Professional Documents
Culture Documents
Haffner Et Al. - 2008 - Multistage Model For Distribution Expansion Planning With Distributed Generation - Part I Problem Formulation
Haffner Et Al. - 2008 - Multistage Model For Distribution Expansion Planning With Distributed Generation - Part I Problem Formulation
Haffner Et Al. - 2008 - Multistage Model For Distribution Expansion Planning With Distributed Generation - Part I Problem Formulation
Abstract—This paper presents a model for use in the problem Load nodes.
of multistage planning of energy distribution systems including
Distributed generation nodes.
distributed generation. The expansion model allows alternatives
to be considered for increasing the capacity of existing substations, B. Binary variables
for installing new ones, for using distributed generation, and for
Alternative of the replacement
the possible change to feeders in terms of addition and removing
feeders sections; combining, subdividing, and load transfer be- branch at stage .
tween feeders; and replacement of conductors. The objective Alternative of the addition
function to be minimized is the present value of total installation branch at stage .
costs (feeders and substations), of operating and maintaining Fixed costs for installation or
the network, and of distributed generation. The model takes expansion of substation node at
operational constraints on equipment capacities and voltage limits stage .
together into account with logical constraints, aimed at reducing
the search space. This paper presents: 1) an extension to the linear Alternative for expansion of
disjunctive formulation to represent the inclusion, exclusion, and substation node at stage .
replacement of branches and 2) a generalization of constraints Investment vector at stage .
related to the creation of new paths which can be applied in , Alternative for utilization of the
more complex topologies. The resulting mixed integer linear branch at stage :
model allows the optimal solution to be found using mathematical means that the alternative is
programming methods, such as the branch-and-bound algorithm.
The validity and efficiency of the model are demonstrated in Part available.
II of this paper. , Alternatives and for
Index Terms—Distributed generation, power distribution, utilization of the replacement branch
power distribution economics, power distribution planning. at stage .
Alternative for utilization of the
NOMENCLATURE addition branch at stage .
A. Sets C. Continuous
variables
, Branches of the fixed network and
defined changes for each branch . , Current of branch in the fixed
, Branches of the replacement network at stage .
network and alternatives for each , , Current of branch in the
branch . replacement network at stage
and their maximum capacities
, Branches of the addition network
and .
and alternatives for each branch .
, Nodes of the existing and candidate , Current of branch in the addition
substation and alternatives for network at stage and its maximum
expanding the capacity of the node . capacity .
, , Current vectors for the fixed,
Manuscript received August 14, 2006; revised February 2, 2007. This work replacement, and addition branches
supported by Companhia Estadual de Energia Elítrica (CEEE). Paper no. at stage .
TPWRD-00470-2006.
S. Haffner is with the Electrical Engineering Department of the State Uni- , , Generation at node at stage and
versity of Santa Catarina (UDESC–CCT–DEE), Joinville, SC, CEP 89223-100, the substations’ maximum capacity.
Brazil (e-mail: haffner@ieee.org). Nodal-load shedding at stage .
L. F. A. Pereira, L. A. Pereira, and L. S. Barreto are with the Electrical
Engineering Department of Pontifical Catholic University of Rio Grande do Vector of nodal-load shedding at
Sul (PUCRS), Sala 150, CEP 90619-900, Brazil (e-mail: pereira@ee.pucrs.br; stage .
lpereira@ee.pucrs.br; barreto@ieee.org). , Distributed generation at node at
Digital Object Identifier 10.1109/TPWRD.2008.917916 stage and its maximum capacity.
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
916 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 23, NO. 2, APRIL 2008
Column vector of the nodal injection forecasts into account [1]–[4]. Initially, a number of authors
at stage . solved a simplified form of this problem, using a static planning
, , Column vectors of the nodal voltages model with a fixed time horizon [5]–[8]. Their work resulted
at stage and their minimum and in a formalization of the problem in a single stage, in which
maximum limits. the resources are introduced at one single time step over the
Investment cost at stage . planning horizon. In general, a short-term planning horizon has
Operation cost at stage . been used so that those investments are selected which corre-
spond to the network’s immediate needs, since the uncertainty
D. Parameters
in forecasts tends to increase as the time horizon increases.
