Professional Documents
Culture Documents
Irr Ra 9184 Infra L
Irr Ra 9184 Infra L
Implementation (Project
Management) of
Infrastructure Projects
Definition:
4
Preparing for the Procurement of
Infrastructure Projects
• No bidding and award of contract shall be made unless the
detailed engineering investigations, surveys and designs,
including the acquisition of the ROW for the project, have
been sufficiently carried out (Section 17.6, RIRR);
• In case of projects with pending acquisition of right of way
site or location, the procurement process may commence,
but no award of contract shall be made until authority or
permit to enter is issued by the property owner; or a
notarized deed of sale or deed of donation is executed in
favor of the government; or a writ of possession is issued
by a court of competent jurisdiction, as the case may be.
Preparing for the Procurement of
Infrastructure Projects
1 c.d. Maximum of 50/65 c.d. from last date of advertisement or posting of IB to bid opening
Opening of Opening of
Submission Eligibility Tech. Opening of
Of Bids Docs and Proposal Financial
Eligibility & Prel. Pre-Bid
Exam. Proposal
Check at least 12 c.d. Conference
Proposal Evaluation
Award of
& Ranking Post-qualification Contract
not more than 5/7 c.d. 45 c.d. max
Maximum of 113/144 c.d. with Minimum 28 c.d. 10
Introduction
Importance of Bidding Documents
Prescribed Format:
− 4th Edition (As Harmonized with the Development Partners) – approved through
GPPB Res. 06-2010, dated 17 December 2010
Introduction
Availability of Bidding Documents:
─ From the time the Invitation to Bid is first advertised/posted until the
Deadline for the Submission and Receipt of Bids
─ Posted (upload) at the PEs website and PhilGEPS website
─ Prospective bidders may download the Bidding Documents from any of
the said websites for free
─ However, bidders shall pay the fee for the Bidding Documents upon
submission of their Bids.
To recover the cost of its preparation and development
Table of Contents
Goods Infra
Sec. I - Invitation to Bid (IB) Sec. I - Invitation to Bid (IB)
Sec. III - Bid Data Sheet (BDS) Sec. III - Bid Data Sheet (BDS)
14
Table of Contents
Goods Infra
Section VII - Technical Specifications Sec. VII - Drawings
17
Instructions to Bidders (ITB)
Documents comprising the Bid: Eligibility and Technical Components
─ Technical Component
a) Bid Security as to form, amount and validity period;
b) Project Requirements
c) Omnibus Sworn Statement
Small B C&D Up to 3 Up to 10 Up to 20 Up to 30
─ Having made an estimate of the facilities available and needed for the
contract to be bid, if any;
B
Bidding Process for Goods & Infra
B at least 12 days
At leastopening
before 12 c.d. of
before bid opening
bids
Yes Pre-Bid
ABC > 1M?
Conference
Bidders No
submit Opening should be w/n
Eligibility, Open Eligibility Envelope & 45/50/65 c.d. from last date
of advertisement/posting
Technical & Conduct Eligibility Check
Financial Env. Opening of 2 envelopes
done within one (1) day
BAC Sec. stamps face of
Ineligible bidder Open Technical Proposal & outer envelope as
may file Motion “RECEIVED” w/ date
for Reconsideration Conduct Prelim. Exam. and time countersigned
by bidder/representative
BAC shall initial every
Within 3 c.d. from page of original copies
receipt of verbal or Open Financial Proposal of all bids
written notification Return bids of ineligible
bidders unopened
BAC prepares Resolve MR filed w/n 3
Abstract of Bids, and Bid Evaluation & Ranking c.d. from receipt of
Evaluation Report notice
C
Bidding Process for Goods & Infra
All bidders
C Post-Dis-
qualified? Yes
BAC/TWG
may conduct
site inspection, Are all Declare Failure
test samples, bids >ABC? Yes of Bidding
and inquiries
of LCB’s past No Yes
performances Modify Specs.
Post-Qualification of
Prepares Post- 2nd
Qualification Lowest Calculated Bidder
Failure?
A
Summary Report No
No
BAC notifies Bidder Yes
Post-disqualified Yes
Post-qualified?
Bidder of reason
Yes
1. BAC Resolution to Resolve any
Post-disqualified
bidders may file Recommend Award pending MR/ Adjust ABC
MRs/Protests 2. Notify losing Bidders Protest before
making any
Award
W/n 4/7 c.d. from Approval/Disapproval Negotiated
receipt of BAC
Resolution of BAC Recommendation D Procurement
Bidding Process for Goods & Infra
D
Resolution
Approved?
No
?
Yes
Yes
C
E
Bidding Process for Infrastructure
Projects Yes E
Sanggunian
Authorization?
Yes No
Contract Contract
Approval by Higher
Authority?
