Year Flexible Pavement (In Lakhs) Rigid Pavement (In Lakhs) Construction Cost Maintenance Cost NPV (1/1.10) N Construction Cost
Year Flexible Pavement (In Lakhs) Rigid Pavement (In Lakhs) Construction Cost Maintenance Cost NPV (1/1.10) N Construction Cost
Year
Construction Cost Maintenance Cost NPV(1/1.10)^n Construction Cost
0 134 - 134 169
1 - 1.20 1.09 -
2 - 1.26 1.04 -
3 - 1.32 0.99 -
4 - 1.39 0.95 -
5 - 26.98 16.76 -
6 - 1.53 0.86 -
7 - 1.61 0.83 -
8 - 1.69 0.79 -
9 - 1.77 0.75 -
10 - 63.91 24.64 -
11 - 1.95 0.69 -
12 - 2.05 0.65 -
13 - 2.16 0.62 -
14 - 2.26 0.60 -
15 - 43.95 10.52 -
16 - 2.49 0.54 -
17 - 2.62 0.52 -
18 - 2.75 0.49 -
19 - 2.89 0.47 -
20 - 104.11 15.48 -
Total NPV Cost 213.29