PROJECT:QͲZONE–LIWANDEVELOPMENTMIXEDUSE SECTION:264300

(MU)PLOTMU002,MU007ANDMU005&006AT
SURGEPROTECTION
DUBAILAND–WADIALSAFAͲ2
Page1of4
JULY2017
CLIENT:M/S.ALMAZAYAREALESTATEFZLLC
REVISION:0
MAINWORKTENDER

PART – 1 GENERAL

1.1 SECTION INCLUDES

1.1.1 This section supplements all other Contract Documents and forms part of every
section of Division 26 Electrical.

1.1.2 Include The Employer’s Requirement as part of this section.

1.1.3 The Contractor shall become familiar with other sections of the Specifications
affecting work of this trade.

1.1.4 Furnish all labour, materials, plant, equipment and appliances and perform all
necessary operations required to execute the work of this section.

1.1.5 This section describes the technical requirements for transient over voltage surge
suppression systems

1.2 RELATED SECTIONS

1.2.1 This schedule is intended to be used as a helpful indication of the related sections
within the Project Specifications. It is not necessarily comprehensive or complete and
it is the Contractor's responsibility to ascertain all applicable sections required to
understand the full Scope of Works intended.

1.3 REFERENCES

1.3.1 The minimum standards for products specified in this section shall be those
standards referred to or relevant BSI standards. In addition, the following additional
standards also apply:

x BS EN 62305 part-4
x BS 6651
x BS 2914
x BS 7671
x CCITT IX K12
x CCITT IX K17
x CCITT IX K25
x ECMA 97
x IEEE C62.41
x UL 1449
x AS 1768

1.4 SUBMITTALS FOR REVIEW

1.4.1 Submit samples, specifications, engineering calculations, catalogue cut sheets,


description of product and installation method in accordance with the Contract
Documents. Submissions shall indicate all dimensions, details of construction,
details of installation, relation and connections with adjoining work.

6HFWLRQ 
PROJECT:QͲZONE–LIWANDEVELOPMENTMIXEDUSE SECTION:264300
(MU)PLOTMU002,MU007ANDMU005&006AT
SURGEPROTECTION
DUBAILAND–WADIALSAFAͲ2
Page2of4
JULY2017
CLIENT:M/S.ALMAZAYAREALESTATEFZLLC
REVISION:0
MAINWORKTENDER

1.4.2 Submit copies of test reports required to be performed on the proposed products.

1.4.3 Submit a list of installation completed where proposed products were used. Submit
single line wiring diagrams showing the wiring configuration for all Surge Protection
Devices (SPD) installed. Show all conductors and terminal numbers.

1.5 QUALITY ASSURANCE

1.5.1 Perform Work in accordance with relevant British Standards and industry standard
codes.

1.6 QUALIFICATIONS

1.6.1 System shall be manufactured by an ISO 9002 certified company with a 10 year
history of supplying transient over voltage suppression systems to ensure credibility
of warranty and continuity of technical support. Five equivalent size project
references shall be provided for reference and system demonstration.

1.7 ENVIRONMENTAL REQUIREMENTS

1.7.1 Store SPD equipment in accordance with the manufacturer’s requirements.

1.7.2 The external environment is hot (up to 52ºC), humid (up to 32ºC saturated and
moisture contents up to 0.030 kg/kg), dusty (up to 70mg/m³) and saline (within
200m of the shoreline).

1.8 WARRANTY

1.8.1 All materials shall have a standard 12 month warranty from the time of practical
completions. The Contractor shall allow for extended warranties beyond this period
where indicated in this document or elsewhere within the main contract documents.
The extended warranties shall be in the Client’s name and be handed over at the time
of practical completion.

PART – 2 PRODUCTS

2.1 SYSTEM SURGE ARRESTORS

2.1.1 All applicable standard specifications noted under item 1.3.1 shall apply.

2.1.2 Transient Voltage Surge Suppression (SPD) shall be provided at each main L.V.
switchboard.

2.1.3 Power Conditioning Filter, Transient Voltage Surge Suppression (SPD), and high
frequency electrical line noise filtering to meet BS 6651 & BS EN 62305 part-4. The
unit shall be connected on the load side of each main switchboard.

