PEKERJAAN LANTAI II

Teluknaga, 29 Sep
No. Jenis Pekerjaan Vol./Sat H.Satuan
1 2 3 4
I PEK.BETON BERTULANG / STRUKTUR
1 Beton kolom
- Uk. 30 x 30 ( K2 ) 4.40 m3 2,200,000.00
- Uk. 10 x 40 2.20 m3 2,150,000.00
2 Beton balok konstruksi
- Uk. 25 x 30 5.90 m3 2,300,000.00
3 Beton lantai
- Beton pelat lantai dan selasar 20.00 m3 2,350,000.00
Sub total I
II PEKERJAAN DINDING
1 Pas. Dinding bata ruangan 58.40 m2 38,400.00
2 Plester & aci 112.00 m 2
34,700.00
Sub total II
III PEKERJAAN LANTAI
1 Pas.krmk Ruang Uk. 40 x 40 133.00 m2 86,620.00
Sub total III
IV PEK.INS.LISTRIK & Acc
1 Instalasi lampu penerangan 16.00 titik 175,000.00
2 Instalasi stop kontak 2.00 titik 165,000.00
Sub total IV
V PEKERJAAN PENGECATAN /
FINISHING
1 Pengecatan dinding vinilex 117.00 m2 25,500.00
2 Pengecatan plafond lt.bawah 133.00 m2 25,500.00
SUB TOTAL VIII
TOTAL PEKERJAAN LANTAI II
Dibulatkan
Teluknaga, 29 September 2018
Jumlah Total
5 6

2,200,004.40
4,730,000.00

13,570,000.00

47,000,000.00
67,500,004.40 67,500,004.40

2,242,560.00
3,886,400.00
6,128,960.00 6,128,960.00

11,520,460.00
11,520,460.00 11,520,460.00

1,225,000.00
825,000.00
2,050,000.00 2,050,000.00

2,983,500.00
3,391,500.00
6,375,000.00 6,375,000.00
93,574,424.40
93,574,500.00