"FILM TITLE"

PRODUCTION COMPANY AND PRODUCTION OFFICE ADDRESS

DAILY PROGRESS REPORT # SHOOT DAY 1- MONDAY 10TH FEBRUARY 2014


PRIVATE & CONFIDENTIAL

PRODUCERS: DIRECTOR:
CO-PRODUCER: DOP:

Main Unit Start Date 10th Feb 2014 LOCATION D/N SCENE NO. SET SYNOPSIS PAGES
Main Unit Wrap Date29 March 2014 D4 37A 1/8
Total Days 39 D6 61pt1 3/8
Days to Date 1 D6 56 6/8
Days Remaining 38 D6 59pt1
Under / Over 0 UNIT BASE 3

TOTAL 4 2/8

MAIN UNIT TIME: Set Ups Pages Act.Timings Est.Timings Spread +/- SCENES COMPLETED:
Call on Set: 08:00 Prev. taken: 0 0 00:00:00 00:00:00 00:00 37A, 61pt1, 56 & 59pt1
Turnover AM: 09:18 Taken today: 19 4 2/8 00:04:14 00:03:42 +00:00:32
Lunch: 13:02-13:32 Taken to date: 19 4 2/8 00:04:14 00:03:42 +00:00:32 No. scenes completed today: 2
Turnover PM: 14:07 Remaining: x 102 4/8 01:35:48 01:35:48 x
Late Break: N/A Total Est.: x 106 6/8 01:40:02 01:39:30 +00:00:32 Scenes Part Complete:61pt1 & 59pt1
Camera Wrap: 18:32 Scenes Scheduled not shot: N/A
TOTAL HRS: 10 Hours 32 Mins Scenes being carried: n/a
Total no. of scenes: 152
Scenes completed to date: 2
Slate Numbers: 1-19
Scenes remaining: 150

ON SET
CONTRACT ARTISTE PART W # of Days P/U M/H/W TRAVEL ON LOC LUNCH WRAP DEPART
No. & Name worked ON SET
SW 1 06:10 06:24 07:53 08:03 13:02 18:32 19:10
SW 1 06:05 06:20 07:53 08:03 13:02 18:32 19:04
SW 1 06:10 06:20 07:53 08:03 13:02 18:32 19:10
SW 1 07:25 07:40 10:16 10:26 13:02 18:32 19:10
SW 1 08:15 08:35 14:40 14:50 13:00 18:32 19:26
SW 1 O/T 09:30 14:40 14:50 13:00 18:32 19:00
SW 1 O/T 09:30 14:40 14:50 13:00 18:32 19:00
SW 1 O/T 09:35 14:40 14:50 13:00 18:32 19:23
SW 1 O/T 09:10 14:40 14:50 13:00 18:32 19:23

STUNTS
N/A

CROWD FACILITIES & ADDITIONAL TRANSPORT


N/A on set 1 x Production Trailer, 1 x Make up Truck, 1 x Costume Truck, 1 x Double Decker
46 x Crowd Fittings @ £25.00 each = £1150.00 Dining Bus, 1 x Base Genny, 3 x Three Ways, 1 x Base Honey Wagon
(Between dates of Weds 5th Feb to Monday 10th Feb 2014)
UP & RUNNING: 05:40
WRAP: 21:30
CATERING c/o DARU MEDICS/ANIMALS/MISC EQUIP/EFFECTS
Estimated Plate Count: 70 Breakfast: 07:00 Unit Medic on set today:
Actual Plate Count: 94 Lunch: 13:00 - 13:30

ADDITIONAL CREW:- ADDITIONAL EQUIPMENT


1 x Daily Electrician - N/A

ALEXA FOOTAGE CAMERA DURATION CAMERA & SOUND ROLLS

PREVIOUS 00:00:00 A CAM 01:19:54 CAMERA ROLLS A01-A06

TODAY 01:19:54 CAMERA GIGABYTES


SOUND ROLLS 1
SHOT TO DATE 01:19:54 A CAM 200.79 GB

NOTES:
1 x hour pre-call & 1 x hour de-rig for Lighting Department
1 x hour de-rig for
Page count, minutes & total no. of scenes are reflective of Shooting Script with PINK REVISIONS dated 10th February
NB: The Shooting Script with PINK REVISIONS dated 10th February is 103 2/8 pages in length. As we are having to shoot scenes in parts due to actors multi- roling, the total
page count showing on the call sheets will total 106 6/8 pages, this is what we will be showing on the progress reports. Please find attached a revised script count
breakdown from Script Supervisor.

SIGNITURE
CO PRODUCER

Cc: