Customer case study

Turner International Middle East


Turner International Middle East uses Prolog® Manager to manage risk
and reduce delays during construction of the world’s tallest building:
Burj Khalifa in Dubai, UAE

Company
Background
Turner Construction Company is Internationally, Turner offers clients Internationally, Turner operates in
recognized as the leading general program, project and construction the same market segments as the
builder in the United States. During management services, including Turner Construction Company;
2009, Turner completed US$8.2B specialty services in predevelopment Turner provides their clients with the
of construction. Turner is the only and material procurement. accessibility and support of a local
builder offering clients a nationwide firm with the strength, stability and
network of offices across the U.S. resources of a global corporation.
Founded in 1902, the firm is a
Turner has been operating in the
subsidiary of HOCHTIEF, a publicly
Middle East since 1975 and in 2006
traded company and one of the
teamed up with Dubai-based global
world’s leading international
property developer Emaar Properties
construction service providers.
PJSC to form a new entity - Turner
According to Engineering News
International Middle East (TiME)
Record’s 2009 “Top 400 Contractors
Sourcebook,” Turner is the - to jointly tap regional growth
leading builder in the healthcare, opportunities. Turner’s current
education, correctional facilities presence in the Middle East and
and commercial office markets North Africa (MENA) region includes
and second in sports. The firm is the United Arab Emirates (UAE),
also a leading builder of multi-unit Saudi Arabia, Egypt, Kuwait, Qatar,
residential buildings, airports and and Senegal.
hotels, motels and convention TiME currently manages a project
centers, as well as a leader in the volume valued at US$32B, including
entertainment, pharmaceutical, Burj Khalifa in UAE. Located in the
telecommunications, religious and heart of Downtown Dubai, the Burj
cultural, government and industrial Khalifa is the “crown jewel” of the
facilities markets.
500-acre mixed-use development.
Turner International LLC, founded After six years of construction, Burj
in 1965, is a subsidiary of Turner Khalifa was successfully completed
and is responsible for Turner’s in January 2010 with homes and
activities in Asia, Europe and offices handed over in the tower.
Latin America and the Caribbean.
Turner International Middle East

Turner Takes on a Lofty Project A Swift Prolog Software


Turner took on a lofty job when they Implementation
were awarded the role of project Implementing Prolog Manager on
manager on Burj Khalifa. When the Burj Khalifa project was swift
construction was complete, the building due to Turner’s expansive experience
would stand 828 meters tall and with the project management


feature 160 stories of hotel, residential, solution. Although the contractor
retail and office space. The massive purchased the project’s Prolog
landmark project would require a great software licenses, which is standard

We consider deal of coordination, and Turner was protocol in the Middle East, it was
Turner’s responsibility to implement
tasked with serving as the mediator
Prolog Manager to between the building owner and all and administer the software. “The
other parties on the job. The project technical implementation was very
be a reliable solution. engineers, consultants and construction easy,” Al Masri says. “Configuring the
management firms (contractors) all fell software to establish procedures for the
It would fulfill all of under Turner’s oversight. documentation management processes
took a bit more time. Yet all of this was
To track and manage the hundreds of
our business needs thousands of documents that would
achieved within a couple of weeks.”

be generated by the multi-billion dollar Turner took advantage of Trimble’s


on the project in project, including submittals, requests- Middle East resources to jumpstart
training efforts, before bringing
terms of managing for-information (RFIs) and drawing
packages, and reduce the risk of additional training in-house. “In

the documents, project delays, Turner needed a strong our experience,” explains Al Masri,
“Prolog Manager operates easily
document management solution with
securing the data flexible reporting capabilities. “The and requires minimal back-of house
solution had to be capable of handling support once the software is up and
and meeting
our reporting
requirements.
“ six years of records and a big number
of different jobs within the overall
project,” explains TiME Project Control
Systems (PCS) Manager, Tareq Al Masri.
running. Eliminating ongoing support
minimizes headaches.”

While Prolog Manager was being


implemented and configured, Turner
The standard construction project tracked early documentation using
management solution for Turner Microsoft Excel logs. Once the project
Construction Company and their management solution was up and
Tareq Al Masri, PCS Manager subsidiaries, including TiME, was Prolog running, the Excel data was imported
Turner International Manager. Turner’s experience with into Prolog Manager to create a
Middle East Ltd. Prolog Manager made it an obvious complete project record, from design
choice for the present project. “We to  closeout.
consider Prolog Manager to be a
reliable solution,” Al Masri states. “It
would fulfill all of our business needs
on the project in terms of managing
the documents, securing the data and
meeting our reporting requirements.”

