"Film Title": Daily Progress Report # Shoot Day 1-Monday 10Th February 2014
"Film Title": Daily Progress Report # Shoot Day 1-Monday 10Th February 2014
PRODUCERS: DIRECTOR:
CO-PRODUCER: DOP:
Main Unit Start Date 10th Feb 2014 LOCATION D/N SCENE NO. SET SYNOPSIS PAGES
Main Unit Wrap Date29 March 2014 D4 37A 1/8
Total Days 39 D6 61pt1 3/8
Days to Date 1 D6 56 6/8
Days Remaining 38 D6 59pt1
Under / Over 0 UNIT BASE 3
TOTAL 4 2/8
MAIN UNIT TIME: Set Ups Pages Act.Timings Est.Timings Spread +/- SCENES COMPLETED:
Call on Set: 08:00 Prev. taken: 0 0 00:00:00 00:00:00 00:00 37A, 61pt1, 56 & 59pt1
Turnover AM: 09:18 Taken today: 19 4 2/8 00:04:14 00:03:42 +00:00:32
Lunch: 13:02-13:32 Taken to date: 19 4 2/8 00:04:14 00:03:42 +00:00:32 No. scenes completed today: 2
Turnover PM: 14:07 Remaining: x 102 4/8 01:35:48 01:35:48 x
Late Break: N/A Total Est.: x 106 6/8 01:40:02 01:39:30 +00:00:32 Scenes Part Complete:61pt1 & 59pt1
Camera Wrap: 18:32 Scenes Scheduled not shot: N/A
TOTAL HRS: 10 Hours 32 Mins Scenes being carried: n/a
Total no. of scenes: 152
Scenes completed to date: 2
Slate Numbers: 1-19
Scenes remaining: 150
ON SET
CONTRACT ARTISTE PART W # of Days P/U M/H/W TRAVEL ON LOC LUNCH WRAP DEPART
No. & Name worked ON SET
SW 1 06:10 06:24 07:53 08:03 13:02 18:32 19:10
SW 1 06:05 06:20 07:53 08:03 13:02 18:32 19:04
SW 1 06:10 06:20 07:53 08:03 13:02 18:32 19:10
SW 1 07:25 07:40 10:16 10:26 13:02 18:32 19:10
SW 1 08:15 08:35 14:40 14:50 13:00 18:32 19:26
SW 1 O/T 09:30 14:40 14:50 13:00 18:32 19:00
SW 1 O/T 09:30 14:40 14:50 13:00 18:32 19:00
SW 1 O/T 09:35 14:40 14:50 13:00 18:32 19:23
SW 1 O/T 09:10 14:40 14:50 13:00 18:32 19:23
STUNTS
N/A
NOTES:
1 x hour pre-call & 1 x hour de-rig for Lighting Department
1 x hour de-rig for
Page count, minutes & total no. of scenes are reflective of Shooting Script with PINK REVISIONS dated 10th February
NB: The Shooting Script with PINK REVISIONS dated 10th February is 103 2/8 pages in length. As we are having to shoot scenes in parts due to actors multi- roling, the total
page count showing on the call sheets will total 106 6/8 pages, this is what we will be showing on the progress reports. Please find attached a revised script count
breakdown from Script Supervisor.
SIGNITURE
CO PRODUCER
Cc:
Downloaded from FutureLearn Course: Film Production: Behind the Scenes of Feature Filmmaking
© Production Guild of Great Britain (February 2016)