Nodal load at node at stage . Subsequently, the problem was adapted to deal with a long-
Vector of nodal load at stage . term time horizon [9]–[13]. This approach resulted in a mul-
Node-branch incidence matrix for tistage formulation of the problem in which resources needed
the fixed network. for the planning horizon can be distributed according to the re-
Node-branch incidence matrix for quirements determined at each stage. Network operators can
the replacement network. thereby accommodate the gradually increasing demand at min-
Node-branch incidence matrix for imum cost, using a long-term planning horizon. The investments
the addition network. needed for the initial steps are effectively executed while the
Impedance of the alternative investments for later stages are reevaluated in the future with
related to the branch of the fixed the use of updated forecasts. The planning horizon is therefore
network. dynamically advanced, with the initial stage always coinciding
, Initial and alternative impedances with the time of execution (month or year).
related to the branch of the The methods used to solve the expansion planning problem
replacement network. can be divided into two categories: methods of mathemat-
Impedance of the alternative of ical programming and heuristic methods, including specialist
the addition network. systems and evolutionary algorithms. Among the methods of
Big number used in the inequalities mathematical programming, the most widely used include mixed
of the disjunctive constraints. integer programming [6], [7], [14]–[16], nonlinear program-
Number of network nodes at stage , ming [17]–[19], dynamic programming [20], [21], and linear
excluding substations nodes. programming [22]. In this approach, it is possible to represent
Present value factors for the the main restrictions explicitly (Kirchhoff’s laws, equipment
investment and operation costs at capacities, voltage drop, and budget) and to minimize fixed
stage . and variable costs arising from installation and substitution of
Operation cost of the alternative equipment. Where mixed integer programming is used, practical
related to the branch . considerations frequently limit the number of solutions and
, Investment and operation costs of make the associated combinatorial problems computationally
the alternative related to the tractable [23]. This, together with the possibilities both of
replacement branch . guaranteeing optimality and of using the computers resources
, Investment and operation costs of currently available, makes the approach very attractive.
the alternative related to the Since 1980, much effort has been directed toward solving the
addition branch . problem of planning distribution by the use of heuristic algo-
, Fixed and variable costs of a rithms, which came to provide an alternative to mathematical
substation located at node . programming. Heuristic methods gained attention because they
Load shedding cost at node . can work in a straightforward fashion with nonlinear constraints
Distributed generation cost at node and objective function, although there is no guarantee that an
. optimum solution can be found. However, in this approach, it is
, Total budget and budget at stage . also easy to introduce aspects, such as losses, reliability, and un-
Number of stages of the planning certainties. Notable among heuristic methods are the branch-ex-
horizon. change algorithms [8], [13], [24], [25] and algorithms based on
Rate of interest for a time period. evolutionary computation [26]–[29]. Other heuristic methods
Number of time periods up to stage that have been used for the problem include specialist systems
counted from a given time reference [30], [31], the ant colony [32], simulated annealing [33], and
(month or year). tabu search [34], [35].