www.trimble.com
Customer case study

Reducing Risks consultant. Prolog Manager provided Powerful Reporting


and Project Delays visibility into these interactions, which Improves Accountability
At the peak of Burj Khalifa allowed Turner to step in and keep Prolog Manager’s reporting capabilities
construction, the project’s total internal construction moving. were also of significant benefit to
and external Prolog software users Turner as they juggled their many
Early in the project, Turner established
reached 175. Turner relied heavily responsibilities, including accountability
21-day cycles for turning around
on Prolog Manager’s Document to the project owner. “Prolog Manager
information, such as submittal reviews.
Management module, which was the is a very powerful reporting tool that
Over time, however, the logs and
primary Prolog software application we utilized in our presentations and in
reports in Prolog software indicated
used on the project, to ensure that our management support,” Al Masri
that actual turn-around times were
the consultants and contractors says. In addition to basic reporting
often significantly less than required.
communicated effectively. Turner features, the software allowed Turner
Armed with this information, Turner
handled much of the data entry, to create comprehensive, graphical
was able to reduce submittal approval
logging documents such as submittals accounts of the project’s status.
cycles to just 10 days, thereby
and RFIs, monitoring response times “Those kinds of custom reports
accelerating the schedule during a
and ensuring that drawing changes were implemented at the beginning
critical time in the project.
were distributed in real time. of the project, and we’re still using
“Every project experiences delays at them today.”
“Our job as project manager is to try
certain stages,” Al Masari says. “By
and avoid delays,” Al Masri states. Turner also utilized Prolog Manager’s
analyzing the logs in Prolog Manager,
“Prolog Manager helped us to do reporting features to analyze data
we were able to propose different
our job in terms of following all the during project disputes and claims.
ways to handle documentation. This
respective parties, making sure that Having a historical record of the
was very helpful for speeding things
documentation was flowing smoothly project, complete with documents,
up.” Toward the end of the project,
between them and rectifying situations dates and responses, provided clarity
Turner leaned even more heavily on
before they caused delays.” The around most issues to quickly put them
the Prolog Manager logs, using them
threat of delays often arrived when a to rest.
on a daily basis to stay on top of the
document needed to be reviewed by a
project and generate reminders to the
second party. For example, a contractor
contractors and consultants regarding
might submit an inquiry that would
outstanding issues.
need an action or response from the

Turner International Middle East Project Profile The total cost for the Burj Khalifa project was about
US$1.5B, with the entire Downtown Dubai having
Burj Khalifa located in Dubai, UAE
a development value of US$20B. Burj Khalifa was
Burj Khalifa is the “crown jewel” of the 500-acre designed to be the centerpiece of the development,
mixed‑use development, Downtown Dubai. At 828 which also includes The Dubai Mall, the world’s largest
meters, Burj Khalifa is the tallest building in the shopping and entertainment destination. At the peak
world. The 160-story tower has 185,000 square meters of construction, more than 12,000 people from over 100
of residential space (1,000+ apartments) and more countries were working on site. In total, 22 million labor
than 28,000 square meters (49 floors) of office space. hours were required to complete Burj Khalifa.
Additionally, the tower contains the world’s first 160-
Owner: Emaar Properties PJSC
room Armani Hotel, in addition to the world’s highest
Project Manager: Turner International Middle East
swimming pool, located on Level 76. Burj Khalifa also
Architect: Skidmore, Owings & Merrill, LLP
boasts the world’s highest observatory deck with an
Project Start Date: January 2004
outdoor terrace, on Level 124.
Project Completion Date: January 2010
Project Cost: US$1.5B
Customer case study

Turner International Middle East

Prolog Software
Keeps Turner on Target
Burj Khalifa, the world’s tallest building,
also features At the Top, Burj Khalifa,
the world’s highest observatory deck
with an outdoor terrace, located on
Level 124, providing breathtaking,
Notable Features
• The Dubai Fountain, the
world’s tallest performing
fountain, which is
illuminated by 6,600 lights
and 50 colored projectors,
and shoots water 150m
“ Our job as
project manager
is to try and avoid
delays. Prolog
unobstructed views of the city, desert (490ft) into the air while Manager helped
and ocean below. An accomplishment playing music
such as this one is never without its • At the Top, Burj Khalifa, the us to do our
challenges. But the right team, buoyed world’s highest observatory
by the best software, helped bring the deck with an outdoor job in terms of
project to completion. terrace located on Level 124
• Burj Park, the 3-hectare
following all the
As Turner looks to its next international
island set on the 12-hectare
project challenge, they will naturally
Burj Lake; at the heart of
respective parties,
look to Trimble for technology
solutions. Al Masri anticipates that the park is a 1.5 hectare
green park
making sure that
Prolog Converge, which wasn’t
available when Burj Khalifa broke documentation was
ground, will improve collaboration
on future projects. “At the end of The opening of Burj Khalifa was held flowing smoothly
the day,” Al Masri states, “Prolog on January 4, 2010. The ceremony
Manager was a powerful tool that featured an array of fireworks, between them and
provided us with an automated system
for real-time document management
and put information at our fingertips.
With Prolog software, we reached our
target, which was to successfully finish
choreographed light, sound and water
displays and a short film depicting the
evolution of the landmark building.
In June of 2010, the Council on Tall
Buildings and Urban Habitat recognized
rectifying situations
before they caused
delays.

the project.” Burj Khalifa with the 2010 Best Tall
Building Middle East & Africa award.
Later that year, Burj Khalifa won the
award for best project of year at the Tareq Al Masri, PCS Manager
2010 Middle East Architect Awards. Turner International
Middle East Ltd.

NORTH AMERICA
10368 Westmoor Dr.
Westminster, CO 80021
buildings.trimble.com www.trimble.com

© Copyright 2014 Trimble Navigation. All rights reserved. WinEst and the WinEst logo are registered trademarks of WinEstimator, Inc., a wholly owned subsidiary of Trimble Navigation, in the United States and other countries. The names and logos of other companies
mentioned herein may be trademarks of their respective owners. This document is for informational purposes only. Trimble Navigation makes no warranties, expressed or implied, in this document. PN 022519-111 (03/15)

You might also like