Professional Documents
Culture Documents
ITS1000m Mini Shelter v100r003c02 Q PDF
ITS1000m Mini Shelter v100r003c02 Q PDF
Issue: 01
Date: 2012-08-13
Preparations 3
Precautions 3
Installation Requirements 3
Mounting Hole Dimensions 4
Tools 5
Installation Process 6
Installing a Single-Cabinet Mini-shelter As a Whole 6
Installing a Single-Cabinet Mini-shelter (Disassembled Mode) 6
Installing a Dual-Cabinet Mini-shelter (Disassembled Mode) 6
Installing a Triple-Cabinet Mini-shelter (Disassembled Mode) 6
Installing a Mini-shelter 7
Installing a Single-Cabinet Mini-shelter with Battery Racks (Disassembled Mode) 7
Installing a Single-Cabinet Mini-shelter with 19-in Racks (Disassembled Mode) 11
Installing a Single-Cabinet Mini-shelter with BTS Racks (Disassembled Mode) 15
Installing a Single-Cabinet Mini-shelter with Combination Racks (Disassembled Mode) 19
Installing a Single-Cabinet Mini-shelter As a Whole 23
Installing a Dual-Cabinet Mini-shelter (Disassembled Mode) 24
Installing a Triple-Cabinet Mini-shelter (Disassembled Mode) 27
Installing a Rack 30
Installing Combination Cabinets 37
Installing Components in a Mini-shelter 38
Installing a Door Status Sensor 38
Installing a Smoke Sensor 39
Installing a Signal Transfer Board 40
Install a Temperature and Humidity Sensor 41
Installing a Battery Temperature Sensor 42
Installing a Water Sensor 42
Installing an ACDB 43
Installing a MTS 43
Installing a DUDU 43
Installing a DCDB 44
Installing a BBU 44
Installing the ETP48200 45
Installing the BTS3900 45
If a Mini-shelter is assembled onsite, the site environment should be equal to or above 0°C.
If the cabinet is scratched during transportation, paint or apply glue to the scratched areas.
Do not step on the base of the shelter to avoid sand and dust.
Before disassembly, clear the space for arranging components, and lay protection materials to protect the components from
scratches and damages. During disassembly, keep small structures and fixtures such as screws together and use
appropriate screwdrivers to avoid stripping screws.
A Mini-shelter should be installed in a high place where water can be easily drained. Swales and the areas prone to
pondings are unsuitable for site construction.
The cabinet must comply with installation space requirements for later cabinet maintenance.
Maintenance personnel must be safe when they maintain at the front door of the Mini-shelter.
The Mini-shelter is not exposed to direct sunlight and stays away from the wind.
When installing a mini-shelter in a residential area, ensure the Mini-shelter doors do not face the residential area.
The following figure shows the required clearances around the Mini-shelter.
≥ 2000 mm
3
Mounting Hole Dimensions
Single-Cabinet Mini-shelter
200 mm
142 mm
899 mm
850 mm
899 mm
850 mm
216 mm
Ø16 mm
Front
Door side
Dual-Cabinet Mini-shelter
200 mm
1748 mm
1699 mm
899 mm
850 mm
216 mm
Ø16 mm
Front
Door side
899 mm
850 mm
850 mm
899 mm
216 mm
Ø16 mm
Front
Door side
4
Cabinet-Combination Mini-shelter (1+1+1)
2727 mm
15 mm 15 mm
200 mm
899 mm
850 mm
899 mm
850 mm
216 mm
Front Ø16 mm
Door side
Tools
Mandatory Tools
Segmented
COAX crimping tool Level blade utility knife Hydraulic pliers Diagonal pliers
Optional Tools
5
Installation Process
Installing a Single-Cabinet Mini-shelter As a Whole Installing a Single-Cabinet Mini-shelter (Disassembled
Mode)
Install components
Remove the top frame Install the top frame
inside the Mini-shelter
Separate the top frame Install the cabinet door Separate the top frame Install the cabinet door
from the top cover from the top cover
Install the middle wall Power on and commission Install the middle wall Power on and commission
panels the Mini-shelter panel the Mini-shelter
6
Installing a Mini-shelter
Installing a Single-Cabinet Mini-shelter with Battery Racks (Disassembled Mode)
Disassembling the Single-Cabinet Mini-shelter
1. Remove the door. 2. Remove the top cover.
Open the cabinet door to an angle of 90 degrees. Remove the four plastic plugs on the exterior of the
top cover using a flat-head screwdriver.
Arrange three persons to lift the door in the vertical direction.
Remove the four screws that secure the top cover to
Move the door outwards till it is away from the Mini-shelter the top beam of the Mini-shelter using a Phillips
and place it vertically. screwdriver. Note that the four screws are configured
with spring washers and large washers.
Raise the top cover from the cabinet interior and
• Do not face the cabinet door top downwards.
• If a cabinet is delivered onsite with its door disassembled and remove the top cover.
configured with an air conditioner, ensure that the door is secured to
the cabinet or stand the cabinet door upright for at least 2 hours
before powering on the air conditioner on the cabinet door.
