Professional Documents
Culture Documents
Successfulcontractmanagement PDF
Successfulcontractmanagement PDF
Successfulcontractmanagement PDF
December 2009
CONTENTS
2. INTRODUCTION.......................................................................................................................2
This guide is for anyone who has responsibility for managing contracts. It is from the point
of view of a buyer or customer. The guidance is generic – that is, its principles are intended
to be applicable to all contracts, although it is likely to be of more relevance to major and
complex service contracts.
The guide provides best practice tips and guidelines so that you can:
actively monitor and control all aspects of the relationship between the service
provider/contractor and your organisation; and
ensure the delivery of a cost effective and reliable service at an agreed price and
standard.
From our experience and those of our clients, the worst way to manage a contract is simply
to leave it to take its course. It will inevitably go wrong and leave an incomplete audit trail.
The guidance in this document should provide you with the know-how to:
manage the contract "start up" effectively and to provide a checklist to assist with
understanding the contract;
This guide does not cover the process of creating a commercial arrangement and assumes
that:
the service provider has been carefully selected and their tender properly evaluated
before contract signature.
For contract management to be successful, it is crucial that the above foundations are in
place.
-1-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
2. INTRODUCTION
Contract management is the process that enables both parties to a contract to meet their
obligations in order to deliver the objectives required from the contract. It also involves
building a good working relationship between the customer and the service provider. It
continues throughout the life of a contract and involves managing proactively to anticipate
future needs as well as reacting to situations that arise.
One of the key aims of contract management is to obtain the services as agreed in the
contract and achieve value for money. This means optimising the efficiency, effectiveness
and economy of the service or relationship described by the contract, balancing costs
against risks and actively managing the customer and service provider relationship.
Contract management may also involve aiming for continuous improvement in performance
over the life of the contract.
This guide concerns customer activities following the signature of a contract, not the
procurement process that leads up to the signing of a contract. However, as mentioned
previously, the foundations for contract management are laid in the stages before contract
signature, including the procurement process. The terms of the contract should include an
agreed level of service, pricing mechanisms, service provider incentives, contract timetable,
means to measure performance, communication routes, escalation procedures, change
control procedures, agreed exit strategy and agreed break options, and all the other formal
mechanisms that enable a contract to function.
The above mentioned formal contract aspects form the framework around which a good
relationship can grow. If the contract was poorly constructed, it will be much more difficult to
make the relationship a success. The contract negotiation process must take account of the
requirements for contract management. It is vital to build a contract that not only identifies
clearly the obligations of the service provider (and indeed the customer), but also enables a
productive relationship built on good communication and mutual trust. While the contract
must be built on a firm formal and legal foundation, it should not be so restrictive that it
precludes flexible, constructive management of the relationship between the customer and
the service provider.
In our experience, the following factors are essential for good contract management:
The right contract: The contract is the foundation for the relationship. It should include
aspects such as allocation of risk, the quality of service required, and value for money
mechanisms, as well as procedures for communication and dispute resolution.
Single business focus: Each party needs to understand the objectives and business of
the other. The customer must have clear business objectives, coupled with a clear
understanding of why the contract will contribute to them; the service provider must
also be able to achieve their objectives, including making a reasonable margin.
-2-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
performance under the contract must be monitored to ensure that the customer
continues to get value for money.
People, skills and continuity: There must be people with the right interpersonal and
management skills to manage these relationships on a peer-to-peer basis and at
multiple levels in the organisation. Clear roles and responsibilities should be defined,
and continuity of key staff should be ensured as far as possible. A contract manager (or
contract management team) should be designated early on in the procurement
process.
Knowledge: Those involved in managing the contract must understand the business
fully and know the contract documentation inside out ("intelligent customer" capability).
This is essential if they are to understand the implications of problems (or opportunities)
over the life of the contract.
Flexibility: Management of contracts usually requires some flexibility on both sides and
a willingness to adapt the terms of the contract to reflect a rapidly changing world.
Problems are bound to arise that could not be foreseen when the contract was
awarded.
Proactivity: Good contract management is not reactive, but aims to anticipate and
respond to business needs of the future.