Time periods of stage . This paper obtains the optimum solution to multistage plan-
ning problem through the use of mathematical programming
I. INTRODUCTION methods. The model considers the possible ways in which nodes
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
HAFFNER et al.: MULTISTAGE MODEL FOR DISTRIBUTION EXPANSION PLANNING WITH DISTRIBUTED GENERATION—PART I 917
utilization of distributed generation, and load shedding. Modi- new branch ; and with increasing the capacity and
fications to branches include installation, replacement, and re- installing a new substation at a node ( and );
moval of feeder segments. The paper also extends the disjunc- • associated with the use of the available network branches,
tive approach typically used in transmission expansion planning there are binary variables , having the value one when
with a dc load-flow network model [36], [37]. In formulating the alternatives are used at stage and the value zero, oth-
transmission and distribution planning problems, nonlinear con- erwise;
straints are expressed in terms of the product of binary and con- • all network branches have associated operational and
tinuous variables. In the classical approach, only the inclusion maintenance costs , , , and );
or noninclusion of a branch is represented by means of a dis- • the available capacities for distributed generation are taken
junctive formulation; with the approach given in this paper, the
into account when defining the planned network expan-
removal and replacement of branches is also dealt with in this
sion;
way.
• in each stage, current injections, nodal voltages, and cur-
To reduce the size of search space in the mixed integer
rent flows satisfy Kirchhoff’s laws;
problem in which the planned expansion is cast, the following
• load is represented by current injections with known values
were introduced: 1) logical constraints which describe in-
vestment limitations; 2) fencing constraints obtained from for each stage;
the Kirchhoff’s currents laws (KCL); 3) constraints on new • limits on conductor capacities, substation capacities, and
paths [38], which are generalized to allow their use with more availability of distributed generation are taken into account
complex topologies. at each stage;
This paper is organized as follows. Section II shows how the • voltage drops in the distribution network are calculated as
optimization problem is modeled, with details of the objective the product of branch current and branch impedance;
function and constraints imposed. Section III describes the load • objective function to be minimized is the present value of
and network models. This paper ends with a presentation of con- investment and operational costs;
clusions. In order to illustrate the effectiveness of the proposed • limits are set on total investment and on investment at
model, four different planning situations of a medium-voltage stage .
distribution network are presented in the second part of this Variables associated with the alterations defined for branch of
paper [39]. the fixed network are written with the superscript . Variables
associated with possible alterations to branch of the replace-
ment network are written with the superscript . Variables as-
II. PROBLEM FORMULATION
sociated with possible alterations to branch of the addition net-
The problem of distribution system planning with a long-term work are written with the superscript . Variables associated
horizon has been modeled taking the following factors into ac- with expansion of the substation at node are written with the su-
count: perscript . With this representation, the number of alterations
• the distribution network is composed of nodes at which associated with each branch or node of the network can be de-
loads and sources are concentrated, and branches forming fined, independent of the alterations defined for other branches
connections between nodes, representing the feeders; or nodes. Thus, some network branches may have just one pos-
• the planning horizon is divided into stages of known sible alteration, others may have two, others three, and so on.
duration, with the variables in the problem being associated Variables showing whether investments should be selected
with each stage; are grouped according to the type of alteration proposed: re-
• two continuous variables are associated with each node: placing the conductor of an existing branch (variables );
one is the absolute value of nodal voltage and the other is addition of a new branch (variables ); installation of a new
the current injection; one continuous variable, current flow, substation or increasing the capacity of a substation at a node
is associated with each network branch; (variables and , respectively). For each stage, the use of
• in each stage to the planning horizon, nodes may be mod- available resources (already existing or previously installed) is
ified by increasing the capacity and installing new substa- associated with a set of binary variables ( , , and )
tions; branches may be modified by conductors replacing with values one when the respective alternative was used at stage
or by adding branch connecting nodes not previously con- .
nected; Alterations to network branches defined a priori (addition, re-
• possible alterations to the network nodes and branches con- placement, or removal) are easily incorporated in the model by
stitute a set of investment alternatives to be used in solving means of limits on variables defined for each stage. For ex-
the network expansion problem; ample, if alternative of branch 5 was available during stage
• associated with the execution of each investment alterna- three, the limits would be given by
tive throughout the stages, there is a binary variable , and . Thus, it would not be possible to use the al-
having the value one when the alternative is selected at ternative in the first two stages. Similarly, a priori alterations
stage and the value zero, otherwise; defined for network nodes (substation capacities) can be intro-
• each type of alteration has investment costs associated with duced into the model by means of limits on existing capacities
replacing one branch by another one ; with adding a defined for each stage.