Remove the wall panels by pushing them from the Remove the top frame.
cabinet interior.
7
Disassembling the Single-Cabinet Mini-shelterb
Straight
flange
8
Installing the Single-Cabinet Mini-shelter b
1. Secure the base. 2. Install the rack.
Place and secure the rack to the base using
eight M5 bolts.
Determine the door opening direction and then place the base
accordingly.
Mounting hole
Draw Move Drill Secure Remove Move Install and
on the base
four the holes the the back the secure
holes base expansi expansion base expansion
on tube bolts bolts
9
Installing the Single-Cabinet Mini-shelter
6. Install the wall panels.
5. Paste adhesive tape.
Paste adhesive tape on the edges of columns Rip off the film from the wall panel.
and top frame (left, right, and rear sides). Insert the wall panel into the installation position and
exert force to press the panel side beside which the
batten is to be installed.
Insert the battens beside wall panels.
Wall
panel
Film
10
Installing a Single-Cabinet Mini-shelter with 19-in Racks (Disassembled Mode)
Disassembling the Single-Cabinet Mini-shelter
1. Remove the door. 2. Remove the top cover.
Open the cabinet door to an angle of 90 degrees. Remove the four plastic plugs on the exterior of
Arrange three persons to lift the door in the vertical direction. the top cover using a flat-head screwdriver.
Move the door outwards till it is away from the Mini-shelter. Remove the four screws that secure the top cover
to the top beam of the Mini-shelter using a Phillips
screwdriver. Note that the four screws are
configured with spring washers and large washers.
•Do not face the cabinet door top downwards. Raise the top cover from the cabinet interior and
• If a cabinet is delivered onsite with its door disassembled remove the top cover.
and configured with an air conditioner, ensure that the door is
secured to the cabinet or stand the cabinet door upright for at
least 2 hours before powering on the air conditioner on the
cabinet door.
11
Disassembling the Single-Cabinet Mini-shelterb
5. Remove the columns. 6. Remove the rack.
Remove the two screws from the bottom of the two Remove the eight M5 screws that secure the
columns. base to the rack, and then remove the rack.
Remove the four columns by pulling them upwards from
the base (two straight flanges are disconnected from
the columns).
Straight
flange
12
Installing the Single-Cabinet Mini-shelter b
1. Secure the base.
2. Install the rack.
Place and secure the rack to the base using
eight M5 bolts.
Determine the door opening direction and then place
the base accordingly. Mounting hole
Draw Move Secure Remove Move Install and on the base
Drill
four the holes the the back the secure
holes base expansi expansion base expansion
on tube bolts bolts
Install the four columns on the base. Insert the feet of the top frame into the mounting holes on
top of the four columns.
Secure the four columns and two straight flanges
by using M5 screws. (Secure the two straight Measure the verticality of the columns using a level and
flanges to columns A and C) ensure that the columns are perpendicular to the ground.
Straight Secure the top and bottom of the four columns using the
flange M5 screws configured with corrugated washers.
Secure the rack top to the top frame using M5 self-tapping
screws.
13
Installing the Single-Cabinet Mini-shelter b
5. Paste adhesive tape. 6. Install the wall panels.
Paste adhesive tape on the edges of columns Rip off the film from the wall panel.
and top frame (left, right, and rear sides). Insert the wall panel into the installation position
and exert force to press the panel side beside
which the batten is to be installed.
Insert the battens beside wall panels.
Wall
panel
Film
14
Installing a Single-Cabinet Mini-shelter with BTS Racks (Disassembled Mode)
Remove the wall panels by pushing them from the cabinet Remove the top frame.
interior.
15
Disassembling the Single-Cabinet Mini-shelterb
Straight flange
16
Installing the Single-Cabinet Mini-shelter b
1. Secure the base. 2. Install the rack.
Place and secure the rack to the base using
eight M5 bolts.
Determine the door opening direction and then place
the base accordingly.
17
Installing the Single-Cabinet Mini-shelter b
6. Install the wall panels.
5. Paste adhesive tape. Rip off the film from the wall panel.
Paste adhesive tape on the edges of columns
Insert the wall panel into the installation position and
and top frame (left, right, and rear sides).
exert force to press the panel side beside which the
batten is to be installed.
Insert the battens beside wall panels.
Wall
panel
Film
1. When inserting the top cover, observe the insertion 1. The figure is for reference only. For details about
direction (indicated by the label) to ensure that the top how to install a cabinet door, see the related
cover points to the correct direction. drawings.
2. After the top cover is installed, push the top cover 2. After installing the Mini-shelter, apply paint or neutral
towards the direction of the door forcibly to minimize the silicon sealant to scratched areas if necessary.
gap between the top cover and the rear wall board.