If contracts are not well managed from the customer side, any or all of the following may
happen:
the service provider is obliged to take control, resulting in unbalanced decisions that do
not serve the customer’s interests;
decisions are not taken at the right time – or not taken at all;
new business processes do not integrate with existing processes, and therefore fail;
people (in both organisations) fail to understand their obligations and responsibilities;
-3-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
There are several reasons why organisations fail to manage contracts successfully. Some
possible reasons include:
the customer team does not match the provider team in terms of either skills or
experience (or both);
the context, complexities and dependencies of the contract are not well understood;
a focus on current arrangements rather than what is possible or the potential for
improvement; and
-4-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
After a contract has been signed there are a number of matters that should be addressed
to provide the foundation for successful contract management. An early step is to ensure
that sufficient resources and senior management support are available to manage the
contract. It is equally important to understand both the contract provisions and contractual
relationships at the outset. In the case where the contract manager has been involved in
earlier procurement phases, we expect that the contact manager will already have
knowledge of issues relevant to implementation.
The following checklist should assist the contract management team with providing a better
understanding of the contract and can be used as a basis for developing an effective
working relationship with the service provider.
3.1 Analyse the contract and agree the service provider's understanding of the contract
Identify the roles and responsibilities of both parties and allocate responsibilities within
the customer organisation.
Confirm agreement with the service provider, especially in relation to any sensitive
matters.
We expect that many customers may have certain procedures that must be followed before
and during contract negotiation and prior to execution of contracts. The procedures may
vary depending on the contract terms, the service provider and project type.
3.2 Gain an understanding of the background to the contract and the relationship that
has been developed with the service provider
Discuss the relationship that has developed with the service provider over the
preceding phases of the contracting cycle.
Meet with the service provider as necessary to further develop the relationship and
address issues that may impinge on effective contract management.
3.3 Establish any required systems for monitoring and reporting, protocols for
communication and recordkeeping arrangements
Draw up a monitoring plan or checklist covering key timelines, critical deliverables and
performance reporting priorities.
3.4 Obtain or confirm licences in relation to intellectual property that have not already
been obtained
-5-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
Brief any members of the contract management team regarding their roles and
responsibilities.
In many instances, not all issues are resolved at the time of contract signature. These need
to be addressed in a timely way during contract start up. These issues can create problems
when managing a contract if not properly dealt with at the correct time.
In situations where there are issues that have not been fully resolved at contract signature,
the contract manager should:
identify and record any agreements or arrangements made by the parties relating to
this when the contract was negotiated;
identify and record aspects of the contract which have been potentially left for future
development; and
identify and record aspects of the contract which will be subject to some other process,
for example, third party approvals.
The detailed review of the contract at contract start up may also identify issues that require
clarification or elaboration in the contract. It is important to address any such issues
promptly. This may require a contract variation or exchange of correspondence. Contract
variations are discussed at section 6.
3.7 Transition
For some contractual arrangements there will be a transition phase. The duration of this
phase can range from a few days to several months. The objectives of this phase are to:
ensure a smooth transition to the new service provider by minimising the risk of a
reduction or loss of services and the impact on end-users and other stakeholders;
establish relationships and systems and procedures that will be used during the life of
the contract, and
complete the transfer of information and/or assets to the new service provider.
For straightforward contracts there may be a number of one-off tasks that need to be
appropriately planned and resourced. In complex contractual arrangements the transition
phase may require a detailed plan or some other formal documentation to ensure all
-6-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
relevant matters are considered and addressed. The way the customer manages the
transition phase will generally be an indication to the service provider about the way the
whole contract will be managed. If, for example, the customer adopts a lenient approach in
respect of the non-achievement of transition targets, the
service provider may take this as a signal of how the customer will deal with under
performance generally.
At the end of the transition phase it is important that a formal assessment is undertaken of
overall contract performance. The extent and method adopted will depend on the
complexity of contract deliverables and how important the results of the transition are to the
success of the contract over its life. For example, where the transition is being used to
finalise details of contract deliverables and performance measures, the outcome of the
transition will dictate the final form of the contract and how it will operate in practice.
The post-transition review should also be used to review the customer's contract
management arrangements, including resource requirements.
