2-07 1. Tools and Equipment: Changing Liners
2-07 1. Tools and Equipment: Changing Liners
CHANGING LINERS
3. PROCEDURES
3.1 FOR REMOVAL
1. REMOVE PISTON AND SUB ROD AS PER SECTION 2: GUIDE 06.
3. REMOVE LINER.
NOTE: IT MAY BE NECESSARY TO PRISE OUT THE LINER WITH
LEVERS BETWEEN LINER COLLAR AND PILOT BUSHING.
3. INSTALL LINER.
___________________________________________________________________________
PPC Manual Sept 95 Rev/1 Page 1
2-07
CHANGING LINERS
7. REPLACE LINER SPRAY MANIFOLD AND COOLANT HOSE.
3.4 COMPLETION
RESTORE PUMP TO OPERATING MODE AS PER SECTION 2: GUIDE 02.
3.5 CHECKS
CHECK SEVERAL TIMES DURING THE FIRST TWELVE HOURS OF OPERATING, TO
ENSURE THAT THE LINER CLAMP REMAINS TIGHT.