Time Schedule Docking Project PDF
Time Schedule Docking Project PDF
1 2 3 4 5 6 7 8 9 10 11 12 13
Bobot Progress
NO DESCRIPTION OF WORKS Lama pekerjaan Alat /Gun
%
Progress % Actual Progress % SEPTEMBER 2018
6 7 8 9 10 11 12 13 14 15 16 17 18
Docking Preparation 5.00% 60.00% 3.00%
Kapal datang & tambat 1 0.50% 0.50%
Hari
Pemasangan kupingan tarik 1 0.50% 0.50%
Hari
Proses Docking 1 Hari 2.00% 2.00%
Proses Undocking 1 Hari 2.00% 2.00%
SANDBLASTING DAN PAINTING 10 Hari 60.00% 69.11% 41.47% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00% 6.00%
Total 100.00% 3.00% 3.94% 11.04% 10.45% 11.02% 11.02% 9.33% 8.23% 8.23% 7.50% 6.00% 8.25% 2.00%
6.94% 17.98% 28.43% 39.45% 50.46% 59.79% 68.02% 76.25% 83.75% 89.75% 98.00% 100.00%