The parties need to understand and comply with the governance arrangements and in
particular the following issues should be considered:
the agenda for each meeting and the timing for the distribution of that agenda prior to
the meeting with any reading material;
the process for documenting the minutes of the meetings. All actions, responsibilities
and accountabilities should be tracked and managed if the contract is to be managed
effectively; and
-7-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
developing and maintaining contact details of key people involved in the contract;
scheduling meetings and other actions required by the contract delivery and
acceptance of the goods or services;
making payments;
To assist the overall management of long term contracts, there can be benefits in
maintaining up-to-date records of key personnel, stakeholders, end-users and/or experts
and their contact details. This can assist in facilitating communications between the parties
particularly where there are changes in personnel or where personnel are geographically
dispersed.
Although notice provisions are not the most glamorous or exciting of clauses, it is often
important to determine at what time notification is considered to have been given or
received. Therefore, the following essentials of a notice provision should be well
understood:
For most contracts, meetings and particular actions will need to occur at specific times
throughout the life of the contract. It is an important element of contract administration that
a schedule of meetings for parties to the contract, end-users and stakeholders is
established in advance, giving the time, place and purpose of the meeting. The schedule
should also list any planned reviews or other key actions.
Delivery refers to receipt of the contracted supplies into the customer's possession as
specified under the contract. Particular care must be taken with phased delivery. If a
service provider fails to deliver supplies by the delivery dates or to the delivery point
specified in the contract there may be consequences for the service provider under the
contract. The contract manager should ensure that various requirements regarding risk of
loss or damage to the goods or services are carried out in accordance with the contract
provisions. The contract manager should ensure that, prior to goods or services being
-8-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
delivered, appropriate risk management measures are put in place in relation to the
security and storage of goods or services. Where appropriate, the contract manager should
also ensure that appropriate insurance coverage for the goods or services has been
arranged.
"Acceptance" is the term used to describe the procedure by which the customer determines
whether the goods or services meet contract requirements. In many contracts, acceptance
of the contract deliverables will occur periodically throughout the life of the contract. In
service contracts, services may be delivered on a continuing basis.
Generally, the contract should set out the process for acceptance. This will usually require
the service provider to provide the contract deliverables in the form specified by the
contract. This may include providing a formal document to the contract manager and
supporting evidence, such as the results of an acceptance testing, that the goods or
services meet the contract requirements. The contract will usually set out a period in which
the customer is able to decide whether to accept or reject the goods or services.
4.5 Payments
Contract payments should only be made in accordance with the provisions of the contract.
Before payments are made evidence is required that the appropriate representative of the
customer has certified that goods and services have been received and have met the
required standard of performance.
It is also important that payments for satisfactory performance are made in line with the
timeframes set out in the contract. Payments for satisfactory performance should not be
delayed because this can undermine the relationship with the service provider.
It is important that the most up-to-date version of the contract incorporating any variations
is formally evidenced in writing and appropriately stored. This provides the basis for making
payments and the ongoing management of the contract.
It is likely by the contract management phase that a system for maintaining documents for
the particular contract will already have been established. If this is not the case, a
recordkeeping system containing all appropriate documentation should be established in
accordance with the customer's recordkeeping policy and practices. If a system already
exists it should be reviewed to ensure that it is appropriate to the contractual arrangement.
Any additional recordkeeping requirements should be identified and any gaps in
documentation addressed.
The following case study highlights a situation where good recordkeeping paid off.
-9-
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
- 10 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
Performance management must be undertaken throughout the life of the contract and for
all contracts, whether straightforward or complex. Along with performance indicators and
standards, arrangements for monitoring and assessment should have been set out and
agreed in the contract along with action that would result from non performance.
Clear links should have been established in the contract between payments for
performance and the effect of non-compliance or under performance on those payments
and the intent to invoke service credits/rebates contained in the contract if necessary.
The performance monitoring and assessment arrangements should also have been
reviewed at the contract start-up stage and any necessary plans, tools or systems
developed.
5.1 Monitoring
Information provided by the service provider for monitoring purposes should be reviewed
and audited, as necessary, to ensure its accuracy and reliability. It can also often be tested
through consulting end-users regarding the goods and services they have received.
