AATVIK CONSULTANCY & INFRASTRUCTURE

E-2/195, ARERA COLONY, BHOPAL (M.P.)

ACE/NDT/2018/ 12 Date : 21/10/2018


Testing Report of NDT (Rebound Hammer) , Adinath Motors, Station Road, Tilak Ganj, Sagar (M.P.)
Slab of M-20 (Old Structure)
(Date of Visit 18/10/2018)
S.No. BLOCK SLAB GRID MEAN OF CASTING R. V.-1 R. V.-2 R. V.-3 R. V.-4 R. V.-5 R. V.-6 AVG. A.R.R.N. S.D R.C.S. A.C.S Remark

1 SLAB -S-1 1 X 1-Y 1 MANUAL 33 35 41 37 25 36 34.50 26.00 4.89 20.00 23.69 OK


2 SLAB -S-2 1 X 1-Y 1 MANUAL 37 34 32 35 38 40 36.00 26.00 2.65 20.00 26.68 OK
3 SLAB -S-3 1 X 1-Y 1 MANUAL 42 43 40 45 40 41 41.83 26.00 1.77 20.00 32.05 OK
4 SLAB -S-4 2 X2-Y1 MANUAL 27 26 25 26 28 27 26.50 26.00 0.96 20.00 20.43 OK
5 SLAB -S-5 2 X2-Y1 MANUAL 28 26 26 25 28 26 26.50 26.00 1.12 20.00 20.31 OK
6 SLAB -S-6 2 X2-Y1 MANUAL 28 32 30 25 25 27 27.83 26.00 2.54 20.00 20.23 OK
7 SLAB -S-7 2 X2-Y1 MANUAL 27 26 26 27 28 28 27.00 26.00 0.82 20.00 20.95 OK
8 SLAB -S-8 3 X 3- Y 1 MANUAL 27 31 33 25 27 23 27.67 26.00 3.40 20.00 19.41 OK
9 SLAB -S-9 3 X 3- Y 1 MANUAL 28 25 26 28 26 25 26.33 26.00 1.25 20.00 20.07 OK
10 SLAB -S-10 3 X 3- Y 1 MANUAL 32 26 34 37 34 22 30.83 26.00 5.18 20.00 20.52 OK
11 SLAB -S-11 3 X 3- Y 1 MANUAL 34 32 33 32 33 32 32.67 26.00 0.75 20.00 25.54 OK
12 SLAB -S-12 3 X 3- Y 1 MANUAL 34 33 33 30 32 28 31.67 26.00 2.05 20.00 23.69 OK
13 SLAB -S-13 1 X 1-Y 1 MANUAL 48 45 38 36 36 33 39.33 26.00 5.34 20.00 27.19 OK
14 SLAB -S-14 1 X 1-Y 1 MANUAL 40 41 39 40 41 42 40.50 26.00 0.96 20.00 31.63 OK

Note : RV = Rebound Value, AVG = Average, ARRN = Average Required Rebound Number, SD = Standard Deviation, ACS = Average Compressive Strength
RCS = Required Compressive Strength

Structural Engineer Authorized Signatory


Ankesh Shrivastava
Ex. Asst. Professor (SATI Engg., Vidisha )