Approved by
HEAD?
? A
Proceed to Contract
Implementation Process
END
RULE XVI – ALTERNATIVE
METHODS OF PROCUREMENT
Sec 48.
Alternative Methods
For Infrastructure Projects
Alternative Methods
NEGOTIATED PROCUREMENT (TWO FAILED
BIDDINGS)
Conditions:
1.Two failed biddings
2.Mandatory review of the following:
Minimum technical specifications
ABC, which may be adjusted up to 20% from last
bidding
32
Alternative Methods
NEGOTIATED PROCUREMENT (TWO FAILED BIDDINGS)
Simultaneous negotiations
33
Alternative Methods
SMALL VALUE PROCUREMENT (NEGOTIATED PROCUREMENT)
A. Conditions :
1.There is an unforeseen contingency requiring immediate purchase
2.Amount does not exceed the threshold
THRESHOLDS:
a) For NGAs, GOCCs, GFIs, and SUCs – P100,000.00
b) For LGUs:
34
Alternative Methods
B. Procurement of Small Value Procurement:
a) For NGAs, GOCCs, GFIs and SUCs – P500,000.00
b) For LGUs
35
Alternative Methods
NEGOTIATED PROCUREMENT (EMERGENCY CASES)
Conditions:
Imminent danger to life or property during a state of calamity
When time is of the essence arising from natural or man-made calamities
Other causes where immediate action is necessary:
To prevent damage to or loss of life or property
To restore vital public services, infrastructure facilities, and other
public utilities
36
Alternative Methods
NEGOTIATED PROCUREMENT (TAKE OVER OF CONTRACTS)
Conditions:
Rescinded or terminated contract
Immediate action is necessary:
To prevent damage to or loss of life or property
To restore vital public services, infrastructure facilities,
and other public utilities
Negotiate starting with the 2nd LCB at the bidder’s original bid
price, then to the next if negotiation fails
Conditions:
1.Subject contract is adjacent or contiguous to an on-going infra or consulting
2.Original contract is a result of competitive bidding
3.Subject contract has similar/related scopes of work
4.Within the contractor’s/consultant’s capacity
5.Same prices or lower unit prices as the original contract less mobilization cost
6.Amount does not exceed amount of the on-going project
7.No negative slippage
8.Negotiations commenced before expiry of original contract
38
Alternative Methods
NEGOTIATED PROCUREMENT (AGENCY-TO-AGENCY)
Conditions:
1.Cost-benefit analysis indicating A-to-A is more efficient and
economical
2.A-to-A does not exceed 25% of PE’s total budget for each
category (goods, infra, consulting), as reflected in its approved APP
3.Servicing agency has mandate to undertake the project
4.Servicing agency owns or has access to necessary tools required
for the project
39
Alternative Methods
NEGOTIATED PROCUREMENT (Scientific, Scholarly or
Artistic Work exclusive Technology and Media Services)
Requirement:
40
Alternative Methods
NEGOTIATED PROCUREMENT (NGO PARTICIPATION)
Condition:
•Appropriation law or ordinance earmarks an amount to be
contracted to NGOs
41
Alternative Methods
NEGOTIATED PROCUREMENT (COMMUNITY
PARTICIPATION)
Conditions:
1.In the interest of project sustainability or to achieve certain
specific social objectives
42
CONTRACT
IMPLEMENTATION
Annex “E” of IRR
43
Notice to Proceed
For infra projects with ABC of 50M and below, the maximum
period is 2 calendar days.
• BAC Secretariat, shall post a copy of the NTP and the approved
contract within fifteen (15) calendar days from its issuance in
the PhilGEPS or the website of the PE, if any. (Section 37.4.2,
IRR of RA 9184)
44
Notice to Proceed
45
Variation Orders – Change Order/Extra
Work Order
46
Extra Work Order – may be issued by the
procuring entity to cover the introduction
of new work necessary for the completion,
improvement or protection of the project
which were not included as items of work
in the original contract.
49
ADDITIONAL/EXTRA WORK COSTING
50
ADDITIONAL/EXTRA WORK COSTING
51
Advance Payment
REQUIREMENTS:
52
Progress Payment
53
RETENTION MONEY
54
Liquidated Damages (Sec. 68)
55
LIQUIDATED DAMAGES
56
LIQUIDATED DAMAGES
57
DEFECTS LIABILITY PERIOD
58
Warranty
(Section 62)
59
WARRANTY PERIOD
62
WARRANTY PERIOD
63
WARRANTY PERIOD
64
WARRANTY PERIOD
65
WARRANTY PERIOD
67
WARRANTY PERIOD
68
WARRANTY PERIOD
69
WARRANTY PERIOD
71
Warranty Security
72
Warranty Security (Sec. 62)