Washer
18
Installing a Single-Cabinet Mini-shelter with Combination Racks (Disassembled Mode)
Disassembling the Single-Cabinet Mini-shelter
1. Remove the door. 2. Remove the top cover.
Open the cabinet door to an angle of 90 degrees. Remove the four plastic plugs on the exterior of
the top cover using a flat-head screwdriver.
Arrange three persons to lift the door in the vertical direction.
Remove the four screws that secure the top cover
Move the door outwards till it is away from the Mini-shelter. to the top beam of the Mini-shelter using a Phillips
screwdriver. Note that the four screws are
configured with spring washers and large washers.
•Do not face the cabinet door top downwards. Raise the top cover from the cabinet interior and
• If a cabinet is delivered onsite with its door disassembled remove the top cover.
and configured with an air conditioner, ensure that the door is
secured to the cabinet or stand the cabinet door upright for at
least 2 hours before powering on the air conditioner on the
cabinet door.
19
Disassembling the Single-Cabinet Mini-shelterb
Straight flange
20
Installing the Single-Cabinet Mini-shelter b
1. Secure the base. 2. Install the rack.
Place and secure the rack to the base using
eight M5 bolts.
Determine the door opening direction and then place the base
accordingly.
Draw Move Drill Secure Remove Move Install and Mounting hole
four the holes the the back the secure on the base
holes base expansi expansion base expansion
on tube bolts bolts
21
Installing the Single-Cabinet Mini-shelter b
6. Install the wall panels.
5. Paste adhesive tape.
Rip off the film from the wall panel.
Paste adhesive tape on the edges of columns
and top frame (left, right, and rear sides). Insert the wall panel into the installation position and
exert force to press the panel side beside which the
batten is to be installed.
Insert the battens beside wall panels.
Wall
panel
Film
1. When inserting the top cover, observe the insertion 1. The figure is for reference only. For details about
direction (indicated by the label) to ensure that the top how to install a cabinet door, see the related
cover points to the correct direction. drawings.
2. After the top cover is installed, push the top cover 2. After installing the Mini-shelter, apply paint or neutral
towards the direction of the door forcibly to minimize the silicon sealant to scratched areas if necessary.
gap between the top cover and the rear wall board.
Washer
22
Installing a Single-Cabinet Mini-shelter As a Whole
Installing a Single Cabinet
Insert the pallet truck into the holes at the bottom of the cabinet and
move the cabinet to the installation place using a pallet track.
Install expansion bolts in the mounting holes at the four corners of the cabinet bottom to secure the cabinet.
If the cabinet is 2.4 m high, remove the two supports from the base after securing the cabinet. For details about how
to remove the supports, see step 7 on page 20.
Draw four Move the Drill Secure the Remove Move Install and
holes cabinet holes expansion tube the back the secure
expansion base expansion
bolts bolts
23
Installing a Dual-Cabinet Mini-shelter (Disassembled Mode)
Installing the Dual-Cabinet Mini-shelter
1. Secure the base.
2. Install the columns.
24
Installing the Dual-Cabinet Mini-shelter
5. Install the middle wall panel.
6. Install the rack.
Place the wall panel between the two cabinets and tighten it
For details about how to install a battery rack, see
using two M5 screws.
pages 30 to 31.
For details about how to install a 19-inch rack, see
page 32.
For details about how to install a BTS rack, see
pages 33 to 34.
For details about how to install a combination rack,
see page 36.
Wall
panel
Film
25
Installing the Dual-Cabinet Mini-shelter
9. Install the top cover.
Place the top cover onto the top frame.
Install four M5 self-tapping screws and large washers.
Install four plastic plugs.
1. When inserting the top cover, observe the insertion direction (indicated by the label) to ensure that the top
cover points to the correct direction.
2. After the top cover is installed, push the top cover towards the direction of the door forcibly to minimize the
gap between the top cover and the rear wall board.
1. The figure is for reference only. For details about how to install a cabinet door, see the related drawings.
2. After installing the Mini-shelter, apply paint or neutral silicon sealant to scratched areas if necessary.
26
Installing a Triple-Cabinet Mini-shelter (Disassembled Mode)
Installing the Triple-Cabinet Mini-shelter
1. Secure the base. 2. Install the columns.
27
Installing the Triple-Cabinet Mini-shelter
5. Install the middle wall panel. 6. Install the rack.
Place the wall panel between the two cabinets and tighten it For details about how to install a battery rack, see
using two M5 screws. pages 30 to 31.
For details about how to install a 19-inch rack, see
page 32.
For details about how to install a BTS rack, see
pages 33 to 34.
For details about how to install a combination rack,
see page 36.
Wall
panel
Film
28
Installing the Triple-Cabinet Mini-shelter
9. Install the top cover.
Place the top cover onto the top frame.
Install four M5 self-tapping screws and large washers.
Install four plastic plugs.
1. When inserting the top cover, observe the insertion direction (indicated by the label) to ensure that the top cover
points to the correct direction.
2. After the top cover is installed, push the top cover towards the direction of the door forcibly to minimize the gap
between the top cover and the rear wall board.
