productivity rates:

1.) demolition = 2 manhr/cu. M


2.) disposal = 1.69 manhr/ cu. m
3.) backfill = 0.82 manhr/ cu. m
4.) clearing = 1.23 manhr/ sq. m
5.) excavation = 8 manhr/cu. m
6.) rebar fabrication = 0.10 manhr/kg