Traffic Diversions and Road Closures

Traffic Diversions

Traffic Diversion Start Date Duration


Along Motorway M1 at St Louis Power Station 17 September 2018 3 months
Along the Vandermeersch Street (phase 1) from
20 September 2018 1 month
CEB Rose Hill junction to Victor Hugo Junction
Along the Vandermeersch Street (phase 2) from 4th week of October
1 month
Victor Hugo Junction to reverend Lebrun Junction 2018
Along the Vandermeersch Street (phase 3) from
Reverend Lebrun Junction to Malartic Street End of November 2018 1 month
Junction

Traffic Diversion Start Date End Date (Tentative)


Provisional by-pass traffic scheme at A1 track
June 2018 February 2019
underpass at GRNW (Montee S)
Lane closure on Brabant St. and Entrecasteux St. May 2018 December 2018
Fast Lanes closures on Motorway M1 September 2018
December 2018
on Southbound Carriageway near CEB St Louis

Start Date (Tentative) End Date (Tentative)


Proposed Diversion Scheme
Modification of road layout at Place D’Ármes
(Closure of one lane Northbound near October 2018 December 2018
McDonalds
Closure of slip lane to Caudan Roundabout on
November 2018 February 2019
M1 southbound towards Maupin Street
Fast Lanes closures on Motorway M1
October 2018 January 2019
on Northbound Carriageway near CEB St Louis

2. Road Closures

Lower Plaines Wilhems (Beau Bassin, Rose Hill & Quatre Bornes)
Ongoing diversion schemes

1. Closure of Duncan Taylor Street (near Rose Hill Market).

End date: September 2019

2. Closure of Vandermeersch Street, between junctions with Raoul Lejeune St. to Beau
Bassin (Gool) roundabout.

End date 18 October 2018


Traffic Diversions and Road Closures

3. Closure of Nelson Mandela Street, Residence Barkly

End date: September 2019

4. Closure of Richelieu Branch Road

End date: September 2019

5. Closure of Vandermeersch Street, between junctions with Raoul Lejeune St. to junction
with Rev. Lebrun Street.

Projected dates: 25 October 2018 to 25 November 2018

3. Traffic Diversions – Road Projects - Upper Plaines Wilhems (Vacoas, Phoenix &
Curepipe)

a) Construction of Grade Separated Junctions at Pont Fer/ Dowlut Roundabouts at


Phoenix
Works Phase 1
(i) Along the North bound carriageway along Motorway M1 as from ‘Dowlut’
Roundabout to Pont Fer Roundabout;
(ii) Along the North bound carriageway along Motorway M1 in front of “Les
Halles”; and
(iii)In the central verge of access road at Pont Fer Roundabout from Thursday 23
August 2018 up to Friday 18 January 2019 from 07 00 hrs to 16 30 hrs

b) Sewerage Project at Highlands – Phase 1 Closure of Tout Court Road in the region of
Highlands, Tout Court Road has been closed to traffic from its junction with Mosque Road to
its junction with Bassin Road as from Friday 21 September 2018 and for a period of 8 weeks.