S – CURVE ATTACH WITH WEEKLY SCHEDULE

PROJECT : GEODIPA ENERGY


SCOPE OF WORK : Interior, Furniture, ME
LOCATION : Aldevo Octagon Building, Jl. Warung Buncit Raya No. 75, Jakarta
01/10 08/10 15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12
October-18 October-18 December-18
DESCRIPTION WEIGHT NUMBER START FINISH 1 2 3 4 5 6 7 8 9 10 11 12 13 Remark
OF WEEKS
1-7 8 - 14 15 - 21 22 - 28 29 - 4 5 - 11 12 - 18 19 - 25 26 - 2 3-9 10 - 16 17 - 23 24 - 30

GEO DIPA ENERGI 100.00 10/2/2018 12/26/2018


PREPARATION 2.11 1 10/2/2018 10/2/2018 2.114
Kick Off Meeting 1 10/2/2018 10/2/2018
PRE CONSTRUCTION 2.39 1 10/2/2018 10/7/2018 2.393
Site Handover 1 10/2/2018 10/2/2018
Site marking 1 10/3/2018 10/7/2018
INTERIOR WORK LT 2 11 10/8/2018 12/24/2018
DEMOLITION WORK 1 10/8/2018 10/12/2018
Demolish existing Interior & furniture 0.61 1 10/8/2018 10/12/2018 0.611
FLOOR WORK 7 10/18/2018 12/5/2018
homogenus tile #1 1.80 3 10/25/2018 11/7/2018 0.599 0.599 0.599
resilient floor finish type-1 1.15 3 11/17/2018 11/30/2018 0.383 0.383 0.383
general server room raised floor in HPL finish 0.08 2 12/1/2018 12/5/2018 0.080
To smooth screed (aci) for vynil & carpet tile 1.03 5 10/18/2018 11/16/2018 0.207 0.207
CEILING WORK 6 10/18/2018 11/23/2018
ceiling gypsum board 1.12 5 10/18/2018 11/16/2018 0.224 0.224 0.224 0.224 0.224
exposed slab ceiling 0.46 5 10/18/2018 11/16/2018 0.092 0.092 0.092 0.092 0.092
wooden lattice ceiling 0.59 2 11/17/2018 11/23/2018 0.293 0.293
gypsum perforated ceiling 0.39 2 11/17/2018 11/23/2018 0.193 0.193
plywood backing for existing perimeter curtain box 0.12 5 10/18/2018 11/16/2018 0.024 0.024 0.024 0.024 0.024
vertical gypsum ceiling in paint finish (PT-1) 0.08 5 10/18/2018 11/16/2018 0.017 0.017 0.017 0.017 0.017

PARTITION WORK 8 10/11/2018 11/30/2018


Partition type gypsum 2.23 5 10/11/2018 11/9/2018 0.445 0.445 0.445 0.445 0.445
glass partition type - 1 1.53 3 11/17/2018 11/30/2018 0.509 0.509 0.509
partition on ceiling cavity 0.51 5 10/25/2018 11/23/2018 0.101 0.101 0.101 0.101 0.101
timber skirting in duco finish 0.35 3 11/17/2018 11/30/2018 0.117 0.117 0.117
DOOR WORK 2 12/1/2018 12/14/2018
swing glass door 1.46 3 12/1/2018 12/14/2018 0.488 0.488 0.488
swing wooden door 1.33 3 12/1/2018 12/14/2018 0.442 0.442 0.442
single firerated metal door 0.37 3 12/1/2018 12/14/2018 0.122 0.122 0.122
WALL FINISHES 4 12/1/2018 12/24/2018
paint finish type - 3 0.13 4 12/1/2018 12/21/2018 0.032 0.032 0.032 0.032
general wallpaper finish type-1 1.18 4 12/6/2018 12/24/2018 0.294 0.294 0.294 0.294
feature column 0.13 4 12/1/2018 12/21/2018 0.033 0.033 0.033 0.033
wall feature 0.61 4 12/1/2018 12/21/2018 0.153 0.153 0.153 0.153
WET AREA 5 11/1/2018 12/4/2018
waterproofing to be applied into floor and wall 0.01 4 11/1/2018 11/21/2018 0.012

high water barier for wudhu 0.02 2 11/22/2018 11/26/2018 0.018


homogenus tile # 0.39 2 11/27/2018 12/3/2018 0.196 0.196
water tap 0.03 53 12/4/2018 12/4/2018 0.001
floor drain 0.01 53 12/4/2018 12/4/2018 0.000
OTHER WORKS 2 12/11/2018 12/24/2018
pendant lamp type 0.40 2 12/20/2018 12/24/2018 0.202 0.202
manual solar screen roller blinds 0.65 3 12/11/2018 12/24/2018 0.218 0.218 0.218
room signage #2 0.16 2 12/20/2018 12/24/2018 0.079 0.079
BUILT IN FURNITURE 5.54 8 11/1/2018 12/21/2018 0.692 0.692 0.692 0.692 0.692 0.692 0.692 0.692 0.692

