LOOSE FURNITURE 3.01 8 11/1/2018 12/21/2018 0.376 0.376 0.376 0.376 0.376 0.376 0.376 0.376 0.692
INTERIOR WORK LT 4 11 10/13/2018 12/24/2018
DEMOLITION WORK 1 10/13/2018 10/17/2018
Demolish existing Interior & furniture 0.61 2 10/13/2018 10/17/2018 0.306 0.306
FLOOR WORK 7 10/23/2018 12/10/2018
homogenus tile #1 1.22 3 10/30/2018 11/12/2018 0.407 0.407 0.407
resilient floor finish type-1 1.19 3 11/22/2018 12/5/2018 0.398 0.398 0.398
general server room raised floor in HPL finish 0.21 2 12/6/2018 12/10/2018 0.210
To smooth screed (aci) for vynil & carpet tile 1.12 5 10/23/2018 11/21/2018 0.224 0.224 0.224 0.224 0.224
CEILING WORK 6 10/23/2018 11/30/2018
ceiling gypsum board 0.72 5 10/23/2018 11/21/2018 0.143 0.143 0.143 0.143 0.143
exposed slab ceiling 0.68 5 11/1/2018 11/30/2018 0.135 0.135 0.135 0.135 0.135
gypsum perforated ceiling 0.20 2 11/22/2018 11/28/2018 0.101 0.101
plywood backing for existing perimeter curtain box 0.12 5 10/23/2018 11/21/2018 0.024 0.024 0.024 0.024 0.024
vertical gypsum ceiling in paint finish (PT-1) 0.08 5 10/23/2018 11/21/2018 0.017 0.017 0.017 0.017 0.017
PARTITION WORK 7 10/16/2018 11/28/2018
Partition type gypsum 1.70 5 10/16/2018 11/14/2018 0.340 0.340 0.340 0.340 0.340
glass partition type - 1 1.36 3 11/8/2018 11/21/2018 0.452 0.452 0.452
partition on ceiling cavity 0.43 5 10/30/2018 11/28/2018 0.087 0.087 0.087 0.087 0.087
timber skirting in duco finish 0.20 3 11/8/2018 11/21/2018 0.068 0.068 0.068
LOOSE FURNITURE 5.00 8 11/1/2018 12/21/2018 0.625 0.625 0.625 0.625 0.625 0.625 0.625 0.625
INTERIOR WORK LT 5 10 10/18/2018 12/24/2018
DEMOLITION WORK 1 10/18/2018 10/22/2018
Demolish existing Interior & furniture 0.61 2 10/18/2018 10/22/2018 0.306 0.306
FLOOR WORK 6 10/23/2018 12/3/2018
homogenus tile #1 0.60 3 11/6/2018 11/19/2018 0.199 0.199 0.199
resilient floor finish type-1 0.13 2 11/22/2018 11/28/2018 0.064 0.064
general server room raised floor in HPL finish 0.08 2 11/29/2018 12/3/2018 0.040 0.040
To smooth screed (aci) for vynil & carpet tile 0.90 5 10/23/2018 11/21/2018 0.181 0.181 0.181 0.181 0.181
CEILING WORK 7 10/30/2018 12/14/2018
flat ceiling gypsum board 0.72 5 10/30/2018 11/28/2018 0.143 0.143 0.143 0.143 0.143
exposed slab ceiling 0.18 5 11/15/2018 12/14/2018 0.036 0.036 0.036 0.036 0.036
wooden lattice ceiling 0.29 2 11/29/2018 12/5/2018 0.147 0.147
ceiling in laminate finish with plywood backing 0.68 2 12/6/2018 12/12/2018 0.340 0.340
plywood backing for existing perimeter curtain box 0.12 5 10/30/2018 11/28/2018 0.024 0.024 0.024 0.024 0.024
vertical gypsum ceiling in paint finish (PT-1) 0.08 5 10/30/2018 11/28/2018 0.016 0.016 0.016 0.016 0.016
PARTITION WORK 7 10/23/2018 12/5/2018
partition gypsum board 2.04 5 10/23/2018 11/21/2018 0.408 0.408 0.408 0.408 0.408
glass partition type - 1 1.66 3 11/15/2018 11/28/2018 0.554 0.554 0.554
gypsum partition on ceiling cavity 0.54 5 11/6/2018 12/5/2018 0.109 0.109 0.109 0.109 0.109
50mm high timber skirting in duco finish 0.35 3 11/15/2018 11/28/2018 0.118 0.118 0.118
0.06 1 0.056
includes plywood backing, all fixings, accessories and indirect lighting 12/18/2018 12/22/2018
closet 0.07 1 12/18/2018 12/22/2018 0.067
under counter lavatory 0.02 1 12/18/2018 12/22/2018 0.018
Accessories Toilet 0.10 1 12/18/2018 12/22/2018 0.103
OTHER WORKS 3 12/4/2018 12/24/2018
manual roller blinds type 1 0.17 3 12/11/2018 12/24/2018 0.055 0.055 0.055
motorized roller blinds type 2 3.12 4 12/4/2018 12/24/2018 0.779 0.779 0.779 0.779
room signage #2 1.02 2 12/20/2018 12/24/2018 0.510 0.510
BUILT IN FURNITURE 6.06 8 11/1/2018 12/21/2018 0.757 0.757 0.757 0.757 0.757 0.757 0.757 0.757
LOOSE FURNITURE 4.87 8 11/1/2018 12/21/2018 0.608 0.608 0.608 0.608 0.608 0.608 0.608 0.608
PROJECT HAND OVER 12 10/3/2018 12/26/2018
Daily cleaning & Final Cleaning 2.80 13 10/3/2018 12/25/2018 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215
Project Hand Over / Office Relocation 1 12/26/2018 12/26/2018
PROGRESS PLANNING 4.72 2.01 2.53 3.58 8.56 9.74 10.39 12.16 12.41 13.47 9.88 7.83 4.42
COMMULATIVE PROGRESS PLANNING 4.72 6.73 9.26 12.85 21.41 31.15 41.54 53.70 66.11 79.57 89.45 97.28 101.70
PROGRESS ACTUAL 5.03 8.71 10.68 13.65
COMMULATIVE PROGRESS ACTUAL
DEVIATION
Prepared by :
PT. Gema Graha Sarana Tbk
Revy
Project Manager