and detail documents for
5 compliance submitted

6 Joint record of NGL taken before start of excavation


7 Excavation lines marked and reference pegs fixed on ground
8 Check safety adequecy
9 Arrangement for dewatering

10 Existing services lines identified and shifted to approved location

After Excavation
1 Grid lines/bench mark transferred

2 Side clearance checked and final trimming done if required

3 Final levels checked and trimming done if required


4 Anti termite treatment

Observations if any :

Above Observations attended to and completed YES NO NA

Note: The quantity mentioned above is approximate measure and can not be considered for any billing purpose. Only JMS to be considered for billing else
GFC drawings are to be referred for quantity.

The above works have been completed and accepted


Vendor CBRE Client

Signature Signature Signature


Name Name Name
Date Date Date
Distribution Original : CBRE - QS cc : Vendor