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
918 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 23, NO. 2, APRIL 2008
(1.3)
(1.4)
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
HAFFNER et al.: MULTISTAGE MODEL FOR DISTRIBUTION EXPANSION PLANNING WITH DISTRIBUTED GENERATION—PART I 919
Equations (3)–(6) are therefore substituted by the following The limits on investment for each stage and for the entire
disjunctive versions given by: planning horizon, are given by the following expressions:
(3.1)
(4.1)
(16)
(5.1)
(6.1)
(19)
(9)
(21)
(10)
For nodes with capacity for distributed generation, current in- • Investments in an increase in capacity of substations may
jections limits for depend on the capacity available only be considered after fixed costs have been affected
at each stage, and are given by
(22)
(11)
The remaining operational limits are the maximum load shed- • The fixed network can only be used when it is available
ding and the range of acceptable values for the nodal voltages at
substations and at nodes where loads or generation are installed (23)
for
• Branches that are candidates for replacement may only be
(12)
used after the corresponding investment has been made
(13)
(14)
(24)
(15)
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
920 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 23, NO. 2, APRIL 2008
(25)
Fig. 2. New path defined for a bridge node with two adjacent branches.
(26)
Fig. 3. New path defined for a bridge node with three adjoining circuits.
(27)
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
HAFFNER et al.: MULTISTAGE MODEL FOR DISTRIBUTION EXPANSION PLANNING WITH DISTRIBUTED GENERATION—PART I 921
TABLE I TABLE II
INVESTMENT ALTERNATIVES FOR THE PATH OF FIG. 2 FEASIBLE INVESTMENT ALTERNATIVES FOR THE PATH OF FIG. 2
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
922 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 23, NO. 2, APRIL 2008
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.
HAFFNER et al.: MULTISTAGE MODEL FOR DISTRIBUTION EXPANSION PLANNING WITH DISTRIBUTED GENERATION—PART I 923
[29] E. Díaz-Dorado, J. Cidrás, and E. Míguez, “Application of evolutionary Sérgio Haffner (S’89–M’01) received the B.E. degree in electrical engineering
algorithms for the planning of urban distribution networks of medium from the Pontifícia Universidade Católica do Rio Grande do Sul (PUCRS), Porto
voltage,” IEEE Trans. Power Syst., vol. 17, no. 3, pp. 1151–1159, Aug. Alegre, Brazil, in 1987, and the M.S. and Dr. degrees in electrical engineering
2002. from Universidade de Campinas (UNICAMP), Campinas, Brazil, in 1990 and
[30] Y. Y. Hsu and J. L. Chen, “Distribution planning using a knowledge 2000.
based expert systems,” IEEE Trans. Power Del., vol. 5, no. 3, pp. Currently, he is an Associate Professor of Electrical Engineering in the
1514–1519, Jul. 1990.
[31] R. Ranjan, B. Venkatesh, and D. Das, “A new algorithm for power Electrical Engineering Department of the State University of Santa Catarina
distribution system planning,” Elect. Power Syst. Res., vol. 62, no. 1, (UDESC). His research interests are in the power systems planning, operation,
pp. 55–65, 2002. and optimization areas.
[32] J. F. Gómez, H. M. Khodr, P. M. de Oliveira, L. Ocque, J. M. Yusta,
R. Villasana, and A. J. Urdaneta, “Ant colony system algorithm for the
planning of primary distribution circuits,” IEEE Trans. Power Syst., vol.
