FLOWCHART FOR QUALITY CONTROL INSPECTION

START

Incoming, In-process, Final


e.g. Arrival of material,
earthworks, pilling,
installation (Mounting
Structure, PV Module, CB,
MVPS, LPS), cable trench
preparation, etc.

QA/QC Team to perform


Repair inspection based on
complete! Checklist / Report / ITP
requirements

Operation Team to REJECT


Result?
perform repair work
?
ACCEPT

Operation Team to
proceed to next stage

END