METHODOLOGY STATEMENTIETHCDOLOGY STATEMENT — OUTDOOR PRINARY SUBSTATION
‘The Upgrading of Marble Factory PSS to 4x6MVA with TIKY feeders at Al
‘Suwaig in Al Batinah Governorate willbe uided into several smaller sections ot
work The inalaton of power cable, power transiomers and protection equipment
‘il be handles by saparat ntallatcn team, The raroure alosted toe poeck
‘be caresyonding toe prec schedule.
“This cocurett desorbes the main consruton actives that wil be executed and
‘he methedoigy that wil be flowed. These events wl flow afte the approval ot
alldesigns by Mazoon Elcticty Company (S.A.0.C) and he appoined Consutant.
1 civiL WoRKS
11 SITEPREPERATION
elo. any werk wil commence on ste the salty fie for
Conssidated Powe Projects and ts subcorirecter wil be submited
to azoen Electicy Company (S.A0.0) or approval.
| Take. over Substation ste from MZEC, Confim construction
boundatis end eri ll esting ences.
Complete Geotechle! suvey to detemine lad bearing eapscty
Foard resus to Cl Orsign Department to optimize equipment
bases and baling degra,
IM. Complete. soll resistiy test to detemine optimum earhmat
‘otiguration by electrical design team,
12. SITE CONSTRUCTION
124 Power Cable trenches
Setting out of the cable trench as per the approved cable
route design
| Got approval tor excavation ram MZEC
|, Excavate he cable ren ane arcade open excavations
IM. Instat sand bedding according to manufacturers
specticalons
the manufacturer's specicalens. The necessary concrete
‘lcks and ean tape wl be nsiaed below ground level as
‘a waming and protecton forthe cable
“The rout wil be frallyinccalod by suitable approved cable
rare nated above ground evaPage 205
METHODOLOGY STATENENT — OUTDOOR PRIMARY SUBSTATION.
41.22 Outdoor Concrete Works
Thi
ie setion cescrbes the construction acts for outdoor
foundations.
a
2 ELECTRICAL
Compete substation ‘Seting Out as per approved General
‘rangement and Foundaton Layout Drawings,
Get approval for excavations rom MZEC. Al excavated
‘metal tobe spok in platform suround,
(Compact inst soln excavated hols to $3%4 MODASSHTO
Complete reiriercemont as per civ base design, instal
Shutlering and pace hldsdown bots nconect postions.
Belore pouring concrete, MZEC end AFAQ to sign off GCP
‘wit egaré to dimensional checks,
‘Gast bases (min MPA concrete) and tsi cubes
‘low 23hr belore stoping of shutleing and rubbing down
(wth carborandum bios a8 moat nigh
‘low 14 days cuting of concrete beloreinstaling sictures
fad squat. "The Sng pec forth ranslormerpnthe
be 28 aye,
INSTALLATION
21 OUTDOOR EQUIPMENT
2.4 HV Equipmentand Structures
Inet main eath-mat as por approved desgn and associated
‘ening.
Insta al equpment support structures. These stuctres tot
{othe foundations complated ding the ch conatcon
Insaation of the HV equpmert wil be done as per the
General rangement Drawing and as pertne manutaturers
‘stalsion prozecure
‘Complete all equpment eathing and carnet tas to maln
feartimal, instal eat spes as required earting design
CGempleto the crop-down teminaions and connections tothe
HV Terminals fhe equipment