While the broad arrangements for actual monitoring over the life of the contract should
generally have been set out in the contract itself, they may need further or more detailed
explanation at contract start-up or during the transition in phase. The level and formality of
any approach to monitoring needs to be governed by the complexity of the contract and/or
the degree of risk involved. In some cases the approach to monitoring may be set out in a
checklist, in others, a plan setting out detailed monitoring arrangements may be needed.
It is important to focus monitoring activity on key deliverables - very detailed monitoring can
be costly and can unduly shift the focus away from achieving contract outcomes. This may
mean establishing priorities for what will be measured at specific time intervals. Collecting
too much information is also costly and the customer may not have the resources to
analyse it to assess performance adequately.
Having a systematic approach to monitoring, which includes the sort of information required
and when it is required, can assist in identifying any potential problems and allow early
remedial action to be taken. It also allows timely reporting to senior management and other
stakeholders. Obtaining relevant information and data may need to be supported by
management information systems or data bases. Some information may be able to be
provided electronically.
- 11 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
The following case study discusses a situation involving too many performance indicators.
user satisfaction;
The basis for performance assessment, that is, indicators with related targets, and
standards should have been set out in the contract. Where performance information is
difficult to establish at the contract development stage, it may require further development
over the life of the contract. The contract provisions should have been framed to allow this.
Developing indicators further during contract management can draw on actual results
achieved, research and feedback from stakeholders.
- 12 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
performance measures are found not to be suitable for the particular contract.
Contract managers need to have assurance that the information used to assess
performance, and to make or withhold contract payments, is accurate. This material will
also be used to keep senior management and other stakeholders informed regarding
progress. Inaccurate information may mean that an actual understanding of performance is
not being obtained and/or poor performance is being masked.
Honest and balanced feedback should be provided to the service provider. Where
performance is satisfactory or above standard, positive feedback to the service provider
can be beneficial to maintaining the relationship. It is also at this stage that any bonus or
incentive payments linked to performance should be made in line with contract provisions.
In cases where performance problems have been identified they should be dealt with
promptly. This means discussing the issues with the service provider in a professional
manner as soon after they arise as possible. When performance problems are addressed
as a normal part of contract management, it should not have an ongoing negative impact
on the relationship between the customer and the service provider.
In some cases, informal remedial action may need to be undertaken. In other cases, more
formal action for under performance may need to be taken and this is discussed in the
section below.
In many cases contracts are completed without problems but contract managers need to be
prepared to address any problems promptly as they arise in accordance with agreed
procedures. Many contract performance problems can be avoided by managing the
relationship well. Under performance can be minimised by having a performance regime
that allows prompt and ongoing feedback, particularly in relation to critical timeframes or
deliverables. The contract manager needs to be aware of any signs of potential under
performance and be able to address them, to the extent possible, before they become
serious. Addressing under performance in this way can avoid the problem worsening
and/or the service provider being confronted by a problem that the customer has known
- 13 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
about for a period of time. Providing the service provider with early warning may mean that
it is easier to address the issues at low cost and with minimal disruption.
At the early stages of under performance, agreeing informal remedial action will often be
the best approach. Such action could include replacing or using additional personnel,
reporting back more frequently on progress, modifying processes or systems or clarifying
the customer's requirements.
Depending on the seriousness of the under performance, the action taken may need to be
more formal and could include:
developing strategies to address the problem and formally documenting them, and
tracking whether they are working in practice; and
The following case study discusses a situation involving "hidden" under performance.
The contract manager investigated and found that the service provider was using the
contractually specified measure of resolution time, based on when the call was logged in a
register by the help desk. However, the service provider had been encouraging staff to log
requests to an e-mail address. When the help desk was busy, there could then be a long delay
before the emails were entered into the help desk register. The automated reporting system
used the date of entry to the register as the start time – not the time the email arrived. This
meant delays experienced by the help desk clients were not properly reflected in reports on
performance.
The service provider was obliged to improve resolution times to those specified, which
meant some increase in staffing of the help desk.
- 14 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
6. CONTRACT VARIATIONS
6.1 Introduction
Provisions to allow and regulate contract variations should be a standard feature of all
contracts. The ability to vary the contract should be directed or controlled by the customer
and should only occur in defined circumstances. It is accepted practice for the variation
mechanism to provide for variations to be agreed between the customer and the service
provider in writing through a formal amendment of the contract. (In technology contracts,
the variation mechanism is usually called a "change management process", "change
control procedure" or something similar).
Variations should be undertaken in line with the change management process (see section
6.2).
The reasons for the variation should be clearly documented. Variations should not be used
to mask poor performance or serious underlying problems and the effect on original
timeframes, deliverables and value for money should be assessed. If the effects are
significant, senior management and other stakeholders may need to be consulted and/or
advised.
Changes to contractual arrangements have the potential to affect the scope and viability of
the contract for either or both parties and making substantive variations to a contract may
require the same degree of input and effort involved in developing the original contract.
They should therefore be planned accordingly. Customers should be alert to the risk that
multiple changes made to a contract over a period of time may shift the overall allocation of
contract risk or transfer particular risks to the customer. It is important to analyse all
consequences of a proposed contract amendment and make sure there are no unintended
effects of the change.
For public sector projects, contract managers also need to ensure that the contract
variations are not of such a level that they significantly change the contract requirement
and/or substantial parts of the original transaction. If this is the case, it may be necessary to
undertake another procurement process because the revised arrangements are
substantially different to those selected through the original procurement.
There are a variety of issues that should be considered in any change management
process to ensure that it is effective.
- 15 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
Before any change request can be properly considered, the customer and the service
provider must understand the implications of the proposed change. To facilitate this, the
change management process may require the service provider (who will normally be in the
best position to assess the likely impact of a change) to prepare an impact report. Ideally,
the impact report will present a full description of the change, including how the change is
to be implemented and, to the extent relevant, detail:
the likely effect of the change on the ability of the service provider to meet its
obligations under the contract;
where appropriate, acceptance testing procedures and acceptance criteria for the
proposed change; and
It is often useful for the change management process to specify how any costs associated
with the change will be allocated between the customer and the service provider.
Ordinarily, the customer should be required to pay for a change only to the extent that the
change cannot reasonably be considered as within the scope of the existing agreement.
Where a change falls outside the scope of the existing agreement, the change
management process may detail the principles that will determine the price to be paid by
the customer. For example, the change management process may stipulate that the price
for any change should be:
reasonable;
competitive; and
no higher than the price at which a customer would be able to procure similar products
or services from another service provider.
The change management process may enable the customer to request the service provider
to provide an auditor's certificate, confirming that the pricing of any change complies with
the pricing principles.
An otherwise detailed change management process will be of little value if, even once the
price to be paid by the customer has been determined, the service provider can simply
refuse to implement the customer's change request.
Accordingly, the change management process may provide that the service provider
cannot unreasonably refuse (either directly or indirectly) a change requested by the
customer. Unreasonable grounds for refusing a change might include:
- 16 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
refusing to include the change under the agreement despite the subject matter being
reasonably related to or connected with the services.
Impact reports, pricing principles and the service provider's obligation to undertake the
change are just some of the matters that need to be considered in any change
management process to ensure that it is effective. A carefully drafted change management
process can mean the difference between the system/services that a customer wanted on
day one, and the system/services that a customer discovered it needed during the term of
the contract.
assessing the reasons for the proposed variation and whether these may indicate an
emerging or actual performance problem;
assessing the impact of the proposed variation on the contract deliverables, particularly
whether the variation or the work it represents is actually required and whether it was
part of the original contract deliverables;
determining the effect the proposed amendment will have on contract price;
meeting any reporting requirements such as updating the customer's contract register
(see next section).
- 17 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
7.1 Introduction
The sections above relate to the management of individual contracts. However, when
looking at contract management across all contracts a customer may have with its different
service providers, the maintenance of a contracts register and the use of electronic
systems are initiatives which may assist customers in more effective contract management.
Contract registers should be used to monitor contract end dates so that the customer is
made aware of opportunities to exercise contract extensions in a timely manner.
the register will contain all relevant contract details and be configured to be able to
produce reports that can be used to meet the customer's management and reporting
responsibilities;
formal procedures will be established for maintaining the accuracy and completeness of
the register. These procedures will provide for a reconciliation or cross-check between
the register and the customer's financial management information system. The
procedures should also provide for a periodic quality assurance review of the register;
the automation, to the extent feasible, of the input of data that will limit, or eliminate the
multiple input of data into different systems, assist in improving consistency and
reducing the incidence of human error;
system access controls designed to ensure unauthorised staff do not have access to,
and cannot amend or alter, contract details; and
There are advantages to using electronic contract management systems, for example
consistency, efficiency and timeliness. These systems are useful in managing the
administrative aspects of contracting and can be particularly useful in organisations that are
geographically disparate. These can range from reasonably simple systems holding data
about key aspects of contracts entered into including critical dates, to sophisticated
- 18 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
proactive electronic contract management systems. These may be off the shelf systems or
systems that are specifically designed for the customer. Developing and implementing
these systems can be costly so it is important to understand the level of functionality that
may be necessary for a particular customer's requirements and the benefits likely to be
realised through the use of them.
Electronic systems can assist in ensuring that contract managers also have access to the
most recent standard contracts and forms, policies, advices and contract management
assistance. They can also facilitate awareness of new and emerging issues, potential risks
and how to manage them. Electronic systems can also provide a contract management
help desk for the provision of information and advice. The easy availability of information
encourages better decision-making and improved contract management. It can also
provide a forum for communication between contract managers in the customer
organisation, enabling them to be aware of other contracts being managed by the
customer, to ask questions of other contract managers in the customer organisation and to
share tips and lessons learned.
- 19 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
8.1 Introduction
As a general rule, a disagreement becomes a dispute when it is not possible for the parties
to resolve it without resort to a formal resolution mechanism. Generally, what a dispute is
and when it is deemed to have occurred is defined in the contract, often in a dispute
resolution clause.
Many disagreements and disputes arise when the parties cannot agree on issues related to
the interpretation of contract provisions, such as the definition of deliverables, how
performance standards are met and/or the effect of unexpected events. These
disagreements may be of a minor nature which can be and are readily resolved. However,
it is important that any possibility of dispute or an actual dispute be recognised at an early
stage and addressed as quickly as possible. Avoiding the escalation of disagreements can
impact on contract deliverables and reduce the costs to both parties.
Most commercial contracts include a dispute resolution mechanism which provides a multi
layered process involving a number of dispute resolution mechanisms. An example would
be a process involving the following:
if the dispute cannot be resolved by negotiation, then the parties may agree or the
contract may provide for an alternative dispute resolution process to attempt to resolve
the dispute. An alternative dispute resolution process is one that does not involve
commencement of proceedings that are finally determinative, namely court proceedings
or arbitration. Instead a dispute resolution clause could provide for processes such as
mediation or expert determination. The requirement for an alternative dispute resolution
process can be mandatory or the contract can provide that the parties may agree to
such a process; and
if the parties do not agree to an alternative dispute resolution process or the alternative
resolution process does not achieve a resolution of the dispute, then the contract can
provide for the parties to then refer the dispute to court proceedings or arbitration.
In facilitative processes the impartial person involved in the dispute (a dispute resolution
practitioner) assists the parties to identify the disputed issues, develop options, consider
alternatives and endeavour to reach an agreement about some issues or the whole
dispute. The most common example of a facilitative process is mediation.
In determinative processes the dispute practitioner evaluates the dispute and makes a
determination. Examples of a determinative processes are arbitration, expert determination
and court proceedings.
- 20 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
The following descriptions of the processes should not be taken as the only descriptions of
the processes. Often the names attached to the processes will mean different things to
different people.
8.2 Negotiation
Negotiation is the most commonly used method of resolving all types of disputes. In its
simplest form it is the process of counterparties discussing the issues with each other and
seeking a mutually acceptable outcome through discussion, without the assistance of other
persons. This is particularly suitable if the customer wishes to maintain an ongoing
relationship with the other party to the dispute. A successful negotiated compromise can
assisting strengthening the business relationship.
Best practice is that parties should negotiate in "good faith", keep an open mind, be willing
to consider options for resolution of the dispute put forward by the opposing party and also
be willing to put forward options for the resolution of the dispute themselves.
It is imperative that persons conducting the negotiations actually have authority to resolve
the dispute, so that approval from the negotiator’s superior officer does not have to be
sought before an outcome can be achieved.
While the contract may not set out specific procedures with respect to how negotiations are
to be conducted, consideration should be given as to whether the contract should address
the following issues:
the party claiming that there is a dispute must give the other party notice of the dispute
including full details of the issue in dispute and any other incidental matters such as
who is authorised to negotiate with respect to the issues in dispute. The notice should
also refer to the negotiation period specified in the contract; and
In our experience, the following factors must normally be present for negotiations to be
successful:
the parties must be in communication with one another and be willing to continue these
communications;
the problem must directly concern the parties in question and not involve third parties;
and
- 21 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
the parties must want to negotiate or at least be willing to do so, and must consider that
the particular dispute involves an issue that is in fact negotiable.
the issues to be negotiated and the authority of the customer's contract manager;
the likely objectives and approaches of the service provider with whom the negotiation
is taking place;
definition and commitment of the resources available including financial and technical
advice;
checks to ensure that both negotiating parties have the necessary legal authority to act
within the scope of their stated or perceived instructions.
8.3 Mediation
Mediation involves an independent and impartial third party who is appointed as the dispute
resolution practitioner (the mediator) and who facilitates the resolution of the dispute
between the parties. The parties agree on the resolution and there is no decision imposed
on the parties by the mediator. This is the reason why mediation can also be used by the
customer to preserve and continue existing relationships with the other party to the dispute.
Mediation is, at its most basic level, an enhanced method for the parties to negotiate a
resolution. It is an appropriate option where:
The main feature of mediation is that it is a voluntary process and a defining characteristic
is that the mediator and the parties will agree before they begin that the process is without
prejudice and that nothing said or produced during the process will be divulged to the Court
in any subsequent proceedings if no settlement is achieved in mediation. This enhances
the effectiveness of a process where parties can feel ready to divulge relevant facts or
interests, and an organisation is protected from expenditure or resources around
challenges to the processes and the outcome.
It should be noted that the legal doctrine around the limits of confidentiality has not been
fully tested by the courts. In general terms parties must reach an agreement on the level of
confidentiality, and sign an agreement to this effect prior to the commencement of the
process. The mediator will not disclose any information for any reason unless specifically
agreed by all parties. Any records, reports, or other documents received by the mediator
while serving in that capacity will be confidential and will be returned to the parties at the
conclusion of the process, and mediator notes will be destroyed at the end of the
mediation.
- 22 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
Information disclosed or documents produced or brought into existence by the parties in the
course of the mediation are not disclosed by the parties for any reason unless specifically
agreed by all parties or required by law.
Mediation can be more difficult where there are issues of legal precedent or where there
are significant disputes of fact. In both instances, there is less scope for negotiation unless
both parties are willing to compromise. Mediation may be appropriate in the following
circumstances:
the parties wish to engage in free and open discussion and are willing to disclose
positions and interests and seek an expeditious solution at an early stage;
there are economic and financial factors which make mediation desirable. This would
include the cost of proceeding to litigation and also the amount of the claim which is
disputed; and
the nature of the dispute and the availability of an appropriate mediator make it
appropriate for mediation.
use by parties of the services of an independent and impartial third party expert, who is
chosen on the basis of their specialist qualification or experience in the subject matter
of the dispute, to give an opinion on some disputed issue of fact or law;
the third party expert having an investigative and decision making role; and
the parties agreeing whether or not the expert’s opinion shall be final and binding or
whether it would be an advisory or recommendatory opinion.
Expert determination is a flexible process as parties negotiate matters such as the structure
of the process, the issues to be submitted to the expert, choice of the expert, procedures
for the expert to receive information and submissions and the use to be made of the
expert’s opinion.
An expert is chosen to give an opinion after considering and investigating the differences
between the parties. Unlike a mediator, an expert is expected to provide an answer to a
particular matter submitted by the parties and it is generally expected that an expert will
reach a decision on the basis of his or her personal opinion and expertise rather than upon
the parties’ submissions or on the law. The parties agree to accept the opinion as binding.
It is up to the parties to agree whether the expert’s decision is final. However, the opinion
may relate to only one factor in the overall dispute and so a negotiated outcome may still
result. The expert plays an investigatory, inquisitor role in eliciting further information and
makes a determination as an expert and not as an arbitrator.
- 23 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
If the parties do not expressly provide otherwise, the expert’s decision can only be
challenged on limited grounds and cannot generally be appealed. These grounds include
failure to follow instructions, fraud and partiality.
In order to widen the scope for a challenge based on mistake, a clause may provide that an
expert's decision is final and binding "in the absence of manifest error". In the absence of
such wording, an obviously wrong decision is usually not susceptible to challenge unless
the expert has materially departed from his instructions or exceeded his jurisdiction.
Manifest error has been held to mean a "plain and obvious error".
Unless the parties have agreed otherwise, an expert is not required to state the reasons for
his decision.
8.5 Arbitration
The essential feature of most arbitrations is that they are consensual, with the parties
electing arbitration as the manner in which to resolve a dispute. Under arbitration, an
"arbitrator" makes decisions which are binding on the parties and it is generally a "win/lose"
solution similar to that of a court outcome. Arbitration, therefore, is the dispute resolution
technique which most closely resembles litigation. Thus, arbitration may be more
appropriate when the customer is not concerned with maintaining an ongoing relationship
with the other party to the dispute. It should be noted that these days the distinction
between litigation and arbitration is less clear than previously, particularly in terms of the
costs.
Generally any dispute, whether of law or fact, that can be decided by a court, may be
referred to arbitration. The key features in arbitration include that:
the parties agree to an arbitrator who is a neutral third party, and who may have
specialty expertise or experience;
the process is private, and not open to the general public, or the media, like a court
hearing;
the process will be confidential if the dispute resolution clause in the contract states that
the arbitration proceedings and any information disclosed are confidential and can only
be used for the purposes of the arbitration;
the arbitration can be formal, like a trial in court with evidence being given on oath and
procedures similar to that involved by the court, or it can be informal (for example,
when a decision is given based on agreed facts and papers);
an arbitral award is widely recognised by the courts and internationally (through the
New York Convention, to which the UK is a signatory); and
Although parties have considerable freedom in determining the scope and nature of an
arbitration, commercial arbitration in England is subject to legislation and court review.
Parties have limited rights of appeal to the courts
- 24 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
The limitation of arbitration is that it can take as long as standard court proceedings, and in
some circumstances can cost more because the parties must pay the costs of the arbitrator
and the physical venue of the arbitration.
8.6 Litigation
Litigation is the act or process of contesting a lawsuit or seeking redress through the courts.
It can be an expensive and time consuming procedure and is generally taken when other
avenues of dispute resolution have not been successful or are not available. Other
approaches to resolving disputes or contractor defaults should therefore be considered
prior to litigation. Appropriate legal and other professional advice should be obtained prior
to considering and commencing litigation.
- 25 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
9. RECORD KEEPING
The following is a list of documents that may need to be created and retained during the
contract management phase:
Risk assessments
Evidence of insurances, indemnities, deeds and/or licences required under the contract
Transition plans
Records of payments
- 26 -
© Taylor Walton LLP 2009
Taylor Walton Technology & Outsourcing Group - Successful Contract Management
Contact Us
If you wish to discuss the content of this guide or any legal matters relating to commercial
contracts, technology contracts or outsourcing, please contact any of the following members of
the Taylor Walton Technology and Outsourcing Group.
Dr Sam De Silva
Partner
01582 390 544
sam.desilva@taylorwalton.co.uk
Mike Pettit
Partner
01582 390 429
mike.pettit@taylorwalton.co.uk
James Carpenter
Partner
01582 390 466
james.carpenter@taylorwalton.co.uk
The information in this guide is not intended to constitute professional legal advice and should not be relied upon
as such. Specialist legal advice should always be sought for your particular circumstances.
- 27 -
© Taylor Walton LLP 2009