LOOSE FURNITURE 3.01 8 11/1/2018 12/21/2018 0.376 0.376 0.376 0.376 0.376 0.376 0.376 0.376 0.692
INTERIOR WORK LT 4 11 10/13/2018 12/24/2018
DEMOLITION WORK 1 10/13/2018 10/17/2018
Demolish existing Interior & furniture 0.61 2 10/13/2018 10/17/2018 0.306 0.306
FLOOR WORK 7 10/23/2018 12/10/2018
homogenus tile #1 1.22 3 10/30/2018 11/12/2018 0.407 0.407 0.407
resilient floor finish type-1 1.19 3 11/22/2018 12/5/2018 0.398 0.398 0.398
general server room raised floor in HPL finish 0.21 2 12/6/2018 12/10/2018 0.210
To smooth screed (aci) for vynil & carpet tile 1.12 5 10/23/2018 11/21/2018 0.224 0.224 0.224 0.224 0.224
CEILING WORK 6 10/23/2018 11/30/2018
ceiling gypsum board 0.72 5 10/23/2018 11/21/2018 0.143 0.143 0.143 0.143 0.143

exposed slab ceiling 0.68 5 11/1/2018 11/30/2018 0.135 0.135 0.135 0.135 0.135
gypsum perforated ceiling 0.20 2 11/22/2018 11/28/2018 0.101 0.101
plywood backing for existing perimeter curtain box 0.12 5 10/23/2018 11/21/2018 0.024 0.024 0.024 0.024 0.024
vertical gypsum ceiling in paint finish (PT-1) 0.08 5 10/23/2018 11/21/2018 0.017 0.017 0.017 0.017 0.017
PARTITION WORK 7 10/16/2018 11/28/2018
Partition type gypsum 1.70 5 10/16/2018 11/14/2018 0.340 0.340 0.340 0.340 0.340
glass partition type - 1 1.36 3 11/8/2018 11/21/2018 0.452 0.452 0.452
partition on ceiling cavity 0.43 5 10/30/2018 11/28/2018 0.087 0.087 0.087 0.087 0.087
timber skirting in duco finish 0.20 3 11/8/2018 11/21/2018 0.068 0.068 0.068

DOOR WORK 3 11/24/2018 12/14/2018


swing glass door 1.47 3 12/1/2018 12/14/2018 0.489 0.489 0.489
swing wooden door 0.54 3 12/1/2018 12/14/2018 0.181 0.181 0.181
single firerated metal door (800x2700mm) 0.37 3 12/1/2018 12/14/2018 0.122 0.122 0.122
Rel Folding solid core partition 5.98 3 11/24/2018 12/3/2018 1.994 1.994 1.994
Rel Folding glass partition (approx. size 3600x2700mm) 3.96 3 11/24/2018 12/3/2018 1.320 1.320 1.320
WALL FINISHES 4 12/1/2018 12/24/2018
paint finish type - 1 0.15 4 12/1/2018 12/21/2018 0.038 0.038 0.038 0.038
general wallpaper finish type-1 0.76 4 12/6/2018 12/24/2018 0.189 0.189 0.189 0.189
feature column 0.37 4 12/1/2018 12/21/2018 0.092 0.092 0.092 0.092
wall feature 0.83 4 12/1/2018 12/21/2018 0.208 0.208 0.208 0.208
OTHER WORKS 2 12/11/2018 12/24/2018
pendant lamp type 0.08 2 12/20/2018 12/24/2018 0.042 0.042
manual solar screen roller blinds 0.57 3 12/11/2018 12/24/2018 0.191 0.191 0.191
room signage #2 0.13 1 12/20/2018 12/23/2018 0.128
BUILT IN FURNITURE 5.10 8 11/1/2018 12/21/2018 0.637 0.637 0.637 0.637 0.637 0.637 0.637 0.637