1. The figure is for reference only. For details about how to install a cabinet door, see the related drawings.
2. After installing the Mini-shelter, apply paint or neutral silicon sealant to scratched areas if necessary.
29
Installing a Rack
This section applies to the scenario of installing a dual-cabinet or triple-cabinet Mini-shelter in disassembled mode.
30
Reshaping a 3-Layer Battery Rack to a 4-Layer Battery Rack
31
Installing a 19-Inch Rack
1. Get the following materials ready.
32
Installing a BTS Rack
33
Installing a BTS Rack
Secure the two 19-inch supports to the rack using thirty-two M5 x 10 self-tapping screws.
Secure the transit brackets to the 19-inch support using eight M5 x 10 self-tapping screws.
Secure the filler panels to the 19-inch support using twelve M6 x 12 self-tapping screws.
If no device is installed under the BTS rack, install the three filler panels to the lower 19-inch rack. If devices are
installed under the BTS rack, no filler panel is required.
34
Installing a Combination Rack
35
Installing a Combination Rack
Install a heat-insulation cotton on the heat-insulation Secure the cable tray to the cabinet top using four M6 x 10
cotton bracket according to the arrow direction. self-tapping screws.
Secure two 19-inch supports to the heat-insulation cotton Secure the cable connection box to the left and right sides
using eight M5 x 10 self-tapping screws and to the top of the rack using four M5 x 10 self-tapping screws.
frame using eight M5 x 10 self-tapping screws.
36
Installing Combination Cabinets
1. Cables from one cabinet are routed into the other cabinet through the cables holes at the cabinet bottom and corrugated
pipes.
2. For ease of turning at the cabinet bottom, use flexible corrugated pipes with an external diameter of 44 mm and the shortest
internal diameter of 32 mm in the areas with the ambient temperatures above –10ºC; use stainless corrugated pipes with the
external diameter of 44 mm and the shortest internal diameter of 31.8 mm in the areas with the ambient temperatures below
–10°C.
Place the L-shape nut base into the cabinet base and align the nut holes with the holes in the base. Then secure the nut base
to the L-shape connection plate using eight M8 x 25 mm bolts.
L-shape L-shape
nut base connection plate
L-shape
nut base
L-shape
connection
Base plate
M8 bolt
Concrete Pad
After installing the cabinet, connect the ground cable between the ground bar in the cabinet and the site ground point.
For details, see page 69. Then, install other devices.
37
Installing Components in a Mini-shelter
Installing a Door Status Sensor
1. Secure the door status sensor.
Secure the cable connection box of the door status sensor to the upper right corner of the cabinet using two M3 x 12 mm
screws.
Secure the magnet box of the door status sensor to the upper left corner of the compartment door using two M3 x 12 mm
screws.
Door status
sensor
Connect one end of the signal cable to the door status port on the signal transfer board to output signals from the output port
and the other end of the signal cable to a port on the monitoring equipment.
38
Installing a Smoke Sensor
1. Secure the smoke sensor.
Secure the smoke sensor base to the cabinet top using two screws screws and fasten the smoke sensor to the base based on
the direction shown in the smoke sensor.
Smoke
Sensor
UIM02C port
39
Installing a Signal Transfer Board
A signal transfer board applies only to the dual-cabinet and triple-cabinet scenario and connects to a maximum of three
door status sensors and three smoke sensors.
40
Installing a Temperature and Humidity Sensor
1. Secure the temperature and humidity sensor
Secure the temperature and humidity sensor base to the cabinet installation board using three M4 x 12 mm screws.
Connect and secure signal cables of the temperature and humidity sensor to the cabinet base, as shown in the following figure
Install the top cover of the temperature and humidity sensor to the cabinet base.
The final installation view is as follows.
In the dual-cabinet Mini-shelter and triple-cabinet Mini-shelter scenarios, install the ambient
temperature and humidity sensor on the 19-inch rack in the equipment compartment.
Temperature and
humidity sensor
41
Installing a Battery Temperature Sensor
1. Secure the battery temperature sensor.
Place the battery temperature sensor on the right rack in the middle of the battery compartment and secure it by using a cabl e
tie.
Sensor probe
Water sensor
42
Installing an ACDB
Slide the alternating current distribution box (ACDB) into the rack along the guide rails and tighten it using four M6 screws .
Installing a MTS
Slide the manual transfer switch (MTS) into the 19-inch rack along the guide rails and tighten it using four M6 screws.
Installing a DUDU
Slide the direct current distribution unit (DCDU) into the 19-inch rack along the guide rails and tighten it using four M6 screws.
43
Installing a DCDB
Slide the DCDB into the 19-inch rack along the guide rails and tighten it by using four M6 screws.
Installing a BBU
Align the two cable claws with the holes on the baseband unit (BBU) and secure the BBU using four M4 screws on the left
and right sides.
Slide the BBU into the 19-inch rack along the guide rails and tighten it using four M6 screws.
44
Installing the ETP48200
Slide the embedded telecom power (ETP48200) into the 19-inch rack along the
guide rails and tighten it using eight M6 screws.
When installing the ETP48200,
take out the PSUs, install the
power subrack, and then reinstall
the PSUs.
45
Installing the RRU (Vertical Installation: One RRU on a Pole)
Change the installation height of the RRU based on the installation layout.
40N•m
46
Installing the Pole
Mounting ears in the same line should be of the same height. The distance between two adjacent
lines of mounting ears should be 14.5 U (644.525 mm).
M6 x 20 screw
Slide bracket
47
Installing the Pole
Secure the pole configured with slide brackets to mounting ears
on the rack. M5 x 15 self-tapping screw
Secure both ends of the vertical pole to the slide brackets in the horizontal pole.
Large washer
Spring washer
M10 x 45 screw
48
Installing the RRU
Install a combiner and surge protection box on the Do not route cables close to RRUs to
transit bracket in the lower part of the cabinet as prevent cable jacket deterioration caused
required. due to high temperature generated when
the RRUs work.
49
Installing the RRU (Front Installation: One RRU on a Pole)
Change the installation height of the RRU based on the installation layout.
40N•m
50
Installing the Pole
Slide bracket
51
Installing the Pole
Secure both ends of the vertical pole to the slide brackets in the horizontal pole.
Large washer
Spring M10 x 45 bolt
washer
Attach the RRU to the pole. The following figure shows the installation of four RRUs.
52
Installing Storage Batteries
Installing Storage Batteries
Install the storage batteries correctly. Use insulation covering on tools to avoid damaging the storage batteries and risking injury.
Three-layer vertical 2 V absorbed glass mat Four-layer vertical 12 V AGM batteries with one output
(AGM) batteries (650Ah for maximum)
53
Connecting Storage Batteries
Two groups of 12 V vertical AGM batteries with two Three-layer vertical 12 V AGM batteries with one output
separate outputs
Two-layer vertical 2 V absorbed glass mat (AGM) Three-layer vertical 12 V AGM batteries with one output
batteries (400Ah for maximum)
54
Routing Cables Through a Feeder Window
Install the feeder window to the wall panel of the Remove the six M5 screws from the feeder window to
communications equipment compartment (with BTS racks). pull out the cover.
Feeder window
Loosen one M8 screw to the right of the feeder window, Open the rubber plug and insert the cable to the cable
remove the entire rubber plug, and pull out the required hole through the clearance.
number of cable hole rubber plugs.
Insert the rubber plug with routed cables into the feeder Secure the cover to the feeder window using six M5
window and tighten the M8 screw to the right side using a screws.
wrench.
Metal strip
55
Installing a Heater
Installing Heater HUA03A-01
Install the heater on the front of the battery rack (this Install the heater in the equipment compartment (on
method is used when the side of the battery rack is the left side of the 19-inch rack).
unavailable).
56
Installing an AC Transfer Busbar
Install the AC transfer busbar in the lower left corner of the battery compartment. If there is no battery compartment,
install it in the equipment compartment.
Heater
Heater
Heater
AC transfer busbar
57
Installing an Air Conditioner Controller
1. Secure the air conditioner controller.
Slide the air conditioner controller into the 19-inch rack along the guide rails and secure it using four M6 screws.
58
Installing an Air Conditioner Controller
3. Install cables for the air conditioner controller.
System power
Monitoring
Air module
conditioner
controller
alarm output Air conditioner alarm
cable output cable
Air conditioner Air conditioner
alarm cable power cable
DC power cable
59
Installing Base Plates
1. Get the following materials ready.
Cabinet front
Secure one side seal plate to the left of the cabinet base by using two M6 screws.
Secure one back seal plate to the rear of the cabinet base by using six M6 screws.
Install two side hole seal plates to the rear and right of the cabinet base and secure each plate using three M6
screws.
Cabinet rear
60
Installing an Antitheft Fence
1. Get the following materials ready. After installing the antitheft fence, do not install base plates for the
cabinet base.
Antitheft wrench
Install two L-shape antitheft fences at the front and rear of the cabinet and secure the two fences to another two fences to
the left and right of the cabinet.
Mount the two L-shape fences to the support bolts in Secure the L-shape fences at the top using one M8 screw
the two sides of the fences. and one M8 nut.
Secure the L-shape fences using two M8 screws and Secure the L-shape fences at the bottom using one M8
two M8 nuts. screw and one M8 nut.
61
Installing an Outdoor Ground Bar
Install the outdoor ground bar on the steel base of the Mini-shelter (recommended).
M8 x 20 (2 PCS)
Ground bar antitheft screw, tightened
securing plate using an antitheft wrench
Under the feeder window in the rear wall panel of the Mini-shelter
Concrete pad
62
Installing a Maintenance Socket
Secure the maintenance socket to the rack using two M6 screws. The system power provides 220 V AC power.
Installing a Lamp
Install the lamp in the power supply compartment of the Mini-shelter, enable the power system to supply -48 V DC power to the
lamp, and mount the lamp that is connected to a power cable on the cable pass ring in the upper part of the 19-inch rack.
Switch on the lamp before using it. The lamp can be moved to other compartments of the Mini-shelter for equipment
maintenance illumination
Lamp
System
power
Open the door lock using a key to Unscrew the lock cylinder to be Secure a new lock cylinder
the degree as shown in the replaced using a Phillips using screws.
following figure. screwdriver.
63
Opening a Cabinet Door
Unscrew the door lock using an M3 antitheft wrench until the keyhole appears and insert the key into the keyhole to open the
cabinet door.
64
Routing Cables in a Mini-shelter
Requirements for Cable Routing
Requirements for routing commons:
Cables are routed through cable trays at both sides of the rack and cable trays at the rack top.
The bending radii of power cables, ground cables, and signal cables should be greater than or equal to five times the radii o f power
cables, ground cables, and signal cables respectively.
Cables should be routed separately without interference.
Routed cables are close to each other, clear, and free of damage.
Cable ties are bundled neatly to the same direction. Cable ties in the same position should be at the same level.
Routed cables are labeled clearly.
Cables routed along the floor should be protected with protection tubes that comply with NFPA70 standards.
Cables to temperature control equipment are bundled first in the cable beam in the upper right of the Mini -shelter and then routed to
the cabinet.
After routing external cables to the Mini-shelter from the cable holes at the bottom of the Mini-shelter, block the cable holes in the
seal cover using black mud.
Requirements for routing special cables:
For power cables:
–48 V DC power cables are bundled together.
Power cables, transmission cables, and signal cables are routed separately and are at least 30 mm away from each other.
When routing multiple power cables, bundle them.
No joint is found in a new power cable.
For protection ground (PGND) cables:
PGND cables in a base station should be connected to the same ground bar.
PGND cables must not be routed in from above. They must be underground or routed indoors.
Both ends of the external conductor of a coaxial cable and the shield layer of a shielded cable should have good electrical c ontact
with the metal shell of the device they connect to.
PGND cables and signal cable should be bundled separately with a proper distance to avoid interference.
Switches or fuses must not be installed on PGND cables.
All conductive metal in the metal shell are connected to protection ground terminals properly.
When the cabinet door is connected to the ground screws at the cabinet bottom using a ground cable, the OT terminal on the
cabinet door should face upwards, the OT terminal at the cabinet bottom should face inwards.
65
Cable Routing Specifications
Cable Routing Specifications for Typical Configurations
DC power cable
Signal cable
HUAWEI
base station
DC power cable
Door status Ambient
AC power cable sensor temperature and Battery temperature
humidity sensor sensor
Signal cable
BBU
66
Cable Routing Specifications for Typical Configurations
Signal cable
BTS3900
市电 Power system
BBU
Battery string
67
Cable Routing Specifications for Typical Configurations
DC power cable
Door status Door status Door status Ambient
sensor 1 sensor 2 sensor 3 temperature Battery temperature
AC power cable
and humidity sensor
sensor
Signal cable
BTS3900
市电 ACDB Power system
Battery string
68
Installing PGND Cables
1. An indoor ground bar should be installed in the cabinet and near the ACDB or power system (when no ACDB is
configured). All ground cables are routed straightly and bound neatly.
2. Ground screws in the cabinet are hexagonal head screws, so cables should be secured using tools such as an
adjustable wrench, a solid wrench, a socket wrench to ensure proper grounding.
3 From the power system to the indoor ground 8 From a rack in a compartment to another rack in
busbar another compartment
4 From the BTS to the indoor ground busbar
69
Installing Power Cables
Installing Power Cables for the ETP48200-A6
Load low voltage disconnection
(LLVD) circuit breaker
Wiring terminal N Battery low voltage disconnection
(BLVD) circuit breaker
Ground bar
AC input circuit breaker Battery circuit breaker
DC output positive busbar (RTN+)
AC output circuit breaker
SMU02B UIM02C
Rectifier
(PSU)
Short-circuiting
copper bar
70
Installing Power Cables for the ETP48200-B6
Rectifier
(PSU)
71
Installing Power Cables for the ACDB-DS-063-N1
Three-phase
Single-phase
72
Installing Power Cables for the ACDB-DS-100-P1
Three-phase
1. Ground bar
2. N copper bar
3. SPD alarm reporter
4. Maintenance socket
5. AC output terminal (QF4)
6. AC output terminal (QF3)
7. AC output terminal (QF2)
8. AC output terminal L1/L2/L3 (QF1)
9. Three-phase D.G. input terminal
L1/L2/L3/N (2QF)
10. Three-phase mains input
terminal L1/L2/L3/N (1QF)
Single-phase
1. Ground bar
2. N copper bar
3. SPD alarm reporter
4. Maintenance socket
5. AC output terminal L (QF4)
6. AC output terminal L (QF3)
7. AC output terminal L (QF2)
8. AC output terminal L (QF1)
9. Single-phase D.G. input terminal
L/N (2QF)
10. Single-phase mains input
terminal L/N (1QF)
73
Installing Power Cables for the DCDB-SZ-100-P1
DC
negative
DC
positive
Ground bar
74
Connecting the Temperature Control Equipment
Connecting the Heat Exchanger Connecting the Intelligent Heat
Exchanger
AC power
DC power cable
cable
System power System power
Dry contact
signal cable Monitoring DC power
module cable Monitoring
module
Dry
contact
signal
cable
DC power
DC power cable
cable
System power System power
Monitoring Monitoring
module Signal cable module
Signal cable
75
Connecting the DC Air Conditioner(PC500D) Connecting the AC Air Conditioner(PC500)
76
Connecting the Communications Cable Between Monitoring Equipment and
Base Stations
Scenario 1: HUAWEI Base Stations
Connection between the monitoring unit and HUAWEI BTSs (BTS3900 GSM, BTS3900 CDMA, BTS3900
UMTS, or DBS3900 WiMAX)
RJ45
3 1+ 5+ 9+ 13+
6 1-(GND) 5-(GND) 9-(GND) 13-(GND)
5 2+ 6+ 10+ 14+
4 2-(GND) 6-(GND) 10-(GND) 14-(GND)
7 3+ 7+ 11+ 15+
8 3-(GND) 7-(GND) 11-(GND) 15-(GND)
77
Scenario 1: HUAWEI Base Stations
When Telecom Protocol is used for monitoring, connect one end of the cable with RJ45 ports to the RJ45 connection on
the ETP48200(SUM02B) and the other end to the port of the host.
When dry contacts are used for monitoring, connect the dry contact outputs ALM1 to ALM8 on the ETP48200 (UIM02C)
to third-party Boolean value inspection ports respectively.
78
Ports on the Monitoring Unit
79
Setting Alarm Parameters on the NetEco
WebUI
80
Checking the Installation
Checking the Cabinet Installation
2 All bolts are tightened, especially the bolts used for electric connection. Flat washers and spring
washers are installed properly.
3 The inside of the cabinet contains no waste tape, cable ties, paper, or packing materials.
81
Checking Electrical Connections
1 All ground cables are copper cables. Cable diameters are correct. No switches or fuses are installed on the cables
and no short circuit occurs.
2 The ground cable, AC power cables, and internal cables are correctly connected and screws are secured. No
short circuit occurs during power input or output.
4 Lugs for power cables and PGND cables are soldered or crimped securely.
5 Power cables and PGND cables are routed and bundles separately from other cables.
8 Wiring terminal of storage batteries are free of damage, break, and acid leakage.
2 Exposed parts near the wiring terminals and lugs are wrapped in PVC insulation tape or heat shrinking
tubing.
3 The flat washers and spring washers of all wiring terminals are securely installed.
4 Cables are bound neatly and cable ties are secured evenly and properly.
5 The routed cable should be convenient for future maintenance and expansion.
82
Powering On and Commissioning the Mini-shelter
Powering On the Mini-shelter
Check the power distribution cable and the cable label.
Verify that the output voltages of the ACDB, ETP48200, and DCDU meet the following requirements:
AC voltage range: 220 V ± 20%
DC voltage range: 38–58 V
Power on the Mini-shelter in the sequence shown in the following figure.
Switch on the output circuit breakers (on the power system) that connect to the DCDU,
storage batteries, temperature control equipment, monitoring equipment, and BBU
For a cabinet delivered in disassembly mode, place the cabinet door vertically for more than 2 hours before power-
on to ensure that the temperature control equipment runs properly.
83
Setting Parameters of the ETP48200(SMU02B)
Qty of Battery - - 1
Set Date - - -
Quick
Settings Set Time - - -
IP Address - - 192.168.0.10
Gateway - - 192.168.0.1
Contact the element management system (EMS), and submit environment monitoring parameters of the
ETP48200(UIM02C) to the EMS (M2000) for correct configuration.
84
Powering On and Commissioning the ETP48200
To avoid damage to storage batteries, switch on the battery circuit breaker only after correctly
setting the battery parameters.
BAT ON
OFF
On A fault occurs.
Fault
Red
indicator Blinking Program is being loaded.
at 4 Hz The indicator is back to
normal after the load is
complete.
85
Powering On and Commissioning Temperature Control Equipment
After powering on temperature control equipment, commission them as described in the following table.
The display panels displays the temperature inside the cabinet correctly.Refer to the fault alarm label on the temperature control
DC intelligent
The LCD displays no alarm code, and the alarm indicator is off (if there equipment to observe whether the LCD displays alarms.
heat exchanger
is a buzzer, the buzzer does not generate sounds).
(AH1500D/AH30
The dry contacts meet requirements.
00D)
All spare parts run properly without strange noise.
Check whether the heat exchanger is working properly. The heat exchanger is working properly.
Check the RUN indicator.
Steady on: DC power is supplied.
