School of Vocational Engineering, Health and Sciences
School of Vocational Engineering, Health and Sciences
PROBLEM 1
Based on the network diagram presented below, complete the table showing the activity relationships.
Complete Table 1 in page 2 by identifying the precedence relationship among the activities.
Activity Predecessor
T1 None
R2 None
H None
S T1
E1 R2
D2 T1
W T1
P1 W
P2 D2, W
T2 S, E1, H
X H
O2 T2, P1
F D2, W
R1 P2, F
E P1, P2, F, T2
L O2, X
G L
PROBLEM 2
Based on the network diagram presented below, complete the table given in page 4. T h e p r o j e c t
starts with the Activity E2 and finishes with the Activity P.
Activity Predecessor
E2 Start
A1 E2
X E2
Z E2
L E2
B X, A1
K3 X, Z
E L, Z
I B
R B
F K3
G K3
N2 E
Q I
S1 E, G, F
K2 R, N2
S2 S1, R
B1 K2, Q
P S2, B1
PROBLEM 3
Based on the network diagram presented below, complete the table showing the activity relationships:
Activity Predecessor
PROBLEM 4
The activities for a project and the precedence relationship among the identified activities are given in
Table 1. The project starts with the activity A and finishes with activity F.
Activity Predecessor
A -
E A
C A
D E
B E, C
F D, B
E D
A
DUMMY
START
F FINISH
C
B
PROBLEM 5
An engineering project consists of 11 different inter-dependent activities. The identified precedence
relationships among the activities are given in Table 2. The project starts with Activity A and Activity E and
finishes with the Activity K.
A - G E
B A H F
C A I G
D C J H, I
E - K B, D, J
F E
A C K
D FINISH
J
START E G I