LOOSE FURNITURE 5.00 8 11/1/2018 12/21/2018 0.625 0.625 0.625 0.625 0.625 0.625 0.625 0.625
INTERIOR WORK LT 5 10 10/18/2018 12/24/2018
DEMOLITION WORK 1 10/18/2018 10/22/2018
Demolish existing Interior & furniture 0.61 2 10/18/2018 10/22/2018 0.306 0.306
FLOOR WORK 6 10/23/2018 12/3/2018
homogenus tile #1 0.60 3 11/6/2018 11/19/2018 0.199 0.199 0.199
resilient floor finish type-1 0.13 2 11/22/2018 11/28/2018 0.064 0.064
general server room raised floor in HPL finish 0.08 2 11/29/2018 12/3/2018 0.040 0.040
To smooth screed (aci) for vynil & carpet tile 0.90 5 10/23/2018 11/21/2018 0.181 0.181 0.181 0.181 0.181
CEILING WORK 7 10/30/2018 12/14/2018
flat ceiling gypsum board 0.72 5 10/30/2018 11/28/2018 0.143 0.143 0.143 0.143 0.143
exposed slab ceiling 0.18 5 11/15/2018 12/14/2018 0.036 0.036 0.036 0.036 0.036
wooden lattice ceiling 0.29 2 11/29/2018 12/5/2018 0.147 0.147
ceiling in laminate finish with plywood backing 0.68 2 12/6/2018 12/12/2018 0.340 0.340
plywood backing for existing perimeter curtain box 0.12 5 10/30/2018 11/28/2018 0.024 0.024 0.024 0.024 0.024
vertical gypsum ceiling in paint finish (PT-1) 0.08 5 10/30/2018 11/28/2018 0.016 0.016 0.016 0.016 0.016
PARTITION WORK 7 10/23/2018 12/5/2018
partition gypsum board 2.04 5 10/23/2018 11/21/2018 0.408 0.408 0.408 0.408 0.408
glass partition type - 1 1.66 3 11/15/2018 11/28/2018 0.554 0.554 0.554
gypsum partition on ceiling cavity 0.54 5 11/6/2018 12/5/2018 0.109 0.109 0.109 0.109 0.109
50mm high timber skirting in duco finish 0.35 3 11/15/2018 11/28/2018 0.118 0.118 0.118

DOOR WORK 2 12/1/2018 12/14/2018


swing glass door 1.56 3 12/1/2018 12/14/2018 0.522 0.522 0.522
swing wooden door 0.41 3 12/1/2018 12/14/2018 0.136 0.136 0.136
single firerated metal door 0.41 3 12/1/2018 12/14/2018 0.136 0.136 0.136
WALL FINISHES 4 12/1/2018 12/24/2018
paint finish type - 1 0.11 4 12/1/2018 12/21/2018 0.026 0.026 0.026 0.026
general wallpaper finish 1.04 4 12/6/2018 12/24/2018 0.260 0.260 0.260 0.260
wall feature 0.98 4 12/1/2018 12/21/2018 0.246 0.246 0.246 0.246 0.246 0.246 0.246 0.246
feature column 0.07 4 12/1/2018 12/21/2018 0.017 0.017 0.017 0.017

WET AREA 7 11/8/2018 12/22/2018


waterproofing to be applied into floor and wall 0.04 4 11/8/2018 11/28/2018 0.022 0.011 0.011
homogenus tile #6 0.65 2 12/4/2018 12/10/2018 0.326 0.326
toilet glass cubicle (incl. Glass door) 0.23 2 12/11/2018 12/17/2018 0.114 0.114
waterproof gypsum to toilet area 0.03 2 11/29/2018 12/3/2018 0.014 0.014
lavatory cabinet w/ solid surface fin 0.09 1 12/18/2018 12/22/2018 0.088

0.06 1 0.056
includes plywood backing, all fixings, accessories and indirect lighting 12/18/2018 12/22/2018
closet 0.07 1 12/18/2018 12/22/2018 0.067
under counter lavatory 0.02 1 12/18/2018 12/22/2018 0.018
Accessories Toilet 0.10 1 12/18/2018 12/22/2018 0.103
OTHER WORKS 3 12/4/2018 12/24/2018
manual roller blinds type 1 0.17 3 12/11/2018 12/24/2018 0.055 0.055 0.055
motorized roller blinds type 2 3.12 4 12/4/2018 12/24/2018 0.779 0.779 0.779 0.779
room signage #2 1.02 2 12/20/2018 12/24/2018 0.510 0.510
BUILT IN FURNITURE 6.06 8 11/1/2018 12/21/2018 0.757 0.757 0.757 0.757 0.757 0.757 0.757 0.757
LOOSE FURNITURE 4.87 8 11/1/2018 12/21/2018 0.608 0.608 0.608 0.608 0.608 0.608 0.608 0.608
PROJECT HAND OVER 12 10/3/2018 12/26/2018
Daily cleaning & Final Cleaning 2.80 13 10/3/2018 12/25/2018 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215 0.215
Project Hand Over / Office Relocation 1 12/26/2018 12/26/2018

PROGRESS PLANNING 4.72 2.01 2.53 3.58 8.56 9.74 10.39 12.16 12.41 13.47 9.88 7.83 4.42
COMMULATIVE PROGRESS PLANNING 4.72 6.73 9.26 12.85 21.41 31.15 41.54 53.70 66.11 79.57 89.45 97.28 101.70
PROGRESS ACTUAL 5.03 8.71 10.68 13.65
COMMULATIVE PROGRESS ACTUAL
DEVIATION

Prepared by :
PT. Gema Graha Sarana Tbk

Revy
Project Manager