ISSUE→Due to the presence of thick jungle during the survey, the embankment quantity could not be ascertained as the
Kondenahalli approach Road runs on tank bund. After the removal of a region of the jungle the required quantity was known.
Due to this embankment qty is raised by 10095cum against 5345.96cum in estimate.
* This road was inspected by SE PRED, Bangalore circle on 4/10/2017 the issue is brought to notice as instructed now it is
proposed in this variation approval.