Measurement Sheet For False Ceiling Work: Project: Ashok SPG CONTRACTOR: DEEPAK Enterprisess
Measurement Sheet For False Ceiling Work: Project: Ashok SPG CONTRACTOR: DEEPAK Enterprisess
Measurement Sheet For False Ceiling Work: Project: Ashok SPG CONTRACTOR: DEEPAK Enterprisess
Erection Area
New Area 44.27 5 1 221.35 2381.726
Ringing Frame 35 2 1 70 753.2
Total 3134.926
Dismentiling Area
New Area 26.84 5 1 134.2 1443.992
Ringing Frame 35 2 1 70 753.2
Total 2197.192
SUMMARY
S.no Discription SQMT SQFT NOS /KG /RMT Rate Total Amt
1 Square Ducting
Labour Erection 1378.4 14831.51944 14 207641.2722
Dismentiling 84.0 903.84 7 6326.88
2 Ducting Insulation
Material 1141.3 12279.95975 27 331558.9133
Labour 1141.3 12279.95975 5 61399.79876
3 False ceiling
Labour 3134.926 12 37619.112
Dismentiling 2197.192 5 10985.96
4 M.S Fram Frabriction Kg 7300 15 109500
5 Black Japan labour 639.8 6883.71 3.5 24092.985
6 Diffsuer Fixing Nos 40 500 20000
7 Round Ducting ( Total Amt)
8 Band 150 Nos 1 700 700
9 Damper 150 Nos 1 900 900
10 Square Ducting M.S Damper
Material Nos 2 12000 24000
Fixing Labour Nos 2 1000 2000
11 False ceiling Material
Wall Angle Nos 50 130 6500
Main Tee Nos 52 190 9880
Cross Tee Nos 220 230 50600
False ceiling sheet (
3040 22 66880
4*2=8*380nos=3040)
Line 1 No
87.425 940.695
88.967 957.287
97.648 1050.692
1378.329 14830.824