PROJECT PHASE 2
Request of Change Design
For
Mixing Chamber Embedded Pipe
(Construction of Intake Facilities, Water Treatment Plant, Reservoir and Elevated Tank)
DWG No.
(NJS) REVIEW
ACCEPTANCE x
CONST.
REV
DEPARTMENT DOCUMENT NO. NO
1. General.................................................................................................................................3
2. Condition..............................................................................................................................3
3. Comparison B/W Ductile Iron Pipe THK., and Stainless Schedule Pipe THK....................3
11. Embedded Pipe Sleeve Detail Drawing ( Stainless SCH20 Sleeve Detail )…………….10
2
1. General
The Contractor would like to request the Engineer to approve Stainless Pipe Sleeve as the for the following items instead
of Ductile Iron Pipe Sleeve
2. Condition
Remark The Mix chamber area Rebar installation of is finished, But Ductile iron pipe delivery
(Reasons) around takes 8 Month , In case Stainless Pipe materials , Site delivery around takes 2
month
3. Comparison B/W Ductile Iron Pipe THK., and Stainless Schedule Pipe THK
2
4. Ductile Iron Pipe Specification
2
6. Stainless Pipe Specification
2
8. Mixing Chamber PLAN Drawing
2
9. Clarifier De-Sludge Piping Detail Drawing ( DN 200 x 32 Nr )
2
10. Clarifier De-Sludge Piping PLAN Drawing
2
11. Embedded Pipe Sleeve Detail Drawing ( Stainless SCH20 Sleeve Detail )