Blinking at 0.5 Hz (on for 1s and then off for 1s): The heat exchanger is
Heat exchanger running properly. Blinking at 0.5 Hz (on for 1s and then off for 1s)
(HX02/HX04/HX Blinking at 4 Hz (on for 0.125s and then off for 0.125s):
05/HXC70S) Communication interruption occurs. Communication is proper in other
cases.
Off: No power is supplied to the heat exchanger.
Check the ALM indicator.
On: An alarm is generated. The ALM indicator is off.
Off: No alarm is generated.
Check whether the TEC air conditioner is working properly. The TEC air conditioner is working properly.
Check the RUN indicator.
TEC air Blinking: The TEC air conditioner is running properly. The RUN indicator is blinking
conditioner Off: No power is supplied to the heat exchanger.
Check the ALM indicator.
On: An alarm is generated. The ALM indicator is off.
Off: No alarm is generated.
AC air
The LCD displays information correctly but no alarm
conditioner Check whether the LCD displays alarms or abnormality.
information is displayed.
(PC500)
DC air
The LCD displays information correctly but no alarm
conditioner Check whether the LCD displays alarms or abnormality.
information is displayed.
(PC500D)
Check whether the natural ventilation unit is working properly. The natural ventilation unit is working properly.
Check the RUN indicator.
Natural Blinking: The natural ventilation unit is running properly. The RUN indicator is blinking.
ventilation unit Off: No power is supplied to the heat exchanger.
Check the ALM indicator.
On: An alarm is generated. The ALM indicator is off.
Off: No alarm is generated.
Check the RUN indicator.
If the indicator is blinking at 1 Hz (on for 0.5s and then off for 0.5s), the
Blinking at 1 Hz (on for 0.5s and then off for 0.5s)
air conditioner monitor is running properly.
Blinking at 4 Hz, the air conditioner monitor experiences an exception.
Check the ALARM indicator.
Air conditioner On: An alarm is generated. The ALARM indicator is off.
controller Off: No alarm is generated.
Check the FAULT indicator.
On: The air conditioner monitor is faulty. The FAULT indicator is off.
Off: The air conditioner monitor is working properly.
The LCD displays information correctly but no alarm
Check whether the LCD displays alarms or abnormality.
information is displayed.
Check the RUN indicator.
On: The heater is working properly. The RUN indicator is steady on.
Heater Off: The heater is not working properly.
(HAU02A-01) Check the ALM indicator.
On: An alarm is generated. The ALM indicator is off.
Off: No alarm is generated.
Heater
Check whether the fan of the heater is working properly. The fan is working properly.
(HAU02A-02)
86
Commissioning the Sensor
Check that all sensors are working properly.
Device Test Method Result
Smoke sensor Use a cigarette to generate smoke around the smoke The ALM indicator is on, and the LCD on the SMU02B
sensor to check whether the smoke sensor generates an displays alarm information.
alarm. After the alarm is cleared, the ALM indicator is off and the
LCD does not display any alarm information.
Water sensor Place the water sensor into a bottle of water to check The LCD on the SMU02B displays alarm information.
whether the water sensor generates an alarm. After the alarm is cleared, the LCD does not display any
alarm information.
Door status Open a compartment door to check whether the door The LCD on the SMU02B displays alarm information.
sensor status sensor generates an alarm. Close the After the alarm is cleared, the LCD does not display any
compartment door to check whether the alarm is cleared. alarm information.
After Commissioning
Block the cable holes in the middle wall board of the Mini-shelter using polystyrene foam.
Block the cable holes in the seal cover using black mud.
Clear the internal foreign materials, such as screws, wiring terminals, and tools.
Close and lock the Mini-shelter doors, and give the keys to the person in charge.
Do not leave any cable in the crack when closing the Mini-
shelter door to avoid dust intrusion.
87
Appendix
Preparing an OT Terminal and Cord End Terminal
88
Cable Label Handwriting Description
Fonts:
To make fonts easy to read and look aesthetic, comply with standard font templates (Chinese font) requirements
when writing labels onsite. International users can decide fonts based on actual conditions. The font size and
number of letters are decided based on actual conditions. The standard font template is as described in the
following table. When filling only Chinese characters, choose fonts of proper size to make your hardwiring readable
and aesthetic.
Standard font template
0 1 2 3 4 5 6 7 8
9 A B C D E F G H
I J K L M N O P Q
R S T U V W X Y Z
Handwriting direction:
(1) The handwriting direction of characters on the power cable label is the same as the direction of "TO: ", as
shown in the following figure.
Pen:
To make fonts easy to read and look aesthetic, use dedicated black grease pens for handwriting. You can purchase
black grease pens (excluding ballpoint pens) based on actual conditions, for example, there is a shortage of
dedicated pens or the dedicated pencils are missing. In special conditions, you can use black ballpoint pens.
However, you are not recommended to use them because handwriting with ballpoint pens is hard to read.
89
Huawei Technologies Co., Ltd.
Address:
Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China
Website: http://www.huawei.com
Email: support@huawei.com