19, no. 2, pp. 996–1004, May 2004. Luís Fernando Alves Pereira received the B.E. degree in electrical engineering
[33] V. Parada, J. A. Ferland, M. Arias, and K. Daniels, “Optimization of
electrical distribution feeders using simulated annealing,” IEEE Trans. from the Pontifícia Universidade Católica do Rio Grande do Sul (PUCRS), Porto
Power Del., vol. 19, no. 3, pp. 1135–1141, Jul. 2004. Alegre, Brazil, in 1987, and the M.S. and Dr. degrees in electrical engineering
[34] I. J. Ramírez-Rosado, J. A. Domínguez-Navarro, and J. M. Yusta-Loyo, from the Instituto Tecnológico de Aeronáutica (ITA), São José dos Campos,
“A new model for optimal electricity distribution planning based on Brazil, in 1989 and 1995, respectively.
fuzzy set techniques,” in Proc. IEEE Power Eng. Soc. Summer Meeting, Currently, he is Professor of Electrical, Control, and Computer Engineering at
Jul. 1999, vol. 2, pp. 1048–1054. PUCRS. His research fields include control and driving of electrical machines,
[35] A. Augugliaro, L. Dusonchet, and E. R. Sanseverino, “An evolutionary control and navigation of mobile robots, and power system planning.
parallel tabu search approach for distribution systems reinforcement
planning,” Adv. Eng. Inform., no. 16, pp. 205–215, 2002.
[36] L. Bahiense, G. C. Oliveira, M. Pereira, and S. Granville, “A mixed
integer disjunctive model for transmission network expansion,” IEEE
Trans. Power Syst., vol. 16, no. 3, pp. 560–565, Aug. 2001. Luís Alberto Pereira received the B.E. degree in electrical engineering from
[37] R. Romero, A. Monticelli, A. Garcia, and S. Haffner, “Test systems the Universidade Federal de Santa Maria, Santa Maria, Brazil. He received the
and mathematical models for transmission network expansion plan- M.Sc. degree from the Santa Catarina Federal University, Florianópolis, Brazil,
ning,” Proc. Inst. Elect. Eng., Gen. Transm Distrib., vol. 1491, no. 1, in 1992 and the Dr.-Ing. degree from the University of Kaiserslautern, Kaiser-
pp. 27–36, 2002. slautern, Germany, in 1997.
[38] A. Monticelli, A. Santos, M. V. F. Pereira, S. Cunha, J. G. Praça, and Currently, he is a Professor of Electrical, Control, and Computer Engineering
B. Park, “Interactive transmission network planning using least-effort at the Pontifical Catholic University of Rio Grande do Sul. His main research
criterion,” IEEE Trans. Power App. Syst., vol. PAS-101, no. 10, pp. fields are design and analysis of electrical machines and power system planning.
3919–3925, Oct. 1982.
[39] S. Haffner, L. F. A. Pereira, L. A. Pereira, and L. S. Barreto, “Multi-
stage model for distribution expansion planning with distributed gen-
eration—Part II: Numerical results,” IEEE Trans. Power Del., vol. 23,
no. 2, pp. 924–929, Apr. 2008. Lucio Sangoi Barreto (S’06) was born in Santa Maria, Brazil, on March 17,
[40] R. K. Ahuja, T. L. Magnati, and J. B. Orlin, Network Flows: Theory, 1980. He received the B.E. degree in mechanical engineering from Universi-
Algorithms and Applications. Upper Saddle River, NJ: Prentice-Hall, dade Federal de Santa Maria, Santa Maria, Brazil, in 2003, the B.S. degree in
1993, p. 846. information systems from Unifra, Santa Maria, in 2007, and the M.S. degree in
[41] C. J. Baldwin, C. A. DeSalvo, C. H. Hoffman, and W. S. Ku, “A model
for transmission planning by logic,” AIEE Trans. Power App. Syst., vol. electrical engineering from the Pontifical Catholic University of Rio Grande do
PAS-78, pp. 1638–1645, 1960. Sul, Porto Alegre, Brazil, in 2007.
Authorized licensed use limited to: Universidad de Castilla La Mancha. Downloaded on June 15, 2009 at 03:23 from IEEE Xplore. Restrictions apply.