CASH ADVANCE BREAKDOWN

OPERASIONAL HSE

DATE REQUEST : 25 februari 2018


DATE REQUIRED : 31 maret 2018
PROJECT : CPI - Intelligent Pigging Services
CONTRACT No : CW1411467 & CW1323988
LOCATION : Duri
AKTIFITAS :

PEMAKAIAN UNIT RATE TOTAL


No KETERANGAN Q'TY
DAY TRIP Rp Rp
1 Biaya permak coverall 22 Rp 120,000 Rp 2,640,000
2 Andromax 1 Rp 450,000 Rp 450,000
3 Transportasi BBM 75 Rp 8,000 Rp 600,000
4 Pulsa 1 Rp 200,000 Rp 200,000
5 ATK 1 Rp 500,000 Rp 500,000
6 Meals 1 Rp 1,500,000 Rp 1,500,000
7 Lain - lain 1 Rp 390,000 Rp 390,000
8 Trainer fundamental B & konsumsi 1 Rp 400,000 Rp 400,000
JUMLAH 6,680,000

Prepared by :
(HERI HERMAWAN)