2.1.4 Unit shall operate on a voltage system of 230/400 volts, 50 Hz. 3 phase grounded star
point.

2.1.5 The unit’s primary mode of protection shall be line-to-neutral. The secondary nodes of
protection shall be line-to-ground and neutral-to-ground.
6HFWLRQ 
PROJECT:QͲZONE–LIWANDEVELOPMENTMIXEDUSE SECTION:264300
(MU)PLOTMU002,MU007ANDMU005&006AT
SURGEPROTECTION
DUBAILAND–WADIALSAFAͲ2
Page3of4
JULY2017
CLIENT:M/S.ALMAZAYAREALESTATEFZLLC
REVISION:0
MAINWORKTENDER

2.1.6 The unit shall include an engineered solid-state high-performance suppression system,
utilizing selenium cells and fused non-linear voltage dependent metal oxide arrestors,
with similar operating characteristics. The unit shall provide solid-state suppression
area of 2520 sq. inches to ensure maximum performance reliability. The unit shall
include a high-frequency extended range-tracking filter. The filter shall reduce fast rise-
time, high frequency, error producing transients and electrical line noise to harmless
levels.

2.1.7 The unit shall include solid-state, long-life, externally mounted LED visual status
indicators that indicate the on-line status of each phase of the unit.

2.1.8 The unit shall incorporate an integral test point, allowing easy off-line diagnostic
testing, which verifies the operational integrity of the unit’s suppression/filter system.
Standard surface-mounted units shall be provided in an enclosure of 14-gauge steel,
painted inside and out. The unit shall include an integral fused and safety interlocked
disconnect switch, located in the unit enclosure with an externally mounted manual
operator. The switch shall disconnect all ungrounded circuit conductors from the
distribution system, to enable testing and maintenance without interruption of power to
the facility’s distribution system. The switch shall be rated for 600 V AC. Each current-
carrying ungrounded circuit conductor connected to the facility’s distribution system
shall be individually fused.

2.2 SURGE SUPPRESSION DEVICES (SPD) DOCUMENTATION & TESTING.

2.2.1 Equipment Manual - The manufacturer shall furnish an equipment manual with
installation, operation, and maintenance instructions for the specified unit.

2.2.2 Drawings - Electrical and mechanical drawings shall be provided by the manufacturer,
which show unit dimensions, weights, mounting provisions, connection details and
layout diagram of the unit.

2.2.3 Suppression Ratings - Documentation of unit’s suppression rating shall be included, as


required product data submittal information. Manufacturer shall make available upon
request certified documentation of applicable Location Category Testing, in full
compliance with BS6651.

2.2.4 Spare Parts - A list of customer-replaceable spare parts shall be included in the unit’s
installation, operation and maintenance instructions. All spare parts shall be quickly
and easily field-replaceable.

PART – 3 EXECUTION

3.1 EXAMINATION

3.1.1 Before ordering any materials / commencing work verify that building structure
associated with the system is within tolerance and take full account of shape
configuration and material properties of the structure.

3.2 HANDLING AND STORAGE

3.2.1 Deliver component parts to site, completely identified in accordance with shop and
6HFWLRQ 
PROJECT:QͲZONE–LIWANDEVELOPMENTMIXEDUSE SECTION:264300
(MU)PLOTMU002,MU007ANDMU005&006AT
SURGEPROTECTION
DUBAILAND–WADIALSAFAͲ2
Page4of4
JULY2017
CLIENT:M/S.ALMAZAYAREALESTATEFZLLC
REVISION:0
MAINWORKTENDER

certified drawings prepared for this work. Store in accordance with manufacturer's
instructions, above ground, properly protected from the weather and construction
activities.

3.3 FABRICATION

3.3.1 All components shall be fabricated at the manufacturers production facility

3.3.2 Before beginning installation in any area, examine all parts of the adjoining work into
which applicable work is to be placed. Should any conditions be found which will
prevent the proper execution of the work, installation shall not proceed in that area
until such conditions are corrected by the contractor.

3.4 FIELD QUALITY CONTROL

3.4.1 Provide field quality control as indicated in The Employer’s Requirements.



3.5 CLEANING

3.5.1 Cleaning installed work as indicated in The Employer’s Requirements.

3.5.2 Remove labels after Work is complete.

3.6 PROTECTION OF FINISHED WORK

3.6.1 Protect work as indicated in The Employer’s Requirements.

3.7 STANDARD SPECIFICATION

3.7.1 The standard specifications for product, service, installation etc. are predominantly
based on relevant BS/EN standards. However, any internationally recognized standard
and complying to intent of the product, service, installation etc. shall also be considered
subject to proper compliance / justification to the satisfaction of engineer.

3.7.2 This standard specification is intended to be used as a helpful indication of work within
this section. It is not necessarily comprehensive or complete and it is the Contractor's
responsibility to ascertain and complete the full works intended and as shown within
the drawings, specification and Contract or thereby implied.

END OF SECTION